Seismic Performance of Pile-To-Pile Cap Connections: An Investigation of Design Issues
Seismic Performance of Pile-To-Pile Cap Connections: An Investigation of Design Issues
ABSTRACT: Damage in recent earthquakes has resulted in the design of pile foundation systems becoming
more conservative, particularly pile-to-pile cap connections. However, the application of current international
design practice results in pile cap joint details having congested steel reinforcement in the pile cap and this is
extremely difficult to construct in accordance with the designers recommendations. The formation of plastic
hinges in the piles remains a serious risk. A review of critical design issues and former research investigations
into the soil-structure interaction of pile systems and the findings of a three-dimensional, nonlinear finite ele-
ment analysis of the system is reported. Significant gaps have been identified between current practice and
the performance of piling systems when subjected to seismic events. Preliminary findings indicate potential
for alternate connection details to improve performance under seismic action. The paper concludes with a
concise summary of current state-of-the-art design approaches and details further research requirements.
KEYWORDS: Pile-to-pile cap connections, nonlinear finite element analysis, seismic performance, interna-
tional design practice, state-of-the-art design approach
8
Electronic Journal of Structural Engineering, 6 (2006)
that because of the difficulties associated with the DIANA (2005), to obtain structural response that
repair of foundation damage occurring during severe can be used to validate the analytical design proce-
earthquakes, it is desirable to design the piles to re- dure and to determine the types of inelastic behav-
main undamaged. Therefore, damage due to recent iours of the system will experience under seismic
earthquakes has resulted in an increased conserva- loads.
tism in the design of piles and pile-to-pile cap con- In this paper, the particular case of a square
nections. In contrast, current recommendations pro- prestressed pile embedded in a cast-in-situ pile cap
duce connection detailing which result in high levels has been analysed. Linear and nonlinear finite ele-
of congestion of steel reinforcement and extreme ment and time history analyses have been conducted
difficulties in construction. to investigate the behaviour of pile-to-pile cap con-
nections under simulated seismic loads.
2 CURRENT PRACTICE
2.1 Design standard
In practice, the use of prestressed concrete piles and
their connection to cast-in-situ reinforced concrete
pile cap is inherent in pile foundations. The connec-
tion distributes shear, axial load, and moment to
each pile underneath the pile cap. All connections
should perform their function at all stages of loading
without any distress, and with an appropriate safety
factor against failure due to overload. From a previ-
ous investigation (Harries and Petrou, 2001) it has
been established that piles tend to develop their flex-
ural capacity without distress to the pile cap pro-
vided that a sufficient embedment length is fur-
nished.
Figure 1. Response and potential plastic hinges of pile group. In general, design criteria for the required seismic
performance of pile foundation system in a ductile
Ideally, the design concept should aim to dissi- earthquake resistant structure, are documented in
pate seismic energy by ductile yielding at plastic many standards, e.g. the American Concrete Institute
hinge regions in the structure above the foundations (ACI), the Australian/New Zealand Standards
or mechanical energy dissipating devices placed be- (AS/NZ), California Department of Transportation
tween the foundation and the structure. i.e., the System (CALTRANS), and Japanese Codes. How-
foundation should be provided with sufficient ever these Standards do not detail the performance
strength to ensure, as far as possible, that they re- of pile-to-pile cap connections. As a result, research
main in the elastic range while energy dissipation on the performance of pile-to-pile cap connections
occurs. Moreover, the embedment detail of the con- subjected to earthquake response is limited and the
nection between the precast prestressed piles and the behaviour of these connections not well understood
cast-in-situ reinforced concrete pile cap is currently due to its complexity. In fact, recent research relat-
investigated in the University of Melbourne to fully ing to the design and detailing of piles and pile-to-
comprehend the seismic behaviour of the overall pile cap connections has relied heavily on the NZS
structures. 3101, the CSA Code, and the ACI Code (Joen and
Park 1990).
