0% found this document useful (0 votes)
1K views30 pages

Dupa PDF Form

Download as pdf or txt
Download as pdf or txt
Download as pdf or txt
You are on page 1/ 30

DETAILED ESTIMATE

Materials Recovery Facility


Tunga, Leyte

ITEM 100(2) - Clearing and Grubbing


Quantity = 1.00 Lump Sum

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00
B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00
C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 4,726.08

Foreman 1 3.00 Days @ P 588.24 P 1,764.72


Unskilled Laborer 3 3.00 Days @ P 329.04 P 2,961.36
P 4,726.08

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 4,726.08


INDIRECT COST - - - - - - - - - - - - - - - - - - P 1,476.90
OCM - - - - - - - - - - - P 708.91
Contractor's Profit - - 472.61
VAT - - - - - - - - - - - 295.38
Mobilization - - - - - - -
P 1,476.90
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 6,202.98
P 6,202.98
Unit Cost =
1.00
= P 6,202.98

Page 1 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 903(1) - Forms and Falseworks


Quantity = 1.00 Lump Sum

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 10,620.00

Assorted Coco Lumber 500.00 Bd. Ft. @ P 15.00 P 7,500.00


1/4" Thk. Ordinary Plywood 10.00 Pc. @ P 270.00 P 2,700.00
CW Nails, Assorted 10.00 Kg. @ P 42.00 P 420.00
P 10,620.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 13,788.40

Foreman 1 5.00 Days @ P 588.24 P 2,941.20


Carpenter 2 5.00 Days @ P 426.64 P 4,266.40
Unskilled Laborer 4 5.00 Days @ P 329.04 P 6,580.80
P 13,788.40

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 24,408.40


INDIRECT COST - - - - - - - - - - - - - - - - - - P 7,627.63
OCM - - - - - - - - - - - P 3,661.26
Contractor's Profit - - 2,440.84
VAT - - - - - - - - - - - 1,525.53
Mobilization - - - - - - -
P 7,627.63
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 32,036.03
P 32,036.03
Unit Cost =
1.00
= P 32,036.03

Page 2 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 803(1)a - Structure Excavation, Common Soil


Quantity = 62.00 cu.m.

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 9,522.00

Foreman 1 5.00 Days @ P 588.24 P 2,941.20


Unskilled Laborer 4 5.00 Days @ P 329.04 P 6,580.80
P 9,522.00

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 9,522.00


INDIRECT COST - - - - - - - - - - - - - - - - - - P 2,975.63
OCM - - - - - - - - - - - P 1,428.30
Contractor's Profit - - 952.20
VAT - - - - - - - - - - - 595.13
Mobilization - - - - - - -
P 2,975.63
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 12,497.63
P 12,497.63
Unit Cost =
62.00
= P 201.57

Page 3 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1705(1) - Fill and Backfill


Quantity = 62.00 cu.m.
Backfill = 10.00 cu.m.

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 4,800.00

Mixed of Sand and Gravel 15.00 Cu.m. @ P 320.00 P 4,800.00


P 4,800.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 1,968.00

Plate Compactor 2.00 Days @ P 984.00 P 1,968.00


P 1,968.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 7,757.28

Foreman 1 2.00 Days @ P 588.24 P 1,176.48


Unskilled Laborer 4 5.00 Days @ P 329.04 P 6,580.80
P 7,757.28

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 14,525.28


INDIRECT COST - - - - - - - - - - - - - - - - - - P 4,539.15
OCM - - - - - - - - - - - P 2,178.79
Contractor's Profit - - 1,452.53
VAT - - - - - - - - - - - 907.83
Mobilization - - - - - - -
P 4,539.15
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 19,064.43
P 19,064.43
Unit Cost =
62.00
= P 307.49

Page 4 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 900(1) - Reinforced Concrete


Quantity = 228.00 cu.m.

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 341,466.00

Portland Cement 591.00 Bag @ P 257.00 P 151,887.00


Coarse Sand 63.00 Cu.m. @ P 615.00 P 38,745.00
Gravel, 3/4 62.00 Cu.m. @ P 870.00 P 53,940.00
12mmØ Def. Bar Grade 40 1,813.00 Kg. @ P 42.00 P 76,146.00
10mmØ Def. Bar Grade 40 444.00 Kg. @ P 42.00 P 18,648.00
No. 16 G. I. Tie Wire 50.00 Kg. @ P 42.00 P 2,100.00
P 341,466.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 4,212.00

Concrete Mixer, 1.0 Bagger 2.00 Days @ P 1,376.00 P 2,752.00


Concrete Vibrator 2.00 Days @ P 730.00 P 1,460.00
P 4,212.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 41,365.20

Foreman 1 15.00 Days @ P 588.24 P 8,823.60


Mason/Steelman 2 15.00 Days @ P 426.64 P 12,799.20
Unskilled Laborer 4 15.00 Days @ P 329.04 P 19,742.40
P 41,365.20

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 387,043.20


INDIRECT COST - - - - - - - - - - - - - - - - - - P 120,951.00
OCM - - - - - - - - - - - P 58,056.48
Contractor's Profit - - 38,704.32
VAT - - - - - - - - - - - 24,190.20
Mobilization - - - - - - -
P 120,951.00
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 507,994.20
P 507,994.20
Unit Cost =
228.00
= P 2,228.04

Page 5 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1046(2)a - CHB Non Load Bearing (including Reinforcing Steel), 100 mm
Quantity = 167.00 sq.m.

