This consultant’s report does not necessarily reflect the views of ADB or the Government concerned, and
ADB and the Government cannot be held liable for its contents. (For project preparatory technical
assistance: All the views expressed herein may not be incorporated into the proposed project’s design.
GOVERNMENT OF REPUBLIC INDONESIA
MINISTRY OF PUBLIC WORKS
DIRECTORATE GENERAL OF WATER RESOURCES
January 2007
Revision 1
Citarum Integrated Water Resource Management Project
Report on Roadmap and Program Development
Contents
Abbreviations
Currency
Acknowledgements
1 Background................................................................1
1.1 Introduction 1
1.2 Project History 1
3 Approach....................................................................6
Abbreviations
ADB Asian Development Bank
AMDAL Indonesian system of environmental assessment
AP affected person
AWP annual work programs
BOD biological oxygen demand
CC Case Composer
CPFPG Compensation Policy Framework and Procedural Guidelines
CRB Citarum River Basin
CSP Country Strategy and Program
DGWR Directorate General of Water Resources of the Ministry of
Public Works
DST decision support tool
EA Executing Agency
EARF Environmental Assessment and Review Framework
ETC East Tarum Canal
GOI Government of Indonesia
GRDP non-government organisation
IA Implementing Agency
ICWRMP Integrated Citarum Water Resources Management Program
IWRM integrated water resources management
JICA Japan International Cooperation Agency
MCV Model Conservation Village
MFF Multi-Tranche Financing Facility
MOA Multi-Objective Analysis
MPW Ministry of Public Works
NGO non-government organisation
NTC North Tarum Canal
NWRSC National Water Resources Steering Committee
O&M operation and maintenance
PA Protected Area
PES payments for environmental services
PIM participatory irrigation management
PIU Project Implementation Units
PJT-II Jasa Tirta Public Corporation II
PMCU Program Management and Coordinating Unit
ppm parts per million
PPTA Project Preparatory Technical Assistance
PROKASIH Indonesian clean rivers program
PWRS Provincial Water Resources Service
ROW right-of-way
RPMCU Roadmap Planning Monitoring and Coordination Unit
RRP Report and Recommendation of the President
SEA strategic environmental assessment
TA technical assistance
TOR Terms of Reference
WA water allocation
WLM waste load model
WQ water quality
WTC West Tarum Canal
WWTP wastewater treatment plant
Citarum Integrated Water Resource Management Project
Report on Roadmap and Program Development
Currency
Currency Unit – Indonesian rupiah (IDR)
IDR1.00 = $0.00011
$1.00 = IDR9,100
Acknowledgements
This report, which describes the processes, activities and results of PPTA
Phase 3 the, is effectively the mission report of the Phase 3 Team leader.
Each of the international team members have prepared their own mission
report. However, significant contributions to this report were made by team
members: Ramon Abracosa, Roger Jackson, Jeremy Bird, Rieks Toxopeus,
Teunis op ten Noort, Tan Bock Thiam, Darrell Kitchener and Romeo Cleto.
In addition, excellent support to the Team Leader was given by the
Indonesian consultant staff, especially Tony Bambang Trihartanto and Sri
Hernowo, and the project office staff.
Finally, the enthusiasm, guidance and tireless efforts of the ADB Mission
Leader, Chris Morris helped the Team Leader and the rest of the Phase 3
team continue on to the end, when at times the task seemed impossible.
Citarum Integrated Water Resource Management Project Page 1
Report on Roadmap and Program Development
1 Background
1.1 Introduction
The water resources of the rivers and groundwater systems in the Citarum
River Basin are critical to social and economic development of the country.
They are essential for urban and industrial development (particularly in
Jakarta and Bandung areas) including export industry, agricultural
production through major irrigation systems, rural water supplies, electricity
generation though hydropower, and fisheries. While the water resources of
the Citarum River Basin are relatively abundant, competition for these
resources has increased significantly over the past 20 years leading to a
situation of acute water stress and depletion of aquifers in some places.
Rapid urbanization has significantly increased the exposure to flood risk.
Environmental degradation has reached a level that compromises public
health and livelihoods, particularly for the urban and rural poor, and incurs
additional economic and financial costs related to the source of bulk water
supply and its treatment. A management focus on integrated water
resources management (IWRM) and sustainability of the water resource has
been emphasized in the 2004 Water Law. The Water Law introduces the
concept of management within the boundaries of a river basin and reflects
the principles of decentralization and devolvement of authority to local levels
as promoted by the program of regional autonomy. Preparations for its
implementation are at a preliminary stage.
Water has been a major area of the Asian Development Bank’s (ADB)
assistance to Indonesia, totalling over $1.5 billion in loans and technical
assistance (TA). Improving sustainable use of water resources in-line with
the ADB “Water for All” policy, together with a strong commitment to build
capacity of local government agencies, are key elements of ADB’s
operational partnership. In particular this partnership stresses the need to
continue implementation of policy reforms, overcome weak coordination
among agencies and develop guidance for cooperative working.
Sustainability of economic growth and pro-poor development are key pillars
of the Country Strategy and Program (CSP) that will be complemented by
strengthening capacity for IWRM in the basin.
1
The original name was the Integrated Citarum Water Resources Management Project.
However, with the change in funding modality and broader scope now envisioned, the
term “program” is considered more appropriate.
Citarum Integrated Water Resource Management Project Page 2
Report on Roadmap and Program Development
2
Integrated Citarum Water Resource Management Project: Final Report for Phases 1
and 2, Nippon Koei, March 2006.
Citarum Integrated Water Resource Management Project Page 3
Report on Roadmap and Program Development
7/2004. These include the establishment of Basin Water Council, for cross-
sectoral coordination, and an implementing unit for water resources
planning and management, or Balai Besar. This is expected to have a
significant impact on the functioning of existing agencies operating in the
basin.
These circumstances led ADB to approve a third phase of the PPTA that
would:
1. Review the work done in the first two phases of the project in the light of
the changed circumstances described above;
2. Assist the stakeholders in the basin determine suitable objectives for
water resource management in the basin over the projected life of the
loan (now generally agreed to be 15 years):
3. Develop a roadmap (to the year 2021) that would set out a timetable of
suitable interventions (projects) to achieve the agreed objectives, noting
that not all of these would be necessarily funded by ADB, but may be
executed with the financial assistance of other donors, or indeed with
the government’s own funds;
4. Determine which interventions might be funded by ADB under the MFF
loan, and what should be included in the first and succeeding tranches;
5. Assist the government to prepare, to the greatest possible extent given
the limited time available, a number of priority projects that will be
included in the first tranche.
6. Assist in the preparation of the RRP for loan fact-finding, appraisal and
eventual approval.
Accordingly, a number of international and national consultants were
recruited to undertake this work, some through Nippon Koei, and some
directly by ADB. Nippon Koei continued to provide administrative, logistical
and technical support. The third phase commenced on 17 July 2006. This
report documents the approach and results of the Phase 3 work, which was
completed on 15 December 2006.
Citarum Integrated Water Resource Management Project Page 4
Report on Roadmap and Program Development
The following national consultants were also employed as part of the project
team:
Citarum Integrated Water Resource Management Project Page 5
Report on Roadmap and Program Development
In addition, the following ADB staff made a significant contribution to the TA:
Name Position
3 Approach
It was clear that a significant amount of valuable work had been done in
Phases 1 and 2, and even though circumstances had changed somewhat,
the bulk of this was like to still be relevant. A primary consideration then was
to maximise the use of that previous work, so as to avoid duplication of
effort.
In addition, the approach taken in Phase 3 was largely to apply a strategic
planning approaches that basically asks three questions:
Where do we want to go (with water resource management in the
basin)?
Where are we now (that is, what are the existing issues/problems)?
How can we get from where we are now to where we want to go (the
“road” we need to take)?
This can be achieved using the following “vision-oriented” approach:
Reaffirm and more clearly define a shared vision of stakeholders for the
future of the Citarum River Basin (to the year 2020);
Compare the present status of water resources in the basin to the
vision, in order to identify the strategic direction that needs to be taken
(the “road” so to speak);
Formulate objectives in a number of key areas that would, if achieved,
lead to the fulfilment of the vision;
Develop a set of interventions (projects) the successful implementation
of which would achieve the objectives in each key area, incorporating as
far as possible the projects identified in Phases 1 and 2;
Design a set of “packages” of project that could be funded under the
proposed tranches under the MFF.
The relationship between the road map and the MFF needs to be clarified.
The road map attempts to cover all necessary (strategic) interventions in the
water sector required over the next 10 – 15 years. As such, it “belongs” to
GOI, not ADB, since ADB could not provide funding for all these
interventions. While ADB is likely to fund many of the interventions, through
the MFF and perhaps other funding modalities (for example, through grants
for technical assistance (TA) projects), other donors and GOI itself may (and
should) fund others. This is shown in Figure 1.
Citarum Integrated Water Resource Management Project Page 7
Report on Roadmap and Program Development
The process for roadmap and MFF development for the Citarum River Basin
is shown in Figure 2.
The Bekasi and Bandung regions are the most heavily populated and
urbanised. Bekasi essentially acts as a satellite city of Jakarta, absorbing
most of the industrial and population expansion to the east. The catchment
of the Bekasi River is rapidly transforming into numerous housing
subdivisions and industrial estates – with development pressure coming
from both the north (Jakarta) and south (Bogor). Paddy fields to the north of
Bekasi are also being converted to residential and industrial uses.
The Bekasi area in particular has been experiencing rapid population growth
and urbanisation. A 2000 census shows that 22% of Bekasi City residents
and 18.5% of Bekasi District residents are migrants that have moved into
the area only within the last five years of the census.
Industrial locations are generally interwoven with settlements and there is
no clear zoning or separation of these land uses in the region. Although
settlements and industry make up only 8.2% of the program area, their
impact on land use change in the region is significant. The mixed industry-
settlement land uses are clustered along a rapidly urbanising corridor
defined by the recently completed expressway linking Jakarta and Bandung,
which passes through Bekasi, Karawang and Purwakarta. The arrowheads
in the urban corridor depicted in Figure 7 show the direction of urban sprawl
stimulated by the new highway corridor. In the coming years, urbanization
will take place both in the form of continued expansion toward the upper
catchments (in Bekasi and Bandung) and via a more recent but accelerating
expansion toward the coast in Karawang.
Citarum Integrated Water Resource Management Project Page 13
Report on Roadmap and Program Development
Bekasi City and Bekasi District, for example, are projected to grow in terms
of population by 20% in 2010, compared with Year 2005 figures (around 2
million each). Karawang’s population, too, is projected to grow from 1.97
million in 2005 to 2.15 million in 2010 (9% growth). Between 2000 and 2005,
Karawang’s population grew by 11%. In the Upper Citarum region
settlement areas increased from 25,000 ha in 1992 to 46,000 ha in 2001.
This corresponded with a 40% decline in paddy field areas, from 12,500 ha
in 1992 to 75,000 ha in 2001. As in Bekasi, the upper basin is experiencing
a rapid conversion of paddy fields into settlements.
The pattern of urbanisation in the region has a significant impact on the
water supply system, not only because of the projected increased demand,
but also because much of the domestic and industrial water supply to
Bekasi and Jakarta passes through the same corridor (West Tarum Canal).
Settlements and commercial establishments are gradually encroaching on
the canal easements, threatening both water quality and water supply
security.
The remaining forests cover only about 10.2% of the program area—
100,600 ha of primary forest, and 34,800 of secondary forest—far less than
the 30% mandated in the Forestry Law (#41, 1999). While nearly all of the
remaining primary forests are designated for protection and conservation,
secondary forests are still considered as production forests where
harvesting of forest products and timber is allowed. Much of the remaining
primary forest is in fragmented condition, reducing their viability as an
ecosystem and making them vulnerable to continuing encroachment and
conversion for upland farming. Creating corridors to link these fragmented
forests is important for ensuring their ability to support biodiversity.
Citarum Integrated Water Resource Management Project Page 15
Report on Roadmap and Program Development
5.2 Poverty
The situation regarding poverty and access to water supply and health
facilities in the 15 districts and municipalities that lie fully or partially in
the Citarum river basin, based on SUSENAS 2004 data, can be
summarised as follows:
A poverty headcount of 2.8 million or 9.7% of the basin population with
poverty levels of the total populations ranging from 1.5% to 4.8% in the
municipalities (which are totally urban) and 2.9% to 26.4% in the
districts (which have a mix of urban and rural populations). In some
districts poverty is more prevalent in the urban population compared to
the rural population, in other districts it is the reverse—there is no clear
pattern.
Access to clean water in the municipalities varies 77-97% of total
population (poor and non-poor), whereas in the districts it is lower and
lies in the range 37-87%; coverage is significantly lower amongst the
poor in all areas except Bekasi and Cianjur where levels between poor
and non-poor are similar.
Coverage of households with toilets in the municipalities varies 94-100%
of total population, whereas in the districts it is 53-89%; in many areas
coverage is significantly lower amongst the poor, but in others (Bekasi,
Depok, Cianjur and Subang) coverage is similar between poor and non-
poor.
The comparison between poverty and coverage of households with
clean water and household with toilets shows that there is a general
trend between low poverty and high coverage of water and toilet
facilities, and higher poverty and lower coverage of facilities (see Figure
9).
Citarum Integrated Water Resource Management Project Page 16
Report on Roadmap and Program Development
120
100
Water coverage
% Coverage 80
60 Toilet coverage
40
Linear (Water
20 coverage)
0 Linear (Toilet
coverage)
0 10 20 30
% Poverty
5.7 Flooding
Flooding is a consequence mainly of changes in the river flow regime, in
turn caused by changes in watershed conditions. As water retention
capacity of the river catchments is reduced by denudation and land
conversion for urban development, flood peaks have increased. As
mentioned above, the ratio of wet season peak flows to dry season low
flows in the upper basin has increased from 3.4 in 1992 to 7.3 in 2003. The
increased flood frequency and severity are also invariably associated with
destructive landslides and mud flows. In the upper basin (Bandung area),
recent severe flooding and mud flows occurred in February 2005 affected
an area covering 2,000 ha. The flooding submerged parts of the area for 7
days and up to 2 meters deep – 50,000 inhabitants had to be evacuated.
Flooding around Bandung has become more frequent and severe. Here,
however, there is no single cause. The problem is due to a combination of:
(i) watershed denudation, (ii) effects of past re-alignment/straightening of
the Citarum River (through cut-offs) which, while alleviating flooding
upstream, increase peak flows downstream, (iii) localized land subsidence
due to groundwater over-pumping that impair drainage, and (iv) clogging of
drainage canals and streams by garbage. Flood-prone areas around
Bandung are located in the south area of the city along the Citarum River.
Citarum Integrated Water Resource Management Project Page 20
Report on Roadmap and Program Development
lands. There have been seven attempts to ‘re-green’ parts of the Basin
since 1976. All these, including the recent Citarik Upland Plantation and
Land Development Project, have failed in this regard. It is widely
considered these failures are because projects have not sufficiently
educated villagers about the importance of their role in such activities, have
not empowered villagers and have tried to accomplish reforestation in short
time frames. In summary, watershed management as it relates to conserv-
ation of biodiversity, either directly or through improved habitat (land, water
and forest) management, ultimately depends in large part on engaging a
large number of villages in conservation efforts. Some feel that poverty is
the root cause of villagers disinterest in improving their stewardship of the
environment. Others consider it is because the population explosion and
subsequent urbanization and peri-urbanization have fragmented village
structures and organizations. This fragmentation has resulted in loss of
village ‘unity’ and subsequent lack of empowerment. This lack, coupled with
inadequate land tenure arrangements and access to land, offers villagers no
incentive to protect land.
3
Here private land refers to land that is covered by formal legal rights (hak milik), and
customary and traditional rights (adat or ulayat).
Citarum Integrated Water Resource Management Project Page 27
Report on Roadmap and Program Development
With regard to the dredging and removal of silt, an estimated 1.4 million m3
of silt and earth will be removed from WTC. Disposal of these dredged
materials is, however, a potential resettlement issue. Project authorities will,
and has actually done so in the past, stockpile re-usable dredged earth on
the embankments of WTC as a temporary staging area. Said re-usable
earth will be used in fortifying or fixing segments of the embankments
needing repair. On the other hand, un-suitable dredged materials, such as
silt, will be dumped in former river beds that came to be as a result of the re-
channelling of the river following the construction of the Curug Weir, the
Cibeet Weir, and the Cikarang Weir. Over the years, local residents have
developed these ex-river beds into productive farmlands using dredged
materials dumped thereat from previous maintenance activities for raising
and levelling the ground. The dumping of 1.4 million m3 particularly in the
ex-river beds will deprive farmers a cropping season, at the minimum.
The following resettlement issues have been identified and will have to be
addressed based on the Compensation Policy Framework and Procedural
Guidelines (CPFPG) developed with the assistance of the PPTA to be
adopted by the Government and concurred with by ADB: (i) use of the
shoulder of the inspection road for the temporary stock-piling of re-usable
dredged materials; (ii) loss of use of areas of the ex-river beds which
residents have made productive over the years with the planned dumping of
spoils thereat; (iii) acquisition of a number of structures on the
embankments and which are concentrated at bridges and road crossings,
including platforms on stilts above the water and which are used for toilet,
bath, and laundry; and (iv) possible disruption, if not total cutting-off, of the
water supply of individual households that tap water directly from the canals
with the use of rubber hoses.
There are associated social issues that need to be addressed in the system
improvement of WTC. These issues revolve around health and sanitation in
Citarum Integrated Water Resource Management Project Page 28
Report on Roadmap and Program Development
the locality and these are rooted to poverty. While for instance owners of
toilet and washing facilities in WTC will be compensated at replacement
cost for these structures, these affected persons (APs) and their
communities also need to be provided with alternative facilities that are
hygienic and that will last. The APs cannot be allowed to rebuild their
temporary toilet facilities in the waterway following completion of civil works
in WTC; it is not just the health of these APs that is at risk but also those of
water users in Jakarta. Another health issue that requires a sustainable
alternative with the clearing of WTC of obstructions concerns the need to
provide communities adjacent to the embankments with safe household
water. Water hoses connected to individual houses abound in the entire
stretch of the canal. The third health-related issue concerns the risk of
sexually-transmitted diseases (for example, HIV/AIDS) spreading during
rehabilitation works on WTC since sections of the inspection road at Bekasi
have many karaoke bars.
The aforementioned are called associated social issues because, while they
are not brought about directly by the project, these health and sanitation
concerns will worsen and might actually be exacerbated during the
execution of the rehabilitation works.
4
As distinct from project planning.
Citarum Integrated Water Resource Management Project Page 33
Report on Roadmap and Program Development
5
Concept Note: Institutional Support for Integrated Water Resources Management in the
6 Ci’s Basin
6
Similar to the one shown in Figure 18.
Citarum Integrated Water Resource Management Project Page 36
Report on Roadmap and Program Development
Irrigation Modernisation
5
– East Tarum Canal
{ } {
Irrigation Modernisation
6
– North Tarum Canal
{ } {
Productive
7
Reforestation
{ } | {
Integrated
8 Management of { } | |
Disaster
Upgrading of Water
9 Source (Upper { }
Cipunegara)
Upgrading of Water
10
Source (Cipancuh)
{ }
Upgrading of Water
11
Source (Ciherang)
{ }
Upgrading of Water
12
Source (Ciputarua)
{ }
Enhancement of
13
System Reliability
{ }
Integrated Erosion
14
Control } { {
Management of Water
15 Environment against { } { {
Domestic Effluent
Management of Water
16 Environment against { } { {
Industrial Effluent
Solid Waste
17
Management
{ } {
7
Integrated Water Management Plan for the Citarum River Basin, Java Irrigation
Improvement and Water Resources Management Project, Consultant’s Report, June
1997.
Citarum Integrated Water Resource Management Project Page 41
Report on Roadmap and Program Development
For all people in the basin to have access to adequate water supply and
sanitation.
Water Sharing To have an equitable water sharing arrangement among the upper and
the lower basin and transboundary water resources (water supply to
Jakarta).
To have clearly defined water rights for all authorised water users.
To have all conflicts over utilisation of the water resources of the basin
resolved quickly and satisfactorily.
Environmental To have comprehensive land use plans in place, and adhered to, in order
Protection to minimise the impacts of human activities on the environment.
Citarum Integrated Water Resource Management Project Page 42
Report on Roadmap and Program Development
Disaster Management To have effective disaster preparedness plans in place for floods and mud
flow events.
10 MFF Tranche 1
10.1 Selection Criteria
In developing a “package” of sub-projects for funding under Tranche 1 of the
MFF, the following criteria should be used.
The sub-projects should:
1. Have high government priority, and hence be included in the roadmap;
2. Together cover a range of key areas and not concentrate on a single
key area;
3. Together address upper basin, as well as lower basin water manage-
ment issues;
4. Be supported by a range of stakeholder groups, and not only “special
interest” groups;
5. Have (at least) adequate economic returns;
6. Have built-in environmental and social safeguards;
7. Be at a sufficiently advanced stage of preparation (including feasibility
studies, procurement documents and GOI readiness) that they can be
commenced with minimal delay after approval by ADB;
8. Not be proposed for funding by other donors.
To some extent, satisfying all these criteria has proved to be fairly difficult,
as the focus of the PPTA changed in mid-2006,, and consultation and
preparation time in Phase 3 has been limited, compared to what is normal
for a PPTA for a loan of this magnitude.
Expenditure by Financier
Total ADB ADB
Project Components ($ Million) GEF GOI
TA Loan
1. Program Management 2.57 2.57
2. Institutional Strengthening for IWRM 2.40 2.40
3. Water Supply Options for Bandung /a 4.81 3.08 1.73
4. Rehabilitation of West Tarum Canal 42.93 27.48 15.46
5. Roll Out of System Rice Intensification /b 4.17 2.67 1.50
6. Community-Driven WSS 5.64 3.61 2.03
7.Basin Water Quality Improvement Strategy 6.42 4.11 2.31
8. Productive Reforestation of Degraded 4.04 4.04
Catchments
9. Project Area Management Biodiversity 4.02 4.02
10. Program Preparation for Tranche 2 1.04 1.04
Total Base Cost 78.04 3.44 8.06 40.94 25.60
Physical Contingencies 3.90 3.90
Price Contingencies 11.31 11.31
Total Base Cost and Contingencies 93.25 3.44 8.06 56.15 25.60
Interest During Implementation 2.87 2.87
Commitment Charges 1.19 1.19
Total Project Cost 97.31 3.44 8.06 60.22 25.60
% of Total Project Cost 100% 4% 8% 62% 26%
ADB and GOI Share of non-grant project
cost 100% 70% 30%
The estimated total investment cost for MFF, including contingencies and
IDC for the Project is $830.13 million (Table 10).
Citarum Integrated Water Resource Management Project Page 51
Report on Roadmap and Program Development
Expenditure by Financier
Total
($ Co- ADB
Tranche Million) ADB TA GOI
finance Loan
A. Tranche 1 - 2007 to 2011 97.31 3.44 8.06 60.22 25.60
12 Implementation Arrangements
12.1 Investment Program Planning, Coordination
and Management
In order to maximise the benefit of ADB support to the Citarum River Basin,
as described in this report, the Roadmap and Investment Program
implementation will be planned, managed and coordinated at three levels:
1. Roadmap by a Roadmap Planning Monitoring and Coordination Unit
(RPMCU) under Bappenas coordinating with the National Water
Resources Steering Committee and supporting the CRB Water Council
in planning, coordinating and monitoring across national and provincial
agencies;
2. Investment Program DGWR as EA through the establishment of a
Program Management and Coordinating Unit (PMCU) in the CRB Balai
Besar ; and
3. On a day-to-day basis through Project Implementation Units (PIUs) in
each Implementing Agency (IA).
A proposed Project Organization Chart is given in Annex 9. The project
activities need to be coordinated in a flexible, transparent, and open
manner. The RPMCU and PMCU should assist in ensuring all basin
stakeholders are involved in Citarum River Basin planning and monitoring
activities. Annual work programs (AWPs) are a necessity due to
government disbursement mechanisms, these should be initiated by PIUs
and consolidated by the PMCU.
