Mobilisation Plan

The mobilisation plan outlines activities to be completed from December 1, 2017 to January 30, 2018. Key activities include site infrastructure development like preparing roads and barricades by December 14th. Organisation and design work is scheduled between December 14th and January 13th including submitting plans for approval. Site office development will occur between December 16th and January 30th consisting of setting up portable buildings, electrical and plumbing work, furniture installation and other facilities.

Uploaded by

Dilip Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (9 votes)
6K views2 pages

Mobilisation Plan

The mobilisation plan outlines activities to be completed from December 1, 2017 to January 30, 2018. Key activities include site infrastructure development like preparing roads and barricades by December 14th. Organisation and design work is scheduled between December 14th and January 13th including submitting plans for approval. Site office development will occur between December 16th and January 30th consisting of setting up portable buildings, electrical and plumbing work, furniture installation and other facilities.

Uploaded by

Dilip Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

 MOBILISATION PLAN

Sl no Activity Name Original Duration Start Finish

MOBILISATION 60 1‐Dec‐17 30‐Jan‐18

1‐Dec‐17 21‐Dec‐17
Site Infrastructure Development 20

1 Preparation of roads to office and site vehicular movement 10 1‐Dec‐17 11‐Dec‐17

Preparation of site boundary barrication with GI Sheets or compund  8 6‐Dec‐17 14‐Dec‐17


2 wall /Gates for vehicular movement
Preparation of Ground for site office/store room/material stack 
10 9‐Dec‐17 19‐Dec‐17
3 room 

4 Vehicle Parking area Development 7 14‐Dec‐17 21‐Dec‐17

5 Drainage and water supply system for labours/Staff 5 11‐Dec‐17 16‐Dec‐17

14‐Dec‐17 13‐Jan‐18
ORGANISATION & DESIGN 30
Submission & Approval of contractor execution plan, quality  30 14‐Dec‐17 13‐Jan‐18
1 plan,HSE Plan & Baseline Prog.

2 Mobilization of key personnel  8 14‐Dec‐17 22‐Dec‐17

3 Submission & approval of Design report 15 17‐Dec‐17 1‐Jan‐18


 MOBILISATION PLAN
Sl no Activity Name Original Duration Start Finish

Site office /Engineers Office Development 45 16‐Dec‐17 30‐Jan‐18

1 Set up of portcabin installation 25 16‐Dec‐17 10‐Jan‐18


2 All plumbing & Electrical fit‐out works 10 23‐Dec‐17 2‐Jan‐18
3 office furniture facility set‐out 10 30‐Dec‐17 9‐Jan‐18
4 Installation of all Electrionic equipments(PC,AC etc.) 6 9‐Jan‐18 15‐Jan‐18
5 Arrangement for supply of power & water  8 15‐Jan‐18 23‐Jan‐18
6 development of staff/labourers toilet facility 15 23‐Dec‐17 7‐Jan‐18
7 Medical/first Aid facility room development 15 7‐Jan‐18 22‐Jan‐18
8 Construction of store room 10 12‐Jan‐18 22‐Jan‐18
9 Construction of materials stacking yard 10 7‐Jan‐18 17‐Jan‐18
10 Construction of security cabin  10 20‐Jan‐18 30‐Jan‐18
11 Development of hard scape around the site office 10 20‐Jan‐18 30‐Jan‐18