Simops Matrix

This document outlines a simultaneous operations matrix for drilling, completion, and production operations. It shows that initial drilling of 30-inch holes can be done in batches of two wells at a time. Subsequent drilling can be done with producing wells online by nippling up or down diverter and low pressure risers. It also lists other simultaneous operations like rigging up equipment on well heads and maintenance of emergency systems.

Uploaded by

thinkpad
Copyright
© © All Rights Reserved
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views

Simops Matrix

This document outlines a simultaneous operations matrix for drilling, completion, and production operations. It shows that initial drilling of 30-inch holes can be done in batches of two wells at a time. Subsequent drilling can be done with producing wells online by nippling up or down diverter and low pressure risers. It also lists other simultaneous operations like rigging up equipment on well heads and maintenance of emergency systems.

Uploaded by

thinkpad
Copyright
© © All Rights Reserved
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 17

SIMULTANEOUS OPERATIONS MATRIX

DRILLING & COMPLETION OPERATIONS PRODUCTION OPERATIONS OTHER OPERATIONS

INITIAL DRILLING SUBSEQUENT DRILLING WITH PRODUCING WELLS

Nipple up/down Diverter and Low Pressure Riser

Rigging Up/Down Equipment onto Well Heads


Drill Conductor 30" Holes (Batch drill 2 wells)

Maintenance of Emergency Systems (RG VII)


Tensioning system instalation / maintenance
Install Tension Decks &Well Bay Structure

Install Tubing Hanger Pack Off and Test

Install Tubing Hanger Pack Off and Test

Well Testing Via Production Equipment


Gas Turbine Operation & Maintenance
Run & Cement 20" Casing (Batch set)
Project Title

Maintenance of Emergency Systems


Install Xmas Tree & BOP (Heavy Lift)

Install Xmas Tree & BOP (Heavy Lift)

Failure of Downhole Safety Systems


Drill 8 1/2" Hole (Hydrocarbon Zone)

Drill 8 1/2" Hole (Hydrocarbon Zone)

Skidding Rig with BOPs Underslung

Production Equipment Maintenance


Run & Cement 10 3/4 x 9 5/8 casing

Run & Cement 10 3/4 x 9 5/8 casing

Remedal and Workover Operations


Electric Line Logging(not planned)

Electric Line Logging(not planned)


Drill 26" hole (Batch drill 2 wells)

Nipple up/down BOP (Heavy Lift)

Nipple up/down BOP (Heavy Lift)