The PCMU should be staffed by a small group of international and national
consultants, supplemented by staff seconded from the implementing
agencies (for the duration of the relevant components). This will have the
benefits of:
• Providing additional staff to undertake the work of the PMCU –
professionals that are familiar with the particular characteristics (physical
and institutional) relevant to each component;
• Improving liaison between the PMCU and the individual PIUs;
• Building the capacity of IA staff through “on-the-job” work experience
alongside international and national consultants.
8
The parallel institutional project funded as an ADB Technical Assistance (described
elsewhere in this report) will have as its primary focus institutional reform and
strengthening, both for organizations dealing with river basin management, and the legal,
policy and planning basis for IWRM.
9
Assuming a water requirement of 200 litres/person/day.
Citarum Integrated Water Resource Management Project Page 56
Report on Roadmap and Program Development
high income families rely on bottle water which priced at about Rp1,000 per
litre. The poor are not able to purchase bottle water and must rely mainly
on piped water for their daily needs.
The rest of the additional water will be used mainly to meet the needs of the
industrial sector. Water is an essential input for virtually all industries; in
particular the textile, food and service sectors. Without the additional water,
growth of these industries will be severely curtailed.
The rehabilitation of WTC will provide sufficient water to cultivate 117,600
ha of paddy as compared with 91,800 ha in the without project situation.
This will increase paddy cropping intensity from 1.53 to 1.93. The Project
will increase the annual paddy cropped area by 25,800 ha by 2025. A total
of 25,800 farmers, each cultivating (2 crops per year) an average of 0.5 ha
of paddy land will benefit from this increase in crop area.
The SRI component in this project will accelerate the adoption of System of
Rice Intensification in the project area. In total, some 45,800 paddy farmers
will benefits from the Project and their net farm income will be raised by
more than 35%. In addition some 15,000 landless farmers or labourers will
also benefit from the increase farming activity and their net income is
expected to be raised by 40%.
10
World Bank, 2004. Global Analysis on Sanitation Investments.
11
ADB, 1996. Economic Evaluation of Environmental Impact, page 238.
Citarum Integrated Water Resource Management Project Page 57
Report on Roadmap and Program Development
mental management concerns into the basin plan and facilitated public
information and involvement in planning. The SEA influenced program
planning by incorporating the following program design criteria: (i) balanced
concern for water utilisation and water quality management; ii) attention to
both human use concerns and ecological protection objectives; (iii) inclusion
of capacity development for environment management and strengthening of
the environmental regulatory system; (iv) inclusion of community
participation and empowerment activities; and (v) management of water as
an economic resource.
The SEA also established a tiered approach to environmental assessment
and planning. The Environmental Assessment and Review Framework
(EARF) specifies procedures for examining more closely the impacts of
projects to be included under each MFF tranche to ensure: (i) consistency
with the basin wide assessment framework and (ii) compliance with ADB
and GOI environmental assessment requirements for individual projects.
The IEE for Tranche 1 was done as a next tier of the SEA, based on the
EARF.
The investment program’s Tranche 1 package is expected to generate
significant environmental benefits in terms of more efficient and equitable
water resources utilization (both surface water and groundwater); adequate
supply to meet growing water demand from households and industry; water
quality improvement; rehabilitation of watersheds that ensure water supply
sustainability and that also enhances socio-economic well-being of
communities; and overall improvement of institutional capacity for
participatory basin management.
Environmental safeguards are incorporated into the package both as pro-
active measures to protect and sustain water resources and to preserve
basin ecosystem functions (including biodiversity), as well as mitigation
measures to deal with any adverse impacts arising from some activities
(notably, WTC rehabilitation).
The extended, three-phase process of developing/designing the program
has been influenced significantly by stakeholder views and preferences. A
more balanced mix of project activities has been incorporated into the
roadmap—addressing quantity and quality as inseparable issues in water
resource management, introducing complementary solutions that combine
engineering and institution-building, allowing for basin management
objectives to encompass overall ecological protection, and taking into
account the interests/sentiments of stakeholders in the upper and lower
parts of the basin.
For purposes of compliance with ADB environmental assessment
guidelines, no additional study or full environmental impact assessment is
needed to further assess the potential environmental impacts of Tranche 1.
However, individual projects associated with potential adverse impacts,
specifically the West Tarum Canal rehabilitation and construction of
communal septic tanks, must comply with the review and clearance
procedures under Indonesia’s AMDAL system.
Citarum Integrated Water Resource Management Project Page 58
Report on Roadmap and Program Development
12
These and other models are briefly described below.
Citarum Integrated Water Resource Management Project Page 60
Report on Roadmap and Program Development
Expert
GIS and
Knowledge,
Databases
Decision Rules
River Water
Case River Water
Quality Planning
Composer Allocation Model
Model
Resource
Economics
Model
Computations
Analysis
14.3.4 Databases
Each DST contains also a (large) number of other databases, most of them
concerning time series that could be linked to the models, GIS and always
to the CC.
Citarum Integrated Water Resource Management Project Page 67
Report on Roadmap and Program Development
Scenario Project
Hydrology
Hydrology Region
Region
Scenario Scenario
BOD5
BOD5 load
load
Population
Population
Scenario
Fish
Case
Case
Fish Cages
Cages
Scenario Scenario
BOD5
BOD5 load
load
Agriculture
Agriculture Time
Time Horizon
Horizon
Scenario Scenario
BOD5
BOD5load
load
Scenario
Industry
Industry
14.3.7 Analyses
Normally, one is interested in how the river system would look like in a
future situation. Since it is not known beforehand, and cannot really
forecast a long time ahead, the boundary conditions such as rainfall (of
which we know that the past series will not be repeated in the same
manner), the approach is the following:
Develop an input data set (rainfall, evaporation, and so on) of sufficient
length (ideally > 40 years) containing wet and dry periods.
Select the inside developments at the preset time horizon (demands,
pollution, and so on).
Run the model(s) for the 40 year of rainfall data, keeping the inside
developments constant.
It is now possible to see how often in these 40 years, preset levels of
demands, pollution, and so on, could not be met, and draw a conclusion
from it for a project, for example increase a WWTP's capacity for that time
horizon. Or, on the other hand, one may just come to the conclusion that the
foreseen capacity of the WWTP is too high.
A DST might also include a multi-criteria analysis13 (MCA) tool to rank
(score) the results of various cases, depending on the weight of
predetermined key values to be included in the MCA.
14.4.1 Objective
The objectives of a DST-Citarum are:
to serve as a platform on which all current modelling activities can be
integrated and analysed.
to serve as an aid for the river basin manager, that can be used to
optimize the integrated water management of the Citarum River Basin.
Scenarios
Different time horizons
Short term
Medium term
Long term
Climate change:
Sea level rise
Change in precipitation
Change in river run-off
Rural and urban developments:
Irrigation/agricultural area
Population growth
13
This is basically the same technique as that known as “multi-objective analysis” that
was used in Phase 1 of the PPTA for selection of projects.
Citarum Integrated Water Resource Management Project Page 70
Report on Roadmap and Program Development
Groundwater abstraction
Rural waste loads
Waste loads from Bandung, Purwakarta, (others?)
Economics:
Market developments
Resource economics: Rice crops, fish prices, (peak) power
production
Measures14
River basin management
Dam construction
Dam operation (Citarum reservoir cascade)
Land use
Dike (re)construction
Dredging (WTC)
Infrastructure (siphons, rehabilitation of main offtake gates, cross-
regulators, etc)
Improvement of WWTPs at industries/industrial estates
Construction of WWTPs Bandung, Purwakarta
Coastal management
Dredging
Infrastructure
Analyses
After processing each case, the user may analyse the results in various
ways: tables, graphs and maps. To compare cases and find out which
solution is the most promising, the DST-Citarum must include a Multi
Criteria Analysis (MCA) tool. The MCA tool presents scores of the different
case, depending on the weight of the key values which are included in the
MCA.
A decision on which key values to be included in the MCA module of DST-
Citarum has to be taken at the design stage. An example of such a key
value may well be the maximum DO concentrations at public water supply
intakes, of the reservoir inflows, or maximum and minimum flows at critical
points in the system.
14
These will come from the roadmap.
Citarum Integrated Water Resource Management Project Page 71
Report on Roadmap and Program Development
15.2 Recommendations
The following recommendations are made as a result of Phase 3 of the
PPTA:
1. A roadmap for achievement of a stakeholder vision for the future of the
Citarum River Basin has been developed after extensive consultation.
GOI should take steps to formalise/ratify this to become part of
government policy.
2. The roadmap is not intended to be a static document and needs to be
regularly updated to reflect changing circumstances. GOI should
establish a small unit (perhaps in Bappenas) to monitor progress on
roadmap implementation, evaluate effectiveness of the interventions
Citarum Integrated Water Resource Management Project Page 72
Report on Roadmap and Program Development
FOREWORD
The process for the development of a roadmap for the Citarum River This has been achieved using the following “vision-oriented” approach:
Basin has followed the basic methodology of strategic planning. Reaffirm and more clearly define a shared vision of stakeholders for
Fundamentally, the approach has been to ask the following three the future of the Citarum River Basin (to the year 2020);
questions:
Compare the present status of water resources in the basin to the
Where do we want to go (with water resource management in the vision, in order to identify the strategic direction that needs to be
basin)? taken (the “road” so to speak);
Where are we now (that is, what are the existing issues/problems)? Formulate objectives in a number of key areas that would, if
achieved, lead to the fulfilment of the vision;
How can we get from where we are now to where we want to go (the
“road” we need to take)? Develop a set of interventions (projects) the successful implement-
ation of which would achieve the objectives in each key area.
Much has been written about the current issues for water resource
The roadmap is seen as belonging to the Government of Indonesia, and
management in the basin, and the key issues are well documented in a
not to the Asian Development Bank or any other donor, even though
variety of documents produced in the last decade. The problems are
ADB is committed to assisting the government to implement the
numerous and cover a variety of areas, including severe deterioration of
roadmap interventions through a major loan and associated technical
water quality, deforestation and degradation of upland catchments,
assistance. As such, the roadmap is an important tool in the dialogue
mining of groundwater and degradation of water control infrastructure.
between GOI and donors that will allow donor assistance to be targeted
These problems have severe economic and social cost consequences to
at the critical issues, and to minimise overlaps and gaps.
the people of the basin.
Close to 70 interventions have been identified as necessary for the
The roadmap itself is simply a set of strategies (and projects/actions to
achievement of the objectives (and hence the vision) for the Citarum
implement those strategies) that define the path between the present
River Basin. These have come from a variety of sources. The costs that
situation with respect to water resources in the basin and the desired
have been assumed for each these come from those sources (factored
outcomes (or vision) for the future – that is, what needs to be done to
into 2006 dollar terms) and can only be considered as indicative, and of
achieve the objectives.
course must be firmed up during project preparation.
VISION FOR THE YEAR 2021
“The government and communities working together
for clean, healthy and productive catchments and rivers,
bringing sustainable benefits to all people of the Citarum River Basin.”
2
STRATEGIC FRAMEWORK
A strategic framework was developed in consultation with a broad range of basin stakeholders to ensure that an integrated approach to the
formulation of the roadmap would be ensured. This is represented in the “house” diagram (below), where the vision for the basin is supported by
activities in a number of key areas, five of which are seen to be “pillars”, with a foundation of two cross-cutting key areas – the “foundation”.
3
Key Areas – Definitions and Objectives
KEY AREAS
4
Key Areas – Definitions and Objectives
5
Key Areas – Definitions and Objectives
6
Key Areas – Intervention Outlines
PROPOSED INTERVENTIONS
COST
KEY AREA Intervention MAIN OUTPUTS / ACTIVITIES SOURCE
($ million)
Institutions and 1.1 Institutional strengthening for • Assistance in establishing apex management body for the basin (Citarum Basin 1.8 PPTA Phase 3
Planning for integrated water resources Water Resources Council) and support unit(s), for improved coordination and
IWRM management policy development.
• Ongoing support and capacity building for the Council and support unit(s).
1.2 Policy development for • Review of current water pricing policies and development of new pricing 0.8 PPTA Phase 3
appropriate water pricing, structures that better reflect cost of delivery and provide incentives for rational
water allocation and balanced water use.
stakeholder participation • Review of current policy instruments for water allocations among water uses
(across sectors and upstream/downstream).
• Review of current policies on stakeholder (and particularly, community)
participation in planning and management of water resources and development
of new policies and mechanisms for a more balanced approach (for all
stakeholders, such as government agencies, NGOs and the community at
large).
1.3 Development of an enhanced • Review of existing plans for water resources development and management in 0.9 PPTA Phase 3
Citarum River Basin Plan for the Citarum River Basin.
IWRM • In collaboration with stakeholders, development of a strategic river basin plan
that will facilitate improved and more integrated water resource management.
• Development and implementation of a mechanism for monitoring the
implementation of the river basin plan by line agencies with that responsibility,
and reporting progress to government to take corrective action if required.
1.4 Improvements to organisational • Setting up of a programmatic AMDAL approach for the basin; training and 0.5 PPTA Phase 3
capacity for environmental guides for project planners and stakeholders in project impact assessment,
assessment review and monitoring following the EARP.
• Capacity building for managers and technical staff responsible for implementing
the AMDAL approach.
Estimated Total Cost 4.0 million USD
7
Key Areas – Intervention Outlines
COST
KEY AREA Intervention MAIN OUTPUTS / ACTIVITIES SOURCE
($ million)
Water Resource 2.1 Upgrading of Water Source for • Construction of a dam and reservoir on the Cibeber River. 60.0 PPTA Phase 1
Development Irrigation (Upper Cipunegara) • Rehabilitation of the existing irrigation water distribution system. Sub-Project #9
and
• Construction of a diversion weir on the Cipunegara River and a diversion tunnel
Management
to convey water to a point upstream of the reservoir to increase inflows to
enable the irrigated area to be increased.
• Possible small-scale hydropower development as part of the water diversion
system.
• Strengthening of institutions for Participatory Irrigation Management among
farmers.
• Development of plans for improved management of the watershed upstream of
the reservoir.
2.2 Upgrading of Water Source for • Construction of the Cipancuh Dam and auxiliary structures, including addition of 65.7 PPTA Phase 1
Irrigation (Cipancuh) moveable steel gates to the top of the spillway crest, and raising of dam wall to Sub-Project #10
increase flood freeboard.
• Strengthening of institutions for Participatory Irrigation Management among
farmers.
• Development of plans for improved management of the watershed upstream of
the reservoir.
2.3 Upgrading of Water Source for • Construction of the Telagaherang Dam and auxiliary structures. 56.4 PPTA Phase 1
Irrigation (Ciherang) • Rehabilitation of the existing irrigation water distribution system. Sub-Project #11
• Strengthening of institutions for Participatory Irrigation Management among
farmers.
• Development of plans for improved management of the watershed upstream of
the reservoir.
2.4 Cisankuy Irrigation • Improved (more efficient) operation of Cisankuy Reservoir. 65.5 Master Plan
Improvement • Improved cropping patterns in the Cisankuy area, to save water. 1997
2.5 Raising of Cirata Dam • Undertake feasibility study. 20.1 Master Plan
• Do detailed engineering design. 1997
• Construct dam and associated works.
8
Key Areas – Intervention Outlines
COST
KEY AREA Intervention MAIN OUTPUTS / ACTIVITIES SOURCE
($ million)
2.6 Investigation of bulk water • Establishment of a stakeholder-driven selection process of options to improve 1.2 PPTA Phase 3
supply options for Bandung the availability of bulk water supplies to Bandung to meet the DMI demand to
urban area 2025.
• Execution of rapid surveys and pre-feasibility studies (review and update any
previous feasibility studies) in order to arrive at a short-list of the most viable
potential options.
• Preparation of detailed feasibility studies (including costing, environmental
impact assessment, and resettlement action plans, etc) leading to the
preparation of SPARs (subproject appraisal reports).
2.7 Implementation of preferred • Detailed engineering design on selected option(s). 0 PPTA Phase 3
bulk water supply alternatives • Preparation of tender documents; contract awards. (Costs assumed
for Bandung urban area to be accounted
• Construction and commissioning.
for in schemes
proposed below)
2.8 Upgrading of water source for • Construction of Cibutarua Weir 190.0 PPTA Phase 1
Bandung and other uses by • Construction of Santosa Reservoir on the Cilaki River. Sub-Project #11
inter-basin transfer
• Construction of a 4.5 km diversion tunnel.
• Construction of a reservoir upstream of Tamiang Cangkir Weir, needed to
compensate irrigation downstream of Cibutarua Weir
• Development of an inter-district agreement regarding cost allocation and
ongoing financial arrangements for diverted water.
2.9 Development of the surface • Review of previous investigations into construction of five reservoirs in the upper 34.7 Master Plan
water of the upper catchment catchment of the Cikapundung River to enhance surface water availability for 1997
of the Cikapundung River Bandung and surrounding area..
• Undertake feasibility study of preferred option.
• Do detailed engineering design.
• Construct dams and associated works.
2.10 Construction of Sukawana • Review of previous investigations into construction of Sukawana Reservior on 7.2 Master Plan
Reservior on the Cimahi River the Cimahi River. 1997
• Undertake feasibility study.
• Do detailed engineering design.
• Construct dam and associated works.
9
Key Areas – Intervention Outlines
COST
KEY AREA Intervention MAIN OUTPUTS / ACTIVITIES SOURCE
($ million)
2.11 Investigation of bulk water • Establishment of a stakeholder-driven selection process of options to improve 1.0 PPTA Phase 3
supply options for Bekasi and the availability of bulk water supplies to Bekasi and Karawang to meet the DMI
Karawang demand to 2025.
• Execution of rapid surveys and pre-feasibility studies (review and update any
previous feasibility studies) in order to arrive at a short-list of the most viable
potential options.
• Preparation of detailed feasibility studies (including costing, environmental
impact assessment, and resettlement action plans, etc) leading to the
preparation of SPARs (subproject appraisal reports).
2.12 Implementation of preferred • Detailed engineering design on selected option(s). 50.0 PPTA Phase 3
bulk water supply alternatives • Preparation of tender documents; contract awards.
for Bekasi and Karawang
• Construction and commissioning.
2.13 Development of an action plan • Review and document available information on groundwater situation in the 0.6 Master Plan
for sustainable groundwater Citarum River Basin, including availability and current use. 1997 (modified
management in the Citarum • Review previous studies on groundwater management options. by PPTA Phase
River Basin 3)
• In conjunction with the bulk water supply options study, prepare an action plan
for effective and sustainable groundwater management.
• Review existing regulatory instruments for groundwater management and
recommend improvements, including mechanisms for compliance management
(enforcement).
2.14 Implementation of the action [Depends on outcomes of the action plan development study – costs indicative only] 5.0 PPTA Phase 3
plan for sustainable ground-
water management in the
Citarum River Basin
2.15 Improved implementation of • Review of existing regulatory framework for groundwater management in the 0.6 PPTA Phase 3
regulations for sustainable Bandung area.
groundwater management in • Evaluation of existing implementation of regulation and identification of
Bandung deficiencies.
• Development of strategies and an action plan for improved effectiveness of
regulation of groundwater use, including recommendations for changes to the
existing regulatory framework.
• Development of a monitoring and evaluation mechanism.
• Capacity building of agencies involved in groundwater management.
2.16 Improvement of Raw Water • Provision of new intake and conveyance facilities for reticulation of water supply. 32.8 PPTA Phase 1
Supply for Bandung • Review of current water pricing policies and development of new pricing Sub-Project #18
structures that better reflect cost of delivery and provide incentives for rational
water use in the Bandung area.
10
Key Areas – Intervention Outlines
COST
KEY AREA Intervention MAIN OUTPUTS / ACTIVITIES SOURCE
($ million)
2.17 Rehabilitation of the West • Detailed engineering design. 41.4 PPTA Phase 1
Tarum Canal for improved • Removal and disposal of sediments from the canal bed, strengthening of Sub-Project #13
water resource utilization embankments. (revised during
Phase 3)
• Separation of Cikarang and Bekasi river flows from the main canal through
construction of by-passes (inverted siphons).
• Capacity building of PJT II for improved management and operation of WTC.
• Implementation of stakeholder-driven selection process of water supply and
sanitation options for riparian communities along West Tarum Canal.
2.18 West Tarum “Canal 2” Project • Review of previous investigations into options for piping water from Jatiluhur 860.0 Master Plan
Reservoir to Jakarta. 1997
• Feasibility study of preferred option.
• Detailed engineering design.
• Construction.
2.19 Irrigation Modernisation – West • Rehabilitation of canal network (secondary and tertiary canals) and water control 50.9 PPTA Phase 1
Tarum Canal structures. Sub-Project #4
• Installation of off-take measurement apparatus.
• Strengthening of institutions for Participatory Irrigation Management among
farmers.
2.20 System Service Improvement • Rehabilitation of the East Tarum Canal, including removal and disposal of 126.2 PPTA Phase 1
and Irrigation Modernisation – sediments, and repair and strengthening of embankments. Sub-Projects #2
East Tarum Canal • Rehabilitation of secondary and tertiary canals and water control structures. and #5
• Installation of off-take measurement apparatus.
• Strengthening of institutions for Participatory Irrigation Management among
farmers.
2.21 System Service Improvement • Rehabilitation of the North Tarum Canal, including removal and disposal of 95.1 PPTA Phase 1
and Irrigation Modernisation – sediments, and repair and strengthening of embankments. Sub-Projects #3
North Tarum Canal • Rehabilitation of secondary and tertiary canals and water control structures. and #6
• Installation of off-take measurement apparatus.
• Strengthening of institutions for Participatory Irrigation Management among
farmers.
11
Key Areas – Intervention Outlines
COST
KEY AREA Intervention MAIN OUTPUTS / ACTIVITIES SOURCE
($ million)
2.22 Development of strategies and • Development and implementation of strategies and actions for water 0.5 PPTA Phase 3
options for demand conservation awareness raising among the community and industries.
management and water • Development and implementation of strategies and actions for industrial water
conservation with respect to recycling (including regulatory and technological measures), and assistance to
industrial and domestic use industries to install recycling technology.
• Development and implementation of strategies and actions for minimisation of
losses from water reticulation systems.
• Review of current water pricing policies and development of new pricing
structures that better reflect cost of delivery and provide incentives for rational
water use.
2.23 Development of improved • Development of an asset register and monitoring system for hydraulic 1.0 PPTA Phase 3
asset management and O&M infrastructure and a system for prioritization of maintenance activities.
procedures for hydraulic • Introduction of clear and accountable operating plans for the delivery of bulk
infrastructure water to irrigation and DMI users
2.24 Rajamandala Run-of-River • Review of previous investigations into options for power generation. 164.3 Master Plan
Power Plant (Citarum River • Feasibility study of preferred option. 1997
below Saguling Reservoir)
• Detailed engineering design.
• Construction.
2.25 Curug Run-of-River Power • Review of previous investigations into options for power generation. 6.0 Master Plan
Plant • Feasibility study of preferred option. 1997
• Detailed engineering design.
• Construction.
Estimated Total Cost 1936.2 million USD
Water Sharing 3.1 Review of allocation priorities • Review of the effectiveness of existing water sharing arrangements (including 0.9 PPTA Phase 3
and optimization of operating water exported to Jakarta).
rules for key sub-basins, • Development of an updated policy for water sharing among water users in the
including the operation of the basin, as well as Jakarta, including an effective conflict/dispute resolution
river / reservoir system as a mechanism.
whole
• Determination of environmental flow requirements to maintain water quality, as
well as flushing flows for sediment and salinity reduction in lower reaches.
• Development of updated and appropriate operating rules for key sub-basins,
including the operation of the river / reservoir system as a whole.
• Review of allocation priorities and clear procedures for sharing water during
periods of drought .
Estimated Total Cost 0.9 million USD
12
Key Areas – Intervention Outlines
COST
KEY AREA Intervention MAIN OUTPUTS / ACTIVITIES SOURCE
($ million)
Environmental 4.1 Development and • Select model conservation villagers using supplied criteria. 0 PPTA Phase 3
Protection implementation of conservation • Appoint initially 15 conservation village mentors.
action plans for model
• Mentors to be the conduit for the delivery of WSM educational material.
conservation villages in
Citarum River Basin • Mentor to receive orientation and programmatic training from a selected
LSM/NGO.
• Mentor to assist develop village conservation action plans.