Current design procedures for pile caps do not
1.2 Aim of study
provide engineers with a clear understanding of the
The aim of this study is to refine the design of pile- physical behaviour of these elements. The current
to-pile cap connections in conjunction with capabili- ACI Building Code procedure/guidance for the shear
ties of developing the moment demands on the piles design of pile caps does not predict adequately the
as a result of the seismic events. This aim is being actual behaviour because this procedure neglects
accomplished by subjecting analytical models of a certain important parameters, such as the amount of
typical connection detail of pile-to-pile cap connec- longitudinal reinforcement, and overemphasize other
tions. A three dimensional (3D) solid model of the parameters, such as the effective depth. In order to
pile and pile cap was generated with the finite ele- achieve efficient connection dimensions, new ad-
ment analysis (FEA) programs, SAP2000 and
9
Electronic Journal of Structural Engineering, 6 (2006)
vanced materials and construction techniques need Figure 2a and 2b show the liquefacted soils during
to be considered. major earthquake affecting inelastic lateral deforma-
The structure and all its components must gener- tion of pile-to-pile cap interface and plastic hinges
ally be designed to resist all loads, deformations and and buckling along the pile length. Four years after,
environmental conditions likely to occur during con- the magnitude of 7.8 Off-Tokachi Earthquake and
struction and normal use, and have adequate durabil- magnitude of 7.4 aftershock caused serious damage
ity. Furthermore, design loads, actions and strengths to a region of Northern Japan, and in particular dam-
are intended to produce a very low probability of age the Anenuma Bridge. Tamura et al. (1973) has
failure during the design life. undertaken post-earthquake inspection revealing
cracks near the top of the piles, and over 2 ft of lat-
eral displacement and as much as 4 in of settlement
2.2 Observation of earthquake events
of the bridge.
Case histories of observed reinforced and The 1978 Off-Miyagi Prefecture Earthquake re-
prestressed concrete piles damage and failure during sulted in a number of cases of damage to prestressed
global major earthquakes are presented as a repre- concrete piles, which were principally caused by
sentative survey in the pile foundation problems. earthquake-induced vibration of the superstructure
The cases are described with extensive indications (Sugimura 1981).
of the pile-to-pile cap performance during strong The Loma Prieta Earthquake was occurred on
shaking and insight into modes of behaviour and 17th October 1989 with the magnitude of 7.0 causing
failure. the impressive failure of many pile-supported struc-
The Niigata Earthquake was the second major tures. It was observed that piles along an alignment
earthquake of 1964 with the magnitude of 7.3 result- that transitioned from stiff to soft foundation soils,
ing widespread soil liquefaction related to damage the site response and structural connection details
and numerous failures of pile supported structures. were the principal failure mechanism. Yashinsky
The 7.2 m long concrete piles of 0.18 m diameter (1998) provided a comprehensive summary of dam-
lost bearing capacity due to liquefaction, and the age to highway systems in the Loma Prieta Earth-
structure of Saiseikai Hostpital tilted and cracked quake such as at the Oakland Outer Harbor Pier 7,
(Kishida 1966). 16 in square prestressed concrete batter piles failed
at or near the connection to the pile cap. It has been
noted that soil liquefaction did not contribute to the
failure, as upper foundation soils comprising soft
clays and organic, with some alluvial sands present.
Similar to severe damage over a large area caused by
the Loma Prieta Earthquake is the 1991 Costa Rica
Earthquake with the magnitude of 7.5 that resulted
soil liquefaction relating to collapse of several pile-
supported bridges. As reported by Priestley et al.
(1991) two of the three spans on the Rio Viscaya
Bridge collapsed due to severe abutment rotation,
a. Inelastic lateral deformation at b. Plastic hinges and buckling
pile distress, and failure of an interior support, also
pile-to-pile cap interface occurred within soil layers
producing from extensive soil liquefaction.
The 1995 Hyogoken-Nanbu (Kobe) Earthquake
with the magnitude of 7.2 was the most destructive
earthquake over 60 years to strike Japan. It was di-
rectly hit on a major metropolitan area that damaged
too many pile foundation systems. The most devas-
tated structural failure during the Kobe Earthquake
was the collapse of an elevated section of the pile-
supported Hanshin Expressway. Mizuno et al.
(1996) has undertaken a survey over more than 30
cases of pile damage observed in precast concrete,
cast-in-place concrete, and steel pipe piles. Damage
patterns consisted of separation between piles and
c. Pile head released from pile d. Damage at pile-to-pile cap
pile caps, damage near the pile head, and damage at
cap connection
deeper portions of piles as shown in Figure 2c and
Figure 2. Pile foundation damage due to strong earthquakes 2d.
