Principal Tensile Stress Check

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

6-52

A principal tensile stress check in shear design is not yet specified by code, but is typically
performed as a method to prevent cracking during service load conditions. Stresses are
calculated using Mohr’s circle to determine principle tension. If the allowable tensile capacity of
the concrete is exceeded, diagonal tension cracks may be anticipated. Typically the maximum
principal tension stress is limited from 3—f’c to 4—f’c (psi). Based on information from AASHTO T-
5 & T-10 Committee meetings held in June, 2004, principle tension stress will be limited to a
value of 3.5—f’c for segmental bridges. It is anticipated that this check will be adopted by
AASHTO LRFD Bridge Design Specifications in the near future. Although it is likely that this
check will only be required at the neutral axis of the web, it is recommended that the top slab and
web interface location be investigated as well. For this example, 3.5—f’c tension will be used as a
maximum allowable value under service loading.

Since principal stress is a function of longitudinal, vertical, and shear stress, it is necessary to
determine concurrent moments for the maximum live load shear. It should be noted that high
principle stresses commonly occur at interior pier locations, and the HL-93 live load moment
corresponding to shear should only use one truck, rather than two as used in calculating negative
moment at interior piers. The live load shall also have a load factor of 0.8 similar to Service III
Limit State or it would be practically impossible to satisfy principal stresses while the extreme
fiber could be in tension.

The maximum principal stresses in this example occurred near the interior piers at the top of the
web for final conditions. From analysis at the critical section, the maximum principle tension
stress was approximately 4.5—f’c; larger than the previously discussed limit. For this particular
example, vertical post-tensioning bars will be used to control the principal tension stress.
Calculations show that (3) 1¼” diameter bars, as shown in Figure 6.10-3, will be needed in each
web to reduce principle tension to an acceptable value. The overstress could also be addressed
by modifying the cross-section (web thickness) or adding more longitudinal compressive stress
(additional strands). The solution presented was deemed acceptable since only a small number
of segments will require vertical post-tensioning. A graph of principle stress prior to addition of
vertical post-tensioned bars can be seen in Figure 6.10-2.

         
  

  

VQ
v
Ib

where

LRFD Design Example Precast Balanced Cantilever Construction


6-53

V = Vertical shear force

Q = First moment of an area with respect to C.G. of section

I = Moment of inertia about C.G. of section

b = Perpendicular web thickness

Figure 6.10-1: Principal Stresses and Mohr’s Circle

Vx  Vy 1

2
f1  4v 2  V x  V y
2 2

where compression stress is positive

For V y 0 : (at sections where no vertical web post-tensioning is present)

va fa u fa  f

where
fa = Allowable principal tension
f = Compressive stress at level on web under investigation

LRFD Design Example Precast Balanced Cantilever Construction

You might also like