Simultaneous Operation (SIMOPS) : Term of Referance (Tor)

Download as pdf or txt
Download as pdf or txt
You are on page 1of 25
At a glance
Powered by AI
The key takeaways are that the document outlines safety procedures for simultaneous operations (SIMOPS) during construction, commissioning, and production activities at an oil and gas facility.

The purpose of the document is to define terms of reference (TOR) for SIMOPS during construction, commissioning, and production activities at the North Bahariya Development in Egypt.

The document covers construction activities like piping installation, scaffolding installation, loading/unloading of heavy objects, as well as commissioning, production macro activities, and drilling/workover activities.

Simultaneous Operation (SIMOPS)

TERM OF REFERANCE (TOR)

Document Reference Number


SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001

Revision 000 CONFIDENTIAL P a g e | 1 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
Revision Control

Issue No. Issued By Issued Date Issued For

0 Jeff Koch 19 Jan 2018 Review and Comment

Revision Approval

Approval Name Title Date Signature

Originator Mohamed Selim HAZOP Chair 19 Jan 2018 Mohamed Selim

Reviewer Jeff Koch, PMP Project Manager 19 Jan 2018

Vice President of
Approval Lance McCarver, PE, PMP 19 Jan 2018
Engineering

Revision 000 CONFIDENTIAL P a g e | 2 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
TABLE OF CONTENTS:
1. INTRODUCTION
2. PURPOSE
3. SCOPE
4. RESPONSIBILITIES
5. PROCEDURE

5.1 Technical Procedure

5.2 Area Classification

5.3 Commissioning

5.4 Meeting

5.5 Work Permit

5.6 Job Safety Analysis (J.S.A.)

5.7 Near Miss and Incident Reporting

5.8 Check-lists

5.9 Plant and Equipment

5.10 Personnel Control

5.11 Alarms and Communication

5.12 Emergency Response

5.13 Lifting and Rigging Operations

5.14 Additional Support Groups

6. REFERENCE
7. APPENDIXES
8. SUGGESTION FORMS

Revision 000 CONFIDENTIAL P a g e | 3 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
1. INTRODUCTION

The facilities of the North Bahariya Development can be broadly subdivided as follows:

• Production wellpads and infield flowlines network in the Abrar, Abrar south, Ganna and Sidra
fields, connecting back to the CPF and Water injection wellpad supplied from water injection
feeding from CPF.

• New Central Processing Facility (CPF), the principal functions of the Central Processing Facility
shall be:
- Oil, gas and water separation
- Oil treatment to export specification
- Crude oil storage tanks with 40,000 Stock Oil Barrel capacity (Two days’ production)
- Water treatment for produced water to re-injection specification
- Treated water storage and injection pumping
- Gas flaring to comply with the HSE and IFC requirement
- Upgrade and extend the existing central electrical power generation plant and power
distribution to fulfill the electrical power requirement for CPF and wellpads
- Utility Systems
- Firefighting system
- Control, Safeguarding and F&G Systems

The CPF and associated wellhead systems will also be provided with the following:

- Single central PLC-based Basic Process Control System (BPCS)


- A process safeguarding and Emergency Shutdown (ESD) system
- A Fire and Gas (F&G) detection system.

• Export Oil Pipeline.

On spec crude Oil shall be evacuated from Norpetco CPF at Abrar to Norpetco Receiving Area
(NRA) 150 Km via trucking and the crude oil will be exported via a 50 Km pipeline from (NRA) to
Qarun Receiving Area (QRA) at Dahshour.

The oil export pipeline will be buried and piggable. No instrumented pipeline leak detection
system shall be provided, but road access shall be maintained along the entire pipeline route to
enable routine visual inspection.

Aimed at creating superior value and boosting the level of satisfaction of the beneficiaries and
with an approach focusing on sustainable, integrated and knowledge-oriented production and
development, the company feels committed to comply with national and international
requirements, regulations and standards in such areas as quality, safety, as well as occupational
and environmental health.

Revision 000 CONFIDENTIAL P a g e | 4 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
2. PURPOSE

The purpose of this Simultaneous Operations (SIMOPS) TOR is to provide all personnel from the
construction and commissioning groups who are involved with simultaneous operations on NORPETCO
project with a sound knowledge of the relevant safe work practices and procedures applicable to
simultaneous operations.

This TOR shall also be used to determine the compatibility, interference and limitations raised during the
planning and operational stages of any simultaneous operation. The activities covered by this document
are as follows:

a) The construction activities (i.e. lifting and rigging, confined space, naked flame and hot works,
etc.)
b) 
 The commissioning activities.
c) Production activities after partial handover to production.
d) Assuring compliance with Permit to Work Procedure.

Should it be deemed necessary, specific operations must be reviewed on a case by case basis with a risk
assessment such as a job safety analysis being developed as need arises. Additionally, the requirements
of this TOR shall ensure that any activity or works in any given area, where joint activities may be on
going simultaneously, are reviewed and analyzed for potential interference or limitation. The
requirements of this TOR are; Establish a mechanism for the review of proposed activities (e.g.
meetings, toolbox talks, etc.) to identify department and subcontractor participation.