• Mentor to assist develop village and community nurseries.
• Mentor to assist with reforestation of village lands and Perum Perhutani lands.
• Mentor to assist with implementation of other aspects of the conservation village
action plans (sanitation, household pollution etc).
• Mentor to assist with tenure arrangements with Perum Perhutani.
4.2 Watershed management • WSM education to the community delivered through the model conservation 0 PPTA Phase 3
community educational village network and pesantren.
program for CRB • Appoint an NGO/LSM to design WSM educational course and source materials.
• This NGO/LSM to orient a group of conservation village mentors and supply
them with programmatic training and educational material.
• Conservation village mentors supply WSM education material to villagers.
• The NGO/LSM supplies WSM material direct to pesantren.
• Model conservation village education program, spatial plans and action plans
tied to recognition of importance of existing PAs and other CRB conservation
domain.
13
Key Areas – Intervention Outlines
COST
KEY AREA Intervention MAIN OUTPUTS / ACTIVITIES SOURCE
($ million)
4.3 Productive Reforestation (1): • Review all existing laws relating to protection of forests in upper catchment 30.0 PPTA Phase 1
Spatial planning for areas, particularly on steep slopes >42 degrees, and evaluate their legal Sub-Project #7
reforestation suitability to provide protection. (enhanced during
• Review existing mosaic of spatial plans in CRB, evaluate the extent to which Phase 3)
they are harmonious, and recommend a process for greater integration of these
plans at all levels.
• Establish a small group (GIS /remote sensing specialist, spatial planner and
landscape ecologist) in the CRB Council to work with and advise kecamatan,
kabupaten, BP DAS, Bappedalda and Bappeda to produce integrated functional
spatial plans.
• Map accurately Perhutani, degraded lands, road, river and DAS boundary
reserves and PAs.
• Map major spring catchment areas, this to require selected hydrological surveys
of important springs.
• Link these above areas for ecological functional integrity.
• Gain multi-stakeholder acceptance for reforestation spatial plan brokered by
CRB Council, as well as allowing for broad public scrutiny.
• Identify priority areas for rehabilitation by reforestation.
4.4 Productive Reforestation (2): • Review and report on the appropriate re-forestation methods in different 0 PPTA Phase 3
Implementation topographic profiles within the area planned for re-forestation to achieve
multiple-purposes. Namely, to: consolidate soil profiles, provide a structurally
and floristically rich vegetation to support biodiversity values and; most
importantly, provide sustainable crops to enhance livelihoods for villagers.
• Institutional strengthening for coordination among local governments and the
basin management organization for watershed management.
• Development of effective land use controls with incentives.
• Implementation of effective compliance management (enforcement).
• Establishment of a farm credit system.
• Training and community development.
4.5 Improvement to village land • Broker MOU contract conditions between villagers and Perum Perhutani that 0 PPTA Phase 3
tenure arrangements with provides long tenure (>30 years) but mandates planting mixed trees that will
Perum Perhutani prevent erosion but provide farmers with a standing crop.
• Advise villagers of the most appropriate reforestation techniques. Broker
prioritization for Forest villagers (desa hutan) to be given priority for such leases.
14
Key Areas – Intervention Outlines
COST
KEY AREA Intervention MAIN OUTPUTS / ACTIVITIES SOURCE
($ million)
4.6 Alternative livelihoods for • Conduct a field survey of the upland villagers (38,000 families) displaced under 0 PPTA Phase 3
displaced upland forest the program “Larangan tumpang sari di kemiringan >42 degrees, 20 May 2003”,
villagers to ascertain suitable sustainable alternative livelihoods.
• Broker preferences for this group of villagers for Perum Perhutani lands and
facilitate preferred livelihoods on this leasehold land.
4.7 Protected area management in • Develop conservation management action plans for the selected protected 0 PPTA Phase 3
CRB areas through stakeholder forums focused on selected conservation targets
(objectives) as follows:
o undertake information ‘mining’;
o form stakeholder groups;
o develop action plans (targets, threats, practical solutions);
o prepare adaptive management plans.
• Conduct rapid biodiversity surveys of three taxonomic groups selected by the
action planning process.
• Conduct habitat mapping in each of these five groups of protected areas.
• Conduct village resource utilization survey of the villages adjoining these
protected areas.
• Establish village conservation groups specific to the selected protected areas
and involve these groups in collaborative management of these protected areas.
4.8 Alternative finance • Review Payment for Environmental Services (PES) practices in Indonesia. 0 PPTA Phase 3
mechanisms for sustainable • Develop an action plan for implementation of PES in the CRB and modify the
community watershed plan following stakeholder review.
management activities in CRB
• Review options for micro-credit facilities for villagers in CRB, including a Basin
‘Trust Fund’ or other rolling funds.
4.9 Riparian zone management to • Determine vegetation floristics and structure most effective in reducing stream 0 PPTA Phase 3
reduce sediment loads in rivers sedimentation.
• Determine width of zone required to minimize sediment loads.
• Identify critical river reaches that contribute high sediment loads to the river.
• Identify land use practices of local farmers that exacerbate riparian erosion and
sedimentation (for example, stock grazing on river banks).
• Develop action plans for improved riparian management in pilot (critical) river
reaches.
• Implement pilot vegetation plantings and improved land management practices
according to action plans developed.
• Review results of pilots.
• Implement improved management in other critical riparian zones across the
basin.
15
Key Areas – Intervention Outlines
COST
KEY AREA Intervention MAIN OUTPUTS / ACTIVITIES SOURCE
($ million)
4.10 Integrated Erosion • Development and implementation of effective land use controls in steep slope 20.0 Part of PPTA
Management for Upper Bekasi areas and incentive systems for farmers to adopt sustainable agricultural Phase 1 Sub-
River, Upper Citarum River and practices. Project #14
Upper Cipunegara River • Erosion and landslide control works in critical areas, including construction of
hillside works (planting, terracing, grass coverage, drainage channels, retaining
walls, and so on).
4.11 Development and (initial) • Prepare strategic options for the River Quality Improvement Action Strategy 0 PPTA Phase 3
implementation of a River including technical, institutional, and legal aspects and focusing on both
Quality Improvement Action incentive and enforcement measures, and drawing lessons from existing
Strategy Plan for the basin programs.
• Raise awareness of the issues and possible solutions at political levels and
within industry and communities and generate commitment among Kabupatens
for implementation of the Strategy
• Based on the content of the agreed Action Plan, implement investment,
institutional strengthening and compliance components.
4.12 Development and (initial) • Data collection and mapping. 0 PPTA Phase 3
implementation of a Water • Institutional aspects, regulations, law enforcement.
Pollution Control Plan for the
• Improvements in the operation and efficiency of the existing WWTPs (factories
Bandung area
and hospitals).
• Community and awareness program for waste disposal.
• Construction of pilot community sanitation centers, simplified community
sewerage systems, and school sanitation systems.
• Capacity building.
• Development of water pollution control plan, and investment projects for
implementation under Tranche 2 and succeeding tranches.
4.13 Sewerage and wastewater • Detailed engineering design for the rehabilitation of existing sewerage and 325.0 Master Plan
treatment upstream of Saguling wastewater treatment facilities, and for the construction of new facilities. 1997
Reservoir • Preparation of tender documents; contract awards.
• Construction and commissioning.
16
Key Areas – Intervention Outlines
COST
KEY AREA Intervention MAIN OUTPUTS / ACTIVITIES SOURCE
($ million)
4.14 Development and (initial) • Data collection and mapping. 0 PPTA Phase 3
implementation of a Water • Institutional aspects, regulations, law enforcement.
Pollution Control Plan for the
• Improvements in the operation and efficiency of the existing WWTPs (factories
Bekasi and Karawang areas
and hospitals).
• Community and awareness program for waste disposal.
• Construction of pilot community sanitation centers, simplified community
sewerage systems, and school sanitation systems.
• Capacity building.
• Development of water pollution control plan, and investment projects for
possible implementation under later tranches.
4.15 Development and • Implementation of improved enforcement (compliance management) of existing 13.7 PPTA Phase 1
implementation of a solid waste laws and regulations regarding solid waste disposal, and strengthening of Sub-Project #17
management strategy and regulatory mechanisms as required.
action plans for the Bandung, • Public education on waste disposal issues.
Bekasi, Cikarang and
• Establishment of equitable and effective cost sharing mechanisms for collection
Karawang areas
and disposal of solid waste.
• Establishment of separated collection systems and improved recycling
processes for solid waste.
• Development of appropriate land-fill areas and practices for disposal of non-
recyclable waste.
• Establishment of monitoring and conservation systems for land-fill areas and
recycling stockpiles.
4.16 Introduction of System Rice • Participatory Rural Appraisal for 3 districts and 16 sub-districts 4.2 PPTA Phase 3
Intensification (SRI) practices • Training of Trainers for 800 farm leaders
in the upper and lower basin to
• Training for 20,000 farmers
conserve water and improve
productivity • Implementation of SRI in 80 demonstration plots
• Farmer empowerment – 660 sessions of training
• Production of organic fertilizer – distribution of 400 units
• Acquisition and distribution of 10,000 decomposer kits
• Acquisition and distribution of 50,000 kg of selected seeds
• Monitoring and reporting
17
Key Areas – Intervention Outlines
COST
KEY AREA Intervention MAIN OUTPUTS / ACTIVITIES SOURCE
($ million)
4.17 Improvement in water quality in • Identify sources and extent of pollution in Saguling, Cirata and Jatiluhur 2.0 PPTA Phase 3
Saguling, Cirata and Jatiluhur Reservoirs.
Reservoirs through • Determine the economic impacts of pollution on other uses of water (such as
management of fish farming hydropower.
and other polluting activities
• Identify actions needed to reduce pollution.
• Identify possibilities for alternative livelihoods for fish farmers and others that
may be impacted by controls on fish farming and other polluting activities.
• Develop and implement an action plan for reducing pollution.
4.18 Integrated coastal zone • 0.6 PPTA Phase 3
management strategy and
action plan for Citarum
coastline
4.19 Implementation of ICZM Action [Depends on outcomes of the action plan development study] 20.0 PPTA Phase 3
Plan
Estimated Total Cost 415.5 million USD
Disaster 5.1 Integrated Management of • Review effectiveness of existing disaster management strategies and 40.0 PPTA Phase 1
Management Water-Related Disaster (basin- coordination arrangements and make recommendations for improvements, Sub-Project #8
wide) particularly in relation to introduction of basin water resources council. And
support units
• Development and implementation of effective land use controls in disaster prone
areas.
• Relocation of households in disaster prone areas.
• Development and implementation of effective controls on sand and gravel
extraction.
• Public awareness campaigns on disaster preparedness.
• Institution strengthening (capacity building) for agencies responsible for:
monitoring; emergency response; evacuation; rescues; and restoration.
• Establishment of a flood forecasting system.
• Develop contingency plans for industrial accidents affecting contamination of the
river system,
5.2 Cipunegara Sub-Basin Flood • Investigate flood management options for the Cipunegara Sub-Basin 10.0 PPTA Phase 3
Management • Develop recommendations for flood management and mitigation of flood
impacts
• Implement recommendations
18
Key Areas – Intervention Outlines
COST
KEY AREA Intervention MAIN OUTPUTS / ACTIVITIES SOURCE
($ million)
5.3 Bekasi Sub-Basin Flood • Investigate flood management options for the Bekasi Sub-Basin 10.0 PPTA Phase 3
Management • Develop recommendations for flood management and mitigation of flood
impacts
• Implement recommendations
5.4 Disaster (mud flow and • Development and implementation of mud flow and landslide forecasting and 13.4 Part of PPTA
landslide) management for warning/evacuation measures. Phase 1 Sub-
Upper Bekasi River, Upper • Relocation of dwellings from disaster-prone areas. Project #14
Citarum River and Upper
• Enhancement of public awareness regarding disaster preparedness.
Cipunegara River
5.5 Strategic options for flood • Review past flood mitigation studies for the Bandung area, and assess current 0.3 PPTA Phase 3
mitigation in Bandung appropriateness.
• Develop new flood mitigation measures if necessary.
• Update recommendations regarding appropriate flood mitigation measures to be
implemented for Bandung.
5.6 Implementation of [Depends on outcomes of the strategic options study] 20.0 PPTA Phase 3
recommended options for flood
mitigation in Bandung
5.7 Review of dam safety for dams • Review current standards for dam safety in Indonesia, and make 1.2 PPTA Phase 3
in the basin recommendations on improvements, if necessary.
• Review current institutional arrangements for dam safety auditing, reporting and
follow up, and make recommendations on improvements, if necessary.
• Review all dams subject to dam safety requirements with regard to compliance
with safety standards and make appropriate recommendations for improvement.
Estimated Total Cost 94.9 million USD
Community 6.1 Development of an Information, • Identification of key stakeholders in the basin (target groups) and behaviours 1.5 PPTA Phase 3
Empowerment Awareness and Education with regard to activities impacting on water resource management.
Strategy (IEAS) for capacity • Identification of messages and knowledge that needs to be communicated to
building of communities across each target group.
the basin for improved
• Identification of an community participation strategy for different aspects of water
participation in water resources
resources planning and management and relevant and available communication
policy development, planning
channels.
and management
• Development of the IEAS and action plan based on a “social marketing”
approach, and to include school education as a key element.
19
Key Areas – Intervention Outlines
COST
KEY AREA Intervention MAIN OUTPUTS / ACTIVITIES SOURCE
($ million)
6.2 Implementation of the [Depends on outcomes of the IEAS development study] 1.0 PPTA Phase 3
Information, Awareness and
Education Strategy
6.3 Support for community- and • Identification of potential NGOs who can facilitate community participation in all 10.5 PPTA Phase 3
NGO-driven initiatives for water project cycles.
supply and sanitation for rural • Socialization and awareness-raising, assessment of community needs.
and peri-urban communities
• Selection of communities based on socioeconomic and health criteria and other
indicators.
• Confirmation of community commitment and willingness to participate.
• Formation of community implementation teams.
• Community problem identification and analysis of technical options.
• Provision of skills training based on communities’ priorities, assets and needs to
generate income and employment opportunities
• Provision of access to capital and markets to directly implement skills acquired
• Formulation of community action plans and proposals.
• Disbursement of funds and construction of approved schemes.
• O&M of completed schemes, and socialization and training support on hygiene
behavioural change
• Facilitate the implementation of identified health, water and sanitation related
projects/programs.
6.4 Establishment of, and ongoing • Work with the Citarum Basin Water Resources Council or Citarum Balai Besar 0.3 PPTA Phase 3
support for a Stakeholder to determine the composition and mandate of the stakeholder forum.
Forum for Bandung Sub-Basin • Legally and practically establish the forum.
under Citarum Basin Water
• Provide ongoing support (financial and advisory) to the forum for up to two
Resources Council or Citarum
years.
Balai Besar
Estimated Total Cost 13.3 million USD
20
Key Areas – Intervention Outlines
COST
KEY AREA Intervention MAIN OUTPUTS / ACTIVITIES SOURCE
($ million)
Data and 7.1 Improvements to water quality • Delineate water quality management areas (e.g., by sub-watersheds) based on 0 PPTA Phase 3
Information monitoring in rivers and predominant land use and nature of water quality concerns/threats; identify key
reservoirs water quality parameters for each area; incorporate into existing clean rivers
program (PROKASIH and SUPERKASIH).
• Develop a plan for water quality monitoring in each water quality management
area reflecting the priority parameters--i.e., instill monitoring as a management
activity--ensuring that water quality monitoring data are actually used to support
improvement programs ( e.g., regulatory enforcement, incentives, community
awareness/participation)
• Develop standardized protocols/guidelines for water and sediment sampling,
laboratory analysis, reporting and data banking (including as input to decision
support tools).
• Establish a water quality laboratory recognition/accreditation scheme (with a
reference laboratory to conduct audits and provide recognition); attract private
sector investments in laboratory services.
• Undertake capacity building (human resources and technology) for selected key
laboratories.
7.2 Improvements to groundwater • Provision of monitoring equipment, increasing the network of monitoring wells 3.0 PPTA Phase 3
monitoring network in the (60 additional wells are estimated to be needed).
Bandung area • Improvement to groundwater database(s) and computer models.
7.3 Improvements to water and • Review existing database arrangements in the various agencies that collect 0.5 PPTA Phase 3
natural resource data water and other natural resource data in the basin.
management and • Recommend improvements to data management, including: institutional
dissemination arrangements (introduction of the “custodianship” concept); data management
policy; and introduction of new technology.
• Recommend improvements to policies and processes for data sharing and
dissemination, including the establishment of a publicly accessible website
where data can be accessed.
7.4 Land degradation and • Provide necessary hardware and software, and training in their use to 0 PPTA Phase 3
biodiversity database for CRB technicians that will be responsible for developing and maintaining the
databases.
• Establish comprehensive Land Degradation and Biodiversity database files
(both in MoF) that are compatible with requirements of the CRB Council and
other natural resource managers.
• Develop suitable Internet based data access systems so that the information
can be readily accessed by the planners, researchers and conservation
managers for the Council.
21
Key Areas – Intervention Outlines
COST
KEY AREA Intervention MAIN OUTPUTS / ACTIVITIES SOURCE
($ million)
7.5 Development of an on-line flow • Undertake hydrologic investigations to confirm operational and economic 1.6 Master Plan
forecasting system on benefits of flow forecasting. 1997
unregulated rivers • Determine key sites for forecasting.
• Examine technological options.
• Acquire and/or develop hardware and software.
• Install system and commission.
• Provide training to system operators to maximize benefits from the system.
7.6 Establishment of an annual • Review of “state of the basin” reporting procedures in other countries. 0.3 PPTA Phase 3
“state of the basin” report • Development and implementation of an appropriate process to produce and
disseminate a “state of the basin” report to identify problem areas,
cause/sources and needed remedies
7.7 Development of an integrated • Identify potentially useful modelling packages that might be used to develop an 0.6 PPTA Phase 3
water quality and quantity integrated river basin water quantity/quality model for the Citarum, and select
model for basin planning the most suitable (against agreed criteria).
studies, and a decision support • Assemble data, develop the model, then calibrate and verify.
tool for improved policy and
• Design and implement a decision support tool for use by relevant agencies for
decision making
policy and planning, that uses the water quantity/quality model as a key element
for analysing scenarios.
7.8 Institutional strengthening and • Identify key research institutions, including universities, government institutes 3.0 PPTA Phase 3
capacity building of water and so on, working in the field of water research, particularly for the Citarum
research organizations River Basin.
• Undertake a needs analysis for capacity building, both for human resources
development and technology, required to undertake effect water-related
research.
• With the selected organizations, identify critical knowledge gaps in the water
field in the Citarum River Basin.
• Prepare and implement appropriate training programs in selected organizations.
• Procure and install appropriate new technology.
7.9 Benchmarking of water and • Identify key water and natural resource data collection and management 0.6 PPTA Phase 3
natural resource data collection agencies that in some way contribute to databases in the basin.
and management agencies • Review best practices from agencies overseas for data collection, management
and dissemination.
• Benchmark identified agencies against best practices.
• Make appropriate recommendations for improvement of data collection,
management and dissemination practices.
Estimated Total Cost 9.6 million USD
22
Citarum Integrated Water Resource Management Project
Report on Roadmap and Program Development
OUTCOME
Improved and integrated water resource • To have appropriate and effective institutional • Legislation and policy documents • Institutional arrangements to be put in
management in place, with government and the arrangements in place for integrated water released by GOI place under new legislation provides a
community working in partnership to achieve a resource management in the basin • Minutes of meetings of the robust framework for IWRM and
shared vision [Note that assistance to put those Citarum Basin Council and other clearly separates resource
arrangements in place will be provided key organisations in the management and development/
through an ADB grant to fund a technical management of the water operational responsibilities
assistance that will run in parallel with resource of the CRB • The government agencies at national,
Tranche 1]
• Progress and final reports of provincial and district level have the
• To have effective partnerships between individual projects funded under resolve to involve the community
government agencies at national, provincial the loan meaningfully in all stages of water
and district level in place to implement resource planning and management
• Survey of communities meant to
planned water and land management • The community is willing to participate
benefit from activities funded
activities to be funded under the MFF loan effectively in all stages of water
under the loan
• To have the community empowered and resource planning and management
• Published information on
capable to play a vital role in the • Agencies are truly willing to share
available databases related to
management of water and land resources information for the benefit of all valid
water, land and related resources
• To have water control infrastructure in place users
to manage the water resource in such a way
as to provide equitable access to good
quality water by all authorised water users
• To have comprehensive and accessible
databases in place to provide decision-
makers, water managers and technical
experts with the best information to
undertake their responsibilities for water
resource management
1
13/12/2006 1:20 PM
DESIGN SUMMARY PERFORMANCE DATA SOURCES ASSUMPTIONS AND RISKS
OUTPUTS
Tranche 1 (Q3 2007 – Q4 2011)
1.1 Rehabilitation of West Tarum Canal • West Tarum Canal restored to its design • Project completion report(s) • Design capacity agreed to is adequate
capacity • Post-completion surveys of water for future water supply needs of
• Water quality improved through exclusion of quality parameters along the Jakarta and irrigation
inflows of polluted water from crossing canal • Agreement with informal settlers will
stream through construction of siphons • Measurement of canal flow rates be reached on resettlement and
• Water control structures restored to full • Post-completion survey of local
compensation arrangements
operational status communities
• Environmental impacts minimised, and in
particular through proper disposal of dredged
material
• Social disruption for those living along the
canal minimised, and in particular access to
water supply and sanitation maintained and
improved if necessary
Sub-Components: Cost: $42,900,000
• Detailed engineering design
• Tendering
• Construction of improvement works
• Associated activities
1.2 Water Supply Options and Improved • The stakeholder forum for Bandung Sub- • Records of forum meetings • Strong commitment from local
Groundwater Management for Basin formed and operating effectively stakeholders to establish the forum
• Feedback from stakeholders
Bandung according to its mandate (to be defined and to participate meaningfully
gained form workshops and other
during the project)
consultations • Willingness of local authorities to
• Broad stakeholder agreement achieved for
preferred option(s) for increasing surface • Ministry of Mines and Energy support the stakeholder forum and
records recognise its value in providing advice
water supplies for Bandung
• Improved groundwater monitoring network in • Post-project surveys • Broad acceptance of the need for
place better management of the limited
groundwater resources and willingness
• A high level of compliance with regulations to comply with regulations
for sustainable groundwater management in
Bandung achieved
Sub-Components: Cost: $4,800,000
• Development of options for increase in surface water supplies
• Improved implementation of regulations for sustainable groundwater management in Bandung
• Improvements to groundwater monitoring network
• Establishment of, and ongoing support for, a stakeholder forum for Bandung Sub-Basin
2
13/12/2006 1:20 PM
DESIGN SUMMARY PERFORMANCE DATA SOURCES ASSUMPTIONS AND RISKS
1.3 Roll-Out of System Rice • Increase in rice yield of greater than 60% • District Agriculture Services • The MOF at national, provincial and
Intensification [Phase 1 - Three • Reduction in need for irrigation water of 45%. records district level are fully committed to
Districts] • implementing this component. They
• Increase in income of rice farmers of at least Farmer surveys
will provide all the trained staff that will
90%. • Appraisal reports
undertake the training program for
• Increase in labour demand of at least 30% farmers.
• Farming communities willing to
participate this component are
identified early in this program.
• The SRI model that will be used has
been proven successful and
sustainable in other main paddy
growing areas in Indonesia.
• All the material required including
seed, organic digester and organic
manure are made available to the
participating farmers.
• Supply of organic manure is increased
at all project sites.
• Farmers are trained on integrated pest
management leading to a reduction in
the use of chemicals and pesticides.
• The project will monitor all aspects of
this program and identify key problems
and take immediate action to resolve
them immediately.
• Farmers organizations are trained to
continue this project activity after the
initial work carried out by the project
staff.
