PLAXIS Introductory 2014 - Tutorial Manual 11
PLAXIS Introductory 2014 - Tutorial Manual 11
PLAXIS Introductory 2014 - Tutorial Manual 11
2.1 GEOMETRY
2.0 m
load
footing
y
sand 4.0 m
a
Figure 2.1 Geometry of a circular footing on a sand layer
In the first calculation, the footing is considered to be very stiff and rough. In
this calculation the settlement of the footing is simulated by means of a
uniform indentation at the top of the sand layer instead of modelling the
footing itself. This approach leads to a very simple model and is therefore
used as a first exercise, but it also has some disadvantages. For example, it
does not give any information about the structural forces in the footing. The
second part of this tutorial deals with an external load on a flexible footing,
which is a more advanced modelling approach.
Project properties
The first step in every analysis is to set the basic parameters of the finite
element model. This is done in the Project properties window. These settings
include the description of the problem, the type of model, the basic type of
elements, the basic units and the size of the draw area.
To enter the appropriate settings for the footing calculation follow these steps:
• In the Project tabsheet, enter "Lesson 1" in the Title box and type
"Settlements of a circular footing" in the Comments box.
• Click the Next button below the tabsheets or click the Model tab.
• In the Type group the type of the model (Model) and the basic element
type (Elements) are specified. Since this tutorial concerns a circular
footing, select the Axisymmetry and the 15-Noded options from the
Model and the Elements drop-down menus respectively.
• Keep the default units in the Units group (Unit of Length = m; Unit of
Force = kN; Unit of Time = day).
• In the General group the unit weight of water (γwater ) is set to 10 kN/m3 .
• In the Contour group set the model dimensions to xmin = 0.0, xmax = 5.0,
ymin = 0.0 and ymax = 4.0.
• Click OK button to confirm the settings.
Hint: In the case of a mistake or for any other reason that the project
properties need to be changed, you can access the Project
properties window by selecting the corresponding option from
the File menu.
• Set the top boundary of the soil layer at y = 4 and keep the bottom
boundary at y = 0 m.
• By default the Head value (groundwater head) in the borehole column is
set to 0 m. Set the Head to 2.0 m (Figure 2.5).
The creation of material data sets and their assignment to soil layers is
described in the following section.
anchors, geogrids, etc.) the system is similar, but different types of structures
have different parameters and therefore different types of material data sets.
PLAXIS 2D distinguishes between material data sets for Soil and interfaces,
Plates, Geogrids, Embedded pile row and Anchors.
To create a material set for the sand layer, follow these steps:
Open the Material sets window by clicking the Materials button in the
Modify soil layers window. The Material sets window pops up (Figure
2.6).
• Click the New button at the lower side of the Material sets window. A
new window will appear with five tabsheets: General, Parameters, Flow
parameters, Interfaces and Initial.
• In the Material set box of the General tabsheet, write "Sand" in the
Identification box.
• The default material model (Mohr-Coulomb) and drainage type
(Drained) are valid for this example.
• Enter the proper values in the General properties box (Figure 2.7)
according to the material properties listed in Table 2.1. Keep parameters
that are not mentioned in the table at their default values.
Figure 2.7 The General tabsheet of the Soil window of the Soil and interfaces
set type
• Click the Next button or click the Parameters tab to proceed with the
input of model parameters. The parameters appearing on the
Parameters tabsheet depend on the selected material model (in this
case the Mohr-Coulomb model).
• Enter the model parameters of Table 2.1 in the corresponding edit boxes
of the Parameters tabsheet (Figure 2.8). A detailed description of
different soil models and their corresponding parameters can be found in
the Material Models Manual.
Figure 2.8 The Parameters tabsheet of the Soil window of the Soil and
interfaces set type
• The soil material is drained, the geometry model does not include
interfaces and the default initial conditions are valid for this case,
therefore the remaining tabsheets can be skipped. Click OK to confirm
the input of the current material data set. Now the created data set will
appear in the tree view of the Material sets window.
• Drag the set Sand from the Material sets window (select it and hold
down the left mouse button while moving) to the graph of the soil column
on the left hand side of the Modify soil layers window and drop it there
(release the left mouse button).
• Click OK in the Material sets window to close the database.
• Click OK to close the Modify soil layers window.
Hint: Existing data sets may be changed by opening the Material sets
window, selecting the data set to be changed from the tree view
and clicking the Edit button. As an alternative, the Material sets
window can be opened by clicking the corresponding button in
the side toolbar.
» PLAXIS 2D distinguishes between a project database and a
global database of material sets. Data sets may be exchanged
from one project to another using the global database. The
global database can be shown in the Material sets window by
clicking the Show global button. The data sets of all tutorials in
the Tutorial Manual are stored in the global database during the
installation of the program.
» The material assigned to a selected entity in the model can be
changed in the Material drop-down menu in the Selection
explorer. Note that all the material datasets assignable to the
entity are listed in the drop-down menu. However, only the
materials listed under Project materials are listed, and not the
ones listed under Global materials.
» The program performs a consistency check on the material
parameters and will give a warning message in the case of a
detected inconsistency in the data.
Visibility of a grid in the draw area can simplify the definition of geometry. The
grid provides a matrix on the screen that can be used as reference. It may
also be used for snapping to regular points during the creation of the
geometry. The grid can be activated by clicking the corresponding button
under the draw area. To define the size of the grid cell and the snapping
options:
Click the Snapping options button in the side toolbar. The Snapping
window pops up where the size of the grid cells and the snapping
interval can be specified. The spacing of snapping points can be further
divided into smaller intervals by the Number of snap intervals value. Use
the default values in this example.