(Hamada 1991; Mizuno 1987).
10
Electronic Journal of Structural Engineering, 6 (2006)
11
Electronic Journal of Structural Engineering, 6 (2006)
Harries and Petrou (2001) undertook experimen- bedded in the cast-in-place pile cap. In the headed
tal tests at the University of South Caroline Struc- embedment (with treatment), pile strands confined
tures Laboratory. Two 18 in. (450 mm) square by 18 with round reinforcement are exposed and embed-
in (5.49 m) long piles were fabricated simultane- ded in the cast-in-place pile cap.
ously in a 40 ft (12.2 m) prestressing bed. In this ex- In this paper, prestressed concrete piles manufac-
periment, a detail connection recommended by tured in Indonesia (Teguh et al. 2003a) and two pile
Sheppard (1983) was adopted where the pile was units tested by Harries and Petrou (2001b), were re-
simply embedded in the pile cap without any treat- viewed and the validity of their hypotheses was rig-
ment so called plain embedment (i.e., no static bars). orously investigated through comparison of the ob-
The connection details used in the first three ex- served and predicted response from linear to
perimental test models of pile-to-pile cap connec- nonlinear behaviour.
tions were based on recommendations by the New
Zealand and Caltrans standards (Caltrans 1990;
4.1 Analytical approach
Standard 1982). The objectives of the studies were
to check the capabilities of pile-pile cap connections To determine the capacity of a plain pile-to-pile cap
to resist large inelastic deformations caused by cy- connection (Figure 3a), it is assumed that a rigid
clic lateral loading. body (pile) embedded in cast-in-place concrete
monolith (pile cap) and based on mobilization of an
internal moment arm between bearing forces Cf and
3 IDENTIFIED GAPS/WEAKNESSES IN Cb as shown in Figure 3b will be utilized. A para-
CURRENT APPROACH bolic distribution of bearing stresses is assumed for
A current state-of-practice design and analysis ap- Cb, and Cf is computed by a uniform stress equal to
plication of the soil-pile interaction considered in the 0.85fc’. The bearing stresses are distributed over the
pile-to-pile cap connections is a complex soil- width of the embedded pile, b. Based on these as-
structure interaction of the pile foundation system sumptions and calibrating the calculated stresses
and not well developed. The unavailability of stan- against experimental data, the required embedment
dardized and validated analysis techniques, and the length, Le, may be determined from Equation 1,
conservative perception, designers routinely ignore where a is the shear span of the pile (distance from
or greatly simplify the present of pile foundations in pile cap to assumed point of zero moment) and β1 is
their analyses. the concrete stress block factor defined in ACI 318-
A special challenge of soil-structure interaction 02, Section 10.2.7.3 (A.C.I. Committee 318 2002) as
problems is in dispute over two disciplines, geotech- presented in Equation 2. The shear span can be in-
nical and structural engineering, and the analysis is creased by an amount equal to the concrete cover, c,
frequently broken into two parts rather than ad- to account for possibility spalling of the soffit of the
dressed in a holistic manner. In fact, a geotechnical pile cap as shown in Figure 3b. The value of b’ is
engineer idealizes a complex multimode superstruc- given by Mattock and Gaafar as the width of the
ture as a single degree of freedom oscillator; while
the structural engineer often represents the poten-
tially nonlinear soil-pile interaction with a simple
linear spring. In this manner, nonlinear system inter-
action between the superstructure and substructure is
artificially prevented. The diverse and non-
standardized design approaches are basically in-
tended to illustrate the lack of professional consen-
sus and the gap between the current state-of-practice
and the current state-of-the-art. These approaches
are also considered as creative applications of lim-
ited tools to complex problems.
