Waste Water Collection Methods System
Waste Water Collection Methods System
Waste Water Collection Methods System
METHODS OF COLLECTION
- The collection lines are sloped to permit the flow to move through the system
with as little pumping as possible.
- The slope of the lines must keep the wastewater moving at a velocity (speed) of
2 to 4 ft/sec . Otherwise at lower Otherwise , at lower velocities solids will settle
out and cause clogged lines velocities , solids will settle out and cause clogged
lines , overflows and offensive odors overflows , and offensive odors
- To keep collection systems lines at a reasonable depth, wastewater must be
lifted (pumped) periodically so that it can continue flowing downhill to the
treatment plant.
VACUUM SYSTEM
- In a vacuum collection system , wastewaters are collected to central points and
then drawn toward the treatment plant under vacuum.
- The system consists of a large amount of mechanical Equipment and requires a
large amount of maintenance to perform properly.
- Generally, the vacuum type collection systems are not economically feasible.
PUMPING STATION
- Pumping stations provide the motive force (energy) to keep the wastewater
moving at the desired velocity.
- They are used in both the force main and gravity systems.
- They are designed in several different configurations and may use different
sources of energy to move the wastewater (i.e., pump , air pressure and
vacuum).
SEWER SYSTEM
• Sewer is an artificial conduit, usually underground, for carrying off waste water
and refuse, as in a town or city.
- Surface waters enters a storm drainage system through inlets located in street
gutters or depressed areas that collects natural drainage.
o Street grade, curb design and gutter depression define the best type of inlet to
select.
o Catch basins under street inlets are connected by short pipelines to the main
sewer system
o Manholes are placed at curb inlets, intersection of sewer lines and regular
intervals to facilitate inspection and cleaning.
o Pipeline gradient follow the general slope of the ground surface such that water
entering can flow downhill to a convenient point for discharge.
o Sewer pipes are set as shallow as possible to minimize excavation while
providing 2 to 4 ft of cover above the pipe to reduce the effect of wheel loading.
o Sewer outlets that terminates in natural channels subject to tides or high water
levels are equipped with flap gates to prevent back flooding into the sewer
system.
o Backwater gates are also used on combined sewer outfalls and effluent lines
from treatment plants where needed.
Rational method is used to calculate the quantity of runoff for sizing of sewers
• Maximum: 10 ft/s (to prevent erosion of the pipe by grit transported in the water.
SAMPLE PROBLEM :
a)What is the maximum population that can be served by an 8-in sanitary sewer laid at
minimum grade using a design flow of 400 gcpd and a flowing full velocity of 2ft/s.
b) Compute the diameter of a storm drain to serve the same population based on
population density = 30 persons per acre, coefficient of runoff = 0.40, 10-yr rainfall-
frequency curve, duration = 20 min and a velocity of flow = 5 ft/s.
ANSWERS:
A. For: (d=8-in,V=2ft/s)
Q = 1,100 persons
A force main is a sewer through which wastewater is pumped under pressure rather
than by gravity flow. (see methods of collection).
Design flows for sewer systems are based on population served using the following per
capita quantities:
Interceptors = 350% of the estimated average dry weather flow (normal infiltration only
for flowing full velocities, excessive infiltration and industrial wastewaters are not
included)
When (V=10ft/s=3.0m/s), special provision must be made to protect the pipe and
manholes against displacement by erosion and shock hydraulic loadings.
SANITARY SEWER SYSTEM DESIGN NOTES :
As a general rule, laterals placed in the street right of way are set a depth of not
less than 11ft (3.3m) below the top of the house foundation.
Service connections are generally extended from laterals to outside the curb line
at the time of sewer placement.
An alternative is to place sanitary sewer behind the curb on one side of the
street, making it readily accessible for service connections on that side.
The minimum recommended size for laterals is 8-in (200 mm) diameter.
Sewers less than 24-in should be laid on a straight line between manholes.
1. Most manholes are circular in shape with an inside diameter of 4ft, which is
considered sufficient to perform sewer inspection and cleaning.
2. For small diameter pipes, the manhole is usually constructed directly over the
centerline of the sewer.
3. For very large sewers, access may be provided on one side with a landing
platform for the convenience of introducing cleaning equipment.
4. Manhole frames and covers are usually cast iron with a minimum clear opening
of 21 in. (54cm).
5. Solid covers are used on sanitary sewers.
TYPES OF MANHOLE
SERVICE CONNECTION
House sewers are laid on a straight line and grade using 4in. (100mm) or 6in.
(150mm) pipe.
The preferred minimum slope is 2%, or ¼ in/ft, although slopes as shallow as
1/8 in./ft are occasionally used.
The service connection to a sanitary sewer is made through a tee branch turned
upward 45° or more from the horizontal so that backflooding does not occur
when the collecting sewer is flowing full.
For a deep sewer, the tee connection and riser pipe are often vertical and maybe
encased in concrete to prevent damage during backfilling.