Revision update
NORSOK D-010, Rev.4
PAF Workshop
14.6.2012
Why update?
• Standard Norge has a
requirement for periodic revision.
Last revised Aug. 2004
• Change proposals has been
received
• Recommendations from OLF Well
Integrity and P&A Forum are
transfered to D-010
• Assess experience / learning from
Montara/Macondo incidents
• Make it more international?
Revision 4 of NORSOK D-010 Well integrity in drilling and well operations
Annex A (Normative)
Revision 4 of NORSOK D-010 Well integrity in drilling and well operations
Editor Group
NORSOK D- 010 rev. 4 Main Editor Co-editor
Name, Company Name, Company
1. Scope Terje Løkke-Sørens en Mi chel l e Montea u, Statoi l
2. Normative & Informative Ref. Terje Løkke-Sørens en Mi chel l e Montea u, Statoi l
3. Definitions and Abbreviations Terje Løkke-Sørens en Mi chel l e Montea u, Statoi l
4. General Principles Tore Fjå ges und, Lundi n Da g Sa nde, Statoi l
5. Drilling Activities Ørja n Bus tnes , Spri ng Energy Arne Hjel l e, Statoi l
6. Testing Activities Ga ry McDona l d, Wi nters ha l l Ari l d Fos s å , Statoi l
7. Completion Activities La rs -Endre Hes tenes ,BG John Hel ge Ol s en, Statoi l
8. Production Activities Anders Hjel l en, BP Hi l de Bra nda nger Ha ga / WIF
9. ST, Susp. & Aban. Activities Ga rry Brews ter, Ta l i s ma n Svei n Inge Ra fos s , Statoi l
10. Wireline Operations Al i s tar Bucha na n, Statoi l Terje Ol s en, COP
11. Coiled Tubing Operations Kenneth Ma ri bu, COP Al i s tar Bucha na n, Statoi l
12. Snubbing Operations Ja ck Nerdrum, Wi l d Wel l Control Al i s tar Bucha na n, Statoi l
13. Under Balanced D&C Ops. Per Ca to Berg, Statoi l Connor Stri ckl a n, Shel l
14. Pumping Operations Kri s tia n Ha a res tad, PTC Not needed
Annex A Ørja n Bus tnes , Spri ng Energy Not needed
Revision 4 of NORSOK D-010 Well integrity in drilling and well operations
Sources of Comments
• Comments obtained through
invitation , + 300
• Recommendations from OLF’s
Macondo report
• Recommendations from PSA’s
Macondo report
Revision 4 of NORSOK D-010 Well integrity in drilling and well operations
Out - in
4. General 8. Production
• Significantly altered • Significantly altered
• Out: • Out: -
– WC equipment arrangement • In:
– Activity program content – Updated handover doc. (OLF 117)
– SIMOPS & Critical Activities – Requirements for operating envelopes
for pressures, temperature, flow rates,
• In (new/strongly enhanced): composition of well fluid and passive
annuli
– When and how to make WBS – Risk of communication between
– Inflow testing - how tubulars /annuli
– Formation testing and acceptance – “Zero” leakage for valves bordering to
– Reilef well plan & well capping external environment / surroundings
– WI management system (e.g. swab valve), (otherwise API RP
14B)
– If risk of loss of containment is
significantly increased by shutting in the
well -> keep producing, pending well
barrier reestablishment.
– Well integrity categorisation according
to OLF 117
Revision 4 of NORSOK D-010 Well integrity in drilling and well operations
Out - in
9. P&A 13 UBD / MPD
• Significantly upgraded • Significantly upgraded
• Out: - • Out: -
• In (new/strongly enhanced) • In:
– Definition of suspension vs. temp. – MPD with surface BOP
P&A – Operating limits
– Examples of P&A options – WC action procedures and drills
– Flow-chart decision making: – WBEAC:
• Section milling • UBD/MPD choke system (new)
• Squeeze or circ. cement into • Staticallly underbalanced fluid
annulus column(nw)
– WBEAC:
• Casing cement, 30 m of bonded
cement
• Cement plug
• Shale formation (new)
• Altenative (to cement) casing
bonding material (new)
Revision 4 of NORSOK D-010 Well integrity in drilling and well operations
!!!