Check List For CONCRETE Block Works

This document is a check list for concrete blinding works between Hunan General Contracting L.L.C. and China Harbour Engineering Co.L.L.C. for a civil works project. The check list outlines preliminary checks of materials, setting out of the first course of block work, and execution checks to ensure proper installation of masonry openings, lintels, wall ties, reinforcement mesh, control joints, pointing, plumbing of walls, and completion of MEP works. The check list requires sign off from the subcontractor, contractor, and Dorsch representative at each stage of work.

Uploaded by

Yash Sharma
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
2K views1 page

Check List For CONCRETE Block Works

This document is a check list for concrete blinding works between Hunan General Contracting L.L.C. and China Harbour Engineering Co.L.L.C. for a civil works project. The check list outlines preliminary checks of materials, setting out of the first course of block work, and execution checks to ensure proper installation of masonry openings, lintels, wall ties, reinforcement mesh, control joints, pointing, plumbing of walls, and completion of MEP works. The check list requires sign off from the subcontractor, contractor, and Dorsch representative at each stage of work.

Uploaded by

Yash Sharma
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

China Harbour Engineering Co.L.L.C.

CHECK LIST FOR CONCRETE BLINDING WORKS

SUBCONTRACTOR : HUNAN general contracting L.L.C CONTRACTOR: CHEC

SECTION OF WORK : CIVIL LACATION :

LEVEL : BELOW GROUND LEVEL

CHECKED BY DATE
STATGE ITEM
HGC CHEC DORSCH
Concrete blocks & samples approved
Mortar mix approved
Block work accessories approved
1.Preliminary
Checks Latest drawing revision used
Method statement, QCP, ITP approved
Check manufacturer’s test certificate for cement, sand and
Masonry Blocks
Set-out (position) and profile with one course of block work
2.setting out installed
Line, level, Alignment, Plumb, dimensions are correct
Gauging and mixing of mortar as per the mortar mix
proportions.
Damp proof course installed where required
Check type and size of blocks are at intended locations of
use.
Bed mortar joints are uniform, horizontally leveled, vertical
joints are lined.
Check tolerances for 3.0 m length on the wall should
be within 3mm and plumb within 6mm.
Masonry openings are correct for hollow metal
3.execution frames, doors & windows, square, plumb, straight
Door and window lintels correct- level and size
Check wall ties, Anchors, Horizontal reinforcing mesh
installed correct- type and spacing
Control joints- size and type correct
Pointing of bed joints
Check walls- Plumb, line, alignment correct
Chasing of block walls or formation of holes
Ensure MEP works/ services completed

FOR S/C QA/QC : FOR CONTRACTOR QA/QC : FOR DORSCH REP :

Name: Sign: Name: Sign: Name: Sign:

Date : Date : Date :