S.N0 Activity Productivity Norms Qty Units Ducting

This document outlines productivity norms for ducting and chilled water piping installation. For ducting, it provides norms in square meters or numbers that can be installed per man per day for various activities like installing ducts, insulation, VAV boxes, flex ducts, and testing. It also provides norms for chilled water piping installation and testing in meters that can be installed per man per day for different pipe diameters. The norms are meant to indicate standard levels of productivity for ducting and piping installation work.

Uploaded by

anoopvvv
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
141 views1 page

S.N0 Activity Productivity Norms Qty Units Ducting

This document outlines productivity norms for ducting and chilled water piping installation. For ducting, it provides norms in square meters or numbers that can be installed per man per day for various activities like installing ducts, insulation, VAV boxes, flex ducts, and testing. It also provides norms for chilled water piping installation and testing in meters that can be installed per man per day for different pipe diameters. The norms are meant to indicate standard levels of productivity for ducting and piping installation work.

Uploaded by

anoopvvv
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Productivity norms

S.N0 Activity
Qty Units
DUCTING:
1 Duct 1.2 – 1.5 Sqm/man/day
2 Insulation 3 Sqm/man/day
3 1 No - VAV 3 Sqm/man/day
4 1 No - ECV 2 Sqm/ man/day
5 1 No – Joint Insulation 0.4 Sqm/man/day
6 1 No - Flexible Duct 1 Sqm/man/day
7 1 No - Plenum 1 Sqm/man/day
8 1 No - MSFD 2 Sqm/man/day
9 1 No - VCD 1 Sqm/man/day
10 Pressure Test per 25 Sqm ducting 4.5 Sqm/man/ day
11 Multipurpose Supports – 4 No 1.5 Sqm/man/day
12 Grills & Diffusers 6 No’s / Man/ day
13 Linear Slot Diffuser 6 Rm / Man / day

Kindly note that here ducting is inclusive Support fixing + Cleat fixing + Sealant application
CHW PIPE:
11" – 2" dia 7.5 Rm/man/day
22" - 3"dia 5 Rm/man/day
34"dia 2.5 Rm/man/day
46"dia 1.5 Rm/man/day
58"dia 1.2 Rm/man/day
610"dia 1 Rm/man/day
7CHW Pipe Insulation 15 Rm/man/day
8Pressure Test for 100 Rm 3 man/day
9Valve Package 1.5 Man / day / unit

Kindly note that here Chilled water piping is inclusive of Support fixing