• In the draw area move the cursor to point (0 4) and click the left mouse
button
• Move along the upper boundary of the soil to point (1 4) and click the left
mouse button again.
• Click the right mouse button to stop drawing.
• In the Selection explorer set the x-component of the prescribed
displacement (Displacementx ) to Fixed.
Mesh generation
When the geometry model is complete, the finite element mesh can be
generated. PLAXIS 2D allows for a fully automatic mesh generation
procedure, in which the geometry is divided into elements of the basic
element type and compatible structural elements, if applicable.
The mesh generation takes full account of the position of points and lines in
the model, so that the exact position of layers, loads and structures is
accounted for in the finite element mesh. The generation process is based on
a robust triangulation principle that searches for optimised triangles. In
addition to the mesh generation itself, a transformation of input data
(properties, boundary conditions, material sets, etc.) from the geometry
model (points, lines and clusters) to the finite element mesh (elements, nodes
and stress points) is made.
In order to generate the mesh, follow these steps:
• Proceed to the Mesh mode by clicking the corresponding tab.
Click the Generate mesh button in the side toolbar. The Mesh options
window pops up.
• The Medium option is by default selected as element distribution.
• Click OK to start the mesh generation.
As the mesh is generated, click the View mesh button. A new window is
opened displaying the generated mesh (Figure 4.9). Note that the mesh
is automatically refined under the footing.
Click on the Close tab to close the Output program and go back to the
Mesh mode of the Input program.
Initial conditions
The 'Initial phase' always involves the generation of initial conditions. In
general, the initial conditions comprise the initial geometry configuration and
the initial stress state, i.e. effective stresses, pore pressures and state
parameters, if applicable.
Click the Staged construction tab to proceed with the definition of calculation
phases. The Water conditions mode may be skipped. When a new project
has been defined, a first calculation phase named "Initial phase", is
automatically created and selected in the Phases explorer (Figure 4.10). All
structural elements and loads that are present in the geometry are initially
automatically switched off; only the soil volumes are initially active.
In this tutorial lesson the properties of the Initial phase will be described.
Below an overview is given of the options to be defined even though the
default values of the parameters are used.
The Phases window (Figure 4.11) is displayed by clicking the Edit phase
button or by double clicking on the phase in the Phases explorer.
By default the K0 procedure is selected as Calculation type in the
General subtree of the Phases window. This option will be used in this
project to generate the initial stresses.
The Staged construction option is available as Loading type.
The Phreatic option is selected by default as the Pore pressure
calculation type.
• The other default options in the Phases window will be used as well in
this tutorial. Click OK to close the Phases window.
For deformation problems two types of boundary conditions exist: Prescribed
displacement and prescribed forces (loads). In principle, all boundaries must
have one boundary condition in each direction. That is to say, when no
Figure 2.15 The Deformations and Water subtrees in the Model explorer
The initial water level has been entered already in the Modify soil layers
window.
• The water level defined according to the Head specified for boreholes is
displayed (Figure 2.16). Note that only the global water level is displayed
in both Phase definition modes. All the water levels are displayed in the
model only in the Water conditions mode.
Phase 1: Footing
In order to simulate the settlement of the footing in this analysis, a plastic
calculation is required. PLAXIS 2D has a convenient procedure for automatic
load stepping, which is called 'Load advancement'. This procedure can be
used for most practical applications. Within the plastic calculation, the
prescribed displacements are activated to simulate the indentation of the
footing. In order to define the calculation phase follow these steps:
Click the Add phase button in the Phases explorer. A new phase,
named Phase_1 will be added in the Phases explorer.
Execution of calculation
All calculation phases (two phases in this case) are marked for calculation
(indicated by a blue arrow). The execution order is controlled by the Start
the number of plastic points in the current calculation step. It will take a few
seconds to perform the calculation. When a calculation ends, the window is
closed and focus is returned to the main window.
The phase list in the Phases explorer is updated. A successfully
calculated phase is indicated by a check mark inside a green circle.
Save the project before viewing results.
the Effective principal stresses option from the appearing menu. The
plot shows the effective principal stresses at the stress points of each
soil element with an indication of their direction and their relative
magnitude (Figure 2.21).
Click the Table button on the toolbar. A new window is opened in which
a table is presented, showing the values of the principal stresses and
other stress measures in each stress point of all elements.
The project is now modified so that the footing is modelled as a flexible plate.
This enables the calculation of structural forces in the footing. The geometry
used in this exercise is the same as the previous one, except that additional
elements are used to model the footing. The calculation itself is based on the
application of load rather than prescribed displacement. It is not necessary to
create a new model; you can start from the previous model, modify it and
store it under a different name. To perform this, follow these steps:
• In the model right-click the line at the location of the footing. Point on
Create and select the Plate option in the appearing menu (Figure 2.23).
A plate is created which simulates the flexible footing.
• In the model right-click again the line at the location of the footing. Point
on Create and select the Line load option in the appearing menu (Figure
2.24).
• In the Selection explorer the default input value of the distributed load is
-1.0 kN/m2 in the y-direction. The input value will later be changed to the
real value when the load is activated.
• Drag the set "Footing" to the draw area and drop it on the footing. Note
that the shape of the cursor changes to indicate that it is valid to drop the
material set.
• Close the database by clicking the OK button.
Hint: If the Material sets window is displayed over the footing and
hides it, click on its header and drag it to another position.
Calculations
• Proceed to the Staged construction mode.
• The initial phase is the same as in the previous case.