Crane Operations Over Well Bay


Run Completion and Set Barrier

Run Completion and Set Barrier

Flaring and Venting Operations

Personnel Working in Well Bay


Run & Cement 13 3/8" Casing

Run & Cement 13 3/8" Casing

Required Platform ESD Level


Skidding Rig Between Slots

Production Commissioning
Moving Rig on and Preload

Jack up and Cantilever Rig

Export Tankers Operations


Run & Cement Conductors

Run & Cement Conductors

Run & Cement 20" Casing


Drill Conductor 30" Holes

Depressurising Systems
Nipple up/down Diverter

Crane Operations Stbd

Crane Operations Port


Helicopter Operations
Run Subsea template

Slickline Operations

Slickline Operations
Pressure Test BOP

Pressure Test BOP

Diving Operations
Pressure Testing
Drill 17 1/2" Hole

Drill 12 1/4" Hole

Drill 17 1/2" Hole

Drill 12 1/4" Hole

Supply Vessels
Run 7" Liner

Run 7" Liner


Drill 26" hole

Producing
Start ESP

Sampling

Hot Work
A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AF AG AH AI AJ AK AL AM AN AO AP AQ AR AS AT AU AV AW AX AY AZ BA BB BC BD BE BF BG BH BI BJ BK BL BM BN BO BP BQ BR BS BT BU
Moving Rig on and Preload 1 * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * RA * RA RA RA * * * * * * * * * Y Y N N * N * N RA *
Jack up and Cantilever Rig 2 * * Y Y * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * RA * RA RA RA * * * * * * * * * Y Y RA Y * Y * N RA *
Run Subsea template 3 * Y * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * Y * Y Y Y * RA * * * * * * * Y Y RA Y * Y * RA Y *
Install Tension Decks &Well Bay Structure 4 Y Y * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * Y * Y Y Y * RA * * * * * * RA Y Y RA Y RA Y * N Y *
Tensioning system instalation / maintenance 5 RA Y RA RA Y Y RA Y Y Y Y Y Y RA RA Y RA RA RA Y RA RA Y Y RA Y Y Y Y Y Y RA RA Y RA RA RA RA RA Y Y Y Y Y N RA RA RA RA Y Y Y Y Y Y Y Y RA Y Y RA Y *
Skidding Rig Between Slots 6 * * N * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * Y RA Y Y Y N RA N N Y Y Y N RA Y Y RA Y P Y Y RA Y *
Drill Conductor 30" Holes (Batch drill 2 wells) 7 * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * Y * Y Y Y * RA * * * * * * Y Y Y RA Y * Y * N Y *
Run & Cement Conductors 8 * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * Y * Y Y Y * RA * * * * * * Y Y Y RA Y * Y * RA Y *
Nipple up/down Diverter and Low Pressure Riser 9 * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * Y * Y Y Y * RA * * * * * * Y Y Y RA Y * Y * RA Y *
Drill 26" hole (Batch drill 2 wells) 10 * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * Y * Y Y Y * RA * * * * * * Y Y Y RA Y * Y * RA Y *
Run & Cement 20" Casing (Batch set) 11 * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * Y * Y Y Y * RA * * * * * * Y Y Y RA Y * Y * RA Y *
Nipple up/down BOP (Heavy Lift) 12 * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * Y * Y Y Y * RA * * * * * * RA Y Y RA Y * Y * N Y *
Drill 17 1/2" Hole 13 * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * Y * Y Y Y * RA * * * * * * Y Y Y RA Y * Y * Y Y *
INITIAL DRILLING

Run & Cement 13 3/8" Casing 14 * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * Y * Y Y Y * RA * * * * * * Y Y Y RA Y * Y * Y Y *


Drill 12 1/4" Hole 15 * * * * * * * * * * * * * * * * * * * * * * * * * * * * * Y * Y Y Y * RA * * * * * * Y Y Y RA Y * Y * Y Y *
Run & Cement 10 3/4 x 9 5/8 casing 16 * * * * * * * * * * * * * * * * * * * * * * * * * * * * Y * Y Y Y * RA * * * * * * Y Y Y RA Y * Y * Y Y *
Drill 8 1/2" Hole (Hydrocarbon Zone) 17 * * * * * * * * * * * * * * * * * * * * * * * * * * * RA * RA RA RA * RA * * * * RA * Y RA Y RA Y * Y * Y Y *
DRILLING & COMPLETION OPERATIONS

Run 7" Liner 18 * * * * * * * * * * * * * * * * * * * * * * * * * * RA * RA RA RA * RA * * * * * * Y RA Y RA Y * Y * Y Y *


Install Tubing Hanger Pack Off and Test 19 * * * * * * * * * * * * * * * * * * * * * * * * * RA * RA RA RA * RA * * * * * * Y RA Y RA Y * Y * Y Y *
Install Xmas Tree & BOP (Heavy Lift) 21 * * * * * * * * * * * * * * * * * * * * * * * * Y * Y Y Y * RA * * * * * RA P RA Y RA Y * Y * N Y *
Run Completion and Set Barrier 22 * * * * * * * * * * * * * * * * * * * * * * * RA * RA RA RA * RA * * * * * * Y RA Y RA Y * Y * Y Y *
Electric Line Logging(not planned) 23 * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * Y * * * * * * * *
Slickline Operations 24 * * * * * * * * * * * * * * * * * * * * * RA * RA RA RA N RA RA N * * RA Y Y RA Y RA Y * Y * Y Y *
Pressure Test BOP 25 * * * * * * * * * * * * * * * * * * * * Y * Y Y Y N * N N * * N Y N RA Y RA Y * Y * Y Y *
Drill Conductor 30" Holes 26 * * * * * * * * * * * * * * * * * * * * Y Y Y Y N RA RA Y Y Y Y Y RA Y Y RA Y * Y Y N Y *
Run & Cement Conductors 27 * * * * * * * * * * * * * * * * * * * Y Y Y Y N RA RA Y RA Y Y Y RA Y Y RA Y * Y Y N Y *
SUBSEQUENT DRILLING WITH PRODUCING WELLS