Establish a matrix of responsible personnel who shall authorize such simultaneous activities.
Ensure simultaneous activities are controlled and performed in a safe manner by;

a) Defining the responsibilities of all personnel involved in the tasks.


b) Appointing a Simultaneous Operations Leader (SOL) to coordinate the activities between the
different organizations.
c) Identifying any preventive safety measures, which shall be implemented prior to
commencement of the simultaneous activities
d) Limiting the number of simultaneous activities in any given area.
e) Avoiding interference during Production Operations after Early Production.
f) Establishing communication channels.
g) Providing training of all personnel involved in the tasks.

To minimize the potential for personnel injury and equipment damage by:

a) Controlling and restricting personnel access to areas where simultaneous activities may be
taking place.
b) Providing specific instruction for securing (making safe) operations and mustering personnel in
case of emergency.
c) Ensuring that all personnel involved in the simultaneous tasks are aware of the specifics of
simultaneous operations and emergency procedure.
d) Identifying hazards and evaluating the consequence of failures.

Revision 000 CONFIDENTIAL P a g e | 5 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
e) This TOR shall further ensure that nothing is done, during the performance of these tasks, to
prejudice the safety of personnel or the Plant.

The work activities covered by this TOR shall include but not be limited to following;

a) Any works significant in nature such as large construction jobs, change-out of major rotating
equipment, naked flame and hot works in restricted areas, blasting and painting works,
radiography, entry into confined space, rigging and lifting works over live equipment or plant,
etc. and which occur in the areas under commissioning control.
b) Any works that pose a significant hazard such as working in areas where there is a risk of
hydrogen sulphide gas (H2S), activities where special chemicals are utilized, works in which
multiple subcontractors are involved, The above examples are not inclusive and other work
activities may also be covered under this Procedure.

3. SCOPE
The requirements of this Simultaneous Operations TOR (SIMOPS) shall be applied to NORPETCO Project
before construction, commissioning and production activities to ensure and highlight and mitigate any
potential restrictions and/or safety impact when planning SIMOPS work activities due to take place at
the same time and in the same/vicinity location.

This TOR shall be applied with attendance of the personnel referenced in the list below.

a) Site Manager
b) General Construction Manager
c) Area Construction Managers
d) Commissioning Manager
e) Installation Commissioning Authorities.
f) Area Commissioning Authorities.
g) HSE Manager
h) Area HSE Managers
i) Simultaneous Operations Leader
j) Production Superintendent
k) Fire and Rescue Chief
l) Subcontractor Site Representatives

3. RESPONSIBILITIES
3.1 SIMOP Chairman - He shall chair the SIMOP session and issue the SIMOP Report with
cover all the critical simultaneous operation and identify the related safety precaution
to be taken, in case it was not covered.
3.2 Site Manager - He has overall responsibility for implementing the SIMOPS Procedures.
3.3 HSE Manager

a) Review SIMOPS activity and agree priorities, interfaces, etc.


b) Check Job Safety Analysis is prepared and approved.
c) Convey HSE expectations to subcontractors.
d) Confirm Work Permit is applied for and approved.
e) Check rigging and electrical tools are inspected.

Revision 000 CONFIDENTIAL P a g e | 6 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
f) Check toolbox meeting held.
g) Check fire and rescue team is notified.
h) Ensure subcontractors are familiar with incident reporting procedures.
i) Ensure on-site construction and safety monitoring occurs.
j) Arrange training, as required.

3.4 Simultaneous Operations Leader (S.O.L.)

The Simultaneous Operations Leader (S.O.L) is responsible for proper coordination and
safe simultaneous interfaces between departments as well as identification and
resolution of any potential impact on other operations.

The S.O.L. liaises with all department heads and supervisors such as Production,
Construction, Commissioning, Maintenance, Safety (HSE), Installation and Area
Authorities. The S.O.L. ensures that all members of the operational teams duly enforce
the requirements of this SIMOPS procedure. However, both Construction and
Commissioning and Production teams shall remain fully responsible for the safe
management of their own operations. The S.O.L. acts under guidance and control of the
Site Manager, additionally he will report and liaise with Construction, Commissioning
and HSE departments as required.

It is the responsibility of the SOL to follow up to completion of all planned SIMOPS


activities and to report to the Site Manager any trend or omission, which could
potentially jeopardize the planning schedule, work areas or Plant. In the event of a
disagreement regarding the safety or schedule of a proposed simultaneous operation or
the continuation of an activity in progress, the matter should be decided by the SOL and
referred to the Site Manager for approval.

The SOL shall attend the daily permit to work coordination meeting.