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 67,563.00

Portland Cement 93.00 Bag @ P 257.00 P 23,901.00


Fine Sand 8.00 Cu.m. @ P 615.00 P 4,920.00
4'' Thk. CHB 2,161.00 Pc. @ P 12.00 P 25,932.00
10mmØ Def. Bar Grade 40 300.00 Kg. @ P 42.00 P 12,600.00
No. 16 G. I. Tie Wire 5.00 Kg. @ P 42.00 P 210.00
P 67,563.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 13,788.40

Foreman 1 5.00 Days @ P 588.24 P 2,941.20


Mason/Steelman 2 5.00 Days @ P 426.64 P 4,266.40
Unskilled Laborer 4 5.00 Days @ P 329.04 P 6,580.80
P 13,788.40

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 81,351.40


INDIRECT COST - - - - - - - - - - - - - - - - - - P 25,422.31
OCM - - - - - - - - - - - P 12,202.71
Contractor's Profit - - 8,135.14
VAT - - - - - - - - - - - 5,084.46
Mobilization - - - - - - -
P 25,422.31
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 106,773.71
P 106,773.71
Unit Cost =
167.00
= P 639.36

Page 6 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1027(1) - Cement Plaster Finish


Quantity = 333.00 sq.m.

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 20,138.00

Portland Cement 64.00 Bag @ P 257.00 P 16,448.00


Fine Sand 6.00 Cu.m. @ P 615.00 P 3,690.00
P 20,138.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 5,018.88

Foreman 1 3.00 Days @ P 588.24 P 1,764.72


Mason 1 3.00 Days @ P 426.64 P 1,279.92
Unskilled Laborer 2 3.00 Days @ P 329.04 P 1,974.24
P 5,018.88

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 25,156.88


INDIRECT COST - - - - - - - - - - - - - - - - - - P 7,861.53
OCM - - - - - - - - - - - P 3,773.53
Contractor's Profit - - 2,515.69
VAT - - - - - - - - - - - 1,572.31
Mobilization - - - - - - -
P 7,861.53
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 33,018.41
P 33,018.41
Unit Cost =
333.00
= P 99.15

Page 7 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

#N/A
Quantity = #N/A #N/A

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 203,498.00

6mm x 50mm x 50mm Angle Bar 1,141.00 Kg. @ P 52.00 P 59,332.00


6mm x 38mm x 38mm Angle Bar 753.00 Kg. @ P 52.00 P 39,156.00
10mm Thk. Steel Plate 168.00 Kg. @ P 46.00 P 7,728.00
6mm Thk. Steel Plate 700.00 Kg. @ P 46.00 P 32,200.00
2" x 4" (2.0 mm) C-purlins 910.00 Kg. @ P 50.00 P 45,500.00
16mm dia. Tension rod 38.00 Kg. @ P 50.00 P 1,900.00
Turnbuckle Std. for 16mmØ Rod 8.00 Pc. @ P 230.00 P 1,840.00
12mmØ x 150mm Anchor Bolts w/ HD Washers 48.00 Pc. @ P 55.00 P 2,640.00
12mm Ø Sag Rod 43.00 Kg. @ P 50.00 P 2,150.00
Red Oxide Metal Primer 6.00 Gal. @ P 590.00 P 3,540.00
Welding Rod 29.00 Kg. @ P 110.00 P 3,190.00
4" Paint Brush 5.00 Pc. @ P 55.00 P 275.00
3" Paint Brush 3.00 Pc. @ P 55.00 P 165.00
Paint Thinner 2.00 Gal. @ P 270.00 P 540.00
Oxygen ( refill / tank 1800 psi) 1.00 cylinder @ P 1,056.00 P 1,056.00
Acetylene ( refill / tank 240 psi ) 1.00 cylinder @ P 2,286.00 P 2,286.00
P 203,498.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 29,215.20

Welding Machine (300 Amp) 6.00 Days @ P 2,968.00 P 17,808.00


Acetylene and Oxygen Outfit 2.00 Days @ P 363.60 P 727.20
Generator Set, 51-100KW 8.00 Days @ P 1,335.00 P 10,680.00
P 29,215.20

