The recent important amendment to the RIBA Outline Plan of Work 2007
affects the wording in stages F1 and F2, which now reads:
F Production Information
F1 Preparation of production information in sufficient detail to enable
a tender or tenders to be obtained.
Application for statutory approvals.
Identification of client’s needs and objectives, business case and possible constraints on
development.
A Appraisal
Preparation of feasibility studies and assessment of options to enable the client to decide
Preparation
whether to proceed. 1
Business
Development of initial statement of requirements into the Design Brief by or on behalf of the justification
Development of concept design to include structural and building services systems, Concept Approval
Tender Preparation and/or collation of tender documentation in sufficient detail to enable a tender or
G
Documentation tenders to be obtained for the project.
Identification and evaluation of potential contractors and/or specialists for the project.
H Tender Action
Obtaining and appraising tenders; submission of recommendations to the client. 3C
Investment
decision
Letting the building contract, appointing the contractor.
J Mobilisation Issuing of information to the contractor.
Construction
L
Completion L2 Assisting building user during initial occupation period.
L3 Review of project performance in use. 5
Benefits
evaluation
The activities in italics may be moved to suit project requirements, ie:
D Application for detailed planning approval;
E Statutory standards and construction safety;
F1 Application for statutory approvals; and
F2 Further information for construction.
G+H Invitation and appraisal of tenders
G H J K L1+2
G* First stage documentation, H* First stage tender may include Contractor’s Proposals, H2 Second stage tender
Contractor’s proposals E F
Note: final design activity by Client may be at stage C, D, E or possibly F. These stages not repeated by contractor
Design and build project two stage tender (all design by contractor)
Planning
Partnering contract
Select specialists H E F1 F2 L3
Design and construction sequences may be as shown for Management contract/ Construction management
Select MC or CM G H L2
J K L1+2
Planning
Select client design advisors 1.3 1.3 review Negotiations / Brief review Compliance audit 5