Nipple up/down Diverter 28 * * * * * * * * * * * * * * * * * * Y Y Y Y N RA N N N N Y N RA Y Y RA Y * Y Y N Y 1


Drill 26" hole 29 * * * * * * * * * * * * * * * * * Y Y Y Y N RA Y Y Y Y Y Y Y Y Y RA Y * Y Y Y Y *
Run & Cement 20" Casing 30 * * * * * * * * * * * * * * * * Y Y Y Y N RA Y Y Y Y Y Y Y Y Y RA Y * Y Y Y Y *
Nipple up/down BOP (Heavy Lift) 31 * * * * * * * * * * * * * * * Y Y Y Y N RA N N N N Y N RA Y Y RA Y * Y Y N Y 1
Drill 17 1/2" Hole 32 * * * * * * * * * * * * * * Y Y Y Y N RA RA Y Y Y Y Y Y Y Y RA Y * Y Y Y Y *
Run & Cement 13 3/8" Casing 33 * * * * * * * * * * * * * Y Y Y Y N RA RA Y Y Y Y Y Y Y Y RA Y * Y Y Y Y *
Drill 12 1/4" Hole 34 * * * * * * * * * * * * Y Y Y Y N RA RA Y Y Y Y Y Y Y Y RA Y * Y Y Y Y *
Run & Cement 10 3/4 x 9 5/8 casing 35 * * * * * * * * * * * Y Y Y Y N RA RA Y Y Y Y Y Y Y Y RA Y * Y Y Y Y *
Drill 8 1/2" Hole (Hydrocarbon Zone) 36 * * * * * * * * * * Y Y Y Y N RA RA Y Y Y Y Y Y Y Y RA Y * Y Y Y Y *
Run 7" Liner 37 * * * * * * * * * Y Y Y Y N RA RA Y Y Y Y Y Y Y Y RA Y * Y Y Y Y *
Install Tubing Hanger Pack Off and Test 38 * * * * * * * * Y Y Y Y N * RA Y Y Y Y Y Y Y Y RA Y * Y Y Y Y *
Install Xmas Tree & BOP (Heavy Lift) 39 * * * * * * * Y Y Y Y N RA N N N N Y N RA Y Y RA Y * Y Y N Y 1
Run Completion and Set Barrier 40 * * * * * * Y Y Y Y N RA RA Y Y Y Y Y Y Y Y RA Y * Y Y Y Y *
Electric Line Logging(not planned) 41 * * * * * N
Slickline Operations 42 * * * * Y Y Y Y N RA RA Y Y Y Y Y Y Y Y RA Y * Y * Y Y *
Skidding Rig with BOPs Underslung 43 * * * Y Y Y Y N RA N N N N N N RA Y Y RA Y RA Y Y N Y 1
Pressure Test BOP 44 * * Y Y Y Y N * N Y Y Y Y Y RA Y Y RA Y * Y Y Y Y *
Remedal and Workover Operations 45 * Y Y Y Y N RA RA Y Y Y Y Y Y Y Y RA Y * Y Y Y Y *
46
47
8
Production Commissioning 48 * Y Y Y N RA Y Y Y Y Y Y Y Y Y RA Y RA Y * Y Y *
Flaring and Venting Operations 49 Y Y Y N Y Y Y Y Y Y Y Y Y Y RA Y RA Y Y Y Y *
Production Equipment Maintenance 50 Y Y N RA Y Y Y Y Y Y Y Y Y Y RA Y RA Y Y Y Y *
PRODUCTION OPERATIONS