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 50,411.12

Foreman 1 17.00 Days @ P 588.24 P 10,000.08


Welder 2 17.00 Days @ P 426.64 P 14,505.76
Semi-Skilled Laborer 4 17.00 Days @ P 380.96 P 25,905.28
P 50,411.12

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 283,124.32


INDIRECT COST - - - - - - - - - - - - - - - - - - P 88,476.35
OCM - - - - - - - - - - - P 42,468.65
Contractor's Profit - - 28,312.43
VAT - - - - - - - - - - - 17,695.27
Mobilization - - - - - - -
P 88,476.35
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 371,600.67
P 371,600.67
Unit Cost =
#N/A
= #N/A

Page 8 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

#N/A
Quantity = #N/A #N/A

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 51,584.00

Fiber Cement Board 4.5mm Thk. 58.00 Pc. @ P 441.00 P 25,578.00


1/2'' x 12'' x 8' Fiber Cement Bd. Sanepa 23.00 Pc. @ P 384.00 P 8,832.00
Furring Channel 0.80x12x38x5000mm 70.00 Pc. @ P 92.00 P 6,440.00
Carrying/Hanger Channel 0.80x12x38x5000mm 32.00 Pc. @ P 132.00 P 4,224.00
0.30 x 1.20m Pre-fab Wood Ceiling Vent Slots 10.00 Pc. @ P 462.00 P 4,620.00
Blind Rivets 1,680.00 Pc. @ P 0.40 P 672.00
Self Drilling Screw 1,740.00 Pc. @ P 0.70 P 1,218.00
P 51,584.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 12,562.56

Foreman 1 9.00 Days @ P 588.24 P 5,294.16


Carpenter 1 9.00 Days @ P 426.64 P 3,839.76
Semi-Skilled Laborer 1 9.00 Days @ P 380.96 P 3,428.64
P 12,562.56

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 64,146.56


INDIRECT COST - - - - - - - - - - - - - - - - - - P 20,045.80
OCM - - - - - - - - - - - P 9,621.98
Contractor's Profit - - 6,414.66
VAT - - - - - - - - - - - 4,009.16
Mobilization - - - - - - -
P 20,045.80
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 84,192.36
P 84,192.36
Unit Cost =
#N/A
= #N/A

Page 9 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

#N/A
Quantity = #N/A #N/A

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 3,525.75

Marine Plywood, 4' X 8' X 3/4" 3 Pc. @ P 1,130.00 P 3,390.00


Wood Glue (Liter) 0.25 Liter @ P 207.00 P 51.75
Assorted Nails 2 Kg. @ P 42.00 P 84.00
P 3,525.75

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 1,395.84

Foreman 1 1.00 Day @ P 588.24 P 588.24


Carpenter 1 1.00 Day @ P 426.64 P 426.64
Semi-Skilled Laborer 1 1.00 Day @ P 380.96 P 380.96
P 1,395.84

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 4,921.59


INDIRECT COST - - - - - - - - - - - - - - - - - - P 1,538.00
OCM - - - - - - - - - - - P 738.24
Contractor's Profit - - 492.16
VAT - - - - - - - - - - - 307.60
Mobilization - - - - - - -
P 1,538.00
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 6,459.59
P 6,459.59
Unit Cost =
#N/A
= #N/A

Page 10 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1014(1)a1 - Prepainted Metal Sheets, below 0.427 mm, Corrugated, Short Span
Quantity = 294.00 sq.m.

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 255,978.00

Corspan 0.50x1220mm Pre-painted Long span Roof 294.00 Sq.m. @ P 650.00 P 191,100.00
Pre-Painted Ridge Roll 0.70x2440mm 42.00 Ln.m @ P 350.00 P 14,700.00
1/2'' x 12'' x 8' Hardi Sanepa 56.00 Pc. @ P 377.00 P 21,112.00
1.25m Double Sided Insulation Foil 294.00 Mts. @ P 64.00 P 18,816.00
Silicon Sealant 8.00 Tube @ P 350.00 P 2,800.00
2 1/2" Metal Tek Screw 2,220.00 Pc. @ P 2.50 P 5,550.00
Touch-up Paint 4.00 Qrt. @ P 380.00 P 1,520.00
Blind Rivets 950.00 Pc. @ P 0.40 P 380.00
P 255,978.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 10,498.00

Foreman 1 5.00 Days @ P 588.24 P 2,941.20


Roof Installer 2 5.00 Days @ P 426.64 P 4,266.40
Unskilled Laborer 2 5.00 Days @ P 329.04 P 3,290.40
P 10,498.00

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 266,476.00


INDIRECT COST - - - - - - - - - - - - - - - - - - P 83,273.75
OCM - - - - - - - - - - - P 39,971.40
Contractor's Profit - - 26,647.60
VAT - - - - - - - - - - - 16,654.75
Mobilization - - - - - - -
P 83,273.75
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 349,749.75
P 349,749.75
Unit Cost =
294.00
= P 1,189.63

Page 11 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1032 - Painting, Varnishing and Other Related Works


Quantity = 77.00 sq.m.