3.5 Commissioning Manager

In addition to the duties defined by the Permit to Work Procedure the Commissioning
Manager is responsible for:

a) Overall control of all commissioning works


b) Authorization of commissioning personnel as follows
I. Installation Authorities
II. Area Authorities
III. Permit Controllers
IV. Panel Operators
V. Senior and Authorized Electrical Responsible Persons
c) Safety Systems Inhibits
d) Control of the Permit to Work Systems

3.6 Installation Authorities

Revision 000 CONFIDENTIAL P a g e | 7 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
In addition to the duties defined by the Permit to Work Procedure area nominated
Installation Authority is responsible for:

a) Evaluating the intended work, including worksite inspections to highlight any potential
implications
b) Evaluating any work regarding possible implications outside their own areas of
responsibility and identifying these implications to the SOL and Permit Controller
c) Identifying the requirements for any electrical and/or process mechanical isolation
d) Ensuring all necessary lock-out and tag- out requirements are in place.
e) Ensured proper authorization, issue and cancellation of all Main Permits in their areas
f) Planning, coordinating and authorizing all Naked Flame Permits.

3.7 Area Authorities

In addition to the duties defined by the Permit to Work Procedure the Area Authority is
responsible for:

a) Authorizing and coordinating any necessary electrical and/or process / mechanical


isolation.
b) Delegating the issue and cancellation of the following Complementary Permits to the
appropriate Senior and Authorized Electrical Person:

i. High Voltage Electrical Isolation.


ii. Sanction for Test.
iii. Low Voltage Electrical Isolation.

c) Limitation of Access. Ensuring proper authorization, issue and cancellation of other


Complementary Permits in their areas. Reporting deviations in the conditions of the
Permit during the progress of the task and, if necessary, the Permit is suspended or
cancelled. Acting as delegate for the Installation Authority during his absence (e.g., on
night shift) for authorization of Main
d) Hot / Main Cold Work Permits, (excludes Naked Flame Work).
e) Arranging with the Senior Panel Operator for any necessary inhibits of emergency
systems.

3.8 General Construction Manager

The General Construction Manager is responsible for:

a) Overall control of all construction activities.


b) Authorization of personnel as follows;
I. Area Construction Managers.
c) Coordinating with the area planning and control sections to ensure most optimum
schedule is achieved for all SIMOPS works.
d) Liaising with the S.O.L. HSE and Commissioning Manager to ensure any conflicting
activities are fully planned, coordinated and resolved.

Revision 000 CONFIDENTIAL P a g e | 8 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
3.9 Area Construction Managers

Overall control of all remaining construction activities for their respective area.
Authorization of personnel as follows;

a. Area Construction Superintendents.


b. Electrical Superintendents. Coordinating with the General Construction Manager
and various planning and control sections to ensure most optimum schedule is
achieved for all SIMOPS works.
c. Liaising with the S.O.L. HSE and Commissioning Managers to ensure conflicting
activities are fully planned and coordinated.

3.10 Task Supervisors

The safety of SIMOPS operations is dependent to a great degree on the general


communication, coordination and cooperation between the Task Supervisors, Safety
Authority and Area Authorities involved. In addition to the usual job preparation, Task
Supervisors shall:

a. Ensure that their works have been planned and that the Area Construction
Manager, SIMOPS Leader, Commissioning Area Authority and other involved
supervisors have been informed of the schedule and any potential constraints and
interferences.
b. Ensure the necessary permits to work are authorized and ready for display at the
work site. Confirm starting time and duration.
c. Confirm evaluation of potential constraints and interference.
d. Check that production operation and emergency procedures comply with SIMOPS
context and to the current schedule of the planned activities.
e. Ensure that necessary equipment and personnel are available, ready to commence
work to schedule and understand the nature of the SIMOPS activity.
f. During the SIMOPS activities, direct control of the works shall be maintained by:

I. Continuous supervision and monitoring.


II. Clear instruction, constantly updated according to progress and events.
III. Enhanced checking and testing.
IV. Good communication and detailed instructions e.g. Tool Box Meetings
(TBMs), method statements, Job Safety Analysis, etc.

The Task Supervisors, however, remain responsible for performing their day-to-day
operations safely with all due regard for people, property and the environment.

3.11 Permit Controller

a. Arranges for permit approval.


b. Checks permit before issue.
c. Closes permit upon completion of the SIMOPS task.

Revision 000 CONFIDENTIAL P a g e | 9 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
4. PROCEDURE