Sub-Components: Cost: $4,170,000
• Identification and appraisal of target areas
• Capacity building
• Progressive implementation of SRI
• Management, monitoring and reporting
3
13/12/2006 1:20 PM
DESIGN SUMMARY PERFORMANCE DATA SOURCES ASSUMPTIONS AND RISKS
1.4 Support for Community- and NGO- • Capacity of participating communities (and • Project progress and financial • Continued support by GOI for the
Driven Initiatives for Improved Water particularly the community implementation reports community-based approach
and Catchment Management teams) enhanced to a level that enables • Survey of participating • Continued support by people in local
effective development and implementation of communities communities
action plans
• Feedback from trainers • Appropriate financing mechanism can
• Action plans developed in participating
• Project completion reports be developed and agreed to by GOI
communities that will lead to improved water
• Continued support by people in local
and catchment management and can be
communities and contribution of labour
implemented locally
and other in-kind inputs
• Appropriate financing mechanism that will
• Funding is made available in a timely
enable participating communities to have
manner and is used wisely in
access to sufficient funds for implementation
accordance with the agreed action
of their action plans
plans
• Action plans implemented successfully within
• Sufficient numbers of local project
agreed time and budget
managers are available
• Project completed on time and on budget to
• Project management is effectively
the agreed standard of quality
undertaken
Sub-Components: Cost: $5,640,000
• Capacity building of local communities
• Assistance to develop village WSS plans
• Implementation of plans and ongoing support
• Programs aimed at behavioural change
4
13/12/2006 1:20 PM
DESIGN SUMMARY PERFORMANCE DATA SOURCES ASSUMPTIONS AND RISKS
1.5 Development and Implementation of a • Key new policies and procedures for water • Project progress reports • Government agencies at all levels will
Basin River Quality Improvement quality management in place and being • Project completion report adopt the new policies and procedures
Strategy and Action Plans implemented effectively •
• GOI policy documents Agencies responsible for water quality
• Improved water quality monitoring system in monitoring and management will
• GOI publications related to water
place and being effectively operated and effectively operate and maintain the
quality records (several agencies)
maintained data systems
• Post-project survey of
• A water quality and pollution source database • Organisations have the desire to
organisations and the community
management system in place and being improve their capacity for water quality
effectively operated and maintained • Records (including minutes of management
meetings) held by the Water
• Appropriate (and well-calibrated and • Responsibilities for implementing the
Resources Council
validated) issue-specific water quality models RWQIS are clearly assigned
in place and being effectively operated and • Organisations with the mandate to
maintained (these should link with the basin- implement the RWQIS undertake their
wide water quantity/quality model – see responsibilities effectively and
Output 6.2) coordinate amongst each other
• An Internet-based WQM information system • Responsibilities for implementing the
to link the district environmental agencies action plans are clearly assigned, and
with other key agencies sufficient GOI funds are made
• Environmental agencies at all levels, available
universities and research organizations have • Organisations with the mandate to
the capacity to undertake water quality implement the action plans undertake
management activities within their mandate their responsibilities effectively and
• Community awareness and understanding of coordinate amongst each other
water quality issues, and how they can • Local project managers are made
contribute to improved water quality, is raised available to manage the various
• Multi-agency/stakeholder planning and activities of the project
coordination system for water quality • Project management is effectively
management in place under the Water undertaken
Resources Council
• Basin-wide River Quality Improvement
Strategy developed, promulgated and being
effectively implemented through action plans
• Water quality management action plans -
combining cooperation, regulatory and
incentive instruments – in place and being
implemented effectively
Sub-Components: Cost: $6.420,000
• Policies and procedures for water quality management
• Improvements to water quality monitoring and data management
• Strengthening of organizational capacity
• Preparation of basin-wide River Water Quality Improvement Strategy (RWQIS)
• Preparation and implementation of area-based pollution sources management action plans
5
13/12/2006 1:20 PM
DESIGN SUMMARY PERFORMANCE DATA SOURCES ASSUMPTIONS AND RISKS
1.6 Program Management • Executing agencies and other relevant • Minutes of meetings and • GOI continues to support the
stakeholders well informed about program workshops with executing execution of the projects and facilitates
progress agencies and other relevant stakeholder support for their
• Executing agencies and other relevant stakeholders preparation
stakeholders participating effectively in • Program status reports • There is a willingness by those
setting the direction of the program and its • Minutes of periodical coordination involved in each of the component
projects workshops projects under this tranche to
• Projects well coordinated, with opportunities cooperate and share information
• Final reports of studies
for information exchange maximised, and • Stakeholders provide sufficient
• Reports produced
conflicts among projects minimised information to identify priority
• Documentation submitted for knowledge gaps
• Priority information needs identified, and
approval of Tranche 2
minor studies undertaken on time and within • Local organisations can be found to
budget that redress those needs • Surveys of NGO representatives undertake the studies effectively
• All monitoring and reporting undertaken in • Reports describing activities of • NGOs are willing to be trained and
accordance with agreed procedures NGOs with respect to the project participate
• Procedures for preparation of PFR for • Monitoring and reporting procedures
Tranche 2 followed and documentation are agreed in advance and adhered to
prepared in accordance with ADB standards • Consultants, local counterparts and
GOI officials work together effective to
prepare the documentation
• ADB and GOI requirements are made
clear and do not change
Sub-Components: Cost: $2,570,000
• Liaison with executing agencies and other relevant stakeholders
• Coordination among projects
• Identify the need for and coordinate implementation of minor studies (up to $400,000 total) to improve knowledge of water issues
in CRB
• Monitoring and reporting of project performance
• Capacity building for NGOs involved in the component projects of Tranche 1
• Coordination of preparation for Tranche 2
6
13/12/2006 1:20 PM
DESIGN SUMMARY PERFORMANCE DATA SOURCES ASSUMPTIONS AND RISKS
Tranche 2 (Q1 2010 – Q4 2015)
2.1 Upgrading of water source for • All civil and associated works completed on • Project completion report • This project is the recommended
Bandung and other uses by inter- time and budget, to agreed quality standards • Inter-district agreement option for surface water supply
basin transfer • All systems commissioned and meeting augmentation in the Bandung Water
agreed service standards Supply Options Study (Tranche 1)
• Inter-district agreement regarding cost • The “donor” district is agreeable to the
allocation and ongoing financial inter-basin transfer at a fair and
arrangements for diverted water negotiated reasonable cost
and finalized • All necessary social and environmental
• All necessary social and environmental safeguards are identified and
safeguards are put in place implemented
• A high level of technical design is
achieved for the project
• Qualified and skilled contractors are
selected for the civil and associated
works, and undertake the construction
to agreed quality standards
• Effective construction supervision is
carried out
Sub-Components: Cost: $190,000,000
• Construction of Cibutarua Weir
• Construction of Santosa Reservoir on the Cilaki River
• Construction of a 4.5 km diversion tunnel
• Construction of a reservoir upstream of Tamiang Cangkir Weir, needed to compensate irrigation downstream of Cibutarua Weir
• Development of an inter-district agreement regarding cost allocation and ongoing financial arrangements for diverted water
7
13/12/2006 1:20 PM
DESIGN SUMMARY PERFORMANCE DATA SOURCES ASSUMPTIONS AND RISKS
2.2 System Service Improvement and • All civil and associated works completed on • Project completion report(s) • All necessary social and environmental
Irrigation Modernization – East Tarum time and budget, to agreed quality standards • Post-completion surveys of water safeguards are identified and
Canal • East Tarum Canal restored to its design quality parameters along the implemented
capacity canal • A high level of technical design is
• Water control structures restored to full • Measurement of canal flow rates achieved for the project
operational status • Post-completion survey of local • Qualified and skilled contractors are
• Environmental impacts minimised, and in communities selected for the civil and associated
particular through proper disposal of dredged works, and undertake the construction
material to agreed quality standards
• Social disruption for those living along the • Effective construction supervision is
canal minimised, and in particular access to carried out
water supply and sanitation maintained and
improved if necessary
Sub-Components: Cost: $126,200,000
• Rehabilitation of the East Tarum Canal, including removal and disposal of sediments, and repair and strengthening of
embankments
• Rehabilitation of secondary and tertiary canals and water control structures
• Installation of off-take measurement apparatus
• Strengthening of institutions for Participatory Irrigation Management among farmers
2.3 Development of strategies and • Water conservation awareness among • Post-project surveys • Communities are receptive to
options for demand management and community and industries in the CRB (and • Measurement of water losses in behavioural change
water conservation with respect to particularly in the Bandung and Bekasi areas) reticulation systems • GOI is willing to make rational
industrial and domestic use raised
• Documentation on water pricing decisions on water pricing and
• Community behaviour towards water use and policies implement them
hygiene changed
• Losses from water reticulation systems
substantially reduced
• New pricing structures that better reflect cost
of delivery and provide incentives for rational
water use developed and implemented
Sub-Components: Cost: $500,000
• Development and implementation of strategies and actions for water conservation awareness raising and behavioural change
among the community and industries
• Development and implementation of strategies and actions for industrial water recycling (including regulatory and technological
measures), and assistance to industries to install recycling technology
• Development and implementation of strategies and actions for minimisation of losses from water reticulation systems
• Review of current water pricing policies and development of new pricing structures that better reflect cost of delivery and provide
incentives for rational water use
8
13/12/2006 1:20 PM
DESIGN SUMMARY PERFORMANCE DATA SOURCES ASSUMPTIONS AND RISKS
2.4 Development and implementation of a • A system of surface water entitlements and • Approved policy documents on • GOI is willing to actively pursue the
water entitlements and licensing licensing (to manage compliance with water entitlements and licensing development and implementation of a
system for surface water users entitlements) appropriate to the Citarum • Post-implementation audits of system of surface water entitlements
situation developed and in place system operation in relevant and licensing
• Staff in the relevant agencies having the agencies • Relevant agencies are willing to
necessary technology and capable of • Records of licences, including actively manage compliance with
operating and maintaining the licensing non-compliance and actions licensing conditions, including
system taken. prosecution and sanctions as may be
• Licence compliance systems in place and necessary
operating effectively • Surface water users are generally
willing to cooperate and see the
benefits of the system, including more
equitable sharing of water amongst
users
Sub-Components: Cost: $2,400,000
• Examination of existing arrangements for managing surface water extractions across the basin
• Review water entitlement allocation and management mechanisms in other countries, both developed and developing
• Design a system of surface water entitlements and licensing (to manage compliance with entitlements) appropriate to the Citarum
situation
• Prepare an implementation plan for the surface water licensing system, including agency responsibilities, technology and human
resource requirements, and training program, and schedule of activities
• In accordance with the implementation plan developed previously, implement the licensing system within the relevant agencies,
including:
o Acquisition and installation of hardware and software
o Preparation of forms and other standard documentation
o Training of staff
o Awareness raising program for water users
o Implementation of licensing procedures
• Progressive “roll-out” of the system, starting with major users of bulk water
9
13/12/2006 1:20 PM
DESIGN SUMMARY PERFORMANCE DATA SOURCES ASSUMPTIONS AND RISKS
2.5 Review of allocation priorities and • An approved GOI policy on allocation of • Government approved policy • Consensus can be obtained among
optimisation of operating rules for key water amongst users in the CRB in place, documents agencies representing different water
sub-basins, including the operation of including clear procedures for sharing water • Reservoir operation records user groups about water allocation
the river / reservoir system as a whole during periods of drought priorities
• Streamflow monitoring records
• An effective conflict/dispute resolution • GOI is prepared to change allocation
mechanism in place and operating priorities if necessary
• Environmental and flushing flows agreed to • Reservoir operators comply with new
and implemented in reservoir operating protocols
protocols
• Updated and appropriate operating rules for
key sub-basins developed and being followed
Sub-Components: Cost: $900,000
• Review of the effectiveness of existing water sharing arrangements (including water exported to Jakarta)
• Development of an updated policy for water sharing among water users in the basin, as well as Jakarta, including an effective
conflict/dispute resolution mechanism
• Determination of environmental flow requirements to maintain water quality, as well as flushing flows for sediment and salinity
reduction in lower reaches
• Development of updated and appropriate operating rules for key sub-basins, including the operation of the river / reservoir system
as a whole
• Review of allocation priorities and clear procedures for sharing water during periods of drought
2.6 Development and implementation of • IEAS and action plan completed • Project documentation • Communities are receptive to
an Information, Education and • Implementation of action plan • Post-project survey of the awareness raising activities
Awareness Strategy for capacity •
• Increase in community awareness of water community Media (newspapers, radio, TV) support
building of communities across the awareness-raising activities
basin for improved participation in resource management issues
• Education authorities agree to modify
water resources policy development,
planning and management curricula to include teaching of water
and environment related principles
Sub-Components: Cost: $1,500,000
• Identification of key stakeholders in the basin (target groups) and behaviours with regard to activities impacting on water resource
management
• Identification of messages and knowledge that needs to be communicated to each target group
• Identification of an community participation strategy for different aspects of water resources planning and management and
relevant and available communication channels
• Development of the IEAS and action plan based on a “social marketing” approach, and to include school education as a key
element
• Implementation of action plan
10
13/12/2006 1:20 PM
DESIGN SUMMARY PERFORMANCE DATA SOURCES ASSUMPTIONS AND RISKS
2.7 Program Management • Monitoring and reporting systems, including • Project reports and other • GOI continues to support the
financial systems, in place and operating documentation execution of the projects and facilitates
effectively • Audit reports stakeholder support
• All ADB and GOI monitoring and reporting • Minutes of coordination and • There is a willingness by those
requirements satisfied stakeholder meetings involved in each of the component
• Effective coordination among component projects under this tranche to
projects cooperate and share information
• Effective information exchange among • Monitoring and reporting procedures
component project teams are agreed in advance and adhered to
• Tranche 3 component projects prepared • Consultants, local counterparts and
effectively GOI officials work together effective to
prepare the documentation
• ADB and GOI requirements are made
clear and do not change
Sub-Components: Cost: $2,400,000
• Liaison with executing agencies and other relevant stakeholders
• Coordination among projects
• Monitoring and reporting of project performance
• Coordination of preparation for Tranche 3
Tranche 3 (Q3 2013 – Q4 2017)
3.1 System Service Improvement and • All civil and associated works completed on • Project completion report(s) • All necessary social and environmental
Irrigation Modernisation – North time and budget, to agreed quality standards • Post-completion surveys of water safeguards are identified and
Tarum Canal • North Tarum Canal restored to its design quality parameters along the implemented
capacity canal • A high level of technical design is
• Water control structures restored to full • Measurement of canal flow rates achieved for the project
operational status • Post-completion survey of local • Qualified and skilled contractors are
• Environmental impacts minimised, and in communities selected for the civil and associated
particular through proper disposal of dredged works, and undertake the construction
material to agreed quality standards
• Social disruption for those living along the • Effective construction supervision is
canal minimised, and in particular access to carried out
water supply and sanitation maintained and
improved if necessary
Sub-Components: Cost: $95,100,000
• Rehabilitation of the North Tarum Canal, including removal and disposal of sediments, and repair and strengthening of
embankments
• Rehabilitation of secondary and tertiary canals and water control structures
• Installation of off-take measurement apparatus
• Strengthening of institutions for Participatory Irrigation Management among farmers
11
13/12/2006 1:20 PM
DESIGN SUMMARY PERFORMANCE DATA SOURCES ASSUMPTIONS AND RISKS
3.2 Improvement in water quality in • Action plan for reducing pollution developed • Project completion report • Support from PLN and PJT II
Saguling, Cirata and Jatiluhur and implemented • Site surveys • Affected fisherfolk and others are
Reservoirs through management of • Social safeguards (including alternative • Water quality measurements willing to accept resettlement and
fish farming and other polluting livelihoods for affected fisherfolk and others) alternative livelihoods
activities developed and put in place
Sub-Components: Cost: $1,500,000
• Identify sources and extent of pollution in Saguling, Cirata and Jatiluhur Reservoirs
• Determine the economic impacts of pollution on other uses of water (such as hydropower)
• Identify actions needed to reduce pollution
• Identify possibilities for alternative livelihoods for fish farmers and others that may be impacted by controls on fish farming and
other polluting activities
• Develop and implement an action plan for reducing pollution
3.3 Development and Implementation of • Strategy and action plan for ICZM developed • Project documents • Coastal communities support initiatives
Integrated Coastal Zone Management • Improvements made to policies and • Site surveys to improve coastal zone planning and
Strategy and Action Plan for Citarum legislation that will lead to a more integrated management
Coastline • Key agency records
approach to CZM
• Monitoring, data collection and databases for
CZM improved
• ICZM action plan implemented, including
development of spatial plans
Sub-Components: Cost: $10,900,000
• Identify key issues for resource management in the CRB coastal zone
• Review existing policies and legislation regarding management of natural and man-made resources in the coastal zone
• Recommend improvements to policies and legislation that will lead to a more integrated approach to CZM
• Review existing knowledge base for coastal zone resources and recommend improvements to monitoring and data collection,
using GIS
• Identify key sites where interventions are required to address local resource management issues
• Identify strategies required to achieve ICZM
• Develop an action plan to implement the agreed strategies, including spatial planning
• Implement the ICZM action plan
12
13/12/2006 1:20 PM
DESIGN SUMMARY PERFORMANCE DATA SOURCES ASSUMPTIONS AND RISKS
3.4 Program Management • Monitoring and reporting systems, including • Project reports and other • GOI continues to support the
financial systems, in place and operating documentation execution of the projects and facilitates
effectively • Audit reports stakeholder support
• All ADB and GOI monitoring and reporting • Minutes of coordination and • There is a willingness by those
requirements satisfied stakeholder meetings involved in each of the component
• Effective coordination among component projects under this tranche to
projects cooperate and share information
• Effective information exchange among • Monitoring and reporting procedures
component project teams are agreed in advance and adhered to
• Tranche 4 component projects prepared • Consultants, local counterparts and
effectively GOI officials work together effective to
prepare the documentation
• ADB and GOI requirements are made
clear and do not change
Sub-Components: Cost: $1,500,000
• Liaison with executing agencies and other relevant stakeholders
• Coordination among projects
• Monitoring and reporting of project performance
• Coordination of preparation for Tranche 4
Tranche 4 (Q1 2018 – Q4 2021)
4.1 Raising of Cirata Dam • All civil and associated works completed on • Project completion report • All necessary social and environmental
time and budget, to agreed quality standards safeguards are identified and
• All systems commissioned and meeting implemented
agreed service standards • A high level of technical design is
• All necessary social and environmental achieved for the project
safeguards are put in place • Qualified and skilled contractors are
selected for the civil and associated
works, and undertake the construction
to agreed quality standards
• Effective construction supervision is
carried out
Sub-Components: Cost: $20,100,000
• Undertake feasibility study
• Do detailed engineering design
• Construct dam and associated works, and commission
13
13/12/2006 1:20 PM
DESIGN SUMMARY PERFORMANCE DATA SOURCES ASSUMPTIONS AND RISKS
4.2 Development and Implementation of • Detailed feasibility studies (including costing, • Project progress reports and • All necessary social and environmental
Preferred Bulk Water Supply Options environmental impact assessment, and completion report safeguards are identified and
for Bekasi and Karawang resettlement action plans, etc) and • Site inspection reports implemented
preparation of SPARs completed • A high level of technical design is
• Detailed engineering design on selected achieved for the project
option(s) completed • Qualified and skilled contractors are
• Construction and commissioning of selected selected for the civil and associated
option(s) completed on time and on budget works, and undertake the construction
to agreed quality standards
• Effective construction supervision is
carried out
Sub-Components: Cost: $50,000,000
• Establishment of a stakeholder-driven selection process of options to improve the availability of bulk water supplies to Bekasi and
Karawang to meet the DMI demand to 2025
• Execution of rapid surveys and pre-feasibility studies (review and update any previous feasibility studies) in order to arrive at a
short-list of the most viable potential options
• Preparation of detailed feasibility studies (including costing, environmental impact assessment, and resettlement action plans, etc)
leading to the preparation of SPARs (subproject appraisal reports)
• Detailed engineering design on selected option(s)
• Preparation of tender documents; contract awards
• Construction and commissioning of selected option(s)
4.3 Cisankuy Irrigation Improvement • All civil and associated works completed on • Project progress reports and • All necessary social and environmental
time and budget, to agreed quality standards completion report safeguards are identified and
• All systems commissioned and meeting • Site inspection reports implemented
agreed service standards • A high level of technical design is
• All necessary social and environmental achieved for the project
safeguards are put in place • Qualified and skilled contractors are
• Improved cropping patterns in the Cisankuy selected for the civil and associated
area identified and implemented works, and undertake the construction
to agreed quality standards
• Effective construction supervision is
carried out
Sub-Components: Cost: $65,500,000
• Undertake feasibility study for Cisankuy Reservoir
• Detailed engineering design
• Construct and commission dam and associated works
• Develop improved cropping patterns in the Cisankuy area, to save water
14
13/12/2006 1:20 PM
DESIGN SUMMARY PERFORMANCE DATA SOURCES ASSUMPTIONS AND RISKS
4.4 Program Management • Monitoring and reporting systems, including • Project reports and other • GOI continues to support the
financial systems, in place and operating documentation execution of the projects and facilitates
effectively • Audit reports stakeholder support
• All ADB and GOI monitoring and reporting • Minutes of coordination and • There is a willingness by those
requirements satisfied stakeholder meetings involved in each of the component
• Effective coordination among component projects under this tranche to
projects cooperate and share information
• Effective information exchange among • Monitoring and reporting procedures
component project teams are agreed in advance and adhered to
• High quality program completion report • Consultants, local counterparts and
submitted on time GOI officials work together effective to
prepare the documentation
• ADB and GOI requirements are made
clear and do not change
Sub-Components: Cost: $1,200,000
• Liaison with executing agencies and other relevant stakeholders
• Coordination among component projects
• Monitoring and reporting of project performance, including financial
• Preparation and submission of program completion report
15
Citarum Integrated Water Resource Management Project
Report on Roadmap and Program Development
Annex 4 Indicative
Implementation Schedule – Total
Investment Program
INTEGRATED CITARUM WATER RESOURCE MANAGEMENT PROJECT
INDICATIVE MULTITRANCHE FINANCING FACILITY PROGRAM (INCLUDING PARALLEL FINANCED PROJECTS)
PROJECT 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
Tranche 1
Loan Financed
Rehabilitation of West Tarum Canal
Parallel Financed
Institutional Strengthening for IWRM
(ADB TA)
Productive Reforestation of Degraded Catchments [Phase 1]
(GEF)
Protected Area Management (Biodiversity) [Phase 1]
(GEF)
Project Preparation for Tranche 2
(ADB TA)
Tranche 2
Loan Financed
Upgrading of water source for Bandung and other uses by inter-basin
transfer
System Service Improvement – East Tarum Canal
Parallel Financed
Ongoing support for WRC and supporting office(s), and capacity
building for WRM agencies at provincial and district level
Policy development for appropriate water pricing, water allocation and
balanced stakeholder participation
Development of strategies and options for demand management and
water conservation with respect to industrial and domestic use
Review of allocation priorities and optimization of operating rules for
key sub-basins, including the operation of the river / reservoir system
Productive Reforestation of Degraded Catchments [Phase 2]
(GEF)
Protected Area Management (Biodiversity) [Phase 2]
(GEF)
Project Preparation for Tranche 3
(ADB TA)
PROJECT 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
Tranche 3
Loan Financed
System Service Improvement – North Tarum Canal
Parallel Financed
Mini- and Micro- Hydropower Basin Study
Tranche 4
Loan Financed
Raising of Cirata Dam
Parallel Financed
Investigation of water supply and sanitation options for urban areas
(apart from Bandung, Bekasi and Karawang)
Development of an on-line flow forecasting system on unregulated
rivers
TOTAL LOAN FINANCED
TOTAL PARALLEL FINANCED Procurement of consultants
CONTINGENCIES Project implementation
TOTAL PROGRAM
Citarum Integrated Water Resource Management Project
Report on Roadmap and Program Development
1
15/12/2006 10:03 AM
2
15/12/2006 10:03 AM
3
15/12/2006 10:03 AM
4
15/12/2006 10:03 AM
5
15/12/2006 10:03 AM
6
15/12/2006 10:03 AM
7
15/12/2006 10:03 AM
8
15/12/2006 10:03 AM
9
15/12/2006 10:03 AM
10
15/12/2006 10:03 AM
11
15/12/2006 10:03 AM
12
15/12/2006 10:03 AM
8.3 Implementation of action plans • Specific area to be reforested by 148 model • Village action plan maps. • Villager interest in developing
villages identified in reforestation spatial • Village spatial maps. village maps, nurseries and utilizing
map. government lands for reforestation
• Legal tenure agreements.