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 48,402.00

Red Oxide Metal Primer 8.00 Gal. @ P 590.00 P 4,720.00


Concrete Neutralizer 4.00 Ltr. @ P 280.00 P 1,120.00
Waste Cotton/Stuppa 2.00 Kg. @ P 67.00 P 134.00
Flat Wall Enamel Paint 7.00 Gal. @ P 560.00 P 3,920.00
Quick Dry Enamel Paint 2.00 Gal. @ P 684.00 P 1,368.00
Acrytex Cast 4.00 Gal. @ P 486.00 P 1,944.00
Plasolux Glazing Putty 1.00 Gal. @ P 632.00 P 632.00
Flat Latex Paint 17.00 Gal. @ P 552.00 P 9,384.00
Semi-Gloss Latex Paint 25.00 Gal. @ P 590.00 P 14,750.00
Acrylic Tinting Colors (1/4 liter) 5.00 Can @ P 200.00 P 1,000.00
Masonry Putty 15.00 Gal. @ P 312.00 P 4,680.00
Fiberglass Tape 4.00 Roll @ P 90.00 P 360.00
Paint Thinner 5.00 Gal. @ P 270.00 P 1,350.00
Sand Paper 55.00 Pc. @ P 28.00 P 1,540.00
Assorted Paint Brush/Roller 1.00 lot @ P 1,500.00 P 1,500.00
P 48,402.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 15,424.08

Foreman 1 7.00 Days @ P 588.24 P 4,117.68


Painter 2 7.00 Days @ P 426.64 P 5,972.96
Semi-Skilled Laborer 2 7.00 Days @ P 380.96 P 5,333.44
P 15,424.08

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 63,826.08


INDIRECT COST - - - - - - - - - - - - - - - - - - P 19,945.65
OCM - - - - - - - - - - - P 9,573.91
Contractor's Profit - - 6,382.61
VAT - - - - - - - - - - - 3,989.13
Mobilization - - - - - - -
P 19,945.65
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 83,771.73
P 83,771.73
Unit Cost =
77.00
= P 1,087.94

Page 12 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1010(2)a - Doors, Flush


Quantity = 13.44 sq.m.

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 18,765.60

Flush Type Solid Core Door 8.40 Sq.m @ P 1,700.00 P 14,280.00


PVC-Flush Door 5.04 Sq.m @ P 890.00 P 4,485.60
P 18,765.60

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 1,014.88

Foreman 1 1.00 Day @ P 588.24 P 588.24


Carpenter 1 1.00 Day @ P 426.64 P 426.64
P 1,014.88

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 19,780.48


INDIRECT COST - - - - - - - - - - - - - - - - - - P 6,181.40
OCM - - - - - - - - - - - P 2,967.07
Contractor's Profit - - 1,978.05
VAT - - - - - - - - - - - 1,236.28
Mobilization - - - - - - -
P 6,181.40
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 25,961.88
P 25,961.88
Unit Cost =
13.44
= P 1,931.69

Page 13 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1010(1) - Frames, Jambs, Sills, Head, Transoms and Mullions


Quantity = 4.00 set

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 1,500.00

Flush Type Solid Core Door Frame 2 Set @ P 500.00 P 1,000.00


PVC-Flush Door Frame 2 Set @ P 250.00 P 500.00
P 1,500.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 1,014.88

Foreman 1 1.00 Day @ P 588.24 P 588.24


Carpenter 1 1.00 Day @ P 426.64 P 426.64
P 1,014.88

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 2,514.88


INDIRECT COST - - - - - - - - - - - - - - - - - - P 785.90
OCM - - - - - - - - - - - P 377.23
Contractor's Profit - - 251.49
VAT - - - - - - - - - - - 157.18
Mobilization - - - - - - -
P 785.90
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 3,300.78
P 3,300.78
Unit Cost =
4.00
= P 825.20

Page 14 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

#N/A
Quantity = #N/A #N/A

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 24,843.00

D1 - 1/4 Thk. 2.10 x 1.70m Glass on Aluminum


Frame (Analok Fin.) 3.57 Sq.m. @ P 4,550.00 P 16,243.50
D2 - 1/4 Thk. 2.10 x 0.90m Glass on Aluminum
Frame (Analok Fin.) 1.89 Sq.m. @ P 4,550.00 P 8,599.50
P 24,843.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 2,687.84

Foreman 1 2.00 Days @ P 588.24 P 1,176.48


Carpenter 1 2.00 Days @ P 426.64 P 853.28
Unskilled Laborer 1 2.00 Days @ P 329.04 P 658.08
P 2,687.84

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 27,530.84


INDIRECT COST - - - - - - - - - - - - - - - - - - P 8,603.39
OCM - - - - - - - - - - - P 4,129.63
Contractor's Profit - - 2,753.08
VAT - - - - - - - - - - - 1,720.68
Mobilization - - - - - - -
P 8,603.39
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 36,134.23
P 36,134.23
Unit Cost =
#N/A
= #N/A

Page 15 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1009(1)a - Jalousie Windows, Glass


Quantity = 18.38 sq.m.