4 PRELIMINARY ANALYSIS
This section presents preliminary analysis of pile-to- Figure 3. Analytical approach for determining pile capacity
pile cap connections focusing on two types of con- plain embedment.
nections, i. e., plain embedment and headed embed-
ment, to improve the capacity of the pile-to-pile cap element into which, in this case, the pile is embed-
connections. In the plain embedment (without treat- ded (Mattock and Gaafar 1982).
ment), the prestressed concrete pile is simply em-
12
Electronic Journal of Structural Engineering, 6 (2006)
Using a slightly different assumed stress distribu- 4.2 Linear finite element analysis
tion, Marcakis and Mitchell (1980) proposed Equa- The study continued with a review of modelling as-
tion 3 to determine the embedment length, Le. This sumptions to assess the effect of varying the degree
expression has also been calibrated against experi-
of structural complexity. The most comprehensive
mental data, where e is the eccentricity from the
form of analysis for reinforced concrete members
point of zero moment to the centre of effective em- uses the finite element (FE) method where individ-
bedment (Figure 3). They define b’ based on a strut- ual bars and elements are separately modelled. A fi-
and-tie approach as being effective width to assumed nite element method allows satisfactory simulation
“tie” steel, limited by a value of 2.5b (Marcakis and of test results, provided accurately defined constitu-
Mitchell 1980). tive models are used. A fixed base pile cap acting as
⎡ ⎤
0 . 66 ⎢ 0 . 58 − 0 . 22 β ⎥ a simple cantilever column was therefore employed
⎛ b' ⎞ in the model.
V u = 4 .5 f c' ⎜ ⎟ β 1 bL e ⎢ 1
⎥
⎝b ⎠ ⎢ 0 . 88 + a ⎥ (1)
A three dimensional (3D) finite element analysis
⎢ A e − c ⎥⎦
⎣ was performed to model the behaviour of the pile-to-
pile cap connection. The objectives of this modelling
For fc’ ≤ 4000 psi (27.6 MPa), β1 = 0.85 and were to determine elastic stress distribution and
for fc’ > 4000 psi (27.6 MPa), 0.65 ≤ β1 ≤ 0.85, load-displacement response of the pile-to-pile cap
where: connection due to axial and simulated seismic loads.
A linear static finite element analysis as initial stage
⎛ f c' − 4000 ⎞
β1 = 0.85 − 0.05⎜⎜ ⎟⎟ of elastic modelling was developed to simulate the
(2)
⎝ 1000 ⎠ seismic behaviour.
The two selected pile units (Harries and Petrou
In addition, the nominal moment capacity of the
2001b) presented in Table 1 to 3 respectively was
piles corresponding to an axial load is predicted us-
analysed using the structural analysis software
ing plane section analysis program RESPONSE- SAP2000 (Wilson 1996). Two element types were
2000 (Bentz 2001).
used for the finite element discretisation of the mod-
0.85 f c b' (A e − c ) els. The concrete pile-to-pile cap was meshed (mod-
Vu = elling surface delineation lines) using a special solid
3. 6 ⎛ A e − c ) ⎞ (3)
1+ ⎜ + c + a⎟ element type in order to easily perform the stress
A e − c) ⎝ 2 ⎠ concentration or failure of concrete in crack-
ing/crushing. Strands and reinforcing bars used in
Curves generated from Equations 1 and 3 are pre-
the pile and pile cap were meshed using truss ele-
sented in Figure 4 as a comparison of the shear and
ments with two different materials (i.e., strands and
moment capacities of the embedment for varying
reinforcing bars).
embedment length and having varying square pile
sizes manufactured in Indonesia (Figure 4). It should Table 1: Unit test variables of pile-to-pile cap connections
be noted that the results from Equations 1 and 3 are Pile unit number Unit P1 Unit P2
similar. It can be summarized that equation proposed Initial prestressing steel 1.394x109 1.394x109
by Marcakis and Mitchell tends to result is slightly (constant) N/m2 N/m2
more conservative embedment capacity values than Applied axial load (in-
the values suggested by the PCI design handbook. crement): assumed as 4.260x106 4.260x106
2
pressure load over the N/m N/m2
pile surface
Maximum lateral loads 1.112x105 N 9.600x104 N
(monotonic & cyclic)
Pile reinforcement:
1. Low relaxa- 12.5 mm 12.5 mm
tion strand (1/2”) (1/2”)
tendon 7 mm 7 mm
2. Wire plain (0.276”), R12 (0.276”), R12
spiral
Pile cap reinforcement: 22 mm 22 mm
1. Main (0.875”), D22 (0.875”), D22
2. Transverse D10 - 152 mm D10 - 152 mm
Pile dimension (B) 0.45 x 0.45 m 0.45 x 0.45 m
Figure 4. Embedment capacity predictions of varying pile sizes Pile cap dimension 2.14 x 0.92 x 2.14 x 0.92 x
manufactured in Indonesia (Teguh et al. 2003a). 2.14 m 2.14 m
Pile embedment length 0.61 m (1.3 B) 0.45 m (B)
13
Electronic Journal of Structural Engineering, 6 (2006)
600
400
Input acceleration (g)
200
0
-200 1 21 41 61 81 101 121 141 161 181 201
-400
-600
Figure 6. A comparison of load-deformation response.
