Activities Done To Remove The Errors in Costing Run/variance Calculation/settlement Request No's
Activities Done To Remove The Errors in Costing Run/variance Calculation/settlement Request No's
Activities Done To Remove The Errors in Costing Run/variance Calculation/settlement Request No's
Request no’s
5) Valuation classes was wrong for some of the materials. For this stock has to be
transferred. Purchase orders and production orders need to be deleted to change valuation
class in material master to the correct valuation class
6) 4105060 cost element is not assigned to cost component structure - configured the
same
8) Automatic batch X has been activated for some materials (tcode: OMWC) in split
valuation
"Please check the valuation catergory as 'H' and then enter the valuation type" and after
that if no price then enter the price from tcode: MR21
Then again select the order in change mode and click on Component overview (F6) to
give automatic backflush option (to bring the plan quantities and make necessary qty
adjustments as per actual production)
Select Backflush option as shown above and then click save. Then confirm the
production order with tcode: CO15 as shown below:
Click on Goods movement and enter actual qty of raw material consumed and batch
Click save and the system confirms for the same as below
Then view the production order target and actual costs in Tcode:CO03 and from the menu
select goto->costs->analysis
Step 1: Set the cut-off period before WIP calculation (tcode: KKA0)
Step 2: Run the WIP (tcode: KKAX for individual order and KKAY for all orders in a
plant)
Click execute
Step 3: Variance calculation (Individual order: KKS2 and collective order KKS1)
Click execute and to see the variance break-up, select the layout as shown beow
Select variance categories (1SAP S04)
Step 4: Variance Settlement (individual order KO88, All orders in a plant CO88)
Click execute
Click on detail list (ctrl+shift+F3)
Old qty as per first screen : 23052.100 Old total Value: Rs. 23052
New qty as per last screen: 23062.100 New total value: (23052+ vairance1085) = 24137
Therefore Old price = 23052 / 23052.100 = Rs.1
New Price = 24137/23062.100 = Rs. 1.05 (this is shown now in the material master)