• Double-click the following phase (Phase_1) and enter an appropriate
name for the phase ID. Keep Plastic as Calculation type and keep
Staged construction as loading type.
• Close the Phases window.
• In the Staged construction mode activate the load and plate. The model
is shown in Figure 2.25.
point of interest and click Search closest. The nodes and stress points
located near that specific location are listed.
• Select the node at exactly (0.0 4.0) by checking the box in front of it. The
selected node is indicated by ’A’ in the model when the Selection labels
option is selected in the Mesh menu.
right-click and select Mark for calculation from the pop-up menu.
Click the Calculate button to start the calculation.
Save the project after the calculation has finished.
• For the x−axis, select point A (0.00 / 4.00) from the drop-down menu.
Select the |u| option for the Total displacements option of the
Deformations.
• For the y −axis, select the Project option from the drop-down menu.
Select the ΣMstage option of the Multipliers. ΣMstage is the proportion
of the specified changes that has been applied. Hence the value will
range from 0 to 1, which means that 100% of the prescribed load has
been applied and the prescribed ultimate state has been fully reached.
This tutorial illustrates the use of PLAXIS for the analysis of submerged
construction of an excavation. Most of the program features that were used in
Tutorial 1 will be utilised here again. In addition, some new features will be
used, such as the use of interfaces and anchor elements, the generation of
water pressures and the use of multiple calculation phases. The new features
will be described in full detail, whereas the features that were treated in
Tutorial 1 will be described in less detail. Therefore it is suggested that
Tutorial 1 should be completed before attempting this exercise.
This tutorial concerns the construction of an excavation close to a river. The
submerged excavation is carried out in order to construct a tunnel by the
installation of prefabricated tunnel segments which are 'floated' into the
excavation and 'sunk' onto the excavation bottom. The excavation is 30 m
wide and the final depth is 20 m. It extends in longitudinal direction for a large
distance, so that a plane strain model is applicable. The sides of the
excavation are supported by 30 m long diaphragm walls, which are braced by
horizontal struts at an interval of 5 m. Along the excavation a surface load is
taken into account. The load is applied from 2 m from the diaphragm wall up
to 7 m from the wall and has a magnitude of 5 kN/m2 /m (Figure 3.1).
The subsoil consists of a stiff sand layer, which extends to a large depth. 50
m of this sand layer are considered in the model.
Since the geometry is symmetric, only one half (the left side) is considered in
the analysis. The excavation process is simulated in three separate
excavation stages. The diaphragm wall is modelled by means of a plate, such
as used for the footing in the previous tutorial. The interaction between the
wall and the soil is modelled at both sides by means of interfaces. The
interfaces allow for the specification of a reduced wall friction compared to the
friction in the soil. The strut is modelled as a spring element for which the
normal stiffness is a required input parameter.
Objectives:
• Modelling soil-structure interaction using the Interface feature
• Advanced soil model (Hardening Soil model)
43 m 5m 2m 30 m 2m5m 43 m
5 kN/m2 /m 5 kN/m2 /m
Strut
1m
to be excavated Sand
19 m y
10 m
Diaphragm wall
20 m
• Defining Fixed-end-anchor
• Creating and assigning material data sets for anchors
• Simulation of excavation (cluster de-activation)
3.1 INPUT
General settings
• Start the Input program and select Start a new project from the Quick
select dialog box.
• In the Project tabsheet of the Project properties window, enter an
appropriate title.
• In the Model tabsheet keep the default options for Model (Plane strain),
and Elements (15-Node).
• Keep the default values for units and the general parameters.
• Set the model dimensions to xmin = 0.0 m, xmax = 65.0 m, ymin = -30.0 m,
ymax = 20.0 m and press OK to close the Project properties window.
Table 3.1 Material properties of the sand layer and the interfaces
Parameter Name Sand Unit
General
Material model Model Hardening soil -
Type of material behaviour Type Drained -
Soil unit weight above phreatic level γunsat 17 kN/m3
Soil unit weight below phreatic level γsat 20 kN/m3
Initial void ratio einit 0.5 -
Parameters
Secant stiffness in standard drained triaxial test ref
E50 4.0· 104 kN/m2
Tangent stiffness for primary oedometer loading ref
Eoed 4.0· 104 kN/m2
5
Unloading / reloading stiffness ref
Eur 1.2· 10 kN/m2
Power for stress-level dependency of stiffness m 0.5 -
Cohesion (constant) cref ' 0.0 kN/m2
◦
Friction angle ϕ' 32
◦
Dilatancy angle ψ 2.0
Poisson's ratio νur ' 0.2 -
K0 -value for normal consolidation K0nc 0.4701 -
Flow parameters
Permeability in horizontal direction kx 1.0 m/day
Permeability in vertical direction ky 1.0 m/day
Interfaces
Interface strength − Manual -
Strength reduction factor inter. Rinter 0.67 -
Initial
K0 determination − Automatic -
Over-consolidation ratio OCR 1.0 -
Pre-overburden pressure POP 0.0 kN/m2
• In the Initial tabsheet keep the default option for the K0 determination
and the default value for the overconsolidation ratio (OCR) and
pre-overburden pressure (POP).
Hint: When the Rigid option is selected in the Strength drop-down, the
interface has the same strength properties as the soil
(Rinter = 1.0).
» Note that a value of Rinter < 1.0, reduces the strength as well as
the the stiffness of the interface.
» Instead of accepting the default data sets of interfaces, data sets
can directly be assigned to interfaces by selecting the proper
data set in the Material mode drop-down menu in the Object
explorers.
