MRP and CBP Steps
MRP and CBP Steps
MRP and CBP Steps
The main function of MRP is to ensure the availability of the required quantity of materials
at right time
Types of MRP:
1) Traditional MRP
This is we do while doing MTO and MTS scenarios. If there is shortage of stock, system
will propose procurement
Configuration:
Process:
1) Create Material – select MRP Views, Forecasting view with other views
2) Under Forecasting tab, you can add past consumption. After entering values, click on
execute forecast. Reorder Point will be set automatically. Select MRP type = Reorder
Point
3) Now whenever material is less than reorder point, run MRP Run. This will generate
Purchase Requisition.
------------------------------------------End---------------------------------------------
In CBP, we will set forecast data for material. Then system will calculate reorder point
automatically. Whenever stock of that material goes below reorder point, system will
generate purchase requisition.
Lead time is time between creation of purchase requisition and receiving of goods.
Pre-requisites –
- Material Master Data – MRP1 View
- MRP type – V1
- Define Reorder Point
- Define MRP Controller
- Define MRP Lot size – HB
- Define Maximum Stock Level
SPRO > Materials Management > Consumption-Based Planning > Procurement Proposals >
Define Order Profile (here you can set NB Order Type for Standard Purchase Order and you
can set Special Transfer too, like Stock Transfer between Plants).
Now, go to SPRO > Materials Management > Consumption-Based Planning > Procurement
Proposals > Define Conversion of Planned Orders into Purchase Requisitions...and so on.
MRP controller – Person name who requested goods after running MRP Run.
After running MRP Run, PR will get created .
So In Purchase Requisition, you can see in item detail, contact person tab.
That is nothing but MRP Controller.