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 9,882.00

W1 - 1.80m X 1.20m Jalousie Window (3-sets) 6.48 Sq.m. @ P 540.00 P 3,499.20


W2 - 1.20m X 1.20m Jalousie Window (5-sets) 7.20 Sq.m. @ P 540.00 P 3,888.00
W3 - 0.70m X1.20m Jalousie Window (4-sets) 3.36 Sq.m. @ P 540.00 P 1,814.40
W4 - 0.70m X0.60m Jalousie Window (3-sets) 1.26 Sq.m. @ P 540.00 P 680.40
P 9,882.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 2,029.76

Foreman 1 2.00 Days @ P 588.24 P 1,176.48


Glass Installer 1 2.00 Days @ P 426.64 P 853.28
P 2,029.76

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 11,911.76


INDIRECT COST - - - - - - - - - - - - - - - - - - P 3,722.43
OCM - - - - - - - - - - - P 1,786.76
Contractor's Profit - - 1,191.18
VAT - - - - - - - - - - - 744.49
Mobilization - - - - - - -
P 3,722.43
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 15,634.19
P 15,634.19
Unit Cost =
18.38
= P 850.61

Page 16 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

#N/A
Quantity = #N/A #N/A

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 23,511.86

Granite/Ceramic Tiles Sq.m. @ P 500.00 P 0


200 x 200mm Wall Tiles 750 Pc. @ P 12.00 P 9,000.00
200 x 200mm Floor Tiles 213 Pc. @ P 16.00 P 3,408.00
Tile Adhesive 25Kg/Bag 16 Bag @ P 450.00 P 7,200.00
Tile Trim 2.40m 15 Pc. @ P 52.00 P 780.00
Tile Grout 2Kg/Bag 31 Bag @ P 80.00 P 2,480.00
Tread Nosing/Edging 3.0m 1.26 Pc. @ P 511.00 P 643.86
P 23,511.86

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 4,485.00

Generator Set, 51-100KW 3.00 Days @ P 1,335.00 P 4,005.00


Grinder 2.00 Days @ P 240.00 P 480.00
P 4,485.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 33,051.60

Foreman 1 15.00 Days @ P 588.24 P 8,823.60


Mason 2 15.00 Days @ P 426.64 P 12,799.20
Semi-skilled Laborer 2 15.00 Days @ P 380.96 P 11,428.80
P 33,051.60

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 61,048.46


INDIRECT COST - - - - - - - - - - - - - - - - - - P 19,077.65
OCM - - - - - - - - - - - P 9,157.27
Contractor's Profit - - 6,104.85
VAT - - - - - - - - - - - 3,815.53
Mobilization - - - - - - -
P 19,077.65
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 80,126.11
P 80,126.11
Unit Cost =
#N/A
= #N/A

Page 17 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1001(8) - Sewer Line Works


Quantity = 1.00 Lump Sum

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 8,352.00

4"Ø PVC Pipe S-1000 10.00 Pc. @ P 620.00 P 6,200.00


4"Ø PVC 90° Tee 3.00 Pc. @ P 135.00 P 405.00
4" Ø PVC Cleanout w/ Plug and Sealing Ring 3.00 Pc. @ P 59.00 P 177.00
4" Ø PVC 45° Single Branch Wye 5.00 Pc. @ P 126.00 P 630.00
4" Ø PVC Coupling 5.00 Pc. @ P 74.00 P 370.00
Solvent Cement 400 cc 3.00 Can @ P 190.00 P 570.00
P 8,352.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 1,776.80

Foreman 1 1.00 Day @ P 588.24 P 588.24


Plumber 1 1.00 Day @ P 426.64 P 426.64
Semi-skilled Laborer 2 1.00 Day @ P 380.96 P 761.92
P 1,776.80

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 10,128.80


INDIRECT COST - - - - - - - - - - - - - - - - - - P 3,165.25
OCM - - - - - - - - - - - P 1,519.32
Contractor's Profit - - 1,012.88
VAT - - - - - - - - - - - 633.05
Mobilization - - - - - - -
P 3,165.25
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 13,294.05
P 13,294.05
Unit Cost =
1.00
= P 13,294.05

Page 18 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1001(9) - Storm Drainage and Downspout