Figure 3.2 The Create plate option in the Create structures menu
• Drag the Diaphragm wall data set to the wall in the geometry and drop it
as soon as the cursor indicates that dropping is possible.
• Click OK to close the Material sets window.
Table 3.2 Material properties of the diaphragm wall (Plate)
Parameter Name Value Unit
Type of behaviour Material type Elastic; Isotropic
Normal stiffness EA 7.5 · 106 kN/m
Flexural rigidity EI 1.0 · 106 kNm2 /m
Unit weight w 10.0 kN/m/m
Poisson's ratio ν 0.0 -
Hint: In general, only one point can exist at a certain coordinate and
only one line can exist between two points. Coinciding points or
lines will automatically be reduced to single points or lines.
To define interfaces:
• Right-click the plate representing the diaphragm wall. Point to Create
and click on the Positive interface option in the appearing menu (Figure
3.3). In the same way assign a negative interface as well.
To define the excavation levels:
Click the Create line button in the side toolbar.
• To define the first excavation stage move the cursor to position (50.0
18.0) at the wall and click. Move the cursor 15 m to the right (65.0 18.0)
and click again. Click the right mouse button to finish drawing the first
excavation stage.
• To define the second excavation stage move the cursor to position (50.0
10.0) and click. Move to (65.0 10.0) and click again. Click the right
mouse button to finish drawing the second excavation stage.
• To define the third excavation stage move the cursor to position (50.0
0.0) and click. Move to (65.0 0.0) and click again. Click the right mouse
button to finish drawing the third excavation stage.
To define the strut:
Click the Create structure button in the side toolbar and select the
Create fixed-end anchor button in the expanded menu.
• Move the cursor to (50.0 19.0) and click the left mouse button. A
fixed-end anchor is is added, being represented by a rotated T with a
fixed size.
Click the Show materials button in the side toolbar. Set the Set type
parameter in the Material sets window to Anchor and click the New
button. Enter "Strut" as an Identification of the data set and enter the
properties as given in Table 3.3. Click OK to close the data set.
• Click OK to close the Material sets window.
Table 3.3 Material properties of the strut (anchor)
Parameter Name Value Unit
Type of behaviour Material type Elastic -
Normal stiffness EA 2·106 kN
Spacing out of plane Lspacing 5.0 m
• Make sure that the fixed-end anchor is selected in the draw area.
• In the Selection explorer assign the material data set to the strut by
selecting the corresponding option in the Material drop-down menu.
• The anchor is oriented in the model according to the Directionx and
Directiony parameters in the Selection explorer. The default orientation
is valid in this tutorial.
• Enter an Equivalent length of 15 m corresponding to half the width of the
excavation (Figure 3.4).
Figure 3.5 The Create line load option in the Create load menu
• Move the cursor to (43.0 20.0) and click. Move the cursor 5 m to the
right to (48.0 20.0) and click again. Right-click to finish drawing.
• In the Selection explorer assign a value of -5 kN/m/m to the
y-component of the load (qy ,start,ref ) (Figure 3.6).
3.3 CALCULATIONS
• In the draw area define a rectangle including all the plate elements
(Figure 3.9).
• Right-click the wall in the draw area and select the Activate option from
the appearing menu. The wall is now visible in the color that is specified
in the material dataset.
• Right-click the distributed load to activate it and select the Activate
option from the appearing menu. The load has been defined in the
Structures mode as −5 kN/m/m. The value can be checked in the
Selection explorer.
• Make sure all the interfaces in the model are active.
Hint: To copy the settings of the parent phase, select the phase in the
Phases explorer and then click the Add phase button. Note that
the settings of the parent phase are not copied when it is
specified by selecting it in the Start from phase drop-down menu
in the Phases window.
• The default settings are valid for this phase. In the Staged construction
mode all the structure elements except the fixed-end anchor are active.
• In the draw area right-click the top right cluster and select the Deactivate
option in the appearing menu. Figure 3.10 displays the model for the first
excavation phase.
Hint: Note that in PLAXIS the pore pressures are not automatically
deactivated when deactivating a soil cluster. Hence, in this case,
the water remains in the excavated area and a submerged
excavation is simulated.
Click the Select points for curves button in the side toolbar. The
connectivity plot is displayed in the Output program and the Select points
window is activated.
• Select some nodes on the wall at points where large deflections can be
expected (e.g. 50.0 10.0). The nodes located near that specific location
are listed. Select the convenient one by checking the box in front of it in
the list. Close the Select points window.
• Click on the Update tab to close the Output program and go back to the
Input program.
Calculate the project.
During a Staged construction calculation phase, a multiplier called ΣMstage
3.4 RESULTS
In addition to the displacements and the stresses in the soil, the Output
program can be used to view the forces in structural objects. To examine the
results of this project, follow these steps:
• Click the final calculation phase in the Calculations window.
Click the View calculation results button on the toolbar. As a result, the
Output program is started, showing the deformed mesh (scaled up) at
the end of the selected calculation phase, with an indication of the
Hint: In the Output program, the display of the loads, fixities and
prescribed displacements applied in the model can be toggled
on/off by clicking the corresponding options in the Geometry
menu.
• Select |∆u| from the side menu displayed as the mouse pointer is
located on the Incremental displacements option of the Deformations
menu. The plot shows colour shadings of the displacement increments,
which indicates the forming of a 'mechanism' of soil movement behind
the wall.
Click the Arrows button in the toolbar. The plot shows the displacement
increments of all nodes as arrows. The length of the arrows indicates the
relative magnitude.