4.1 PLANNING and CONTROL

a. Commissioning Planning When both construction and commissioning


operations shall be undertaken at the same time on NORPETCO Project, Then
accurate evaluation and control of the operational parameters are of prime
importance for SIMOPS operations, safety and efficiency. For this purpose,
commissioning will maintain two sets of permanently up-dated and marked-up
copies of electrical one-line diagrams identifying energized circuits and P & IDs
identifying pressurized equipment, location of isolations (spades, spools, valves,
etc.) one copy for commissioning use the other copy for the SIMOPS Operations
Leader (S.O.L.). Early Production Activities On the projects which achieve early
production, the areas which shall be under SIMOPS control must be allocated
b. SIMOPS Planning and Control - Any SIMOPS activity undertaken by
Construction, Commissioning and/or Production Operations shall be reviewed
and scheduled to minimize any potential interference or safety impact.
Information relevant to any SIMOPS activity, which has potential impact to the
other personnel working in the same area, shall be informed to all concerned
personnel prior to the commencement of the planned SIMOPS activity.
c. SIMOPS activities for which special safety precautions shall be subject to a risk
evaluation such as a Job Safety Analysis (JSA).
d. Urgent decisions regarding any SIMOPS shall fall under the responsibility of the
General Construction Manager, the S.O.L. and the Commissioning Manager,
who, through joint agreement, shall reach conclusion as to which activity takes
precedent.
e. Construction Planning - The latest revision of the Master Construction Schedule
(MCS) shall be referred when planning for SIMOPS activities. Every effort shall
be extended to ensure conflicting activities are well planned and do not create
potential impact to other works ongoing at the same time in the same area.

4.2 Area Classification:

Two types of areas are defined on projects:

Construction Areas: All construction areas fall under the responsibility of the General
Construction Manager and the Area Construction Managers. These areas by nature do
not have any live systems and are still under construction completion. In general no
permit to work is required to work in these areas however, for certain tasks the
construction permit to work procedure applies.

Commissioning Areas: All areas which fall under the responsibility of the Commissioning
Manager shall be deemed as Restricted Areas. Restricted areas shall be surrounded by
security fencing and shall have warning signs erected. All work in restricted areas must
be performed with a valid permit to work and entry is also restricted to
authorized/permitted personnel.

Revision 000 CONFIDENTIAL P a g e | 10 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
The commissioning areas fall into two categories as follows:

a) Restricted Areas. The restricted areas shall be clearly identified at the


worksite and include fencing around areas. The restricted areas contain a mix of
live systems and systems that are still under construction completion. Special
care shall be taken when working in these areas to ensure that the requirements
of this Procedure are fulfilled.

b) Prohibited Area. A prohibited area shall be clearly identified by warning


tapes and signboards.

4.3 Commissioning

The Commissioning Manager has responsibility for the planning of all commissioning
works and for establishing, together with the SIMOPS Leader, the requirements of the
SIMOPS activities. This shall include but not be limited to the following:

• Planning of concurrent activities performed by different sections.


• Ensuring that a general agreement on work organization and schedule is
reached to minimize disruption.
• Promote good and effective communication between all work parties.
4.4 Planning

The Commissioning Manager shall issue planning forecasts which are reviewed by
respective management planning groups to identify areas of Simultaneous Operations.
When SIMOPS are identified the Commissioning Manager will advise all affected parties
and the Construction and Commissioning planning schedules will be updated to
incorporate SIMOPS. The commissioning program shall incorporate all relevant
information relating to SIMOPS including constraints, limitations, and areas of conflict
and include or refer to applicable emergency procedures. The S.O.L will inform all
parties involved in the works, obtain acceptance for the operation plan and any
identified constraints.

When conflicting operations are identified the S.O.L. will liaise with Construction and
Commissioning Managers to decide which activity takes priority.

4.5 SIMOPS Preparation

Prior to commencing SIMOPS the General Construction Manager, Commissioning


Manager and SOL will meet with all involved parties to verify the aspects of the
operation, confirm emergency procedures and identify any constraints and/or
limitations and conflicting activities. Once the planning of the operation is confirmed
and the detailed program and/or procedures approved, every effort shall be extended
to mobilize equipment and personnel to meet and achieve the schedule. Methods of
communication shall be clearly established between all work parties during the planning
of any SIMOPS activity.

Revision 000 CONFIDENTIAL P a g e | 11 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
4.6 Organization for SIMOPS

All Site personnel, without exception, have an individual responsibility to ensure that
any SIMOPS activities are carried out correctly and efficiently. The named positions in
Column 1 of the following Table have further specific and clearly defined
responsibilities. Not all of the named positions are NORPETCO Job Titles but are
functional titles for the purpose of this SIMOPS TOR.

Each of the positions and their associated responsibilities are described individually in
sub-section 3.1 through 4.11 of this procedure.

The below table is arranged to show the correspondence between the NORPETCO
Functional Titles (as defined in this SIMPOS TOR) and the duties associated with those
functions. 


Procedure Definition Duties Responsible Person


Has overall responsibility for
Site Manager Site Manager
SIMOPS.
General Construction Coordinates construction General Construction
Manager activities related to SIMOPS. Manager
Coordinates all SIMOPS
activities between the
Assistant Commissioning
SIMOPS Leader (S.O.L.) various departments.
Manager
Authorizes planned work to
go-a- head.
Coordinates all
Commissioning Manager Commissioning activities Commissioning Manager
relating to SIMOPS.
Defines plant status for work.
Area Commissioning
Installation Authority Authorizes commissioning
Manager
work to go-ahead.
Arranges any required
isolations. Authorizes work Commissioning Shift
Area Authority
permit. Monitors working Supervisor
practices.
Arranges for permit approval.
Checks permit before issue.
Permit Controller Closes permit upon Permit Controller
completion of the SIMOPS
task.
Defines safety requirements.
Safety Authority Provides Risk Assessment. Area HSE Manager/SI
Monitors working practices.