Quantity = 1.00 Lump Sum

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 7,271.00

4"Ø PVC Pipe S-1000 8.00 Pc. @ P 620.00 P 4,960.00


2"Ø PVC Pipe S-1000 4.00 Pc. @ P 291.00 P 1,164.00
4" Ø PVC Coupling 5.00 Pc. @ P 74.00 P 370.00
2"Ø x 45° Elbow 1.00 Pc. @ P 14.00 P 14.00
2"Ø PVC Wye (Single Branch) 1.00 Pc. @ P 81.00 P 81.00
2"Ø x 90° Elbow 8.00 Pc. @ P 14.00 P 112.00
Solvent Cement 400 cc 3.00 Can @ P 190.00 P 570.00
P 7,271.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 1,776.80

Foreman 1 1.00 Day @ P 588.24 P 588.24


Plumber 1 1.00 Day @ P 426.64 P 426.64
Semi-skilled Laborer 2 1.00 Day @ P 380.96 P 761.92
P 1,776.80

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 9,047.80


INDIRECT COST - - - - - - - - - - - - - - - - - - P 2,827.44
OCM - - - - - - - - - - - P 1,357.17
Contractor's Profit - - 904.78
VAT - - - - - - - - - - - 565.49
Mobilization - - - - - - -
P 2,827.44
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 11,875.24
P 11,875.24
Unit Cost =
1.00
= P 11,875.24

Page 19 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1002(5) - Plumbing Fixtures


Quantity = 1.00 Lump Sum

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 14,264.00

Water Closet w/ Tank Fitttings & Accessories 1.00 Set @ P 6,500.00 P 6,500.00
Lavatory w/ Fitttings & Accessories 1.00 Set @ P 6,500.00 P 6,500.00
4''x4'' Floor Drain Stainless 1.00 Pc. @ P 84.00 P 84.00
Faucet (Chrome) 2.00 Pc. @ P 460.00 P 920.00
Tissue Holder 1.00 Pc. @ P 260.00 P 260.00
P 14,264.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 6,979.20

Foreman 1 5.00 Days @ P 588.24 P 2,941.20


Plumber 1 5.00 Days @ P 426.64 P 2,133.20
Semi-skilled Laborer 1 5.00 Days @ P 380.96 P 1,904.80
P 6,979.20

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 21,243.20


INDIRECT COST - - - - - - - - - - - - - - - - - - P 6,638.50
OCM - - - - - - - - - - - P 3,186.48
Contractor's Profit - - 2,124.32
VAT - - - - - - - - - - - 1,327.70
Mobilization - - - - - - -
P 6,638.50
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 27,881.70
P 27,881.70
Unit Cost =
1.00
= P 27,881.70

Page 20 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

#N/A
Quantity = #N/A #N/A

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 6,687.00

32mmØ PPR Pipe 7.00 Pc. @ P 575.00 P 4,025.00


25mmØ PPR Pipe 5.00 Pc. @ P 357.00 P 1,785.00
25mmØ x 90° Elbow 16.00 Pc. @ P 27.00 P 432.00
25mmØ Equal TEE 5.00 Pc. @ P 35.00 P 175.00
32mmØ Coupling 5.00 Pc. @ P 26.00 P 130.00
32mmØ x 25mmØ PPR Reducer 4.00 Pc. @ P 35.00 P 140.00
P 6,687.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 1,776.80

Foreman 1 1.00 Day @ P 588.24 P 588.24


Plumber 1 1.00 Day @ P 426.64 P 426.64
Semi-skilled Laborer 2 1.00 Day @ P 380.96 P 761.92
P 1,776.80

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 8,463.80


INDIRECT COST - - - - - - - - - - - - - - - - - - P 2,644.94
OCM - - - - - - - - - - - P 1,269.57
Contractor's Profit - - 846.38
VAT - - - - - - - - - - - 528.99
Mobilization - - - - - - -
P 2,644.94
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 11,108.74
P 11,108.74
Unit Cost =
#N/A
= #N/A

Page 21 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

#N/A
Quantity = #N/A #N/A

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 24,118.00

Lockset (kwikset) 9.00 Pc. @ P 1,300.00 P 11,700.00


3" x 4" Ball Bearing Hinge 22.00 Pair @ P 419.00 P 9,218.00
Drawer/ Cabinet Handle 1.00 Lot @ P 1,200.00 P 1,200.00
Cancel Hinge 1.00 Lot @ P 2,000.00 P 2,000.00
P 24,118.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 6,719.60

Foreman 1 5.00 Days @ P 588.24 P 2,941.20


Carpenter 1 5.00 Days @ P 426.64 P 2,133.20
Unskilled Laborer 1 5.00 Days @ P 329.04 P 1,645.20
P 6,719.60

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 30,837.60


INDIRECT COST - - - - - - - - - - - - - - - - - - P 9,636.75
OCM - - - - - - - - - - - P 4,625.64
Contractor's Profit - - 3,083.76
VAT - - - - - - - - - - - 1,927.35
Mobilization - - - - - - -
P 9,636.75
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 40,474.35
P 40,474.35
Unit Cost =
#N/A
= #N/A

Page 22 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1100(1)f - (Conduits, Boxes and Fittings) Polyvinyl Chloride Pipes (PVC/uPVC)
Quantity = 150.00 meters

