Productivity Rate

The document outlines productivity rates for various construction works including masonry, plastering, carpentry, steelworks, tiling, excavation, door installation, and ceiling works. It provides the expected daily productivity for tasks like laying different thicknesses of concrete hollow blocks, plastering walls and columns, installing forms and beams, fabricating and installing steel, laying various sizes of floor and wall tiles, pouring concrete, and more. Productivity is listed based on the number of workers required and quantities expected to be completed in a day for each task.

Uploaded by

Jo An Valdez
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (10 votes)
22K views4 pages

Productivity Rate

The document outlines productivity rates for various construction works including masonry, plastering, carpentry, steelworks, tiling, excavation, door installation, and ceiling works. It provides the expected daily productivity for tasks like laying different thicknesses of concrete hollow blocks, plastering walls and columns, installing forms and beams, fabricating and installing steel, laying various sizes of floor and wall tiles, pouring concrete, and more. Productivity is listed based on the number of workers required and quantities expected to be completed in a day for each task.

Uploaded by

Jo An Valdez
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

PRODUCTIVITY RATE

MASONRY WORKS
1. CHB LAYING (productivity per day)
4" CHB 7 sq. m 1 Mason + 1 Labor
5"CHB 8-7.5 sq. m 1 Mason + 1 Labor
6"CHB 7 sq. m 1 Mason + 1 Labor

2. PLASTERING (productivity per day)


WALL 7.8 sq. m 1 Mason + 1 Labor
COLUMN 1 Column 1 Mason + 1 Labor
BEAM 3.5 L.M 1 Mason + 1 Labor

CARPENTRY WORKS/FORMWORKS
(productivity per day)
COLUMN 2 column 2 Carpenter + 1 Labor ***plus CONCRETE POURING
BEAM 12 m 1 Carpenter + 1 Labor
SLAB 3 span 2 Carpenter

STEELWORKS
(productivity per day)
RING FABRICATION 200-250 pcs 1 Steelman
INSTALLATION 2000-2500 Kgs 2 steelman + Labor

TILEWORKS
1. FLOORING (productivity per day)
60X60 10-12 sq. m 1 Tile Setler + Labor
40x40 10 sq. m 1 Tile Setler + Labor
30x30 6-8 sq. m 1 Tile Setler + Labor

2. WALL(CR) (productivity per day)


20x60 4-5 sq. m 1 Tile Setler + Labor

EXCAVATOR (productivity per day)


1.5 cu.m 2 Labor ***depends on soil structure

DOOR INSTALLATION (productivity per day)


3-4 sets 1 carpenter + Helper

DOOR JAMB INSTALLATION (productivity per day)


3-4 sets 1 carpenter + Helper

CEILING WORKS (productivity per day)


1. METAL FURRING + 40 sq. m 2 finishing carpenter
ACCESSORIES
2. UPVC Panel 30 sq. m 2 finishing carpenter
PRODUCTIVITY RATE
MASONRY WORKS
1. CHB LAYING (productivity per day)
4" CHB 7 sq. m or 85 pcs 1 Mason + 1 Labor

CONCRETE POURING (productivity per day)


1. ROOF BEAM 2.5 cu.m manpower: 5
PRODUCTIVITY RATE
MASONRY WORKS
1. CHB LAYING (productivity per day)
4" CHB 7 sq. m 1 Mason + 1 Labor
5"CHB 8-7.5 sq. m 1 Mason + 1 Labor
6"CHB 7 sq. m 1 Mason + 1 Labor

2. PLASTERING (productivity per day)


WALL 12.66 sq. m 1 Mason + 1 Labor
WALL 7.21 sq. m 1 Mason + 1 Labor ***tiktik + layout + wall edge
COLUMN 1 Column 1 Mason + 1 Labor
BEAM 3.5 L.M 1 Mason + 1 Labor

CARPENTRY WORKS/FORMWORKS
(productivity per day)
COLUMN 2 column 2 Carpenter + 1 Labor ***plus CONCRETE POURING
BEAM 12 m 1 Carpenter + 1 Labor
SLAB 3 span 2 Carpenter

STEELWORKS
(productivity per day)
RING FABRICATION 200-250 pcs 1 Steelman
INSTALLATION 2000-2500 Kgs 2 steelman + Labor
SLAB REINFORCEMENT 33 sq. m 1 Steelman + 3 labor

CONCRETE POURING (productivity per day)


1. ROOF BEAM 2.5 cu.m manpower: 5

TILEWORKS
1. FLOORING (productivity per day)
60X60 10-12 sq. m 1 Tile Setler + Labor
40x40 10 sq. m 1 Tile Setler + Labor
30x30 6-8 sq. m 1 Tile Setler + Labor

2. WALL(CR) (productivity per day)


20x60 4-5 sq. m 1 Tile Setler + Labor

EXCAVATOR (productivity per day)


1.5 cu.m 2 Labor ***depends on soil structure

DOOR INSTALLATION (productivity per day)


3-4 sets 1 carpenter + Helper

DOOR JAMB INSTALLATION (productivity per day)


3-4 sets 1 carpenter + Helper
CEILING WORKS
1. METAL FURRING + (productivity per day)
ACCESSORIES 40 sq. m 2 finishing carpenter
2. UPVC Panel 30 sq. m 2 finishing carpenter