• In the Stresses menu point to the Principal effective stresses and select
the Effective principal stresses option from the appearing menu. The
plot shows the effective principal stresses at the three middle stress
points of each soil element with an indication of their direction and their
relative magnitude. Note that the Central principal stresses button is
selected in the toolbar. The orientation of the principal stresses indicates
a large passive zone under the bottom of the excavation and a small
passive zone behind the strut (Figure 3.13).
To plot the shear forces and bending moments in the wall follow the steps
given below.
• Double-click the wall. A new window is opened showing the axial force.
• Select the bending moment M from the Forces menu. The bending
moment in the wall is displayed with an indication of the maximum
moment (Figure 3.14).
• Select Shear forces Q from the Forces menu. The plot now shows the
shear forces in the wall.
• Select the first window (showing the effective stresses in the full
geometry) from the Window menu. Double-click the strut. The strut
force (in kN) is shown in the displayed table.
Hint: The Window menu may be used to switch between the window
with the forces in the wall and the stresses in the full geometry.
This menu may also be used to Tile or Cascade the two
windows, which is a common option in a Windows environment.
• Click the Curves manager button on the toolbar. As a result, the Curves
manager window will pop up.
• Click New to create a new chart. The Curve generation window pops up.
• For the x-axis select the point A from the drop-down menu. In the tree
select Deformations - Total displacements - |u|.
• For the y-axis keep the Project option in the drop-down menu. In the
tree select Multiplier - ΣMstage.
• Click OK to accept the input and generate the load-displacement curve.
As a result the curve of Figure 3.15 is plotted.
The curve shows the construction stages. For each stage, the parameter
ΣMstage changes from 0.0 to 1.0. The decreasing slope of the curve in the
last stage indicates that the amount of plastic deformation is increasing. The
results of the calculation indicate, however, that the excavation remains stable
at the end of construction.
PLAXIS 3D
18.0 m
75.0 m
Building 75.0 m
z=0
z = -2
z 40.0 m
Clay
z = -40
x
GEOMETRY
Objectives:
• Starting a new project
• Creation of soil stratigraphy using a single borehole
• Creation of material data sets
• Assigning material
• Modelling of plates and defining material data set for plates
• Generation of mesh
• Generating initial stresses using the K0 procedure
• Defining a Plastic calculation
• Activation and deactivation of structural elements
Project properties
The first step in every analysis is to set the basic parameters of the finite
element model. This is done in the Project properties window. These
properties include the description of the problem, the basic units and the size
of the draw area.
To enter the appropriate properties for the foundation calculation follow these
steps:
• In the Project tabsheet, enter "Tutorial 1" as the Title of the project and
type "Settlements of a foundation" in the Comments box (Figure 4.3).
• Proceed to the Model tabsheet by clicking either the Next button or the
Model tab (Figure 4.4).
• Keep the default units in the Units box (Length = m; Force = kN; Time =
day ).
• The General box indicates a fixed gravity of 1.0 G, in the vertical
direction downward (-z). The value of the acceleration of gravity (1.0 G)
can be specified in the Earth gravity box. This should be kept to the
default value of 9.810 m/s2 for this exercise. In the γwater box the unit
weight of water can be defined. Keep this to the default value of 10
kN/m3 .
• Define the limits for the soil contour as xmin = 0, xmax = 75, ymin = 0 and
ymax = 75 in the Contour group box.
Hint: In case of a mistake or for any other reason that the project
properties need to be changed, you can access the Project
properties window by selecting the corresponding option in the
File menu.
Hint: PLAXIS 3D can also deal with layers that are discontinuous, i.e.
only locally present in the model area. See the Reference
Manual for more information.
In the current example, only one soil layer is present, and only a single
borehole is needed to define the soil stratigraphy. In order to define the
borehole, follow these steps:
Click the Create borehole button in the side toolbar to start defining the
soil stratigraphy. Click on position (0 0 0) in the geometry. A borehole will
be located at (x, y ) = (0 0). The Modify soil layers window will appear.
• In the Modify soil layers window add a soil layer by clicking on the Add
button. Keep the top boundary of the soil layer at z = 0 and set the
bottom boundary to z = −40 m.
• Set the Head value in the borehole column to −2 m (Figure 4.5). The
creation of material data sets and their assignment to soil layers is
described in the following section.
Figure 4.6 General tabsheet of the Soil and interfaces data set window
Figure 4.7 Parameters tabsheet of the Soil and interfaces data set window
• Click the Initial tab and check that the K0 determination is set to
Automatic. In that case K0 is determined from Jaky's formula: K0 =
1 − sin ϕ.
• Click the OK button to confirm the input of the current material data set.
The created data set appears in the tree view of the Material sets
window.
• Drag the set Lacustrine clay from the Material sets window (select it and
hold down the left mouse button while moving) to the graph of the soil
column on the left hand side of the Modify soil layers window and drop it
there (release the left mouse button). Notice that the cursor changes
shape to indicate whether or not it is possible to drop the data set.
Correct assignment of the data set to the soil layer is indicated by a
change in the colour of the layer.
• Click the OK button to close the Material sets window.
• Click the OK button to close the Modify soil layers window.
• Drag and drop the data sets to the plate indicating the rigid foundation.
• Close the Material sets window.
Table 4.2 Material properties of rigid foundation
Parameter Name Rigid foundation Unit
Thickness d 2 m
Weight γ 50 kN/m3
Type of behaviour Type Linear, isotropic −
Young's modulus E1 3 · 107 kN/m2
Poisson's ratio ν12 0.15 −
As the mesh is generated, click the View mesh button. A new window is
opened displaying the generated mesh (Figure 4.9).