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 3,700.00

Polyvinyl Chloride PVC 15mm Ø 100.00 Mts. @ P 21.00 P 2,100.00


Polyvinyl Chloride PVC 20mm Ø 50.00 Mts. @ P 32.00 P 1,600.00
P 3,700.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 2,791.68

Foreman 1 2.00 Days @ P 588.24 P 1,176.48


Electrician 1 2.00 Days @ P 426.64 P 853.28
Semi-Skilled Laborer 1 2.00 Days @ P 380.96 P 761.92
P 2,791.68

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 6,491.68


INDIRECT COST - - - - - - - - - - - - - - - - - - P 2,028.65
OCM - - - - - - - - - - - P 973.75
Contractor's Profit - - 649.17
VAT - - - - - - - - - - - 405.73
Mobilization - - - - - - -
Prepared by: P 2,028.65
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 8,520.33
P 8,520.33
Unit Cost =
WENCESLAO B. NADERA 150.00
Engineer II = P 56.80

Page 23 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1100(4)a - (Conduits, Boxes and Fittings) Conduit Elbow, RSC


Quantity = 76.00 piece

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 5,041.00

15mmØ PVC Elbow 60.00 Pc. @ P 38.00 P 2,280.00


20mmØ PVC Elbow 15.00 Pc. @ P 45.00 P 675.00
Solvent Cement 800 cc 2.00 Can @ P 380.00 P 760.00
#16 G.I. Tiewire 3.00 Kg. @ P 42.00 P 126.00
19mmØ X 3.00m Copper Weld Ground Rod 1.00 Pc. @ P 1,200.00 P 1,200.00
P 5,041.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 1,395.84

Foreman 1 1.00 Day @ P 588.24 P 588.24


Electrician 1 1.00 Day @ P 426.64 P 426.64
Semi-Skilled Laborer 1 1.00 Day @ P 380.96 P 380.96
P 1,395.84

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 6,436.84


INDIRECT COST - - - - - - - - - - - - - - - - - - P 2,011.51
OCM - - - - - - - - - - - P 965.53
Contractor's Profit - - 643.68
VAT - - - - - - - - - - - 402.30
Mobilization - - - - - - -
Prepared by: P 2,011.51
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 8,448.35
P 8,448.35
Unit Cost =
WENCESLAO B. NADERA 76.00
Engineer II = P 111.16

Page 24 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1100(11) - (Conduits, Boxes and Fittings) Octagonal Junction/ Utility Boxes, PVC/uPVC
Quantity = 78.00 piece

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 2,580.00

Octagonal Junction Box 42.00 Pc. @ P 34.00 P 1,428.00


Utility Box 36.00 Pc. @ P 32.00 P 1,152.00
P 2,580.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 1,014.88

Foreman 1 1.00 Day @ P 588.24 P 588.24


Electrician 1 1.00 Day @ P 426.64 P 426.64
P 1,014.88

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 3,594.88


INDIRECT COST - - - - - - - - - - - - - - - - - - P 1,123.40
OCM - - - - - - - - - - - P 539.23
Contractor's Profit - - 359.49
VAT - - - - - - - - - - - 224.68
Mobilization - - - - - - -
Prepared by: P 1,123.40
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 4,718.28
P 4,718.28
Unit Cost =
WENCESLAO B. NADERA 78.00
Engineer II = P 60.49

Page 25 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1101 - Wires and Wiring Devices-Electrical Wires


Quantity = 1,868.00 meters

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 21,535.00

2.0mm² THHN Wire Stranded 200.00 Mts. @ P 24.00 P 4,800.00


3.5mm² THHN Wire Stranded 250.00 Mts. @ P 29.00 P 7,250.00
5.5mm² THHN Wire Stranded 100.00 Mts. @ P 38.00 P 3,800.00
30mm² THHN Wire 15.00 Mts. @ P 275.00 P 4,125.00
RJ6 Cable Wire 20.00 Mts. @ P 65.00 P 1,300.00
8.0mm² THHN Wire Stranded 5.00 Mts. @ P 52.00 P 260.00
P 21,535.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 15,055.20

Foreman 1 5.00 Days @ P 588.24 P 2,941.20


Electrician 3 5.00 Days @ P 426.64 P 6,399.60
Semi-Skilled Laborer 3 5.00 Days @ P 380.96 P 5,714.40
P 15,055.20

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 36,590.20


INDIRECT COST - - - - - - - - - - - - - - - - - - P 11,434.44
OCM - - - - - - - - - - - P 5,488.53
Contractor's Profit - - 3,659.02
VAT - - - - - - - - - - - 2,286.89
Mobilization - - - - - - -
Prepared by: P 11,434.44
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 48,024.64
P 48,024.64
Unit Cost =
WENCESLAO B. NADERA 1,868.00
Engineer II = P 25.71