Revision 000 CONFIDENTIAL P a g e | 12 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
Initiates permits. Defines
scope of work. Ensures that
all persons working under his Person responsible for the
Task Supervisor
control conform to PTW work
conditions. Ensures the task
is completed to schedule.
Table 1: SIMOPS Definitions and Duties

4.7 Meetings
4.7.1 Regular SIMOPS meetings shall be held and are required to:

a. Ensure the highest standards of safety awareness for all personnel.


b. Ensure proper communication, cooperation and coordination is maintained
between the different teams working on the SIMOPS.
c. Ensure proper planning and progress of SIMOPS activities to minimize
unproductive downtimes.
d. Ensure strict application of the Site HSE Plan and Commissioning Permit to
Work Procedure.
4.7.2 Prior to start-up of SIMOPS activities a kick-off meeting shall be convened by the
Commissioning Manager, General Construction Manager, SIMOPS Leader and
supervision undertaking the SIMOPS works to ensure that all precautions have been
implemented and equipment is available to carry out the intended task to the
planned schedule.
4.7.3 In addition to usual topics and tasks, the kick-off meeting is the opportunity for
supervisory personnel to:

a. Review and confirm planning of future concurrent activities, according to the


actual progress of running operations and to identify potential conflicts.
b. Authorize work to be performed under the permit to work system highlighting
SIMOPS events and address safety concerns.

4.7.4 Tool Box Talks shall be held on daily basis and shall include current SIMOPS topics in
their agenda. Specific emphasis will be given to the SIMOPS having potential impact
on commissioning and production activities and methods of raising the alarm in the
event of an emergency. Toolbox meetings shall also address the Job Safety Analysis
and necessary escape routes, location of safety equipment and muster points.
4.8 Work Permits - The Work Permit Procedure is applicable for all SIMOPS works on
NORPETCO project. The mentioned Work Permit Procedure shall be utilized for all
activities performed on commissioning period up to operation.
4.9 Job Safety Analysis

The objective of a Job Safety Analysis (J.S.A.) is to systematically review high risk or
frequently performed tasks to identify and mitigate safety hazards before the tasks
commence. The objective of the JSA is to analyze potential hazards associated with a
specific task.

Revision 000 CONFIDENTIAL P a g e | 13 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
The JSA is a behavior tool used to identify and minimize risk associated with routine,
non-routine and high-risk job tasks. Job Safety Analysis is a structured approach for
identifying potential hazards in a job and devising corrective steps. Since it considers
actions (behaviors) as well as physical and environmental conditions, it is a good way to
increase safety awareness and achieve sustainable improvements in safety
performance.

The extent of the SIMOPS works shall be evaluated using this method of hazard
identification and as a minimum the JSA shall address the following;

d) Identification of the work area, including plot plans, P&ID, isometric drawings
etc. and a method statement for the work execution.
e) Review of the key steps of the work.
f) Hazard identification.
g) Permit to Work requirements.
h) Lock out and tag out requirements.
i) Crane operation requirements.
j) Tools and equipment.
k) PPE and any additional requirements for fall protection, special protective
clothing, etc.
l) Toolbox Meetings.
m) Emergency response preparations
n) Material handling and waste management plan (as required).
o) Housekeeping.

The results of the JSA study will be incorporated into the work schedule and shall be
endorsed by the SIMOPS Leader, prior to commencing the SIMOPS activities. See
Appendix 1 of this Procedure for example of JSA checklist.

4.10 Near Miss and Incident Reporting

Near miss and incident reporting for any SIMOPS activity shall be in accordance with the
Incident & Accident Reporting Procedure,

A formal report shall be issued for each and every near miss and/or incident relating to
any SIMOPS activity.

4.11 Check-lists

The preparation of the SIMOPS activities as far as organization, equipment, material and
procedures are concerned, shall be shared between construction and commissioning
organizations.

To assist these organizations in preparing for pre-determined start-up phases, the


SIMOPS checklist will be used prior to each step of the works and responsibilities
allocated to the disciplines and supervisors in charge. See Appendix 3 of this Procedure
for SIMOPS checklists. This checklist is completed by Safety Authorities and Approved by

Revision 000 CONFIDENTIAL P a g e | 14 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
SIMOPS Leader (S.O.L). After Approved this document is reviewed by Commissioning
Manager for closing.

4.12 Plant and Equipment

Subject to the requirements defined in the developed checklists all plant and equipment
(existing and new purchase) shall conform to hazardous area classification, other plant
and equipment will be subject to and controlled by the Permit to Work System.
Examples may include but are not limited to:

a) Vehicles.
b) Electrical equipment and portable electrical hand tools.
c) Power tools.
d) IS communication system.
e) Lifting equipment.
f) Hand tools.

