Week8 AssignmentQuestionandSolution
Week8 AssignmentQuestionandSolution
a. A path
b. A critical path
c. A Network
d. None of the above
4. This is the estimate of the shortest possible time in which an activity can be completed under ideal
condition?
5. This is the maximum possible time it could take to accomplish the job?
6. ________________ is a technique that allows us to redraw the activity network to more closely
sequence project subtasks to make the overall network sequence more efficient?
1. Lagging
2. Laddering
3. Sequencing
4. Beta distribution
7. ____________________ is the maximum delay possible for an event without affecting its overall
duration?
1. Float
2. Slack
3. Delay activity
4. Lagging
8. The project activities, precedence relationships and durations are described in the table. The critical
path of the project is?
a. P-R-T-V
b. Q-S-T-V
c. P-R-U-W
d. Q-S-U-W
9. If the earliest starting time for an activity is 8 weeks, the latest finish time is 37 weeks and the
duration time of the activity is 11 weeks, then the total float is equal to:
a. 18 weeks
b. 14 weeks
c. 56 weeks
d. 40 weeks
a. 10
b. 17
c. 27
d. 37
Week 9