Click on the Close tab to close the Output program and go back to the
Mesh mode of the Input program.
Initial conditions
The 'Initial phase' always involves the generation of initial conditions. In
general, the initial conditions comprise the initial geometry configuration and
the initial stress state, i.e. effective stresses, pore pressures and state
parameters, if applicable. The initial water level has been entered already in
the Modify soil layers window. This level is taken into account to calculate the
initial effective stress state. It is therefore not needed to enter the Water
conditions mode.
When a new project has been defined, a first calculation phase named "Initial
phase", is automatically created and selected in the Phases explorer (Figure
4.10). All structural elements and loads that are present in the geometry are
initially automatically switched off; only the soil volumes are initially active.
The Phases window (Figure 4.11) is displayed by clicking the Edit phase
button or by double clicking on the phase in the Phases explorer.
Figure 4.11 The General tabsheet in the Phases window for Initial phase
Construction stage
After the definition of the initial conditions, the construction of the building can
be modelled. This will be done in a separate calculation phase, which needs
to be added as follows:
Click the Add button in the Phases explorer. A new phase, named
Phase_1 will be added in the Phases explorer.
• Double-click Phase_1 to open the Phases window.
• In the General tabsheet, write (optionally) an appropriate name for the
new phase in the ID box (for example "Building") and select the phase
from which the current phase should start (in this case the calculation
phase can only start from Initial phase, which contains the initial stress
state).
• The default settings are valid for this Plastic phase calculation (Figure
4.12).
• The calculation parameters for phase Building have now been set. Click
OK to close the Phases window.
• In the Model explorer click the square in front of the plate to activate the
plates.
Execution of calculation
All calculation phases (two phases in this case) are marked for calculation
(indicated by a blue arrow). The execution order is controlled by the Start
from phase parameter.
Click the Calculate button to start the calculation process. Ignore the
warning that no nodes and stress points have been selected for curves.
During the execution of a calculation, a window appears which gives
information about the progress of the actual calculation phase (Figure 4.13).
The information, which is continuously updated, shows, amongst others, the
calculation progress, the current step number, the global error in the current
iteration and the number of plastic points in the current calculation step.
It will take a few seconds to perform the calculation. When a calculation ends,
the window is closed and focus is returned to the main window.
• The phase list in the Phases explorer is updated, showing green tick
marks to indicate that the calculations were finished successfully. An
unsuccessful calculation would be indicated with a red cross.
Before viewing results, save the project.
Figure 4.14 Shadings of Total displacements at the end of the last phase
In the Output window click the Iso surfaces button to display the areas
having the same displacement.
In this case, the model is modified so that the basement consists of structural
elements. This allows for the calculation of structural forces in the foundation.
The raft foundation as well as the walls of the basement consist of 50 cm
thick concrete. The loads of the upper floors are transferred to the floor slab
by a column and by the basement walls. The column bears a point load of
11650 kN and the walls carry a line load of 385 kN/m, as sketched in Figure
4.15. The column itself, however, will not be modelled.
11650 kN
5.3 kN/m2
12.0 m 12.0 m
6.0 m 6.0 m
In addition, the floor slab is loaded by a distributed load of 5.3 kN/m2 . The
properties of the clay layer will be modified such that stiffness of the clay will
increase with depth.
Objectives:
• Saving project under a different name
• Modifying existing data sets
• Defining a soil stiffness that increases with depth
• Moving structures
• Modelling of beams and defining material data set for beams
• Assigning point loads
Geometry input
The geometry used in this exercise is the same as the previous one, except
that additional elements are used to model the foundation. It is not necessary
to create a new model; you can start from the previous model, store it under a
different name and modify it. To perform this, follow these steps:
Start the PLAXIS 3D program. The Quick select dialog box will appear
in which the project of case A should be selected.
• Select the Save project as option in the File menu to save the project
under a different name (e.g. "Tutorial 1b").
The material set for the clay layer has already been defined. To modify this
material set to take into account the stiffness of the soil increasing with depth,
follow these steps:
Open the Material sets window by clicking the Show materials button.
• Make sure that the option Soil and interfaces is selected as Set type.
• Select the Lacustrine clay material set and click the Edit button.
• In the Parameters tabsheet, change the stiffness of the soil E ' to 5000
kN/m2 .
• Enter a value of 500 in the E 'inc box in the Advanced parameters. Keep
the default value of 0.0 m for zref . Now the stiffness of the soil is defined
as 5000 kN/m2 at z = 0.0 m and increases with 500 kN/m2 per meter
depth.
• Click OK to close the Soil window.
• Click OK to close the Material sets window.
The shape of the building has now been created. Next step will be the
definition of the material data set for the basement walls and floor.
Open the material data base and set the Set type to Plates.
• Select the Rigid foundation material and delete it by clicking the Delete
button.
• Create a data set for the basement slabs according to Table 4.3.
• Drag and drop the data set to the basement floor and the basement
walls accordingly. It may be needed to move the Material sets window by
clicking at its header and dragging it.
• Click the OK button to close the Material sets window.
Table 4.3 Material properties of the basement slabs
Parameter Name Basement slabs Unit
Thickness d 0.5 m
Weight γ 15 kN/m3
Type of behaviour Type Linear, isotropic −
Young's modulus E1 3 · 107 kN/m2
Poisson's ratio ν12 0.15 −
Hint: When specifying a unit weight, please consider the fact that the
element itself does not occupy any volume and overlaps with the
soil elements. Hence, it might be considered to subtract the unit
soil weight from the real unit weight of the plate, beam or
embedded pile material in order to compensate for the overlap.