All plant and equipment for use within the SIMOPS areas (i.e. live) will be subject to pre-
inspection and color coding to signify inspection has been completed. Personal
protective equipment and escape equipment shall be suitable for use within a sour
(H2S) service environment if required.

4.13 Personnel Control

All areas under simultaneous operations shall be restricted to unauthorized access by


personnel not involved in the operation.

The following measures shall be put in place to control entry into these areas.

4.13.1 Entry into Restricted Areas

Access to restricted areas will be controlled by badges, manned security points and
the permit to work system. Construction personnel shall not be allowed access into
any restricted area without a valid permit to work and exchanging their gate pass at
the security gate control.

4.13.2 Alarms and Communication

A full-time safety supervisor shall be stationed in each of the restricted areas and
shall maintain communication between the construction and commissioning
personnel. Emergency alarms shall be activated in each of the restricted areas.

4.13.3 Emergency Response

All emergency evacuations shall be carried out in accordance with the Emergency
Response Procedure. Whenever mustering of personnel is required, all construction

Revision 000 CONFIDENTIAL P a g e | 15 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
and commissioning production personnel shall muster outside of the restricted
areas.

4.13.4 Lifting and Rigging Operations

Prior to entry into a SIMOPS area, all cranes and rigging equipment shall be
inspected and confirmed as fit for purpose. All lifting operations over live
equipment shall be subjected to a risk assessment, which shall be approved by Main
Contractor Heavy Lifting Supervisor. Risk Assessments shall include as a minimum
the following information:

a) Plot Plan showing crane location with respect to intended lift and center of
Gravity of the load.
b) Boom Length.
c) Boom Angle.
d) Crane Radius.
e) Crane Capacity.
f) Maximum Load
g) Block Weight
h) Rigging Weight.
i) Total Weight.
j) Percentage of crane capacity.
k) Counter Weight (as applicable).

The crane manufacturer’s specifications and limitations shall be taken into account
when planning any lift over live plant. The crane operator shall be qualified and be
in possession of a valid crane operator’s license. He shall be familiar with the type of
crane being operated and shall be tested for competency.

A competent rigging supervisor who has been properly trained in rigging and lifting
practices shall be present at the work place at all times during the lifting activities.

4.14 Additional Support Groups

The following supporting groups are available at site on twenty-four hours basis and
shall fully support any SIMOPS activity as required.

4.14.1 Fire and Rescue Team

If required, the fire and rescue team shall be called out to stand-by during SIMOPS
works and shall fully support the commissioning and construction personnel during any
SIMOPS activity.

4.14.2 Project Guard

All Site security shall be carried out in accordance with the Site Security Plan. The
Project Guard is responsible for maintaining security of the restricted areas and the

Revision 000 CONFIDENTIAL P a g e | 16 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
Guard shall check all personnel entering into a restricted area for the following:

a) All personnel are in possession of an authorized work permit prior to entry into
a restricted area.
b) Shall check all workers upon entry and exit from the restricted area for
unauthorized removal of tools, materials and equipment.
c) All personnel exchange their gate pass for restricted area pass upon entry into
the restricted area.
d) No hand phones are carried into the restricted area.
e) No cameras are carried into the restricted area.
f) All walkie-talkies used within the restricted area are intrinsically safe.
g) No smoking rule is enforced within the restricted area.

The restricted (fenced) areas shall be manned with a Project Guard on twenty-four
hours basis.

5. REFRENCES

NEBOSH (National Occupational Health & Safety) Regulation

6. APPENDIXES

Appendix1 - JSA Hazard Checklist

Appendix 2 - SIMOPS Responsibilities

Appendix 3 - SIMOPS Checklist

Appendix 1 - JSA Hazard Checklist Potential Hazards

Revision 000 CONFIDENTIAL P a g e | 17 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
1. Ignition Sources
2. Pressure
3. Lifting Overhead Works
4. Falls
5. Machinery
6. Heat Stress
7. Scaffolding
8. Chemical Exposure to Hazardous Atmosphere
9. Confined Spaces
10. Noise
11. Working and Walking Surfaces
12. Environment and Weather Arc, Flash, Welding
13. Open Holes
14. Fire/Explosion Spills Slips/Trips Chips/Slivers
15. Pinch Points
16. Hot Surfaces
17. Simultaneous Operation
18. Work at Height
19. Spill Control/Contingency Plan
20. Fire Fighting
21. Emergency Evacuation Procedures
22. Eyewash/Safety Shower Location
23. Material Safety Data Sheets
24. Other – Describe

Hazard Controls and Emergency/Contingency Plans

1. Personnel Protective Equipment


2. Physical Barriers
3. Safety Equipment
4. Ignition Source Controls.
5. Lock Out Tag Out
6. Required Work Permits
7. Fall Protection/Open Hole Policy Other - Describe
8. Hard Hats Safety Shoes Safety Glasses Face Shield
9. Goggles
10. Cotton Gloves Leather Gloves
11. Hot Bolting Policy