• Areas to be replanted by each village through lease agreements.
• Monitoring reports of leasing
mapped with GPS and located on • Villagers have the capacity to carry
agreements.
reforestation map. out reforestation and protect their
• Nurseries adequate to reforest each village • Reports of project consultants plantations from vandals.
employed to advise and assist with
component of the reforestation spatial map • Project model village mentors have
developed by model villages. reforestation and best farming practices
the capacity to assist implement
• Tenure agreements signed between each activities.
village and with appropriate government
agency.
• 70% of leased areas by each model village
replanted with mixed trees as a dominant
vegetation
8.4 Institutional development • Project spatial plans inculcated into • Provincial, district and village spatial • Government spatial planners are
provincial, districts and village spatial plans. plans. interested in participating in the
• Spatial planning staff from the province and • Project supervisor reports on trainees. project exercises.
districts trained by programmatic activities • Post project survey of accuracy of • Spatial planners in programmatic
working with the Project planning team. locations in spatial plans training remain in their posts to
• Accuracy of spatial plans improved such influence later iterations of their
that positions within spatial zones can spatial plans
readily be located with GPS
8.5 Improvement to village land tenure arrangements • Land tenure arrangements for periods of • Tenure agreement documents • leases on their land for periods >30
with Perum Perhutani >30 years available to farmers years to encourage villagers to
plant trees and not annual crops
8.6 Alternative livelihoods for displaced upland forest • 3000 Upland farmers assisted to establish • Tenure agreements with government • Conflicts between displaced upland
villagers mixed tree farms in government lands agencies farmers and local farmers for leases
to reforest government land.
13
15/12/2006 10:03 AM
14
15/12/2006 10:03 AM
15
15/12/2006 10:03 AM
16
Citarum Integrated Water Resource Management Project
Report on Roadmap and Program Development
Annex 6 Proposed
Implementation Schedule –
Tranche 1
Integrated Citarum Water Resources Project - Tranche 1
WBS Task Name Estimated Indicative Funding Implementing
Duration Cost Source Agency 2007 2008 2009 2010 2011
($'000) Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
0 Total Tranche 1 60 79,230
months
1 Program Management 60 months 2,000 AusAID Balai Besar
Page 1
Integrated Citarum Water Resources Project - Tranche 1
WBS Task Name Estimated Indicative Funding Implementing
Duration Cost Source Agency 2007 2008 2009 2010 2011
($'000) Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2 Institutional Strengthening for Integrated Water Resources 48 months 2,400 ADB TA Balai Besar
Management
2.1 Procurement of Consultants
2.1.1 Procure consultants 6 months
2.2 Sub-Component 1: Capacity Building and Support 800
2.2.1 Assistance in establishing the Water Resources Council (covering 6 months
Citarum and eastern Basins), river basin management office and
support unit(s) for improved policy development and coordination
2.2.2 Ongoing support and capacity building for the Council, river basin 36 months
management office and support unit(s)
2.3 Sub-Component 2: Data and Modelling 750
2.3.1 Establish a land degradation and biodiversity database for CRB,
consolidating existing data from various organisations
2.3.5 Design and implement a decision support tool for use by relevant 4 months
agencies for policy and planning
2.4 Sub-Component 3: "State-of-the-Basin" Reporting 250
2.4.1 Review of “state of the basin” reporting procedures in other countries 3 months
Page 2
Integrated Citarum Water Resources Project - Tranche 1
WBS Task Name Estimated Indicative Funding Implementing
Duration Cost Source Agency 2007 2008 2009 2010 2011
($'000) Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
3 Water Supply Options and Improved Groundwater Management 36 months 5,900 MFF
for Bandung Tranche 1
3.1 Procurement of Consultants
3.1.1 Procure consultants 6 months
3.2 Sub-Component 1: Options for Increase in Surface Water Supplies 2,000
3.2.1 Execution of rapid surveys and pre-feasibility studies (review and 6 months
update any previous feasibility studies) in order to arrive at a short-list
of the most viable potential options
3.2.2 Preparation of detailed feasibility studies (including costing, 6 months
environmental impact assessment, and resettlement action plans,
etc) leading to the preparation of SPARs
3.2.3 Detailed engineering design for selected option(s) for Bandung 10 months
supplementary surface water supply
3.3 Sub-Component 2: Improved implementation of regulations for 600
sustainable groundwater management in Bandung
3.3.1 Review of existing regulatory framework for ground¬water 2 months
management in the Bandung area
3.3.2 Evaluation of existing implementation of regulation and identification 2 months
of deficiencies
3.3.3 Development of strategies and an action plan for improved 4 months
effectiveness of regulation of groundwater use, including
recommendations for changes to the existing regulatory framework
3.3.4 Development of a monitoring and evaluation mechanism 2 months
3.3.5 Capacity building of agencies involved in groundwater management 2 months
3.4 Sub-Component 3: Improvements to groundwater monitoring 3,000
network
3.4.1 Provision and installation of monitoring equipment, increasing the 20 months
network of monitoring wells
3.4.2 Review of existing groundwater databases and models, and 3 months
identifacion of improvements needed
3.4.3 Improvement to groundwater database(s) and computer models 12 months
3.5 Sub-Component 4: Establishment of, and ongoing support for, a 300
stakeholder forum for Bandung Sub-Basin under Citarum Basin
3.5.1 Work with the Citarum Basin Water Resources Council or Citarum 2 months
Balai Besar to determine its composition and mandate
3.5.2 Legally and practically establish the forum 4 months
3.5.3 Provide ongoing support (financial and advisory) to the forum for up 24 months
to two years
Page 3
Integrated Citarum Water Resources Project - Tranche 1
WBS Task Name Estimated Indicative Funding Implementing
Duration Cost Source Agency 2007 2008 2009 2010 2011
($'000) Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
4 Rehabilitation of the West Tarum Canal 54 months 43,000 MFF
Tranche 1
4.1 Procurement of Consultants
4.1.1 Procurement of DED/Construction Supervision Consultant 6 months
Page 4
Integrated Citarum Water Resources Project - Tranche 1
WBS Task Name Estimated Indicative Funding Implementing
Duration Cost Source Agency 2007 2008 2009 2010 2011
($'000) Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
5 Roll-Out of System Rice Intensification in Three Districts (two 54 months 4,300 MFF
downstream and one upstream) Tranche 1
5.1 Procurement of Consultants
5.1.1 Procure consultants 6 months
5.2 Sub-Component 1: Appraisal of Target Areas 60
5.2.1 Participatory Rural Appraisal for 3 districts and 16 sub-districts 42months
intermittent
5.3 Sub-Component 2: Capacity Building 1,120
5.3.1 Training of Trainers for 800 farm leaders 45 months
intermittent
5.3.2 Training for 20,000 farmers 45 months
intermittent
5.3.3 Implementation of SRI in 80 demonstration plots 45 months
intermittent
5.3.4 Farmer empowerment – 660 sessions of training 42 months
intermittent
5.4 Sub-Component 3: Progressive implementation of SRI 2,520
5.4.1 Production of organic fertilizer – distribution of 400 units 45 months
intermittent
5.4.2 Acquisition and distribution of 10,000 decomposer kits 45 months
intermittent
5.4.3 Acquisition and distribution of 50,000 kg of selected seeds 45 months
intermittent
5.5 Sub-Component 4: Management, monitoring and reporting 600
5.5.1 Project management 48 months
intermittent
5.5.2 Monitoring and reporting 42 months
intermittent
Page 5
Integrated Citarum Water Resources Project - Tranche 1
WBS Task Name Estimated Indicative Funding Implementing
Duration Cost Source Agency 2007 2008 2009 2010 2011
($'000) Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
6 Support for Community- and NGO-Driven Initiatives for Improved 54 months 6,800 MFF
Water and Catchment Management Tranche 1
6.1 Procurement of Consultants
6.1.1 Procure consultants 6 months
6.2 Sub-Component 1: Capacity Building and Planning 800
6.2.1 Identification of potential NGOs who can facilitate community 2 months
participation in all project cycles
6.2.2 Undertake KAP (knowledge-attitude-practices) surveys 3 months
6.2.3 Socialization and awareness-raising (including media information 6 months
campaigns), assessment of community needs
6.2.4 Selection of communities based on socio-economic and health 2 months
criteria and other indicators
6.2.5 Confirmation of community commitment and willingness to participate 1 month
6.3.3 O&M of completed schemes, and socialization and training support 10 months
on hygiene behavioural change
Page 6
Integrated Citarum Water Resources Project - Tranche 1
WBS Task Name Estimated Indicative Funding Implementing
Duration Cost Source Agency 2007 2008 2009 2010 2011
($'000) Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
7 Development and Implementation of a Basin River Quality 60 months 6,100 MFF
Improvement Strategy and Action Plans Tranche 1
7.1 Procurement of Consultants
7.1.1 Procure consultants 6 months
7.2 Sub-Component 1: Policies and Procedures for Water Quality 340
Management
7.2.1 Prepare guidelines/procedures for establishing institutional 2 months
mechanisms to manage water quality
7.2.2 Prepare guidelines/procedure for assessment of pollution sources, 2 months
delineating water quality management areas and preparing action
plans
7.2.3 Assess performance and effectiveness in the Citarum basin of 3 months
existing cooperation-based programs and identify complementary
regulatory measures
7.2.4 Policy study and recommendations on use of incentives/pollution 2 months
charges for water quality management, including procedural
guidelines for implementation
7.3 Sub-Component 2: Improvements to Water Quality Monitoring and 1,860
Data Management
7.3.1 Design and develop a basinwide water quality monitoring program 3 months
based on concept of water quality management areas
7.3.2 Design and develop a water quality and pollution source database 5 months
management system, with capability for mapping pollution sources
7.3.3 Develop appropriate water quality modeling techniques, including 6 months
calibration, testing and demonstration in key water quality
7.3.4 Design and develop an Internet-based WQM information system to 3 months
link the district environmental agencies with other key agencies
7.3.5 Equip district environment staff with basic water quality monitoring 3 months
equipment (on site testing and sampling kits)
7.3.6 Implement integrated water quality monitoring system based on 41 months
action plans (which identify priority pollutants, sources, control
measures, targets)
7.4 Sub-Component 3: Development of Organisational Capacity 1,000
7.4.1 Design and implement a training program on the various guidelines 3 months
for district environment protection agencies
7.4.2 Design and develop a basin-wide information campaign for raising 6 months
public awareness of water quality management issues
7.5 Sub-Component 4: Preparation of Basin-Wide River Quality 500
Improvement Strategy
7.5.1 Set up multi-agency/stakeholder planning and coordination system 2 months
(under Balai Besar) for water quality management
7.5.2 Identify strategic policy issues, such as objectives and standards for 1 month
water quality
7.5.3 Delineate and prioritise water quality management areas and 3 months
mobilize area stakeholders, including technical support units from the
districts/province and Balai Besar
7.5.4 Conduct pollution source inventories and pollution load assessments 6 months
in key water quality management areas (prioritize Bandung and
Bekasi)
Page 7
Integrated Citarum Water Resources Project - Tranche 1
WBS Task Name Estimated Indicative Funding Implementing
Duration Cost Source Agency 2007 2008 2009 2010 2011
($'000) Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
7.5.5 Develop a basin-wide River Quality Improvement Strategy for the 3 months
Basin as a framework for action planning in priority water quality
management areas
7.5.6 Policy review and re-planning 3 months
7.6.3 Performance monitoring and evaluation of area action plans and 6 months
reporting to the Citarum Ware Resources Council through the Balai
Besar
Page 8
Integrated Citarum Water Resources Project - Tranche 1
WBS Task Name Estimated Indicative Funding Implementing
Duration Cost Source Agency 2007 2008 2009 2010 2011
($'000) Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
8 Productive Reforestation of Degraded Catchments in CRB 45 months 3,930 GEF
Page 9
Integrated Citarum Water Resources Project - Tranche 1
WBS Task Name Estimated Indicative Funding Implementing
Duration Cost Source Agency 2007 2008 2009 2010 2011
($'000) Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
8.7 Sub-Component 6: Alternative livelihoods for displaced upland 1,200
forest villagers
8.7.1 Conduct a field survey of the upland villagers (38,000 families) 3 months
displaced to ascertain suitable sustainable alternative livelihoods
8.7.2 Broker preferences for this group of villagers for Perum Perhutani 3 months
lands and facilitate preferred livelihoods on this leasehold land
8.7.3 Subsidise 3000 farmers for one year to establish alternatives 12 months
Page 10
Integrated Citarum Water Resources Project - Tranche 1
WBS Task Name Estimated Indicative Funding Implementing
Duration Cost Source Agency 2007 2008 2009 2010 2011
($'000) Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
9 Protected Area Management in CRB (Biodiversity) 42 months 4,200 GEF
Page 11
Integrated Citarum Water Resources Project - Tranche 1
WBS Task Name Estimated Indicative Funding Implementing
Duration Cost Source Agency 2007 2008 2009 2010 2011
($'000) Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
10 Project Preparation for Tranche 2 (Indicative Only) 9 months 600 ADB TA Balai Besar
Page 12
Citarum Integrated Water Resource Management Project
Report on Roadmap and Program Development
Roadmap
Indicative MFF Indicative Total Cost Tranche 1 Estimated Total Cost
Total Cost ($ '000) ($ '000)
Co-
Key Areas: ADB Loan ADB Grant GOI Total ADB Loan ADB Grant GEF GOI Total
($ '000) Financer
Institutions and Planning $10,000 $10,000 $10,000 $2,400 $2,400
WR Development and Management $2,362,510 $276,420 $5,000 $182,060 $463,480 $28,870 $19,740 $48,610
Water Sharing $133,000 $2,000 $25,000 $3,000 $30,000 $5,000 $1,810 $6,810
Environmental Protection $250,000 $3,500 $8,000 $48,500 $60,000 $8,060 $8,060
Disaster Management $100,000 $0 $0
Community Empowerment $59,000 $25,000 $10,000 $19,600 $54,600 $7,070 $1,480 $8,550
Data and Information $20,000 $9,560 $5,440 $5,060 $20,060 $1,040 $1,040
Program Management and Project Preparation $20,000 $3,520 $8,480 $12,000 $2,570 $2,570
SUBTOTAL $2,954,510 $320,000 $15,440 $53,060 $261,640 $650,140 $40,940 $3,440 $8,060 $25,600 $78,040
Contingencies and IDC $800,000 $180,000 $180,000 $19,270 $19,270
TOTAL $3,754,510 $500,000 $15,440 $53,060 $261,640 $830,140 $60,210 $3,440 $8,060 $25,600 $97,310
Citarum Integrated Water Resource Management Project
Report on Roadmap and Program Development
A. Introduction
1. Financial and economic analysis were undertaken to evaluate the sustainability of
the Project. This analysis was undertaken comparing the cost and benefits in the case of with
and without project situation. Financial analysis examines its sustainability from the
beneficiaries’ point of view while economic analysis determines its viability from the social
and economic perspective. The two major project benefits that are considered for Tranche 1
is the additional water made available for: (i) domestic, manufacturing and industrial (DMI)
uses; and (ii) paddy cultivation.
B. Major Assumptions
3. The major project activities will be implemented over the period from 2007 to
2011. The economic life of the Project is assumed as 25 years with the full economic benefits
realized in 2025 or project year 19. Investment costs including all consultancy, civil works
and equipment costs are in constant 2006 prices. The exchange rate used is Rp9,300 to
US$1.00 which is the rate used by GOI in preparing their 2007 budget. The World Bank
MUV1 index is used to adjust future commodity prices to constant 2006 prices. Forecast
prices of traded commodities are based on World Bank commodity price projections while
prices of other commodities are based on prevailing local market prices. Prices for rice,
phosphate and potassium fertilizer are based on import parity while those for nitrogenous
fertilizer at export parity. The 2015 forecast prices are used for deriving farm-gate commodity
and fertilizer prices.
3. The standard conversion factor (SCF) used in this analysis is 0.9 while that for
labor is 0.8. The price of labor is Rp25,000 per day which is the prevailing rate in the project
area.
4. The program area – Citaram Basin - covers the most strategic river basin in the
country, with a population of 28 million. The 2 most important urban centers – Jakarta
(population 13.2 million) and Bandung (population 4.0 million) are either located within or
depend on this basin for its water supply. The total area of irrigated agricultural land is some
300,000 ha producing about some 3.0 million tons of paddy or 6 % of the national output.
The Citarum River system also supplies 80% of Jakarta’s raw water. Some 10% of the
population are living below the poverty line, 50% of households do not have proper toilet
facilities and 40% of them do not have access to pipe water.
5. Average annual demand from the Jatiluhur reservoir has increased from
140m3/sec in 1996 to 156m3/sec in 2004 and this demand is growing at an annual rate of
5%. However, inflow into the Saguling reservoir has been decreasing. Between 1986 and
1991, dry season flow into the Saguling reservoir was 38% of the average annual flow. This
1
World Bank, MUV Index 2004.
percentage went down to 36% between 1992 and 1997, and declined further to 34% starting
in 1998. Watershed degradation is seen as the principal cause. Denuded catchments have
reduced capacity to capture rainwater, resulting in high peak flows during the rainy months.
In turn, the lower water retention capacity reduces the amount of water available for release
as “base flow” during the summer months.
7. In Bandung, an estimated 90% of the population, and 98% of the industries, rely
on groundwater. The lowering of the groundwater level is reportedly up to 5m/year in some
places. The cumulative water level decline since 1920 has been 85m. In 2005, it was
estimated that land subsidence had reached 0.8m. In order to get clean water, industrial
wells have to be drilled to beyond 150m. Industrial groundwater abstraction has also had a
devastating effect on shallow wells on which numerous households depend.
8. Watershed erosion is a serious problem in the upper river basin where hillsides
are steep and the catchment denuded. Even on steep slopes, farmers cultivate non-
perennial crops which do not provide adequate ground cover from the heavy monsoon rains.
The soils, derived from volcanic tuff, are easily erodible and are prone to land slides. High
peak flows have also increased the rate of river bank erosion. Hydrologic flow regimes have
been adversely changed by land degradation, notably the loss of adequate forest cover and
the prevalence of hillside farming in the upper catchments. The degraded catchments have
reduced capacity to capture rainwater, resulting in high peak flows during the rainy months
which carry large amounts of eroded soil. Landslides and mud flows are frequent during the
rainy season. These areas have erosion rates in excess of 60 ton/ha/year. At a
conservatively estimate of $10/ha, this would represent a loss of $1.0 million/year for the
entire watershed of some 100,000 ha.
10. Along the lower Citarum River levees/embankments built during the Dutch period
help confine flooding within the river’s meander zone and provide protection to the
surrounding settlements. However, large areas of the flood zone within the levees have been
planted with crops and fruit trees that have the effect of retarding flood flow, contributing to
high water levels. Also, a long term effect of the river embankments has been to raise the
river bed due to sediment accumulation, since the levees prevent the spilling of sediments
onto the surrounding plain. Consequently, floodwater levels inside the levees have risen
above the level of the surrounding land, putting the population at risk in case of levee failure.
11. At the Citarum River mouth, the build-up of deposited sediments has created
sand dunes that impede floodwater discharge. Combined with the effect of high tides, the
constricted river outlet causes perennial inundation of the lower basin near the delta as the
water is forced to back up into the alluvial plain.
12. The population within the program area is growing at more than 3% annually,
attributed in part to influx of migrants drawn in by the region’s rapid pace of development.
The combined effects of untreated domestic sewage, solid waste disposal and industrial
effluents have significantly increased pollution loads in the Citarum River system. In the
upper basin, river water that is polluted by domestic and industrial wastes from the Bandung
metropolitan area is funneled into the Saguling reservoir. In recent years, the BOD
concentrations in the Cikapunding River (a major tributary of the Saguling River that flows
through Bandung) were still reported to reach as high as 100 mg/l.
13. Runoff from farmed hillside areas, in addition, brings in large amounts of nutrients
(nitrogen and phosphorus) that induce eutrophication in the reservoirs. At Saguling where the
problem is most significant, nitrogen loading has been estimated at 33,350 ton/year, and for
phosphorus, 4,370 ton/year. Algal blooms and their subsequent decay have been blamed for
the regular occurrence of fish kills and considerable damage to the floating fish cage
industry. In turn, the uncontrolled expansion of fish cage operations is exacerbating the
effects of polluted water coming into the reservoir. Improper or excessive fish feeding in the
floating cages adds to the organic waste load as unconsumed feed accumulates on the
reservoir bed and through periodic suspension (for example, at the start of the rainy season
when increased inflows induce mixing in the reservoir) increases oxygen demand.
14. Pollution in the lower basin - particularly in the downstream portion of the West
Tarum Canal - poses an even more urgent water quality problem. The WTC supplies 80% of
Jakarta’s (surface) raw water supply, and hence is vital to the well-being of 8 million
inhabitants. On its route to Jakarta, the WTC intersects the Bekasi River which drains an
area rapidly being developed for residential and industrial use. At the Bekasi River’s
confluence with the WTC, the average annual BOD concentration in 2004 was 48mg/l
(measured at the weir site). The pollution load in the Bekasi River is caused by untreated
household sewage, industrial wastewater, and solid waste dumped along the river banks.
15. Lack of proper solid waste management contributes to both pollution and
flooding. Garbage deposited along canals and riverbanks contribute to the high BOD. They
also clog drains and accumulate on riverbeds reducing discharge capacity. Average daily
solid waste generation is estimated at 6,500m3/day, of which about 1,500m3/day is not
collected and properly disposed of. Thus the annual uncollected garbage that invariably ends
up accumulating in the drainage system and rivers amounts to something like 500,000m3.
The estimate inflow of solid waste into the reservoir is 250,000m3/year.
16. Along the West Tarum Canal, reduction in conveyance capacity is due both to
sediment deposits and the prolific growth of aquatic plants (which create friction in water
flow). Apart from contributing to the bottom detritus, aquatic plants trap silt and accelerate
canal shallowing. Plant growth is promoted by the use of the canal as toilet and
bathing/washing area for residents, which adds substantial quantities of plant nutrients in the
water. Residential and commercial establishments along the canal are dense particularly
downstream of the waterway from Cikarang and Bekasi to Jakarta. Wastewater and garbage
from these establishments are disposed of directly into the canal.
D. Project Benefits
1. Water For DMI
17. In the without-project situation, silting, damage to the canals and hydro-
mechanical equipments is gradually reducing the amount of water available for irrigation and
DMI by 0.5% annually, or a fall from 51.1m3/sec in 2005 to 46.5m3/sec in 2025 (Table 1). As
compared with the without-project situation, the Project aims to increase water available for
irrigation by 4.5m3/sec, for DMI by 19.6m3/sec and for flushing by (1.0m3/sec) or a total of
25.1m3/sec by the year 2025.
19. The Project will increase the water available from the current level of 51.1m3/sec to
3
71.6m /sec by 2025. The bulk of this increase in water supply will go towards meeting the
growing demand for water for DMI in Jakarta, and Curug-Berkasi. The DMI uses will benefit
from an increase of 2.5% annually in their water supply (or by 19.6m3/sec).
19. Without-project, water available for Jakarta will fall from 16.1m3/sec in 2005 to
14.5m /sec in 2015 and to 12.9m3/sec by 2025. The Project will increase the supply of water
3
to Jakarta and Curug-Berkasi DMI by 2.5% annually. This increase is barely adequate to
meet the growing demand for water for all DMI uses and there is a need for consumers to
use this water more efficiently.
Table 1: Water Supply from WTC, With and Without Project, m3/sec
Items 2005 2010 2015 2020 2025
Without Project
Irrigation 30.0 28.5 27.0 25.5 24.0
DMI Consumers
DMI – JKT 16.1 15.3 14.5 13.7 12.9
DMI - Curug Bekasi 7.0 6.7 6.3 6.0 5.6
DMI – Total 23.1 21.9 20.8 19.6 18.5
DMI Consumers
DMI – JKT 16.1 18.6 21.1 23.6 26.1
DMI - Curug Bekasi 7.0 8.3 9.5 10.8 12.0
DMI – Total 23.1 26.9 30.6 34.4 38.1
DMI Consumers
DMI – JKT 0.0 3.3 6.6 9.9 13.2
DMI - Curug Bekasi 0.0 1.6 3.2 4.8 6.4
DMI – Total 0.0 4.9 9.8 14.7 19.6
20. The cropping intensity mainly for rice in the lower reaches of the Jatiluhur
irrigation system has decreased by 25% in recent years due to the shortage of irrigation
water caused by the degradation of the main and the secondary canals. Overall, the water
delivery from the Jatiluhur system is inefficient due to (i) seepage from the canals, (ii)
evaporation loss, and (iii) delivery loss.