-800
As seen there are crack damage propagating along Time (second)
the tensile fibre as well as stress concentrations oc-
curred at the interface between the pile head and pile Figure 7 Ground acceleration input (Kobe Earthquake, 1995).
cap and these stress concentrations also occur at the
opposite face when the lateral load is reversed.
14
Electronic Journal of Structural Engineering, 6 (2006)
-60
Time (second)
16
Electronic Journal of Structural Engineering, 6 (2006)
17
Electronic Journal of Structural Engineering, 6 (2006)
The use of finite element models is effective in New Zealand Standard. (1982). "Code of Practice for the De-
capturing global and local behaviour of pile to pile sign of Concrete Structures, NZS 3101, Part 1: 1982."
Standard Association of New Zealand, Wellington.
cap connections Additional investigation into the in- Nogami, T., Ed. (1987). Dynamic Response of Pile Founda-
fluence of bond-slip under cyclic loading is required. tions--Experiment, Analysis, and Observation, Proceedings
Ideally, effective tools and guidelines should be de- of a session of the Geotechnical Engineering Division of
veloped to assist in the practical and efficient design the American Society of Civil Engineers in conjunction
of pile-to-pile cap connections. with the ASCE Convention in Atlantic City, ASCE, New
Jersey,185 p.
Pam, H. J. (1988). "Seismic Performance of Prestressed Con-
crete Piles and Pile-Pile Cap Connections," Ph.D Thesis,
7 REFFERENCES University of Canterbury, Christchurch, New Zealand.
A.C.I. Committee 318. (2002). Building Code Requirements Pam, H. J., and Park, R. (1990a). "Flexural Strength and Duc-
for Structural Concrete (ACI 318-02) and Commentary tility Analysis of Spirally Reinforced Prestressed Concrete
(ACI 318R-02), Piles." Prestressed Concrete Institute Journal, Vol. 35, No.
Bentz, E. (2001). "User Manual: Response-2000, Shell-2000, 4, July/August 1990, pp. 64-83.
Triax-2000, and Membrane-2000." Version 1.1. Pam, H. J., and Park, R. (1990b). "Simulated Seismic Load
Building Research Institute. (1996). "A Survey Report for Tests on Prestressed Concrete Piles and Pile-Pile Cap Con-
Building Damages due to The 1995 Hyogo-ken Nanbu nections." Prestressed Concrete Institute Journal, Vol. 35,
Earthquake." Ministry of Construction Japan. No. 6, November/December 1990, pp. 42-61.
Caltrans. (1990). Bridge Design Specifications, California De- Priestley, M. J. N., Seible, F., and Calvi, G. M. (1996). Seismic
partment of Transportation, Sacramento, California Design and Retrofit of Bridges, Wiley, New York
Carr, A. J. (2001). "RUAUMOKO Program: Inelastic Dynamic Priestley, M. J. N., Singh, J., Youd, T., and Rollins, K. (1991).
Analysis (3D Version)." 3-Dimensional Version(University "Costa Rica Earthquake of April 22, 1991 Reconnaissance
of Canterbury, New Zealand). Report." Publications 91-02, Earthquake Engineering Re-
de Witte, F. C., and Kikstra, W. P., Eds. (2002). DIANA Finite search Institute, pp. 59-91.
Element Analysis, User's Manual: Release 8.1, TNO Build- Sheppard, D. A. (1983). "Seismic Design of Prestressed Con-
ing and Construction Research, Delft, The Netherlands crete Piling." Prestressed Concrete Institute Journal, V. 28,
de Witte, F. C., and Kikstra, W. P., Eds. (2005). DIANA Finite No. 2, March-April 1983, pp. 20-51.