For partially overlapping plates, beams or embedded piles the
reduction of the unit weight should be proportional.
Open the material data base and set the Set type to Beams.
• Create a data set for the horizontal beams according to Table 4.4.
Assign the data set to the corresponding beam elements by drag and
drop.
Table 4.4 Material properties of the basement beams
Parameter Name Basement beam Unit
Cross section area A 0.7 m2
Volumetric weight γ 6.0 kN/m3
Type of behaviour Type Linear −
Young's modulus E 3 · 107 kN/m2
Moment of Inertia I3 0.058 m4
I2 0.029 m4
Mesh generation
Click the Generate mesh. Keep the Element distribution as Coarse.
Inspect the generated mesh.
• Click on the Close tab to close the Output program and go back to the
Mesh mode of the Input program.
As the geometry has changed, all calculation phases have to be redefined.
Initial conditions
As in the previous example, the K0 procedure will be used to generate
the initial conditions.
• All the structural elements should be inactive in the Initial Phase.
• No excavation is performed in the initial phase. So, the basement
volume should be active.
Construction stages
Instead of constructing the building in one calculation stage, separate
calculation phases will be used. In Phase_1, the construction of the walls and
the excavation is modelled. In Phase_2, the construction of the floor and
beams is modelled. The activation of the loads is modelled in the last phase
(Phase_3).
The calculation type for the phases representing the construction stages
is set by default to Plastic.
• In the Phases window rename Phase_1 to "Excavation".
• In the Staged construction mode deactivate the soil volume located over
the foundation by selecting it and by clicking on the checkbox in front of
it in the Selection explorer.
• In the Model explorer click the checkbox in front of the plates
corresponding to the basement walls to activate them.
In the Phases explorer click the Add phase button. A new phase
(Phase_2) is added. Double-click Phase_2. The Phases window pops
up.
• Rename the phase by defining its ID as "Construction". Keep the default
settings of the phase and close the Phases window.
• In the Model explorer click the checkbox in front of the plate
corresponding to the basement floor to activate it.
• In the Model explorer click the checkbox in front of the beams to activate
all the beams in the project.
Add a new phase following the Construction phase. Rename it to
"Loading".
• In the Model explorer click the checkbox in front of the Surface loads to
activate the surface load on the basement floor. Set the value of the
z -component of the load to -5.3. This indicates a load of 5.3 kN/m2 ,
acting in the negative z -direction.
• In the Model explorer, click the checkbox in front of Line loads to activate
the line loads on the basement walls. Set the value of the z -component
of each load to -385. This indicates a load of 385 kN/m, acting in the
negative z -direction.
• In the Model explorer click the checkbox in front of Point loads to
activate the point load corresponding to the one on the basement
column. Set the value of the z -component of the load to -11650. This
indicates a load of 11650 kN, acting in the negative z -direction.
Click the Preview phase button to check the settings for each phase.
As the calculation phases are completely defined, calculate the project.
Ignore the warning that no nodes and stress points have been selected
for curves.
Save the project after the calculation.
As the displacements of the raft foundation are rather high, embedded piles
will be used to decrease these displacements. These embedded piles
represent bored piles with a length of 20 m and a diameter of 1.5 m.
Objectives:
• Using embedded piles
• Defining material data set for embedded piles
• Creating multiple copies of entities
Geometry input
The geometry used in this exercise is the same as the previous one, except
for the pile foundation. It is not necessary to create a new model; you can
start from the previous model, store it under a different name and modify it.
To perform this, follow these steps:
Start the PLAXIS 3D program. The Quick select dialog box will appear
in which the project of Case B should be selected.
• Select the Save project as option in the File menu to save the project
under a different name (e.g. "Tutorial 1c").
• Drag and drop the Pile data to the embedded pile in the draw area. The
embedded pile will change colour to indicate that the material set has
been assigned successfully.
• Click the OK button to close the Material sets window.
Click the Select button and select the embedded pile.
Click the Create array button.
• In the Create array window, select the 2D, in xy plane option for shape.
• Keep the number of columns as 2. Set the distance between the
columns to x = 12 and y = 0.
• Keep the number of rows as 2. Set the distance between the rows to
x = 0 and y = 12 (Figure 4.19).
• Press OK to create the array. A total of 2x2 = 4 piles will be created.
Mesh generation
As the geometry model is complete now, the mesh can be generated.
Create the mesh. Keep the Element distribution as Coarse.
View the mesh.
• Click the eye button in front of the Soil subtree in the Model explorer to
hide the soil. The embedded piles can be seen (Figure 4.20).
• Click on the Close tab to close the Output program and go back to the
Mesh mode of the Input program.
Performing calculations
After generation of the mesh, all construction stages must be redefined. Even
though in practice the piles will be constructed in another construction stage
than construction of the walls, for simplicity both actions will be done in the
same construction stage in this tutorial. To redefine all construction stages,
follow these steps:
5 EXCAVATION IN CLAY
This tutorial describes the construction of an excavation pit in soft clay. The
pit is a relatively small excavation of 12 by 20 m, excavated to a depth of 6.5
m below the surface. Struts and walings are used to prevent the pit to
collapse. After the full excavation, an additional surface load is added on one
side of the pit.