Gas Turbine Operation & Maintenance 51 Y N RA Y Y Y Y Y Y Y Y Y RA Y RA Y Y Y Y *


Maintenance of Emergency Systems 52 N RA Y Y Y Y Y Y Y Y Y RA Y RA Y Y Y Y *
Failure of Downhole Safety Systems 53 N N N N N N N N N N N N N N N N N 2
Pressure Testing 54 RA RA RA RA Y Y RA Y Y RA Y RA Y Y Y Y *
Rigging Up/Down Equipment onto Well Heads 55 RA RA RA RA RA Y Y Y RA Y RA Y Y RA Y *
Start ESP 56 Isolation Status Codes Y Y Y Y Y Y Y RA Y RA Y Y Y Y *
Producing 57 Y Y Y Y Y Y RA Y RA Y Y Y Y *
Sampling 58 1 Shut in at SSSV and Depressurised to SSSV Y Y Y Y Y RA Y RA Y Y Y Y *
Depressurising System 59 2 Topside Shut in and Depressurised Y Y Y Y RA Y RA Y Y Y Y *
Well Testing Via Production Equipment 60 3 Topside Shut in Y Y Y RA Y RA Y Y Y Y *
61
62

Personnel Working in Well Bay 63 Y Y RA Y RA Y Y Y Y *


Hot Work 64 KEY Y RA Y RA Y Y Y Y *
Helicopter Operations 65 N N N Y Y Y Y *
OTHER OPERATIONS

Crane Operations stbd 66 * Not Applicable Y RA Y Y RA Y *


Crane OperationsPort 67 Y Hazards Assessed and Acceptable (PTW may still be requied) RA Y Y RA Y *
Crane Operations Over Well Bay 68 N Hazards Assessed and Not Acceptable Y Y RA Y *
Supply Vessels 69 Y RA Y *
A Risk Assessment Is Required To Determine The Nature/Location/Timing
Export Tankers Operations 70 RA Y Y *
Of The Proposed Activities, And Can They Occur Simultaneous
Diving Operations 71 Y *
Maintenance of Emergency Systems (RG VII) 72
73
74
SIMULTANEOUS OPERATION KEY PERSONNEL

COMPANY NAME CONTACTS NAME PHONE No E - MAIL ADDRESS


SIMULTANEOUS OPERATIONS CHANGES REGISTER

Matrix Matrix
No Additions Deletions Location Location Identifcation Of Operation & Comments
Additions Deletions
SIMULTANEOUS OPERATIONS CHANGES REGISTER
Party 1

Matrix Matrix
No Additions Deletions Location Location Identifcation Of Operation & Comments
Additions Deletions
SIMULTANEOUS OPERATIONS CHANGES REGISTER
Party 2

Matrix Matrix
No Additions Deletions Location Location Identifcation Of Operation & Comments
Additions Deletions
SIMULTANEOUS OPERATIONS CHANGES REGISTER
Party 3

Matrix Matrix
No Additions Deletions Location Location Identifcation Of Operation & Comments
Additions Deletions
SIMULTANEOUS OPERATIONS CHANGES REGISTER
Party 4

Matrix Matrix
No Additions Deletions Location Location Identifcation Of Operation & Comments
Additions Deletions
SIMULTANEOUS OPERATIONS CHANGES REGISTER
Party 5

Matrix Matrix
No Additions Deletions Location Location Identifcation Of Operation & Comments
Additions Deletions
SIMULTANEOUS OPERATIONS CHANGES REGISTER
Party 6

Matrix Matrix
No Additions Deletions Location Location Identifcation Of Operation & Comments
Additions Deletions