Safety Equipment Required

1. Work Vest/Life Jacket Full Body Harness Life Lines


2. Safety Barricade
3. Rubber/Chemical Gloves, Apron
4. Work Permit Proper Tools
5. Respirator
6. Fire Extinguisher Fire Retardant Tarps

Revision 000 CONFIDENTIAL P a g e | 18 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
7. Lock Out Tag Out
8. Gas Detector
9. Hearing Protection Caution Tape

Appendix 2 - SIMOPS Responsibilities

Revision 000 CONFIDENTIAL P a g e | 19 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
Arrange SIMOPS Meeting
Review SIMOPS activity and
agree priorities, interfaces, etc.
Check Method Statement is
prepared and approved.
Check Job Safety Analysis is
prepared and approved.
Convey HSE expectations to
subcontractors.
Confirm Work Permit is applied
for and approved.
Check all tools and equipment is
ready.
Check rigging and electrical tools
are inspected.
Check toolbox meeting held.
Check fire and rescue team is
notified.
Ensure subcontractors are
familiar with incident reporting
procedures.
Ensure on-site construction and
safety monitoring occurs.
Arrange training, as required.

1. General Construction Manager


2. Area Construction Manager
3. SIMOPS Leader
4. Commissioning Manager
5. Installation Authority
6. Area Authority
7. HSE Manager Task Supervisor

Appendix 3 - SIMOPS Checklist

Person in Charge: ...............................


Subcontractor: ...................................

Revision 000 CONFIDENTIAL P a g e | 20 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
Activity: .......................................... Location: ..........................................
Construction: .....................................
Unit: ................................................
Commissioning: .................................
Production: .......................................
Date: ...............................................

Y N
N
SIMOPS Checklist e / If No, Explain
o
s A

General

Has person-in-charge been


1.
assigned for the SIMOPS?
Has supervisory cover
2.
been provided?
Has SIMOPS work plan
3.
been developed?
Is copy of permit
4.
available?
Have all persons involved
5. in the SIMOPS been
instructed in;
5a. SIMOPS procedures
Emergency procedures
5b.
and alarms.
5c. Muster Point Locations.
Fighting equipment and
5d.
locations?
Is good housekeeping
6.
practiced?
Is smoking restricted to
7.
designated areas?
Has electrical equipment
8. been suitable grounded
and inspected?
Have all personnel
working in the restricted
9.
area registered at the
security gate?
Are personnel at risk from
10. H2S?
Are personnel issued with
11. an H2S escape mask?

Revision 000 CONFIDENTIAL P a g e | 21 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
Are welding works
12.
required?
Are all non-essential
13. personnel removed from
the SIMOPS area?
Gas Checking

1. Are gas detectors


calibrated and tested?
Do gas detectors initiate
2. and audible alarm when
LEL is detected?
3. Is gas tested authorized
for this activity?
Safety
1. Is adequate PPE being
worn?
2. Is fire watch / stand-by
man assigned?
3. Are a fire hose and/or fire
extinguisher available?
4. Barriers and warning signs
erected?
5. Are gas checks completed
and recorded?
6. Is MSDS available?

7. Has emergency response


team been informed?
8. Is radiography required?
Are confined space
9. procedures being
followed?
10. Are gas detectors and/or
ESD systems inhibited?
11. Are all sparks being
contained?
14. Has JSA been developed?
Construction Work – Naked Flame Works
1. Are daily toolbox
meetings held?
2. Is work permit authorized
and available?

Revision 000 CONFIDENTIAL P a g e | 22 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
3. Are conditions of the
permit being followed?
Are suitable flame-
4. retardant materials being
used to contain sparks?
Have all necessary
5. isolations been
completed?
Are welding machines
6. inspected and positioned
in suitable location?
Are welding cables
7. insulated and in good
condition?
Are compressed gas
8. cylinders secured, fitted
with flame arrestors and
free from grease and oil?
Construction Works – Rigging and Lifting
Are rigging and lifting
1. personnel qualified and
competent?
Has risk assessment been
2. undertaken and
addressed with all
personnel?
Are the crane, shackles and
3. slings visually inspected prior
to the start of lifting
operations?
4. Is the rigging and lifting
equipment colour coded?
5. Is the crane operation
qualified?
6. Are crane inspection records
available?
Is rigging supervisor clearly
7. identified by wearing a green
work vest?
Construction Works – Blasting and Painting
1. Has toolbox meeting been
held?
2. Are paints and thinners
stored in safe location?
3. Have critical lines and vessels
been identified, checked and

Revision 000 CONFIDENTIAL P a g e | 23 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
determined as safe to blast?
Is surrounding area
4. sufficiently protected from
blast materials and pain
overspray?
Commissioning Works
Is all equipment
1. depressurized and/or
isolated?
2. Is equipment purged of gas
and/or vapour?
Is electrical and/or
3. mechanical equipment
locked-out and tagged?
4. Are open drains and culverts
covered?
5. Are all necessary permits to
work authorized?
6. Are electrical isolations
recorded?
7. Are process/mechanical
isolations recorded?
8. Is commissioning Supervisor
assigned?

