Project Resources: Double - Storey Bungalow

This document provides a summary of tasks, resources, and timelines for a double-storey bungalow construction project. It lists 27 construction tasks including site clearing, foundation work, building the ground floor, first floor, roof, and external works. For each task it specifies the unit of measurement, quantity of materials, expected production rate, estimated duration, and risk percentage. The project is scheduled to be completed within an estimated 4 months, with individual tasks ranging from 1 to 9 days. Risk percentages between 1-5% have been added to estimated durations to allow for potential delays.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
154 views6 pages

Project Resources: Double - Storey Bungalow

This document provides a summary of tasks, resources, and timelines for a double-storey bungalow construction project. It lists 27 construction tasks including site clearing, foundation work, building the ground floor, first floor, roof, and external works. For each task it specifies the unit of measurement, quantity of materials, expected production rate, estimated duration, and risk percentage. The project is scheduled to be completed within an estimated 4 months, with individual tasks ranging from 1 to 9 days. Risk percentages between 1-5% have been added to estimated durations to allow for potential delays.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

PROJECT RESOURCES

Task Name unit quantity group of production rate duration 5% risk estimated duration Estimation
work day
Double -Storey
Bungalow
Project Start
Preliminary
Work
Performance
Bond
Insurance
Monthly Report

Monthly 25 1 20 1.25 0.06 1.31 2


Report 1

Survey Work m2 250 1 80 3.13 0.16 3.129 4


2
Site Clearing m 150 1 15 10.00 0.50 10.50 11
Excavation
Work
Remove Top Soil m2 1500 2 190 3.95 0.20 4.14 5
Pad Footing m3 30 3 35 0.29 0.01 0.30 1
Excavation
Task name unit quantity Group of production rate duration 5% risk estimated estimation
work duration
Building Work
Ground Floor
Substructure
Foundation
Pad Footing
Formwork m2 650 2 103 3.16 0.16 3.31 2
Reinforcement kg 700 3 50 4.67 0.23 4.90 2
Concrete Work m3 685 3 120 1.90 0.10 2.00 3
Dismantle of m2 1000 5 50 4.00 0.20 4.20 5
Formwork
Column Stump
Reinforcement kg 110 3 350 0.10 0.01 0.11 1
Formwork m2 89 2 200 0.22 0.01 0.23 1
Concrete Work m3 100 2 11 4.55 0.23 4.77 5
Dismantle of m2 55 3 140 0.13 0.01 0.14 1
Formwork
Task name unit quantity Group of production duration 5% risk estimated estimation
work rate duration
Superstructure
Beam (GF)
Formwork m2 1740 3 150 3.87 0.19 4.06 5
Reinforcement kg 1960 3 250 2.61 0.13 2.74 3
Concrete Work m3 1467 2 400 1.83 0.09 1.93 2
Dismantle of m2 1350 2 150 4.50 0.23 4.73 5
Formwork
Slab (GF)
Reinforcement kg 3564 5 330 2.16 0.11 2.27 3
Concrete Work m3 4500 5 450 2.00 0.10 2.10 3
Column (GF)
Reinforcement kg 658 3 150 1.46 0.07 1.54 2
Formwork m2 768 2 210 1.83 0.09 1.92 2
Concrete Work m3 445 3 230 0.64 0.03 0.68 1
Dismantle of m2 338 2 130 1.30 0.07 1.37 2
Formwork
Brickwork Wall
Ground Floor
Internal m2 699 2 150 2.33 0.12 2.45 3

External m2 699 2 150 2.33 0.12 2.45 3


Task name unit quantity Group of production duration 5% risk estimated estimation
work rate duration
First Floor
Superstructure
Beam (1F)
Formwork m2 453 2 120 1.89 0.09 1.98 2
Reinforcement kg 450 3 125 1.20 0.06 1.26 2
3
Concrete Work m 448 2 140 1.60 0.08 1.68 2
Dismantle of m2 250 2 160 0.78 0.04 0.82 1
Formwork
Slab (1F)
Reinforcement kg 455 2 170 1.34 0.07 1.41 2
3
Concrete Work m 353 1 170 2.08 0.10 2.18 2
Column (1F)
Reinforcement 440 2 150 1.47 0.07 1.54 2
2
Formwork m 500 2 140 1.79 0.09 1.88 2
Concrete Work m3 510 2 120 2.13 0.11 2.23 3
2
Dismantle of m 320 1 230 1.39 0.07 1.46 2
Formwork
Brickwork
Wall (1F)
Internal m2 521 2 245 1.06 0.05 1.12 2
External m2 521 2 245 1.06 0.05 1.12 2
Staircase
Reinforcement kg 360 2 125 1.44 0.07 1.51 2
Formwork m2 85 2 120 0.35 0.02 0.55 1
Concrete Work m3 150 2 140 0.54 0.03 0.57 1
Dismantle of m2 60 1 150 0.40 0.02 0.42 1
Formwork
Task name unit quantity Group of production rate duration 5% estimated estimation
work risk duration
Roof
Roof Beam
Formwork m2 450 2 120 1.88 0.09 1.97 2
Reinforcement kg 552 2 110 2.51 0.13 2.63 3
Concrete Work m3 525 2 130 2.02 0.10 2.12 3
2
Dismantle of m 234 1 150 1.56 0.08 1.64 2
Formwork
Roof Trusses m2 990 3 90 3.67 0.18 3.85 4
Roof Coverings m2 990 3 90 3.67 0.18 3.85 4
Architectural Work
Window and
Door
Installation
Window And Door no 28 2 90 0.16 0.01 0.17 1
Frame
Window And Door no 28 2 90 0.16 0.01 0.17 1
Leaf
Wall
Finishing m2 2500 6 50 8.33 0.42 8.75 9
2
Painting m 2500 4 90 6.94 0.35 7.29 8
Floor Finishes
Waterproofing m2 250 3 45 1.85 0.09 1.94 2
Cement Render m2 250 3 20 4.17 0.21 4.38 5
Floor Tiles m2 85 2 62 0.69 0.03 0.72 1
Task name unit quantity Group of production rate duration 5% risk estimated estimation
work duration
Infrastructure
Work
M&E
Electrical
Ground Floor
342 1 90 3.80 0.19 3.99 4
First Floor 260 1 90 2.89 0.14 3.03 4
Plumbing
Ground Floor 200 1 70 2.86 0.14 3.00 3
First Floor 100 1 70 1.43 0.07 1.50 2
External Work
Fencing and m2 250 1 80 3.13 0.16 3.29 4
Gate
Concrete m3 5 1 50 0.10 0.01 0.11 1
Driveway
Sewerage 80 1 50 1.60 0.08 1.68 2
Road and 90 1 60 1.50 0.08 1.58 2
Drainage
Testing/ m2 250 1 160 1.56 0.08 1.64 2
Inspection/
Handover
Project Finish