Element Analysis, User's Manual: Release 9.0, TNO Build- Silva, P. F. (1998). "Experimental and Analytical Models to
ing and Construction Research, Delft, The Netherlands Predict the Response of Pile to Pile Cap Connections Under
Hamada, M. (1991). "Damage of Piles by Liquefaction- Simulated Seismic Loads," Ph.D dissertation, University of
Induced Ground Displacements." The Third US Conference California, San Diego, California.
Lifeline Earthquake Engineering, ASCE, Los Angeles, US, Silva, P. F., Seible, F., and Priestley, M. J. N. (2001). "Influ-
pp. 1172-1181. ence of Strand Development Length in Formation of Plastic
Harries, K. A., and Petrou, M. F. (2001a). "Behaviour of Pre- Hinges in Prestressed Piles." PCI Journal, V. 46 No.
cast, Prestressed Concrete Pile to Cast-in-Place Pile Cap 3(May-June), pp. 76-89.
Connections." PCI Journal( July-August), pp. 82-92. Standard, N. Z. (1982). Code of Practice for The Design of
Harries, K. A., and Petrou, M. F. (2001b). "Behaviour of Pre- Concrete Structures, NZS 3101, Part 1: 1982, Standards
cast, Prestressed Concrete Pile to Cast-in-Place Pile Cap Association of New Zealand, Wellington
Connections." PCI Journal(July-August), pp. 82-92. Sugimura, Y. (1981). "Eathquake Damage and Design Method
Joen, P. H., and Park, R. (1990). "Simulated Seismic Load of Piles." Stockholm, pp. 865-868.
Tests on Prestressed Concrete Piles and Pile-Pile Cap Con- Tamura, Fujiwara, T., and Morishige, R. (1973). "Damage of
nections." Prestressed Concrete Institute Journal, V. 35, pp. Rigid Frame Bridges in the Off Tokachi Earthquake 1968."
42-61. Japan Earthquake Engineering Symposium 1973, Tokyo,
Kishida, H. (1966). "Damage of Reinforced Concrete Build- Japan, pp. 147-154.
ings in Niigata City with Special Reference to Foundation Teguh, M., Duffield, C. F., and Mendis, P. A. (2003a). "Seis-
Engineering." Soils and Foundations, JSSMFE, Vol. 6, No. mic Performance of Piles Designed and Constructed in In-
1, pp. 71-88. donesia." The Ninth East Asia-Pacific Conference on Struc-
Marcakis, K., and Mitchell, D. (1980). "Precast Concrete Con- tural Engineering and Construction, Bali, Indonesia, 16-18
nections With Embedded Steel Members." PCI Journal, V. December 2003, pp. GPE-17-22.
25, No. 4(July-August 1980), pp. 88-116. Teguh, M., Hutchinson, G. L., Mendis, P. A., and Duffield, C.
Mattock, A. H., and Gaafar, G. H. (1982). "Strength of Em- F. (2003b). "Introduction to Seismic Performance of
bedded Steel Sections as Brackets." ACI Journal, V. 79, Prestressed Concrete Pile-to-pile Cap Connections." De-
No. 2, pp. 83-93. partment of Civil and Environmental Engineering, Univer-
Mendis, P. A. (2001). Design of High-Strength Concrete Mem- sity of Melbourne.
bers, Engineers Australia Pty Limited, Melbourne, Austra- Wilson, E. L. (1996). "SAP2000 Integrated Finite Element
lia Analysis and Design Structures." CSI Computers & Struc-
Mizuno, H. (1987). "Pile Damage During Earthquake in Japan tures Inc., Berkeley, California.
(1923-1983)." Proceedings of a session of the Geotechnical Yashinsky, M. (1998). "The Loma Prieta, California, Earth-
Engineering Division of the American Society of Civil En- quake of October 17, 1989-Highway Systems." Profes-
gineers in conjunction with the ASCE Convention in Atlan- sional Paper 1552-B, USGS, Washington.
tic City, New Jersey, pp. 53-78.
Mizuno, H., Iiba, M., and Hirade, T. (1996). "Pile Damage
During the 1995 Hyogoken-Nanbu Earthquake in Japan."
The 11th World Conference on Earthquake Engineering
(WCEE), Acapulco, Paper No. 977.
18