Page 26 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1101(7)a1 - Single PoleWall Switch On One Switch Plate


Quantity = 36.00 Set

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 8,324.00

Single Pole wall switch on one switch plate 11.00 Set @ P 150.00 P 1,650.00
Duplex(2 single Pole wall switch on one Switch Plate) 2.00 Set @ P 180.00 P 360.00
Duplex Convenience Outlet 16.00 Set @ P 180.00 P 2,880.00
Cable Outlet 1.00 Set @ P 250.00 P 250.00
Aircon Outlet 5.00 Set @ P 350.00 P 1,750.00
Grounding Clamp for 8.0mm² THHN Wire 1.00 Set @ P 550.00 P 550.00
Electrical Tape (Big) 12.00 Roll @ P 32.00 P 384.00
Rubber Tape (Big) 4.00 Roll @ P 125.00 P 500.00
P 8,324.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 1,776.80

Foreman 1 1.00 Day @ P 588.24 P 588.24


Electrician 1 1.00 Day @ P 426.64 P 426.64
Semi-Skilled Laborer 2 1.00 Day @ P 380.96 P 761.92
P 1,776.80

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 10,100.80


INDIRECT COST - - - - - - - - - - - - - - - - - - P 3,156.50
OCM - - - - - - - - - - - P 1,515.12
Contractor's Profit - - 1,010.08
VAT - - - - - - - - - - - 631.30
Mobilization - - - - - - -
Prepared by: P 3,156.50
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 13,257.30
P 13,257.30
Unit Cost =
WENCESLAO B. NADERA 36.00
Engineer II = P 368.26

Page 27 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1102(1) - Panel Boards w/ Main and Branch Breakers


Quantity = 12.00 set

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 13,550.00

Panel Board 100A Main, 1P, CB, 14 Branches 1.00 Pc. @ P 12,500.00 P 12,500.00
15A, 1P, CB Plug-In Type 3.00 Pc. @ P 350.00 P 1,050.00
P 13,550.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 4,187.52

Foreman 1 3.00 Days @ P 588.24 P 1,764.72


Electrician 1 3.00 Days @ P 426.64 P 1,279.92
Semi-Skilled Laborer 1 3.00 Days @ P 380.96 P 1,142.88
P 4,187.52

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 17,737.52


INDIRECT COST - - - - - - - - - - - - - - - - - - P 5,542.98
OCM - - - - - - - - - - - P 2,660.63
Contractor's Profit - - 1,773.75
VAT - - - - - - - - - - - 1,108.60
Mobilization - - - - - - -
Prepared by: P 5,542.98
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 23,280.50
P 23,280.50
Unit Cost =
WENCESLAO B. NADERA 12.00
Engineer II = P 1,940.04

Page 28 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1103 - Lighting Fixtures


Quantity = 22.00 set

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 5,072.00

Fluorescent lighting Fixture w/ HPF-NCPF 7.00 Set @ P 546.00 P 3,822.00


1-40 Watts Surface Mounted
Compact Flourescent Lamp (CFL) 10 Watts Medium, 5.00 Set @ P 250.00 P 1,250.00
keyless type Porcelain outlet
P 5,072.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 2,791.68

Foreman 1 2.00 Days @ P 588.24 P 1,176.48


Electrician 1 2.00 Days @ P 426.64 P 853.28
Semi Skilled 1 2.00 Days @ P 380.96 P 761.92
P 2,791.68

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 7,863.68


INDIRECT COST - - - - - - - - - - - - - - - - - - P 2,457.40
OCM - - - - - - - - - - - P 1,179.55
Contractor's Profit - - 786.37
VAT - - - - - - - - - - - 491.48
Mobilization - - - - - - -
Prepared by: P 2,457.40
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 10,321.08
P 10,321.08
Unit Cost =
WENCESLAO B. NADERA 22.00
Engineer II = P 469.14

Page 29 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM B.7 - Occupational Safety and Health Program


Quantity = 2.00 month

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 647.40

Safety Helmets 2.00 M-mo. @ P 7.50 P 15.00


Safety Shoes 2.00 M-mo. @ P 83.10 P 166.20
Safety Gloves 2.00 M-mo. @ P 233.10 P 466.20
P 647.40

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 7,942.50

First Aider 1 2 Mmo.s @ P 1,740.00 P 3,480.00


Part-time safety practitioner 1 1.75 Mmo.s @ P 2,550.00 P 4,462.50
P 7,942.50

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 8,589.90


INDIRECT COST - - - - - - - - - - - - - - - - - - P 1,331.43
OCM - - - - - - - - - - - P 0.00
Contractor's Profit - - 858.99
VAT - - - - - - - - - - - 472.44
Mobilization - - - - - - -
P 1,331.43
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 9,921.33
P 9,921.33
Unit Cost =
2.00
= P 4,960.67

Page 30 of 30

You might also like