Revision 000 CONFIDENTIAL P a g e | 24 of 24


Doc. No.: SNBL-STSI/FEED 001/2018-STSI-HSE-REP-0001
All information contained herein is confidential and is released only to the intended recipient as directed by STS.
ANNEX A OF 1902-00-BFRV-13005

SIMOPS MATRIX

A.2.1

A.2.2

A.3.1

A.3.2

A.4.1

A.4.2

A.4.3

A.4.4

A.4.5

A.4.6

A.4.7

A.5.1

A.5.2

A.5.3

A.6.1

A.6.2

A.6.3
A.1

A.2

Loadig/Unloading of Heavy Objects (Working Material/SkidA.3

A.4

A.5

A.6

B.1

B.2

B.3

B.4

B.5

C.1
A

C
Scaffolding Installation/Handrail Removing
n/a NOT APPLICABLE

Construction Activities
Y ALLOWED
Activity / ID Number

Preparation Activities
ALLOWED WITH RESTRICTIONS

Gang Way Installation

Movement of Heavy Objects


N NOT ALLOWED

Movement of Heavy Objects

Umbilical Installation / Pulling up


A Construction Activities

Installation Activities
0

Riser & J-Tube Installation


A.1

N/B Precommissioning / Commissioning / Start up


A.2 Preparation Activities -

Piping Installation

Cutting Grinding and Welding


A.2.1 Gang Way Installation n/a -

Electrical (Construction)
Skid Installation
A.2.2 Scaffolding Installation/Handrail Removing n/a - R

Verifications & Test Activities


A.3 Loadig/Unloading of Heavy Objects (Working Material/Skid) - - - -

Flanges used for hydrotest removal

Mechanical (Precomm / Comm / Start up)


A.3.1 Movement of Heavy Objects n/a - R N -
A.3.2 Movement of Heavy Objects n/a - R N - R

Instrumental (Precomm / Comm / Start up)


Painting & Touch up

Electrical (Precomm / Comm / Start up)

Production Export line(s) Pressurization/Depressurization


A.4 Installation Activities - - - - - - -

Non Destructive Tests


A.4.1 Piping Installation N - R N - N N -
A.4.2 Skid Installation N - R N - N N - Y
A.4.3 Riser & J-Tube Installation N - N N - N N - N N
A.4.4 Umbilical Installation / Pulling up N - R N - N N - N N n/a
A.4.5 Electrical (Construction) N - R N - N N - N N N N

Production Macro Activities


A.4.6 Cutting Grinding and Welding N - R N - N N - Y Y N N N

Hydrotest
A.4.7 Painting & Touch up Y - Y Y - Y Y - Y Y Y Y Y Y
A.5 Verifications & Test Activities - - - - - - - - - - - - - - -
A.5.1 Non Destructive Tests N - N N - N N - N N N N N N N -

Single Well Start Up

Drilling/Workover activities on Wells


A.5.2 Hydrotest N - R N - N N - Y Y R Y N Y Y - N
A.5.3 Flanges used for hydrotest removal

Normal Production
N - R N - N N - N N N N N N Y - N n/a

Single Well Start Up

Drilling/Workover Activities
A.6 N/B Precommissioning / Commissioning / Start up - - - - - - - - - - - - - - - - - - -
A.6.1 Mechanical (Precomm / Comm / Start up)

Normal Production
N - R N - N N - N N N N N N Y - N N N -
A.6.2 Electrical (Precomm / Comm / Start up) N - R N - N N - N N N N N N Y - N N N - N
A.6.3 Instrumental (Precomm / Comm / Start up) N - R N - R R - N N N N N N Y - N N N - N N
B Production Macro Activities
B.1 Single Well Start Up n/a - n/a n/a - n/a n/a - n/a n/a n/a n/a n/a n/a n/a - n/a n/a n/a - n/a n/a n/a -
B.2 Normal Production n/a - n/a n/a - n/a n/a - n/a n/a n/a n/a n/a n/a n/a - n/a n/a n/a - n/a n/a n/a - R
B.3 Single Well Start Up N - N N - N N - N N N N N N R - N N N - N N N - N R
B.4 Normal Production N - R N - R R - N N N N N N Y - N N N - N N N - R Y R
B.5 Production Export line(s) Pressurization/Depressurization n/a - n/a n/a - n/a n/a - n/a n/a n/a n/a n/a n/a n/a - n/a n/a n/a - n/a n/a n/a - N n/a N R
C Drilling/Workover Activities
C.1 Drilling/Workover activities on Wells n/a - n/a n/a - n/a n/a - n/a n/a n/a n/a n/a n/a n/a - n/a n/a n/a - n/a n/a n/a - R Y R Y R -

NOTE: Recommendations and Restrictions for simultaneous operations "Allowed with Restrictions" to be defined in a more advanced Design Phase.

You might also like