21. Without project, water available for paddy irrigation is estimated to decline from to
30.0m3/sec in 2005 to 24.0 m3/sec in 2025 with the cropped area falling from 106,900 ha to
91,803 ha over this period and the cropping intensity declining from 1.78 to 1.53 (Table 2).
22. The rehabilitation of WTC will increase the water available to 28.5m3/sec
sufficient to cultivate 117,600 ha of paddy and restore its cropping intensity to 1.93. The
Project will increase the annual paddy cropped area by 25,800 ha by 2025. A total of 25,800
farmers, each cultivating an average of 0.5 ha of paddy land will benefit from this increase in
crop area.
23. Compared with the situation in 2005, there will be a shortfall of 1.5m3/sec of
water available for paddy irrigation in the with project situation. This implies that the paddy
sector will have to use their water more efficiently. This can be achieved with better controls
of the gate operations and lining of field canals.
24. The adoption of the system of rice intensification which reduces the water
demand from growing paddy by 40% is beneficial. It is estimated that converting 10,000 ha of
paddy cultivation to this system will save 63 million m3/year of water equivalent to 2.0m3/sec.
Table 2: Area of Irrigated Paddy and Dryland Crop – With and Without Project
Without Project
Item 2004 2007 2010 2015 2020 2025
Total command area- ha 57,900 57,900 57,900 57,900 57,900 57,900
25. Without-project: (i) water supply from Jatiluhur and WTC decrease by 1.1%
annually; (ii) water supply for Jakarta decrease by 1.1% annually: (iii) water supply for paddy
farmers decrease by 1.2% annually: (iii) water available for flushing decrease by 1.2%
annually; (iv) 35,000 households in Jakarta deprived of pipe water annually; (v) factories in
the Jakarta area reduce water usage by 1% annually; (vi) production of paddy from the
project area fall by 100,000 tons annually; (vii) annual economic growth rate for Jakarta and
its vicinity reduced by 0.5 to 1.0%; and (viii) potential serious conflict on water rights between
urban dwellers and farmers in the year 2010.
26. With-project: (i) water supply from Jatiluhur and WTC increase by 2.0%
annually; (ii) water supply for Jakarta increase by 2.5% annually; (iii) additional 200,000
households in Jakarta provided with pipe water annually; (iv) factories in the Jakarta area
increase their water usage by 2.0% annually; (v) production of paddy for the project area
increase by 150,000 tons annually; (vi) annual economic growth rate for Jakarta and its
vicinity increased by 0.5 to 1.0%; (vii) avoidance of serious conflict on water rights between
urban dwellers and farmers.
E. Water Charges
27. Perusahaan Umum Jasa Tirta II (PJT II), a state owned corporation, established
by Government Regulation 94/1999, is responsible for conducting self-funding operation and
maintenance (O&M) of the Jatiluhur infrastructure project, which includes a dam with an
impounding capacity of 3 billion m3, a 187 MW hydro-electric power station capable of
generating 900 million Kwh/year, and canals and irrigation structures capable of irrigating
240,000 ha of paddy fields and supplying 800 million m3 of water for domestic, manufacturing
and industrial (DMI) use. It is also responsible for: (i) collecting from the water users funds for
O&M of the Jatiluhur water systems; and (ii) managing the Citarum River basin
(conservation, utilization, and flood control mitigation). The management function of PJT II is
limited to acting as an operator of the system without having a regulatory function.
28. In 2005, its main source of income was Rp115,990 million1 from the sale of
electricity to PLN and Rp71,170 million from sale of water for a total of Rp187,160 million.
Currently, the water users pay to PJT II only 35% the required O&M cost. It charged its users
and average of Rp87/m3. The raw water that is used for Jakarta is sold at only Rp122/m3 or
2.1% of the price that the average consumers pay for their water supply. The water tariff for
Jakarta which is set by the Governor of Jakarta is Rp5,923/m3 for 2006. This rate is set
annually and there is a request from PDAM Jaya2 to raise this rate by 20% for the year 2007.
29. With-project, the price of raw water will have to be raised to Rp250/m3 to provide
PJT 2 with adequate funds for its operation and maintenance of the Jatiluhar Project
including the canal system. This doubling of water charges will represent only a 1.0%
increase in the water charges for DKI uses. In the longer term, the improvements in water
quality brought about by this Project will reduce the cost of water treatment and reduce the
need to raise water charges to the end uses.
30. Assurances will be obtained from the relevant authorities that this proposed
increase in the rate for raw water will be implemented in conjunction with the implementation
of this project.
F. Project Components
1
A total of 966.6 million Kwh at Rp120/kwh; 435 million m3 of raw water to Pam Jaya at Rp122/m3, 180
million m3 to PDIM at Rp45/m3 and 200 million m3 at Rp50/m3 to industries. The PDIM and industries draw
their water from various points along the canals. However PJT ll annual financial statement showed that in
2005, there collected only 82% of the money due to them.
2
City owned water company.
(vi) support for community and NGO-driven initiatives for improved water and
catchment management;
(vii) development and implementation of a basin water quality improvement
strategy and action plan:
(viii) productive reforestation and degraded catchment;
(ix) project area management (biodiversity) phase 1;
(x) program preparation for Tranche 2: and
32. The project management component will provide for funding the incremental and
other costs related to project implementation, including the provision of Technical Assistance
(TA), the undertaking of special studies and the maintenance of continuing liaison (and
reporting) as required between the DGWR, MPW and ADB. The Project will support the
government, partly through the Project Management component and partly through the
Institutional Strengthening component, to discharge this responsibility and will provide
operational support and funds for the Project Implementation Units (PIUs) in each District. In
practice the PIUs will comprise staff drawn from a number of district government institutions
related to water supply, agriculture, environment and health.
33. In DGWR headquarters, the Project will partly fund the establishment of a Project
Coordination and Management Unit (PCMU) to coordinate all project activities and perform
functions more appropriately undertaken at this level (procurement, accounting etc.). To
provide policy guidance for the overall project and to approve work programmes and budgets
a Steering Committee would be established within DGWR, and expenses related to the
meetings and visits of this committee would be funded by the Project. Some support would
also be provided, as an extension of the PCMU’s role, to the Provincial administrations to
facilitate coordination functions1.
34. The DGWR will second staff either full or part time, as appropriate for each
position, to facilitate project implementation and these staff will be assisted and supported by
a Technical Assistance programme. Overall, the Project will provide funding for office
accommodation, equipment, vehicles and all operating expenses related to project
management.
35. The project management component also includes allowances for contracted
studies undertaken by third parties, which are intended to cover baselines, impact
evaluations and special subject studies. In addition there are allowances for undertaking the
project mid-term and completion assessments, which would be undertaken by project staff
assisted by consultants. The estimated cost of this component is $2.56 million.
36. This component is designed to address the shortcomings of the current institutional
arrangements that are characterized by highly sectoral division of work and lack of
coordination, as well as weak enforcement. In most cases, the regulatory frameworks and
standards are generally in place (e.g. for pollution control). This component, through various
interventions will pave the way for improved overall capacity to manage environmental
quality in the basin. The long term environmental impact is positive and highly significant.
37. It will focus in strengthening and coordinating the work of various institutions
involved with: (i) influence of land use on water demand, flooding and river water quality (e.g.
1
The staffing and responsibilities of the different management units are described under “Implementation
Arrangements”.
urbanization, transition from agriculture, land use zoning); (ii) balancing demand and supply
side solutions to meet water demand; (iii) influence of land use practices in catchments on
sustainability of reservoirs; (iv) effect of groundwater over-pumping on access by the poor
and cost of abstraction, land subsidence and contamination of aquifers; (v) influence of
waste and wastewater disposal practices on suitability of water for downstream supplies,
cost of treatment, public health, river ecosystem, groundwater quality; (vi) inequity of
upstream and downstream supply; (vii) insufficient maintenance increases risk of canal
breach and interruption of water supply to strategic centres (e.g. Jakarta) and consequent
economic loss; (viii) trade off between revenue generation from hydropower and other non-
revenue earning use (e.g. dry season irrigation); and (iv) link between Government Policy on
absence of irrigation fees and sustainability of infrastructure. The estimated cost of this
component is $2.40 million.
38, This component will focus on development of water supply options for
Bandung, specifically to address its over-dependence on groundwater. The emphasis will
be on finding alternative surface water source for industries currently mining the area’s
deep groundwater. The long term objective is to enable groundwater levels to recover.
This will reduce the cost of pumping water for domestic use. Re-allocating groundwater
away from industry is also economically advantageous as the cost of treating water for
industrial requirements is less than for domestic use.
39. It will formulate an action plan to increase the use of surface water for Bandung while
reducing its reliance on groundwater. In addition, 236 villages (with a population of 20,000)
will be supplied with clean water, sanitation facilities and solid waste disposal. The economic
benefits of providing clean water and sanitation facilities are high. The World Bank estimates
that the returns from such project are 5 to 20 times the actual investments1. The estimated
cost of this component is $4.81 million.
41. SRI differs from the normal irrigated rice system in that it only requires intermittent
rather than continuous flooding. In this system, the soil is only kept moist and periodically
aerated. This results in a water savings of 40 to 50% and with water becoming a scare
commodity; it is likely that this system will be more widely accepted in the future.
42. Together with the reduction in water requirements, the new technology requires
changes in cultivation method comprising of: (i) selecting only strong seeds and planting
them in plastic trays; (ii) transplanting seedlings to field after 8 to 15 days; (iii) planting
seedlings at 30cm spatial intervals; (iv) providing a ditch at the perimeter of plot to drain
excess water; (v) reducing the amount of water use to only wet the soil to a depth of 2 cm;
(vi) increasing the use of organic fertilizer (in conjunction with reduced levels of chemical
1
World Bank, 2004. Global Analysis on Sanitation Investments.
fertilizer) to improve the soil structure; (vii) reducing the use of chemicals since the stronger
plants are less susceptible to pest and diseases; (viii) increasing weeding rounds by
compacting the soil 4 times per crop; and (ix) providing intermittent water supply. The main
impact of these changes is the increase in rice yield by 50 to 100% and increasing the labor
requirements by 25 to 50%.
43. This system was first tested and evaluated by the Agency for Agricultural
Research and Development (AARD) in Sukamandi in West Java in 1999. Paddy yields in this
trial increased by 50% in the first year (from 4.1t/ha to 6.2t/ha) and by 100% in the second
year. In 2002 to 2004, the MOA expanded this test to 200 locations. The results of testing in
Eastern Indonesia in over 1,350 ha showed that paddy yields have consistently increased by
more than 180%. Within the project area, the Department of Agriculture, Bandung, has
successfully implemented this system to 340 ha of farmers fields in 2005 and their program
for 2006 is to expand this system to an additional 400 ha. For 2007, the DGLW of MOA is
implementing this program for 3,000 ha in 14 provinces.
44. The main impediment to implement SRI to a larger area is the lack of funds to
support a training program to assist farmers to adopt this system. The cost of this training
program including demonstration farm and providing some material inputs to farmers is
estimated at Rp3.5 to Rp4.0 million/ha.
45. The objective of the SRI component in this project is to accelerate the adoption of
System of Rice Intensification (SRI) in the project area. Some 10,000 ha of paddy land will
be targeted under this project. The component will: (i) increase rice yield by an average of
45% (from 5.5 to 8.0 t/ha); (ii) reduce the need for irrigation water by 45% (from 18,000 to
11,700 m3/ha1); (iii) increase labor use by 36% (from 70 to 95 person day/ha); (iv) increase
total cost of production by 31% (from Rp3.26 to Rp4.28 million/ha); (v) increase net income
by 56% (from Rp4.54 to Rp7.06 million/ha) and increase gross margin by 50% (from Rp6.29
to Rp9.44 million/ha). The comparative data for the paddy crop grown under flooded
irrigation and SRI is shown in Table 3.
46. This SRI component will be implemented in 3,000 ha in Bekasi district, 3,000 ha in
Karawang district and 4,000 ha in Bandung district. A total of 20,000 farmers will benefit from
this sub-project. A total of 20,000 farmers will benefit from this component.
1
JWRMP Study, 1998.
47. The overall savings in water requirement from this sub-project is 63 million m3/year
valued at Rp15.75 billion (at Rp250/m3 or the same rate as charged for raw water) or $1.70
million per year. This is equivalent to $170/ha/year as compared to the implementation cost
of $417/ha. This savings in water is not included as a project benefit for the SRI component
as this benefit is included in the raw water sold for DMI uses. However it is important to note
that the water savings benefits from adopting SRI is sufficient to justify its adoption even if
there is no significant increase in crop yield. The estimated cost of this component is $4.17
million or $417 per ha.
(vi) Support for Community and NGO-driven Initiatives for Improved Water and
Catchment Management
48. The main objective of this component is to improve public health and reduce
waterborne diseases in rural riparian communities in the upper catchments and along the
WRC. This improvement will be brought about by providing these communities with the
opportunity to install potable water supply and hygienic sanitation facilities. At the same time,
the capacity of participating communities will be enhanced to a level that enables effective
development and implementation of village action plan. The estimated cost of this
component is $5.64 million.
49. Under this component, the basin will be divided into several water quality
management areas; each with its specific nature and problem. The control strategies and
water quality parameters monitored for each area would be dictated by the characteristics of
the area and the dominant source. In each area, stakeholders will effectively participate in
drawing up and implementing solutions.
50. In area with high industrial industries (such as Bandung and Bekasi), an area
action plan will be drawn up to deal with pollution problems at the source. Such plans would
be oriented around combination of strategies that involve expansion of cooperation schemes
under PROKASIH PROPER, strengthening of regulatory (command-and-control) systems,
and use of incentives.
52. The Project will take advantage of opportunities to expand design to generate
complementary environmental benefits, i.e., rehabilitating degraded land and promoting
biodiversity. Along this line, “re-greening” of watersheds will be planned so as to provide the
best long-term possibility to protect the water resource quality and quantity and at the same
time helping restore other landscape ecological functions. This is based on the premise that
the most effective watershed rehabilitation strategies are those that re-establish basic
ecosystem processes.
53. This component aims to reduce threats to protected areas in the Citarum River
Basin and their surrounding landscape by engaging nearby villages in both improved
conservation practice and land stewardship. It will encourage community based reforestation
of degraded public lands throughout the Citarum River Basin, including government
degraded lands, especially on steep mountain slopes, riparian, road and watershed
boundary zones, spring catchments and by ‘enrichment’ of village gardens and other village
lands. It will improve land stewardship through both implementation of village conservation
action plans and through community education programs targeted at villages and schools.
55. A total of 36,000 farmers will be assisted to plant fruit trees and other economic
crops in their riverine areas to reduce soil erosion and to restore the fertility and productivity
of their farm land. The loss in agricultural productivity caused by soil erosion has been
estimated at 4 to 7% per year1. The estimated cost of this component is $8.04 million.
56. This component will conserve the unique internationally important biological
diversity found in the Citarum River Basin remnant patches of the West Java Montane Forest
type. It will establish protocols and models of best conservation management design and
practice in an Indonesian Model National Park and a variety of other protected area types,
and leverage these practices to other Indonesian protected areas. This component will also
promote alternative funding mechanisms for biodiversity conservation management in the
Citarum River Basin upper watersheds.
58. Seven model villages will be assisted to implement action plan to promote the
regeneration of their flora and fauna. A total of 1,000 farmers will participate in this
component. The estimated cost of this component is $4.10 million (Table 11).
59. This component will fund several feasibility studies and planning for
implementation of Tranche 2. The estimated cost of this component is $1.04 million.
1
ADB, 1996. Economic Evaluation of Environmental Impact, page 238.
G. Total Project Cost and Financing Plan
60. The estimated total investment cost for Tranche 1, including contingencies and
IDC for the Project is $97.31 million. The total base cost is estimated at $78.04 million while
the total base cost with contingencies is $93.25 million (Table 4).
Expenditure
by
Project Components Total Financier
ADB -
Million $ ADB -TA GEF Loan GOI
ADB and GOI Share of non-grant project cost 100% 70% 30%
61. It is estimated that ADB loan will be $60.22 million or 70% of the non-grant
project cost while the GOI will provide $25.60 (30%). The proposed financing arrangements
at this stage are very tentative and variable and will be firmed up at Appraisal.
62. The total project base cost is $73.19 million and the total cost with contingencies
is $86.31 million. Canal rehabilitation is the largest component representing 55% of the base
cost.
H. Income With and Without Project1
63. The total of 46,000 paddy farmers, each with an average holding of 0.5 ha, will
benefit from this Project. Some 26,000 farmers will benefit from having irrigation facilities
which will enable them to plant paddy in their existing holding instead of their current practice
of cultivating dryland crop. Another 20,000 farmers will benefit from the SRI program which
will raise their paddy yield from the existing level of 5.5 tons to 8.0 tons/ha.
64. System of Rice Intensification. Currently, the average farm family with 0.5 ha of
paddy land (cropped twice yearly) earn an income of Rp7.8 million/year from sale of his
paddy crop, Rp0.5 million from sale of other farm produce and receives Rp1.0 million from
off-farm work for a total gross income of Rp9.3 million (Table 5). Deducting Rp2.0 million for
farm expenses, his yearly net income is Rp7.3 million or Rp1.8 million per capita or 20%
above the poverty income level2 per family. The landless laborer who forms 25% of the farm
population currently earns only Rp4.0 million or 33% below the poverty line income. The
average per capita income for the farming community is Rp1.6 million or 7% above the
poverty line.
65. With Project, the farmer annual net income will be raised to Rp10.1 million with
80% of this income derived from his paddy crop. This income is 40% above the poverty line
income assuming that the poverty line income is raised by 20 percent above the existing
level. Similarly, the landless laborer income, with additional work from the SRI paddy
cultivation will be raised to Rp5.5 million or 25% below the poverty level.
66. With project, the paddy farmer and the community net income will be raised by
38% with the poverty incidence reduced from the current level of 20% to less than 10%.
67. New Irrigated Areas. Currently, the average farm family earn an income of
Rp5.6 million/year from sale of his dryland crop such as corn, Rp0.5 million from sale of other
farm produce and receives Rp1.0 million from off-farm work for a total gross income of Rp7.1
million (Table 6). Deducting Rp1.5 million for farm expenses, his yearly net income is Rp5.6
million or Rp1.4 million per capita or 7% below the poverty income level per family. The
landless laborer who forms 25% of the farm population currently earns only Rp4.0 million or
33% below the poverty line income. The average per capita income for the farming
community is Rp1.3million or 13% below the poverty line.
68. With Project, the farmer annual net income will be raised to Rp7.8 and this
income will place just marginally (4%) above the poverty line income. Similarly, the landless
laborer income, with additional work from the paddy cultivation will be raised to Rp5.5 million
or 25% below the poverty level.
69. With project, the paddy farmer and the community net income will be raised by
38% with the poverty incidence reduced from the current level of 25% to less than 15%.
70. The main quantifiable benefits are those arising from: (i) the additional 19.6
m3/sec of water for Jakarta, Curug and Bekasi: and (ii) the additional 4.5 m3/sec of water for
paddy cultivation.
1
Preliminary figures which will be updated after the results of the socio-economic survey are completed.
2
The national poverty line income in 2006 is Rp1.5 million per capita per year or Rp6.0 million ($645) per
year for a family of 4.0 members (Source: Badan Pusat Statistik. 2003, figures adjusted to 2006 prices).
71. Additional Water for Domestic, Municipality and Industrial Use (DMI). Some
10m3/sec of water will be available to meet the domestic need of some 4.5 million additional
residents1 of Jakarta and Bekasi. Currently piped water is priced at a range of Rp800 to
Rp10,000 per m3: the lower rate for low income areas, and the highest rate for high rise
buildings with an average water charge of Rp5,923/m3 or Rp5.9/litre. Many of the middle and
high income families rely on bottle water which priced at about Rp1,000 to Rp2,000/lite. The
poor are not able to purchase bottle water and must rely mainly on piped water, canal or
groundwater for their daily need.
72. The rest of the additional water (9.6m3/sec) will be used mainly to meet the needs
of the industrial sector. Water is an essential input for virtually all industries; in particular the
textile, food and service sectors. Without the additional water, growth of these industries will
be severely curtailed.
73. The financial price of raw water sold to PDAM Jaya and other users is Rp87/m3.
Raw water charges are currently heavily under-priced at less than 35% of its O&M cost. For
the financial and economic analysis, the average water tariff used is the proposed rate of
Rp250/m3.
1
Assuming a water requirement of 200 litres/person/day.
Table 5 : Farmers Income With and Without Project - Rp
System Rice Intensification Project
Farmers
Land
Items Owner Labor Total
75% 25% 100%
Without Project - 2007
Income
1. Farm Income
Paddy 5.5 ton at Rp1.42 million/ton 7,810,000 5,857,500
Other Farm Income 500,000 375,000
2. Off-farm Income 1,000,000 1,000,000 1,000,000
Labor at Rp25,000/day *120 days 3,000,000 750,000
Gross Income 9,310,000 4,000,000 7,982,500
Farm Expenses 2,000,000 1,500,000
Net Income 7,310,000 4,000,000 6,482,500
Number family members 4.00 4.00 4.00
Per capita income 1,827,500 1,000,000 1,620,625
74. Water for Additional Paddy Cultivation. The rehabilitation of WTC will provide
sufficient water to cultivate 117,600 ha of paddy as compared with 91,800 ha in the without
project situation. This will increase paddy cropping intensity from 1.53 to 1.93. The Project
will increase the annual paddy cropped area by 25,800 ha by 2025. A total of 25,800
farmers, each cultivating (2 crops per year) an average of 0.5 ha of paddy land will benefit
from this increase in crop area.
(ii) Economic Analysis
75. Based on the above, the project wide FIRR and EIRR calculations have taken
into account the incremental benefits and costs in an aggregated cash flow, built up in line
with physical achievements by year and the phasing of benefits. The project financial internal
rate of return (FIRR) and economic internal rate of return (EIRR) was estimated at 16.3%
and 19.3% respectively.
76. The FIRR and EIRR sensitivities were examined for: (i) changes in project cost
(10% higher), (ii) revenue (10% lower), and (iii) a combination of (i) and (ii). (Table 7). The
results of this analysis show that the project is still viable under these all these unfavourable
situations.
Project
Item
FIRR(%) EIRR(%)
Base Case 16.3 19.3
Capital Cost + 10 % 15.0 17.7
Benefit – 10% 14.6 17.5
Capital Cost +10% 13.4 15.9
77. The switching values of the main project variables are shown in Table 8. This
indicates that the project will remain economically viable at an EIRR of 12.0% even if one of
these important variable are changed by: (i) project cost raised by 58%; (ii) incremental
benefits reduced by 37%; (iii) proposed water tariff rate reduced by 68%; and (iv) reduction in
proposed increased in paddy cropped area by 80%.
Shortfall in Incremental
Benefits 24.0 37.0
76. The nominal weighted average cost of capital (WACC) is 6.0% which is
considerably lower than the project FIRR of 19.3 percent (Table 9).
Project
77. Table 10 and 11 show the detailed cost for FIRR and EIRR analysis for Tranche 1.
78. The estimated total investment cost for MFF, including contingencies and IDC for
the Project is $830.13 million (Table 12).
Table 12: Cost Estimates and Financing Plan for MFF
(million)
Expenditure
by
Tranche Total Financier
Co- ADB -
Million $ ADB -TA financier Loan GOI
79. It is estimated that ADB loan will be $500 million (or 60% of the project cost),
ADB TA $15 million (2%), other co-financier contribution $53 million (6%) and GOI $262
million (32%).The proposed financing arrangements at this stage are very tentative and
variable and will be firmed up at Appraisal.
