Estimate of The Proposed Godown at Feroke: SI No Description No. Length Breadth Depth Quantity Amount

The document provides an estimate for the proposed godown in Feroke. It lists 19 line items with descriptions of work like excavation, piling, concrete work, masonry, plastering and reinforcement. The quantities, rates and amounts are specified for each item. The grand total for all the work is estimated to be Rs. 22,10,840.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
80 views

Estimate of The Proposed Godown at Feroke: SI No Description No. Length Breadth Depth Quantity Amount

The document provides an estimate for the proposed godown in Feroke. It lists 19 line items with descriptions of work like excavation, piling, concrete work, masonry, plastering and reinforcement. The quantities, rates and amounts are specified for each item. The grand total for all the work is estimated to be Rs. 22,10,840.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

ESTIMATE OF THE PROPOSED GODOWN AT FEROKE

SI
No Description No. Length Breadth Depth Quantity Amount
Earth work excavation in ordinary
soil including all cost and
conveyence etc complete
1
3
Say 55.00 @ 350 /M 19250.00

Chipping and chiseling existing pile


for required depth as per structural
drawing including cost and
conveyance of all materials and
2 labour charges,removal of debris
from site etc. complete.

Say 18.00 @ 1,500 /RM 27000.00

P.C.C 1:4:8 Using 40 mm nominal


size b/s including all cost
3 conveyance etc complete.
3
Say 6.00 @ 6,700 /M 40200.00

Dry rubble masonry for foundation


including all cost and conveyence etc
4 complete.
3
Say 5.00 @ 2,750 /M 13750.00

Random rubble masonry in C.M 1:6


for basement including all cost and
5
conveyence etc complete.
3
Say 3.00 @ 3,700 /M 11100.00

R.C.C M20 Using 20 mm nominal


size b/s including all cost
6 conveyance etc complete.
3
For Pilecap Say 10.00 @ 8,400 /M 84000.00

R.C.C M20 Using 20 mm nominal


size b/s including all cost
7 conveyance etc complete.
3
For Plinth beam Say 11.00 @ 9,300 /M 102300.00

page1of3
ESTIMATE OF THE PROPOSED GODOWN AT FEROKE

SI
No Description No. Length Breadth Depth Quantity Amount
Earth filling in basement with
available soil including all cost and
conveyence etc complete
8
3
Say 205.00 @ 290 /M 59450.00

P.C.C 1:4:8 Using 40 mm nominal


size b/s including all cost
9 conveyance etc complete.

3
Flooring Say 46.00 @ 5,150 /M 236900.00
R.C.C M20 Using 20 mm nominal
size b/s including all cost
10
conveyance etc complete.
3
For Column Say 12.00 @ 12,350 /M 148200.00

Laterite masonry 1:6 including all


11 cost and conveyance etc complete.
3
Say 93.00 @ 6,550 /M 609150.00

Solid block masonry 1:6 including all


12 cost and conveyance etc complete.
3
Say 4.00 @ 7,700 /M 30800.00

R.C.C M20 Using 20 mm nominal


size b/s including all cost
conveyance etc complete.
13
For Tie beam
3
Say 6.00 @ 12,350 /M 74100.00

R.C.C 1:1.5:3 Using 20 mm nominal


size b/s including all cost
14 conveyance etc complete.
3
For Roof Slab Say 2.00 @ 10,750 /M 21500.00

Plastering in C.M 1:4 including all


15 the cost conveyance etc complete.
2
For inside wall Plastering Say 594.00 @ 265 /M 157410.00

page2of3
ESTIMATE OF THE PROPOSED GODOWN AT FEROKE

SI
No Description No. Length Breadth Depth Quantity Amount
Plastering in C.M 1:3 9 mm thick
including all cost and conveyance etc
16 complete.
2
For Ceiling Plastering Say 8.00 @ 250 /M 2000.00

Plastering in C.M 1:4 including all


17 the cost conveyance etc complete.
2
For wall outside Plastering Say 554.00 @ 300 /M 166200.00

Plastering in C.M 1:3 9 mm thick


including all cost and conveyance etc
18 complete.
2
For Floor Plastering Say 447.00 @ 390 /M 174330.00

REINFORCEMENT:-
Supply, Straighten, Handle, bend
,crank, fix and tie in position as per
the structural drawing of consultant
in all R.C.C items of different work
and different level including cost of
GI binding wire 18 BWG complete
(on actual length measurements of
fabricated steel work including
19 authorized lappages only at
theoretical weights for the different
sections) at all levels Hi yield
strength deformed bars.

Say 4,000.00 @ 58.30 /Kg 233200.00

Note : Steel - Tulsyan, Cement - Chettinad

Grand Total 2210840.00


( Rupees Twenty Two Lakhs Ten Thousand Eight Hundred and Forty only )