4.0 m
50.0 m 4.0 m
(30 20) (50 20)
(34 19) (41 19)
80.0 m
Objectives:
• Using the Hardening Soil model
• Using interface features
• Defining over-consolidation ratio (OCR)
• Changing water conditions
• Selection of stress points to generate stress/strain curves
• Viewing plastic points
z = -6
z = -9.5
Soft clay
-9) z = -20
Figure 5.2 Cross section of the excavation pit with the soil layers
5.1 GEOMETRY
Project properties
• Start a new project.
• Enter an appropriate title for the project.
• Define the limits for the soil contour as xmin = 0, xmax = 80, ymin = 0 and
ymax = 50.
Hint: When the Rigid option is selected in the Strength drop-down, the
interface has the same strength properties as the soil
(Rinter = 1.0).
» Note that a value of Rinter < 1.0, reduces the strength as well as
the stiffness of the interface.
• Create a second plate between (30 32 0), (50 32 0), (50 32 -11) and (30
32 -11), a third plate between (50 32 0), (50 20 0), (50 20 -11) and (50
32 -11) and a fourth plate between (50 20 0), (30 20 0), (30 20 -11) and
(50 20 -11).
• Create a data set for the sheet pile walls (plates) according to Table 5.2.
Assign the data sets to the four walls.
• Select all four vertical surfaces modelling the sheet pile walls and assign
both positive and negative interfaces to them using the options in the
right mouse button menu.
To define the bottom of the excavation pit with points at z=-6.5, follow next
steps:
Click the Create surface button.
• In the command line, type "30 20 -6.5 30 32 -6.5 50 32 -6.5 50 20 -6.5"
to define the bottom of the excavation pit.
Click the Create structure button.
Click the Create beam button from the additional tools displayed to
create beams (walings) around the circumference at level z = -1 m.
• Click on (30 20 -1), (30 32 -1), (50 32 -1), (50 20 -1), (30 20 -1) to draw
the walings. Click on the right mouse button to stop drawing walings.
Create a beam (strut) between (35 20 -1) and (35 32 -1). Press <Esc> to
end defining the strut.
Create data sets for the walings and strut according to Table 5.3 and
assign the materials accordingly.
Copy the strut into a total of three struts at x = 35 (existing), x = 40, and x
= 45.
Create a surface load defined by the points: (34 19 0), (41 19 0), (41 12
0), (34 12 0). The geometry is now completely defined.
Hint: The first local axis is indicated by a red arrow, the second local
axis is indicated by a green arrow and the third axis is indicated
by a blue arrow. More information related to the local axes of
plates is given in the Reference Manual.
Figure 5.4 Preview of the steady state pore pressures in Phase_3 in a cross
section
• Click the Search closest button. The number of the closest node and
stress point will be displayed.
• Click the checkbox in front of the stress point to be selected. The
selected stress point will be shown in the list.
• Select also stress points near the coordinates (37.5 19 -5), (37.5 19 -6)
and (37.5 19 -7) and close the Select points window.
• Click the Update button to close the Output program.
Start the calculation process.
Save the project when the calculation is finished.
After the calculations, the results of the excavation can be viewed by selecting
a calculation phase from the Phases tree and pressing the View calculation
results button.
Select the final calculation phase (Phase_4) and click the View
calculation results button. The Output program will open and will show
the deformed mesh at the end of the last phase.
• The stresses, deformations and three dimensional geometry can be
viewed by selecting the desired output from the corresponding menus.
For example, choose Plastic points from the Stresses menu to
investigate the plastic points in the model.
• In the Plastic points window, Figure 5.6, select all the options except the
Elastic points and the Show only inaccurate points options. Figure 5.7
shows the plastic points generated in the model at the end of the final
calculation phase.
Start selecting structures. Click at a part of the wall to select it. Press
<Ctrl + A> simultaneously on the keyboard to select all wall elements.
The selected wall elements will colour red.
• While holding the <Ctrl> key or <Shift> key on the keyboard, double-click
at one of the wall elements to see the deformations plane of the total
displacements |u| in all wall elements.
To generate a curve, select the Curves manager option from the Tools
menu or click the corresponding button in the toolbar.
• All pre-selected stress points are shown in the Curve points tabsheet of
the Curves manager window.
• Create a new chart.
• Select point K from the drop-down menu for x−axis of the graph. Select
1 under Total strains.
• Select point K from the drop-down menu for y−axis of the graph. Select
σ '1 under Principal effective stresses.
• Invert the sign of both axis by checking the corresponding boxes (Figure
5.8).
• Click OK to confirm the input.
The graph will now show the major principal strain against the major principal
stress. Both values are zero at the beginning of the initial conditions. After
generation of the initial conditions, the principal strain is still zero whereas the
principal stress is not zero anymore. To plot the curves of all selected stress
points in one graph, follow these steps:
• Select Add curve → From current project from right mouse button
menu.
• Generate curves for point L, M and N in the same way.
The graph will now show the stress-strain curves of all four stress points
(Figure 5.9). To see information about the markers, make sure the Value
indication option is selected from the View menu and hold the mouse on a
marker for a while. Information about the coordinates in the graph, the
number of the point in the graph, the number of the phase and the number of
the step is given. Especially the lower stress points show a considerable
increase in the stress when the load is applied in the last phase.
To create a stress path plot for stress point L follow these steps:
• Create a new chart.
• In the Curves generation window, select point L from the drop-down
menu of the x−axis of the graph and σ 'yy under Cartesian effective
stresses.
• Select point K from the drop-down menu of the y−axis of the graph.
Figure 5.10 Vertical effective stress (σ 'zz ) versus horizontal effective stress
(σ 'yy ) at stress point L located near (37.5 19 -5)