1. Economic Analysis for MFF
80. The project FIRR and EIRR calculations have taken into account the incremental
benefits and costs in an aggregated cash flow, built up in line with physical achievements by
year and the phasing of benefits. The project FIRR and EIRR was estimated at 12.3% and
17.0% respectively. This FIRR and EIRR are indicative figures and will be confirmed after the
feasibility studies identify the actual project cost and benefits. This analysis did not consider
the cost and benefit of the SRI component
Table 10: Financial Cost and Benefits of Tranche 1 Project – Rp Million
Year Program Inst Water WTC Com/NGO Water Degrated Biodiversity Tranche Total Total Net
Mag'ment Strength Option Initiative Quality Land 2 Cost Benefit Benefit
FIRR 16.28 %
NPV 197,933 million
1. Program Management
2. Institutional Strengthening for IWRM
3. Water Supply Options and Improved Ground Water Management for Bandung
4. Rehabilitation of West Tarum Canal
6. Support for Community and NGO Driven Initiative for Improved Water and Catchment Management
7. Development and Implementation of a Basin Water Quality Improvement Strategy and Action Plan
8. Productive Reforestation of Degraded Catchment
9. Project Area Management Biodiversity Phase 1
10. Program Preparation for Tranche 2
Year Program Inst Water WTC Com/NGO Water Degrated Biodiversity Tranche Total Total Net
Mag'ment Strength Option Initiative Quality Land 2 Cost Benefit Benefit
FIRR 19.18 %
NPV 310,786 million
Citarum Integrated Water Resource Management Project
Report on Roadmap and Program Development
Annex 9 Proposed
Implementation Arrangements –
Tranche 1
Other Ministry of Ministry of National Water
Other Ministry of Ministry of Ministry of Ministry of
Other
Ministries Mines and Public Bappenas Resources
Ministries Environment Health Agriculture Forestry
Ministries Energy Works Steering Committee
Roadmap Planning,
DG Director Director- Director- Monitoring and
IAARD DGWR
Watersheds General General General Coordination Unit
Balai Besar
PIU
PIU PIU PIU PIU PIU Directorate Program
of Irrigation PIU Management and
Coordination Unit
WTC Program
Consultants Consultants Consultants Consultants Consultants Mgt
Consultants
Consultants
National
Governor
West Java
Province
Provincial Provincial
Provincial Provincial West Java Provincial Mines and Water Provincial
Environmental Health AIAT Forestry Energy Resources Bappeda
Services Services Services Services Services
Consultants
Perhutani
Provincial
DistrictHeads
District Heads
District Heads
District District
District District District Mines and District
Water
Environmental Health Forestry Energy Bappeda
Resources
Services Services Services Services Service
Services
Receiving
Organisations
District
Organizational Structure of
NGOs, Project Implementation Units and
Communities, Civil Society Organisations
Community Project Management
Facilitators
Field
Citarum Integrated Water Resource Management Project
Report on Roadmap and Program Development
(Preliminary Draft)
RATIONALE OBJECTIVE
The Integrated Citarum Water Resource Management The key objective of program management is the
Project is a 15 year, multi-sectoral project with a total effective implementation of Tranche 1 of the MFF.
cost of around $1 billion, planned to be used in four
tranches. The project consists of a large number of
component projects in different sectors, but there are COMPONENTS
many inter-relationships among them. This means
that strong coordination among the projects is • Monitoring and reporting of project
required, along with effective monitoring and reporting performance, including financial
mechanisms to allow GOI and ADB to ensure that the management
funds are being disbursed in accordance with the
plans and in a timely way. In addition, information • Liaison with executing agencies and other
exchange among the component projects will improve relevant stakeholders
performance overall, and minimise wasted effort • Coordination among component projects
caused by overlaps.
The inherent flexibility in the MFF modality adds • Identification of the need for and
additional complexity to the ICWRMP. After Tranche coordination of implementation of minor
1, the indicative project plans initially approved may be studies (up to $400,000 total) to improve
modified to some extent in the light of changing knowledge of water issues in CRB
circumstances and needs. • Capacity building for NGOs involved in the
Also, the stakeholders of this project are many and component projects of Tranche 1
varied, from both the public and private sector, and
there is an emphasis on community-driven activities to • Coordination of preparation for Tranche 2
ensure that interventions lead to outcomes that deliver
community needs. Meaningful liaison with these
stakeholders will be essential for project success. In
addition, a mechanism for ensuring that approved
recommendations of the Project Steering Committee
are implemented within the component projects is
required.
An effective management group needs to be formed to
undertake these broad program management tasks.
This is to consist of a small consulting team of
international and national consultants, together with
relevant technical staff seconded from the
implementing agencies. A contract will initially be let
for the program management for Tranche 1 only.
1
Integrated Citarum Water Resource Management Project
Component Name West Tarum Canal Rehabilitation Project
Project Area West Java - Kabupaten Karawang and Bekasi
Duration 54 months Part of MFF Yes Tranche 1
Key Areas Addressed Irrigation & DMI demand, O&M, water quality, institutional, environmental,
resettlement
Estimated Cost USD 40.372 million
Implementing Agency Balai Besar (under Ministry of Public Works)
RATIONALE OBJECTIVES
Deforestation, urbanisation and industrial development The general objective is:
in (i) the catchment area of the Cikao (Purwakarta), a Design and implementation of all civil works,
tributary that enters the Citarum just upstream of West hydro-mechanical equipment, pollution prevention
Tarum Canal (WTC) intake at Curug weir; and (ii) the measures, institutional and financial settings to
catchments of rivers intercepted by the WTC, being improve the water quality of the WTC and to
the Cibeet, Cikarang and Kali Bekasi have caused an establish a reliable and sustainable conveyance
increase of the erosion rate, occurrence of flash floods, and supply system that can meet the water quality
and uncontrolled discharge of untreated waste water standards and the water demand for irrigation and
and garbage, resulting in deterioration of the water domestic, municipal and industrial purposes (DMI)
quality in the WTC and its feeding rivers. up to 2025.
Urbanisation and industrial development in the region
along the WTC, particularly between Cikarang and COMPONENTS
Jakarta, dumping of waste, construction of make-shift
toilets in the canal and the drains discharging in the tail A. Project Management
end of the WTC are sources of a further decrease of B. Consulting Services DED comprising a.o. :
the water quality - Feasibility study Cikarang and Cibeet bypass.
Lack of operational and maintenance staff, adequate - Detailed design canal and related structures.
maintenance equipment and materials and the limited - Topo surveys and geotechnical investigations.
financial resources of PJT-II, have caused excessive - Hydrometric and sediment sampling program.
sedimentation in certain canal reaches; malfunctioning - Hydrological study Cibeet, Cikarang & Bekasi.
of control and measuring gates in cross regulators and - Satellite image interpretation for irrigation areas.
irrigation offtakes; and damaged trash racks and other
- Preparation of peak water demand model.
hydro-mechanical equipment. This has resulted in a
- Preparation of hydraulic canal model.
reduced conveyance capacity in some canal sections
- Detailed design of siphons & separation walls.
and difficulties in a proper operation of the water
- Improve canal operation and maintenance.
regulating and measuring structures.
- Refurbishment of hydro-mechanical equipment.
In order to overcome, or at least reduce, the above
- Prepare cost estimate and tender documents.
shortcomings to a manageable level, it is necessary to
- Pollution control and public awareness.
implement the recommendations for improvement of
- Study Institutional and legal framework of PJT-II.
institutional settings, rehabilitation works of canal and
- Analyse financial and revenue base of PJT-II.
related structures, installation of hydro-mechanical and
procurement of maintenance equipment, resulting from C. Construction of Civil Works of WTC and CFC
the West Tarum Canal Rehabilitation Project. - Canal excavation and dredging.
- Fill and slope stabilisation.
- Construction of siphons and partition walls.
- Bridges, maintenance road, drains, etc.
- Rehabilitation of canal structures.
D. Installation of hydro-mechanical equipment
- Refurbishment of eight (8) hydraulic pumps.
- Installation of control and measuring gates.
- Procurement and installation of trash racks.
- Replacement of spillway gates of Cibeet weir.
E. Workshops and Training of canal O&M
F. Resettlement of affected persons
1
Integrated Citarum Water Resource Management Project
Project Name Roll-Out of System Rice Intensification in Three Districts
Project Area West Java - Kabupaten Karawang and Bekasi
Duration 54 months Part of MFF Yes Tranche 1
Key Areas Addressed Reduce demand for water for rice irrigation, Increase availability of water for
DMI
Estimated Cost USD 4.17 million
Executing Agencies Ministry of Agriculture
RATIONALE OBJECTIVES
Currently, the annual irrigation water supplied to The objective is to accelerate the adoption of
57,000 ha of rice fields in WTC is about 1.57 billion m3 System of Rice Intensification (SMI) in the Project
or 27,600 m3/ha. The water used for irrigation is Area. Some 10,000 ha of paddy land will be
3
estimated at 6,000 m /ha for the main season and targeted under this project.
3
12,000 m /ha for the off-season giving a total of 18,000 The main impact of this sub-project are:
m3/ha/year. The irrigation efficiency is only 65%.
(i) Increase rice yield by 63%.
The adoption of the SMI will result in reducing the
water requirement from 18,000 m3/ha/year at present (ii) Reduce the need for irrigation water
to 11,700 m3/ha/year; a savings of 45%. by 45%.
The overall savings in water requirement from this (iii) Increase income of rice farmers by
sub-project is 63 million m3/year valued at Rp7.69 95%.
billion or $826,450. (iv) Increase labour use by 30%.
The SMI program will benefit from the infrastructure Sub-project will be implemented in 5,0000 ha in
improvements planned under this Project. These Bekasi district and 5,000 ha in Karawang district.
improvements will increase the reliability and A total of 20,000 farmers will benefit from this sub-
sustainability of the irrigation water conveyance. project.
However, there need to be more careful attention to
gate operation to maintain the desirable wet conditions
in the plot. COMPONENTS
The main features of the SMI are: (i) selecting only
strong seeds and planting them in plastic trays; (ii) A. Project Management comprising 5 field visits per
transplanting seedlings to field after 8 to 15 days; (iii) year.
planting seedlings at 30cm spatial intervals; (iv) B. Participatory Rural Appraisal for 3 districts and 16
providing a ditch at the perimeter of plot to drain sub-districts.
excess water; (v) reducing the amount of water use to
only wet the soil to a depth of 2 cm; (vi) increasing the C. Training of Trainers for 800 farm leaders.
use of organic fertilizer (in conjunction with reduced D. Training of Farmers for 20,000 farmers.
levels of chemical fertilizer) to improve the soil
structure; (vii) reducing the use of chemicals; (viii) E. Demonstration Plots – 80 plots.
weeding by compacting the soil 4 times per crop; and F. Farmer Empowerment – 660 sessions.
(ix) providing intermittent water supply.
G. Production of Organic Fertilizer – distribution of
This system leads to a 50 to 100% increase in rice
400 units
yield due to: (i) increased activity of aerobic and
anaerobic bacteria aiding vigorous plant growth; (ii) H. Decomposer – distribution of 10,000 kits
increased tillering; (iii) reducing damage caused by I. Seed Supply – distribution of 50,000 kg of selected
storm, pest and diseases; and (iv) reducing the seeds.
competition among seedlings for plant nutrients.
J. Monitoring and Evaluation – preparing 27 reports.
1
Integrated Citarum Water Resource Management Project
Project Name Community Rural Water Supply and Sanitation
Project Area Riparian rural communities in the upper Citarum catchment and along the
West Tarum Canal (WTC)
Duration 36 months Part of MFF? Yes Tranche 1? Yes
Key Areas Addressed Community empowerment
Estimated Cost US$1.64 million
Implementing DG Human Settlements, MPW; Ministry of Health (EAs)
Agencies Provincial/Local Public Works Agencies; Provincial/Local Health Agencies;
NGOs, CBOs (IAs)
RATIONALE OBJECTIVE
From the brief discussions carried out during field visits, To improve public health and reduce waterborne
rural communities in the upper catchment and along the diseases in rural riparian communities in the upper
West Tarum Canal (WTC) seem to have adequate catchment and along the WTC, by improvements
drinking water supplies (from springs and shallow wells to water supply and sanitation.
respectively), and sanitation facilities, but a
comprehensive survey is needed to properly assess the
situation. Conditions are poor along the Citarum river COMPONENTS
south of Bandung city where there is considerable 1. Identification of potential NGOs who can
domestic and industrial pollution and most people facilitate participatory village/community
dispose of waste in traditional ways, including rivers. development planning focusing on issues of
Very often in this kind of environment there is a high environment, health and livelihoods,
incidence of waterbone and water-related disease as community participation in all project cycles.
poor people, and particularly children and women suffer 2. Socialization and awareness-raising about
most from using water unfit for human consumption and community health, hygiene, sanitation and
from poor hygiene practices and behavior. water supply, access, and quality. and
Any ICWRMP interventions should be community- assessment of needs.
driven, based on the processes developed under the 3. Selection of communities based on
ongoing WSLIC-II and CWSH projects and SANIMAS socioeconomic and health criteria and other
(Sanitasi Masyarakyat - community-based sanitation), indicators.
and using the resources of NGOs and CBOs active in 4. Formation of community implementation
the field. teams with members drawn from community
stakeholders in a transparent, inclusive, and
accountable manner.
5. Community problem identification and
analysis meetings to determine priority
problems and possible solutions, through
presentations of water supply and sanitation
options (informed choice menu*), investment
costs, O&M costs.
6. Provision of skills training based on
communities’ priorities, assets and needs to
generate income and employment
opportunities.
7. Provision of access to capital and markets to
directly implement skills acquired.
8. Formulation of community action plans and
proposals.
9. Disbursement of funds and construction of
approved water supply and sanitation
schemes, together with supporting
socialization and training activities.
10. Operation and maintenance of completed
schemes, and socialization and training
support on hygiene behavioural change.
1
Citarum Integrated Water Resource Management Project
Report on Roadmap and Program Development
(Preliminary Draft)
2. Feasibility Components
The feasibility component comprises the following components:
(a) siphon, link canal and separation wall for the WTC-Cikarang crossing; and
(b) separation of CFC and WTC by separation wall and a siphon to BTb23.
3. Design Components
The main design components are:
(a) improvement of the conveyance capacity of the WTC and CFC by excavation and dredging works and
stabilization of the banks;
(b) propose and design appropriate measures for improvement of the operation and maintenance of
WTC, CFC and sediment traps;
(c) design of the Bekasi siphon and related hydro-mechanical equipment;
(d) design of Cikarang siphon, separation wall and related hydro-mechanical equipment, if feasible;
(e) design of CFC siphon, separation wall and related hydro-mechanical equipment, if feasible;
(f) investigate and propose rehabilitation works for existing canal crossings and design new bridges;
(g) determine condition of the hydraulic pumps in Curug and propose refurbishing works;
(h) inspect hydro-mechanical canal equipment, as gates, trash racks and spillway gates of Cibeet weir
and propose the necessary repair or replacement works; and
(i) prepare tender documents, specification and engineer’s cost estimate.
4. Scope of Works
4.1 General
The following scope of works has been formulated based on the results of the Integrated Citarum
Water Resources Management Project (ICWRMP) and other available information. Details of the
feasibility and design work as well as the corresponding activity and work schedule will be finalised in
the inception period.
2
Technical Issues
(a) Determine water availability in Bekasi, Cikarang and Cibeet rivers.
Collect, update and analyse hydrologic data of the catchment areas of the Cibeet, Cikarang and
Bekasi rivers in order to determine (i) the reliable flows available for irrigation and DMI purposes;
and (ii) the supplemental flows from the WTC to the irrigation areas after construction of one or
more siphons to bypass flow interception from the 3 (three) rivers.
(b) Determine irrigation areas under command of WTC and CFC.
Determine the present irrigation areas under command of the West Tarum Canal (WTC) and
Cibeet Feeder Canal (CFC) by interpretation of aerial photographs and/or satellite images,
verified by field investigations. Investigate how much irrigated land served by the WTC system
has been taken out of production during the past years and estimate how much more irrigated
area is projected or expected to be converted to other forms of land use.
(c) Future DMI demand.
Analyse the present commitments of PJT-II for delivering raw water to (ex) PT Thames PAM Jaya
(TPJ), PDAM’s along the WTC and secondary canals and the various industrials estates and
discuss with the relevant authorities, private companies and private users the location of future
offtakes and projected raw water demand.
(d) Review water demand from WTC and CFC.
Review the water demand for present and future irrigation command areas of the WTC & CFC
and the raw water demand for domestic, municipal and industrial (DMI) purposes, which is now
supplied from the WTC as well as the future demand for the years 2010, 2015, 2020 and 2025.
Included in this review should be the existing and proposed agreements for raw water supply
between PJT-II and the PDAM’s and between PJT-II and other users in the private and industrial
sector.
(e) Flushing demand.
Investigate if regularly flushing of the rivers crossing the Bekasi-Cawang reach is still required. If
this is the case, consider the possibility to meet this demand by surcharging.
(f) Preparation of a water demand/canal capacity model.
Prepare and run a water demand model in order to determine the required design capacity of the
various canal reaches for the present and future water demands in the WTC and CFC. The
model shall at least include the following parameters: irrigated area, cropping pattern, golongan
system, efficiency, irrigation and DMI demand, location major offtakes, and inflow from crossing
rivers, situation with and without interception of water from these rivers.
(g) Hydraulic verification and estimation of seepage losses.
Undertake a hydraulic verification of the WTC and CFC conveyance capacity at critical reaches
and measure the canal seepage losses through field investigations and hydrometric surveys.
(h) Preparation of a hydraulic canal model.
Prepare and run a one-dimensional steady state hydraulic model of the WTC and CFC in order to
determine hydraulic gradients, effect of variations in water demands on water levels, required
capacity of security devices as emergency gates and spillways, offtake and cross regulator levels,
energy losses over cross structures, etc.
(i) Canal conveyance capacity.
Analyse if the conveyance capacity of the WTC and CFC is sufficient to meet the present and
future water demand and propose measures to improve, restore or increase the capacity by
means of surcharging, widening, deepening, lining, sheet piling, etc., if required.
(j) Investigate and improve canal operation and maintenance.
Survey and investigate all cross regulators, irrigation offtakes and other regulating structures and
determine the type and operation conditions of these structures. Undertake a study of the canal
gate system, propose and design improvements based on ease of operation, discharge
measurement and sediment distribution. Measures could include changes to the existing Romeijn
gate system or replacement with other types of gates. Examine alternative solutions for system
operation simplification and recommend the most suitable one for implementation. The study
should also cover PJT-II’s operational and maintenance staff, funds and equipment and present
recommendations for improvement measures of staff, equipment and required maintenance
budget.
3
(k) Flow measurement.
Investigate how and when canal flows are measured including type and location of measurement
structure(s), status of structure, last time calibrated, reliability of Q-h curve and propose measures
for improvement, if required, as new calibration, additional measuring structures, measurement by
acoustic devices, etc.
(l) Sediment transport.
Carry out a sediment sampling programme in the WTC, CFC, crossing rivers and sediment traps
and determine the sediment balance of the WTC system in the cases with and without
interception of Cibeet, Cikarang and Bekasi flows.
(m) Operation and maintenance of sediment traps.
Investigate present operation and maintenance of the sediment traps in the WTC and CFC and, if
found to be inadequate, propose and design adequate measures for improvement based on the
results and conclusions of the sediment sampling programme.
(n) Design of Bekasi siphon.
Investigate the situation of the WTC level crossing with the Bekasi river and prepare the detailed
design of siphon and link canal to the WTC with appropriate trash racks, gates, flow measuring
devices, outlet gates to the Bekasi for additional supply to the North Bekasi Canal (NBC) and the
emergency spillway.
(o) Design of Cibeet and Cikarang crossings.
To avoid that Cibeet and Cikarang water with high sediment loads is intercepted by the WTC, it is
proposed to construct bypasses through means of siphons and partition walls. Based on the
results of the feasibility study, prepare the required detailed designs for the proposed measures to
improve the water quality in the WTC, being siphons, separation walls or improvement of
sediment trap maintenance.
(p) Stabilisation of canal banks and side drains.
Investigate the sliding problems of the canal bank in the reach between Curug and Cibeet,
propose and design measures to stabilise the canal banks. In some canal reaches, especially the
reaches in deep cut, erosion material will flow into the canal during the wet season. Propose and
design measures to prevent that runoff and erosion material from roads and slopes in deep cut
can enter the canal.
(q) Maintenance road.
Investigate the condition of the maintenance road along the right bank and propose and design
road improvement works, if required.
(r) Seepage losses at structures.
Investigate the occurrence and size of canal seepage losses at the major culverts, irrigation
offtakes, emergency spillways and other major structures. Propose and design improvement
measures, if required.
(s) Drainage inlets into the WTC.
Locate and survey all drainage inlets into the WTC and investigate measures to isolate and divert
the drainage flows into natural drains or proposed parallel drains. Especially, measures are
required in the section Bekasi-Jakarta and in other sections of the WTC passing through urban
areas and which are vulnerable to pollution.
(t) Toll road along Bekasi-Cawang.
Due technical consideration shall be given to the alignment of the proposed Bekasi-Cawang toll
road, with respect to implications in design of the rehabilitation works for the section Bekasi-
Cawang.
(u) Canal crossings.
Survey and locate all canal crossings as bridges, cross regulators, makeshift bridges and small
ferries. Analyse the status of the crossing structures and the degree of obstruction to canal flows.
Propose measures and carry out detail design for improvement, rehabilitation, widening, removal
or new crossings, as appropriate.
(v) Spoil dump areas and dredging method.
Investigate locations for possible spoil dumps required to receive material from canal excavation
and dredging and cleaning of the sediment traps. Investigate and advise on the most suitable
dredging methods and equipment, allowing for use of the same or similar equipment during later
4
maintenance and allowing for constraints in available work space and spoil dump areas. Prepare
cost estimate and specifications on dredging works and especially on the method of measurement
and payment.
(w) Cikao pollution control.
Review and update the hydrologic data of the Cikao; analyse the river flows and water quality;
and identify existing and potential future sources of water pollution and composition of their
effluent. Propose measures to either improve the Cikao river water quality by treatment of effluent
entering the Cikao both in the short and in the long term or to isolate the Cikao flow from the
Citarum through measures as separation of the flow of the Cikao and Citarum during the dry
season. Investigate the possibility of introducing a public awareness program concerning river
pollution and garbage collection.
(x) Pollution control and public awareness.
Investigate the canal reaches passing through urban and industrial areas that are vulnerable to
pollution and propose pollution control measures. These measures could include construction of
drains parallel to the WTC, canal fencing and improvement of existing fencing, construction of
concrete vehicle barriers on the canal side of all roads with public access, covering of the canal,
construction of garbage containers, construction of MCKs, regulatory measures, etc. Investigate
the possibility of introducing a public awareness program concerning pollution and use of WTC
water, use of MCKs and garbage collection.
(y) Encroachment in the Right of Way (RoW) of WTC.
Survey and record nature and type of encroachment in the RoW of the WTC and the issues
related to relocation of squatters and infrastructure in the RoW. Propose measures to relocate
people and infrastructure from the WTC RoW area.
(z) Resettlement and compensation, if required.
If resettlement of the squatters living in the RoW is required, address the institutional issues of
how preparation and implementation of resettlement will be undertaken, how it will be funded,
what skills are required and where that capacity is to be found and develop a Resettlement Action
Plan (RAP).
(aa) Capacity of Hydraulic Pumping Station at Curug (CHPS).
Determine the overall capacity of the pumps in the Curug hydraulic pumping station, especially
the nine (9) pumps that have recently been refurbished, and check whether the capacity is
sufficient to cope with the present and future water demands and the possible additional hydraulic
head losses in the WTC. Determine the effect of possible surcharging of the WTC on the pump
operation and the effect of the water level downstream of Curug weir on the pump efficiency.
(ab) Hydro-mechanical equipment in WTC.
Investigate the condition of present hydro-mechanical equipment in the WTC system, comprising
trash racks, water level control and measuring gates, flushing gates, and propose refurbishment,
repair or replacement of the equipment as appropriate. Prepare the design of all hydro-
mechanical equipment required for the proposed new siphons.
(ac) Spillway gates Cibeet weir.
Inspect the 3 (three) gates of the Cibeet weir and evaluate the operation conditions of the gates,
which were installed more than 50 years ago. Prepare specifications and a cost estimate for
repair, rehabilitation or replacement for the gates and appurtenant electro-mechanical equipment,
as appropriate.
(ad) Detailed design and cost estimate.
Prepare detailed design, tender drawings, cost estimates and implementation schedules for the
proposed WTC rehabilitation and improvement works.
Institutional Issues
(ae) Legal Framework PJT-II.
Study and review the legal framework of PJT-II and suggest changes, if deemed necessary,
based on the future role of PJT-II in basin water resources management.
(af) Revenue base of PJT-II.
Review PJT-II’s revenue base and suggest, based on cost recovery concept, strengthening PJT-II
revenue, also propose an institutional study component for development of PJT-II based on its
revised role and responsibility.
5
(ag) Financial situation of PJT-II.
Study PJT-II's financial situation, especially the revenue side of its finance should be focused on,
which shall include (i) rates for bulk raw water supply to (ex) PT Thames PAM Jaya (TPJ) and
other private and public customers; (ii) the kWh price of power supplied to PLN and generated at
the Jatiluhur dam; and (iii) other revenue sources.
5. Study Requirement
The West Tarum Canal Rehabilitation study is divided into the following three phases: (i) inception phase;
(ii) feasibility phase of possible Cibeet and Cikarang bypasses; and (iii) detailed design phase. Detailed
design of the selected option for the Cibeet and Cikarang crossing will start after the feasibility phase,
while detailed design of the other canal rehabilitation and improvement works will start after the inception
phase.
To undertake the WTC Rehabilitation project the Ministry of Public Works will engage the services of a
consulting firm or firms through requirement procedures as stipulated in the Government regulation and
acceptable to the Bank. It is anticipated that a total of 122 person-months of professional staff will be
required comprising 47 person-months of International professional staff and 75 person-months of
National professional staff. Further, about 50 person-months of sub-professional staff and technical staff
and 60 person-months of supporting staff will be required.
The topographic surveys, geotechnical investigations, hydrometric surveys and sediment sampling
programme for the feasibility and design phase will be undertaken through LCB subcontracts, which will
be supervised by the Consultants.
6. Resettlement
Resettlement of informal settlers in certain areas along the canal and in the soil dump areas will be
required. This will involve compensation for loss of livelihood and amenity, as well as rehabilitation.
(1) Conduct a socio- economic survey and alternative livelihood appraisal of 540 settlers (small shops,
temporary trader shelters and those living on sediment spoil dump areas) on inner embankments.
Identify willingness of settlers on sloping outer embankments to be relocated. Evaluate socio-
economic options for settlers on the WTC embankments,
(2) Identify alternative replacement land. Identify re-training possibilities. Negotiate compensation and
6
rehabilitation activities for informal settlers and legitimate resident affected by construction. Develop a
rehabilitation plan and negotiate compensation and rehabilitation for affected households near Cibeet
Syphon, Cikarang & Bekasi Weir. Facilitate compensation payments and undertake rehabilitation
program.
(3) Assist broker appropriate tenure leases contracted with informal settlers. Fence and sign post outer
boundaries along the course of WTC with limited entry points for current informal settlers. Form a
mobile group to monitor and report to authorities further encroachment and disturbances on the WTC
embankments.
7. Expertise Requirements
The feasibility and design study will be undertaken by a team of experts comprising International and
National professional staff. In general, preference will be given to International professional staff that has
work experience in Indonesia or in other Southeast Asian countries. It is expected that the following
professional staff and qualifications will be required:
6.1 International Professional Staff
(1) Team Leader/Water Resources Engineer
Should be university graduated civil engineer with about 20 years experience in the field of water
resources development and management. He should also have experience in operation and
design of irrigation systems, river systems and maintenance of infra-structure projects. He should
have preferably worked in Indonesia and/or other Southeast Asian countries in the field of water
resources planning, operation and design of major irrigation systems and raw water supply
projects. Further, he should have experience in management of a multi-disciplinary team for a
minimum period of 10 years and be capable of concise reporting and have a working knowledge
of Bahasa Indonesia. His duties will include all duties normally assigned to a team leader such as
liaison with the Ministry of Public Works and other Indonesian institutions, liaison with and
reporting to his home office, coordination of the feasibility, design and investigation work, overall
responsibility for administrative, financial, and technical reporting, progress planning and overall
guidance to the professional and supporting staff.
(2) Senior Hydrologist
Should be a university graduate with at least 15 years experience in operational hydrology,
collection, storage and interpretation of hydrological and meteorological data using appropriate
processing methods and modelling techniques. He should be familiar with the use of computer
for data processing, computer basin models as well as advanced computer analysis techniques.
Further, he should have experience in water resources assessment, water balance studies and
modelling of rainfall-runoff relations. He should have experience in Southeast Asia and preferably
in Indonesia in the field of water resources. Hid duties will also include supervision of the
proposed hydrometric survey programme.
(3) Senior Geotechnical Engineer
Should be a university graduate with at least 15 years experience in planning of geotechnical
investigations, collection and analysis of geotechnical data for design of high embankments,
foundations for weirs, siphons and other water related structures. His duties will include
preparation of a subcontract for geotechnical field investigations and soil laboratory testing,
supervision of such investigations and testing and interpreting borelogs and soil parameters.
(4) Water Resources Planner/Irrigation Engineer
Should be a university graduate with about 15 years experience in water resources planning. He
should have experience in planning of water availability and water demand for irrigation and DMI
and preparation of water balance studies by using appropriate computer models. Preferably, he
should have worked in Indonesia or in other Southeast Asian countries in the field of water
resources planning.
(5) Remote Sensing Specialist
Should be a university graduate with about 15 years experience in the field of interpretation of
aerial photographs and satellite images related to water resources, land use and agriculture. His
main duty will be determination of the irrigation areas at present under command of the WTC and
the CFC.
(6) Senior Hydraulic Engineer
Should be a university graduate with at least 15 years experience in planning and hydraulic
design of large conveyance systems such as irrigation canals and pipelines including appurtenant
7
hydraulic structures as weirs, siphons, water level control and measuring structures, culverts, etc.
Further, he should have experience in preparation and running of hydraulic canal models.
(7) O & M Expert
Should be a university graduate with about 15 years of experience in the O&M of irrigation and
drainage systems. He should have experience in the planning of O&M, improvement of irrigation
and drainage system operation and its management.
(8) Senior Structural Design Engineer
Should be a university graduate with at least 10 years relevant experience in planning and
detailed design of structures in large conveyance systems such as weirs, siphons, intake and
outlet works, gated regulators, retaining walls, sheet piling, tunnels, bridges, etc. He should have
profound knowledge of detail design of water retaining structures and construction planning,
including preparation of design and tender drawings. His duties will be to plan and prepare detail
designs of the major structures, execute design calculations, prepare the relevant specifications
and guide the National structural and civil engineers in their design work, preparation of the bill of
quantities, cost estimate and design and tender drawings.
(9) Hydro-Mechanical Specialist
Should be a university graduate with at least 15 years experience in planning, design, installation
and operation of hydro mechanical equipment used in water resources infrastructure, such as
pumping plants, trash racks, hydraulic gates, measuring gates, spillway and flushing gates, etc.
Further, he should also have experience in preparation of specifications for procurement of
mechanical equipment and testing of hydro-mechanical equipment.
(10) Senior Sedimentologist
Should be a university graduate in civil engineering with at least 10 years of experience in
hydraulic modelling, sediment sampling and sediment analyses. His duties will be preparation of a
subcontract for a sediment sampling programme, supervision of the sampling programme,
analysis of the results, estimation of the sediment transport in the river and canal system and
advice on operation of the sediment traps.
(11) Dredging Expert
Should be a university graduate in civil engineering with at least 8 years of experience in planning,
set-up and execution of small scale dredging and earth moving operations. It will be his task to
advise on the most suitable dredging methods for canal and sediment traps, allowing for the use
of the same or similar equipment during later maintenance and allowing for constraints in
available work space and spoil dump areas. He will also advise on the types of equipment to be
used, estimate the construction fleet requirements, unit cost and production rates, prepare
specifications for dredging works, advise on equipment requirements for maintenance,
maintenance scheduling and programming.
(12) Water Quality Specialist
Should be a university graduate with about 15 years of experience of which at least 5 years in
river basin water quality management. He should have experience in the field of setting up water
quality assessment programmes, measurement of water quality in rivers and canals, water quality
analysis, methods to improve water quality in rivers, water treatment processes and water quality
models. He should preferably have experience in Southeast Asia or in Indonesia.
(13) Drinking Water Specialist
Should be a university graduate with at least 10 years experience in the field of drinking water
treatment and waste water treatment. He should have knowledge about chemical engineering
and the capability to collect and analyse water quality data, chemicals to be used in the treatment
process, control of the drinking water treatment process and propose measures for adjustment
and improvement.
(14) Senior Economist
Should be a university graduate with at least 15 years experience in economic analyses of water
resources projects involving irrigation and drainage, drinking water supply, water quality, hydro
power and canal maintenance. He should be capable of evaluating project costs and benefits,
requirements for operation and maintenance of canals and sediment traps and financial analyses
of the project components. Preferably, he should have at least 5 years of experience in Indonesia
or in Southeast Asia.
(15) Institutional Specialist
Should be a university graduate in public administration with about 15 years of experience in the
8
field of organization of public, private and semi-government services of which at least 5 years in
Indonesia and/or other Southeast Asian countries. He should have knowledge of the legal setting
for water resources institutions and be able to analyse institutional functioning and propose
institutional development strategies.
6.2 National Professional Staff
(1) Deputy-Team Leader/Water Resources Engineer
Should be a university graduate in civil engineering with about 15 years experience in the field of
water resources planning, feasibility studies, design of irrigation and drainage systems and related
structures and raw water supply. Further, he should have ample experience in managing project
teams for design studies. His duties will include liaison with the Team Leader as well as his own
home office, preparation of coordination with various local authorities and survey and
investigations contractors, overall guidance to the National staff members, reporting on special
subjects to the Client and participation in feasibility and design work.
(2) Topographical Engineer
Should be a university graduate with about 10 years experience in collection and review of
topographical data, measurement of cross sections and levelling, preparation of contracts for
topographical surveys and supervision of field work. He will be responsible for planning of the
survey work, its supervision and preparation of survey data and maps for detailed design. His
duties will further include quantity estimation of canal excavation and dredging works and
determination of the location and dimensions of cross regulators, irrigation offtakes and other
important canal structures.
(3) Geotechnical Engineer
Should be a university graduate with about 10 years experience in the geotechnical aspects of
foundation design of large hydraulic structures and siphons as well as in the design of canal
banks in unstable soil and embankments in high fill. Further, he should have ample experience in
analyses of materials used for fill and foundation of hydraulic structures and supervision of
geotechnical field investigations and laboratory testing.
(4) Water Quality Engineer
Should be a university degree with at least 10 years experience in collection, evaluation and
analyses of water quality data and implementation of water quality monitoring programmes. He
should have the capability to collect, evaluate and analyse data about waste water sources and to
propose water pollution control programmes.
(5) Hydrologist
Should be a university graduate with a strong background in hydrology and about 10 years
experience in collection and analysis of climatologic and hydrological data and setting up of an
appropriate database. He should be able to assess water availability in river basins, analyse
floods and prepare water balance of river basins. He should also have experience in execution
and supervision of hydrometric measurement programmes for canal and river flows and
calibration of flow measuring structures.
(6) Irrigation Design Engineer
Should be a university graduate with about 10 years experience in planning and design of
irrigation and drainage systems including determination of irrigation demands and water
availability analysis. He should also have knowledge of operation and maintenance of irrigation
canals and related control and measuring structures as Romeijn and Crump de Gruyter gates.
(7) Hydraulic Design Engineer
Should be a university graduate with about 10 years experience in hydraulic design of irrigation
and drainage canals and appurtenant structures such as weirs, siphons, cross regulators,
irrigation off takes, etc. He should also have experience in calculation and verification of the
conveyance capacities of existing canals.
(8) Irrigation O&M Engineer
Should be a university graduate with at least 10 years of experience in planning of O&M
requirements (equipment, manpower, maintenance intervals) for large irrigation and drainage
conveyance systems, including maintenance excavation, cleaning of canal banks, etc. Further,
he should have experience in investigation and implementation of operation improvement
measures for large conveyance systems, including water level control, flow measurement and
maintenance of sediment traps.
9
(9) Structural Engineer
Should be a university graduate with about 7 years of experience in structural design of hydraulic
structures such as weirs, siphons, spillways, culverts, cross regulators and irrigation off takes as
well as in the design of roads and bridges. His duties will be preparation of detailed design of
canal structures and improvement works, relevant specifications and structural design and tender
drawings.
(10) Civil Engineer
Should be a university graduate with at least 7 years of experience in preparation of bills of
quantities, cost estimating and preparation of design and tender drawings. His duties will be
preparation of the bill of quantities, engineer’s cost estimate and design and tender drawings.
(11) Contracts Engineer
Should be a university graduate with at least 10 years of experience in preparation of
prequalification documents, tender documents and schedules for construction works. He should
also have experience in preparation of tenders and contracts for International Competitive Bidding
(ICB) and Local Competitive Bidding (LCB).
(12) Environmental Specialist
Should be a university graduate with environmental background and about 8 years of experience
in environmental impact assessment (EIA) of water resource development and related projects.
This shall include experience in environmental impact and in the assessment of resettlement and
compensation. He must have experience in the preparation of Environmental Impact Assessment
reports according to the national guidelines (AMDAL). The consultant shall be assisted by the
Sociologist/Public Participation Specialist.
(13) Sociologist/Public Participation Specialist
Should be a university graduate in social geography or spatial planning with about 8 years of
experience in the field of regional development planning, assessment of social impacts of water
resources development and related projects and in public participation activities. Further, he
should have experience in identification of socio-economic problems related to resettlement,
preparation of resettlement plans and compensation arrangements.
(14) Economist
Should be a university graduate with at least 10 years of experience in the economic and financial
analyses of water resources projects. He should have experience in projects for water
conveyance systems, drinking water supply and water quality and must be able to compare
alternatives.
(15) Institutional Specialist
Should be a university graduate with about 10 years of experience in the field of organisation of
public services. He should have ample knowledge of the legal setting for water resources
institutions and be able to analyse institutional functioning and propose institutional development
strategies.
(16) Legal Expert
Should be a university graduate with about 20 years experience in the field of the legal aspects of
organizations of public services. He should have knowledge of the legal settings for water
resources institutions and water pollution control. He should have the capability to analyse legal
functions, water resources policies and strategies and to propose adjustments to improve
management of water resources development.
7. Reporting
The Consultant shall prepare and submit the following reports to the Client and the Bank during the period
of services. All reports and drawings shall be in the English language and with standard dimensions,
unless otherwise specified. The SI system shall be used in all reports, computations and drawings.
During the course of the consulting services, the following reports are to be submitted:
(1) Inception Report
The Consultant will submit an Inception Report 45 days after commencement of the services. This
report will present the Consultant’s preliminary evaluation of the scope of works, field conditions,
availability and status of data and reports, detailed work plan, subcontracts for topographical surveys,
geotechnical investigations, hydrometric surveys and sediment sampling programme (15 copies).
10
(2) Feasibility Report of Cibeet and Cikarang bypass
A Feasibility Report at the end of the 6th (sixth) month, presenting the alternatives selected, being
separation of the WTC flow from the Cibeet and/or the Cikarang or improvement and adequate
maintenance of the sediment traps considering the improvement of water quality in the WTC. This
report should present clear recommendations and justification of the chosen alternative(s) for
improvement of the water quality and sediment situation in the WTC (15 copies).
(3) Report about Legal and Institutional Issues of PJT-II
A Report at the end of the 6th (sixth) month, presenting the findings of the study about the legal
framework, institutional setting, revenue base and financial situation of PJT-II (15 copies).
(4) Draft Design Report
At the end of the 10th (tenth) month from the start of services, the Consultant will submit a Draft Design
Report which will describe the general approach of the study, detailed design of canal, required
structures and equipment to improve canal operation, the Bekasi siphon, option to improve the water
quality and sediment condition in the WTC at the crossing with Cibeet and Cikarang. It should also
include the results of topographical surveys, geotechnical investigations, laboratory testing and
hydrometric and sediment sampling programmes carried out during the study (15 copies).
(5) Final Design Report
At the end of the services, the Consultant will submit a Final Design Report which will describe the
general approach, standards used, detailed design of canal, works and equipment required for
improved canal operation, Bekasi siphon and chosen options for interception/bypassing of the Cibeet
and Cikarang flows, including design calculations for the major components. It should also include the
results of topographical surveys, geotechnical investigations, laboratory testing and hydrometric and
sediment sampling programmes carried out during the study (15 copies).
(6) Prequalification Document
At the end of the 6th (sixth) month from the start of services, the Consultant will submit Prequalification
Documents for the proposed improvement works (15 copies).
(7) Draft Tender Document
At the end of the 10th (tenth) month from the start of services, the Consultant will submit Draft Tender
Documents for the agreed packages comprising (i) Invitation for Tenders; (ii) Instructions to Tenderers;
(iii) General Conditions (FIDIC); (iv) Particular Conditions; (v) Specification; (vi) Letter of Tender and
Appendix; and (vii) Forms, Securities and Schedules (10 copies).
(8) Final Tender Documents
After approval of the Draft Tender Documents by the GoI and ADB, the Consultant will prepare the
Final Tender Documents for the agreed packages comprising (i) Invitation for Tenders; (ii) Instructions
to Tenderers; (iii) General Conditions (FIDIC); (iv) Particular Conditions; (v) Specification; (vi) Letter of
Tender and Appendix; (vii) Bill of Quantities; (viii) Forms, Securities, Schedules, etc.; and (ix) Tender
Drawings (15 copies).
(9) Quarterly Progress Report
The Consultant will submit at the end of each study quarter a progress report giving a summary of the
progress, team activities during the reporting period, technical and management problems, if any,
contract administration, financial and person-months utilisation and work anticipated to be carried out
in the next progress reporting period (10 copies).
(10) Completion Report
At the end of the services, the Consultant will submit a short Completion Report with details about the
way the feasibility study and detailed designs were carried out, reports submitted, person-months used
and costs incurred (10 copies).
12
ICWRMP Program Management – TOR for Consultants
2. Scope of Work
The following main activities will be undertaken
General
• Implement sound project management practices within the Program Management Unit
• Design and implement quality management procedures applicable to the program, and promote these
among the component projects.
Monitoring and reporting
• Prepare and maintain a performance monitoring and evaluation mechanism for the component
projects.
• Establish and maintain an accounting system that summarises information provided by the component
projects and provides consolidated reports.
• Seek and receive regular and frequent (at least 6-monthly) financial and progress reports from each of
the component projects. Prepare written consolidated reports and submit to the Project Steering
Committee.
• Attend Project Steering Committee meetings and report as required.
• Provide ad hoc information to the Project Steering Committee, Executing Agency and Implementing
Agencies as required.
Stakeholder Liaison
• Establish a network of contacts among stakeholder groups associated with each of the component
projects, as well as relevant national, provincial and district agencies and ADB.
• Act as a point of contact for all stakeholder representatives.
• Provide advice on request to stakeholder representatives.
• Facilitate six-monthly stakeholder workshops to discuss relevant issues related to progress and
coordination.
• Develop and maintain a website to provide a means of information access by stakeholders and the
1
public, and well as providing a mechanism for feedback (stakeholder forum).
Project Coordination
• Establish formal links with the team leaders of each of the component projects and act as a point of
contact.
• Facilitate six-monthly workshops for component project staff to discuss relevant issues related to
progress and coordination, as well as common technical issues.
• Identify potential overlaps and inefficiencies among projects and report these to the Project Steering
Committee.
• Deal with procedural issues related to project management and in particular to interpretation and
application of relevant GOI and ADB procedures and guidelines.
Minor Studies
• Identify the need for minor studies (up to $400,000 total) to improve knowledge of water issues in CRB.
• Make recommendations to the Project Steering Committee and seek approval for these studies.
• As approved, recruit local consultants, universities, institutes or other appropriate organizations to
undertake the studies.
• Manage the implementation of the studies.
• Promulgate the results of the studies widely among component projects, stakeholders and elsewhere.
Capacity Building for NGOs
• Identify NGOs involved in the various component projects of Tranche 1.
• Undertake a training needs analysis for each of the NGOs – in relation to the roles they will be required
to play in the particular component projects.
• Develop a comprehensive training program for each of the NGOs, and implement them.
• Monitor performance of each NGO during the period of the component project implementation.
• Provide mentoring for NGOs and be a resource in times of difficulty.
• Facilitate exchange of information among the NGOs.
Preparation of Tranche 2
• Assist the Executing Agency to confirm (or otherwise) the component projects to be included in
Tranche 2 of the MFF, including the facilitation of stakeholder consultations.
• Assist in the preparation of the necessary documents for recruitment of consultants to undertake
preparation of the Tranche 2 component projects.
• Assist in the submission of the documents to GOI and ADB (as may be necessary).
• Assist the Executing Agency in the preparation of the Periodic Financing Request for submission to
ADB.
3. Expertise Requirements
The program management will be undertaken by a team of experts comprising International and National
professional staff. In general, preference will be given to International professional staff that have work
experience in Indonesia or in other Southeast Asian countries. It is expected that the following
professional staff and qualifications will be required:
3.1 International Professional Staff
(1) Team Leader/Water Resources Specialist
Should be a university graduated civil engineer with about 20 years experience in the field of
water resources development and management. He/she should also have experience as a team
leader in charge of multi-disciplinary aid projects. He/she should have preferably worked in
Indonesia and/or other Southeast Asian countries in the field of water resources and river basin
planning and management. Further, he should have experience in management of a multi-
disciplinary team for a minimum period of 10 years and have good communication and report
writing skills.
2
(2) Monitoring and Evaluation Specialist
Should be a university graduate with at least 15 years experience in designing and implementing
monitoring and evaluation systems for large programs and/or projects. In addition, he/she should
have experience in the field of water resource management, preferably in Indonesia and/or other
Southeast Asian countries.
(3) Unallocated Pool of Specialists
It is impossible to clearly define all requirements for skills and experience necessary for the
execution of the required program management functions. Therefore, a pool of specialists will be
created (up to 12 months total) to cater for specific needs as may arise from time to time. Such
specialists may include (but not be limited to): economist, hydrologist, civil engineer,
environmental scientist, legal specialist.
3.2 National Professional Staff
(1) Deputy-Team Leader/Water Resources Engineer
Should be a university graduate in civil engineering with about 15 years experience in the field of
water resources planning and management. Further, he/she should have ample experience in
managing project teams for multi-disciplinary projects. Formal qualifications in project
management would be an advantage.
(2) Financial Management Specialist
Should be a university graduate with about 10 years experience in economics, accounting or
business. He/she should have experience in water-related projects, and establishing and
implementing financial management systems for large programs/projects. A knowledge of GOI
financial management requirements is essential and a knowledge of ADB procedures would be an
advantage.
(3) Water Engineer
Should be a university graduate with about 10 years experience in the engineering aspects of
water resource management, including planning, construction, operation and maintenance of
water control infrastructure. Experience in working on internationally funded water resource
projects in Indonesia would be an advantage, as would experience in preparation of
prequalification documents, tender documents and schedules for construction works.
(4) Sociologist/Public Participation Specialist
Should be a university graduate in social geography or spatial planning with at least 10 years of
experience in the field of regional development planning, assessment of social impacts of water
resources development and related projects and in public participation activities. Further, he/she
should have experience in working with Indonesian NGOs, Experience in identification of socio-
economic problems related to resettlement, preparation of resettlement plans and compensation
arrangements would be an advantage.
3. Reporting
The Consultant shall prepare and submit the following reports to the Client, the Bank and the Project
Steering Committee during the period of services. All reports and drawings shall be in the English
language and with standard dimensions, unless otherwise specified. During the course of the consulting
services, the following reports are to be submitted as a minimum:
• Inception Report [within two months of commencement]
• Program Management Manual (detailing the performance monitoring and evaluation mechanism for the
component projects) [within three months of commencement]
• Financial Management Manual [within two months of commencement]
• Quarterly Progress and Financial Reports
• Annual Progress and Financial Reports
• Other regular reports required by GOI and ADB
• Program Completion Report