Sapp Operating Guidelines
Sapp Operating Guidelines
OPERATING GUIDELINES
14 AUGUST 1996
-Page 2 -
TABLE OF CONTENTS….
PAGE NO’S:
- PREAMBLE 4
- INTRODUCTION 4
PREAMBLE
The objective of this document is to ensure that all the Operating Members of the
Southern African Power Pool (SAPP) operate the interconnected Southern
African network efficiently and effectively and that all Members participate
equitably in the obligations and in the benefits resulting from the Pool. These
guidelines will be amended from time to time by the Operating Sub-Committee of
the SAPP, as the need arises.
All interconnected utilities to SAPP must comply with the contents of this
document. It can also be used as a basis to prepare more detailed documents
governing the operation of each individual network.
INTRODUCTION
The English language, both written and spoken, will be the medium of official
communication between the Operating Members of the SAPP.
In practice, certain Clauses are more important than others. Therefore, the
Clauses are classified either as Operating Requirements or as Operating
Recommendations.
A. GENERATION CONTROL…
B. VOLTAGE CONTROL…
Each System and Control Area shall operate capacitive and inductive reactive
resources so as to maintain within specified limits, the voltage levels inside
the Systems and at the Points of interconnection. Reactive power generation,
transmission equipment switching and load shedding if necessary, shall be
implemented to maintain these voltage levels. Each System and Control Area
shall have adequate MVAr reserves so as to maintain the voltage to
acceptable levels under credible contingency conditions.
Control Areas which are interconnected shall select one Control Area each
year to monitor time error and to issue time error correction orders.
D INTERCHANGE SCHEDULING…
G. CONTROL SURVEYS…
The System Controller’s displays and consoles shall offer him a clear
and understandable picture of his Control Area parameters. This
includes all the necessary information from other Control Areas in
addition to his own.
---oOo---
-Page 8 -
Each Control Area shall operate its active power resources to ensure a
level of operating reserve sufficient to account for such considerations as
errors in load forecasting and exchange schedules, generation or
transmission equipment unavailability, number and size of generating
units, forced outage rates, maintenance schedules, regulating
requirements, and load diversity between Control Areas. Following the
loss of load or active power resource(s), the Control Area shall take
appropriate steps to reduce its Area Control Error to zero within ten (10)
minutes.
(iii) the limitations, if any, upon the amount of interruptible load which may
be considered as quick reserve.
This philosophy shall not be less onerous than the minimum reserve policy
specified in this Guidelines.
Each Control Area shall supply its own reactive power requirements,
including appropriate reserves to maintain voltage levels during a
contingency. The reserve shall be located, electrically, where it can be
applied effectively and timeously when a contingency occurs.
C. TRANSMISSION OPERATION…
D. RELAY CO-ORDINATION…
H. MAINTANANCE CO-ORDINATION….
Each System shall prepare inspection and maintenance schedules for its
generation and transmission facilities, its protection, control and
communication equipment and of any other relevant facility. These
inspection and maintenance schedules shall be co-ordinated with those of
other affected Systems and Control Areas to ensure that the equipment
outages will not violate the reliability criteria.
---oOo---
-Page 11 -
C. LOAD SHEDDING….
After taking all other remedial steps, a System or Control Area whose integrity
is still in jeopardy due to insufficient generation or transmission capacity, shall
shed load rather than risk an uncontrolled failure of components making up
the interconnection between Control Areas.
I. SYSTEM RESTORATION….
depending upon the incident. Even though the restoration shall be done as
speedily as possible, System Controllers shall avoid premature action to
prevent another collapse of the system.
---oOo---
B. SELECTION….
Each System and Control Area shall select its System Controllers based on
criteria that are designed to promote reliable operation.
C. TRAINING….
Each System and/or Control Area shall provide its personnel with training that
is designed to promote reliable operation.
Each System and Control Area’s personnel shall supply the information
required by other Systems, Control Areas or by the Operating Sub-
Committee.
---oOo---
-Page 14 -
A. NORMAL OPERATIONS
Each Control Area shall plan its future operations in co-ordination with
other affected Control Areas to ensure that normal interconnection
operation will proceed in an orderly and consistent manner.
Each System and Control Area shall maintain comprehensive and co-
ordinated procedures to deal with long-term capacity or energy shortages.
D. LOAD SHEDDING
Each System and Control Area shall prepare a program of manual and
automatic load shedding sufficient to arrest frequency or voltage decay, or
extreme power flows that could cause an uncontrolled failure of failure of
components of the Interconnection. The program shall be co-ordinated
throughout the Interconnection so as to avoid high transmission loading
and extreme voltage deviations.
E. SYSTEM RESTORATION
Each System and Control Area shall develop and periodically update a
plan of action to restore its system in an orderly manner in the event of a
partial or total shutdown. This plan shall be co-ordinated with other
Control Areas to ensure a consistent Interconnection restoration.
---oOo---
GUIDELINE VI : TELECOMMUNICATIONS….
A. FACILITIES….
Each System and Control Area shall install adequate and reliable
telecommunication facilities for their own needs and those of other
Systems and Control Areas so as to ensure that the exchange of
information necessary to maintain the reliability of the Interconnection can
take place. Wherever possible, there will be back-up facilities and route
diversity.
C. LOSS OF TELECOMMUNICATIONS….
---oOo---
-Page 16 -
Adjacent System or Adjacent Control Area: Any System or Control Area directly
Interconnected with (so as to be significantly affected by the existence of) another System or
Control Area.
Area Control Error (ACE): The instantaneous difference between actual and scheduled tie
line interchanges between Control Areas, taking into account the difference between the
scheduled and actual frequency.
Cold Reserve: Cold Reserve is all generating capacity available for operation but not
synchronized to the system; it is the Slow Reserve plus Quick Reserve.
Control Area: Control Area shall mean an electrical System with borders defined by points
of Interconnection and capable of maintaining continuous balance between the generation
under its control, the consumption of electricity in the Control Area and the scheduled
interchanges with other Control Areas.
Control-Performance Criteria (CPC): The CPC survey provides two measures of the
performance of ACE. The measures are referred to as A1 – Zero Crossing, and A2 –Ld
Compliance.
Demand: The rate at which energy is being used by the customer, expressed in MW or
GW.
Emergency Energy: Emergency Energy shall mean energy supplied from other Operating
Members to an Operating Member who experiences a loss of generating or transmission
facilities as the result of an unscheduled outage (or outages) or any cause not reasonably
foreseeable. Such energy shall be available for a period of six (6) hours starting from the
occurrence of the emergency, after which the Operating Member must obtain other types of
services or shed load, should the shortage continue.
Emergency Generation. Emergency Generation is the short- term generation of the plant
above its rated capacity.
-Page 17 -
Force Majeure: Force Majeure shall have the same meaning as in Clause 2.18 of the
SAPP Agreement Between Operating Members shall apply, except for Clause 2.18.4 which
shall read as follows:
“any other cause beyond the control of a Party, provided the Party experiencing such cause
and the other Party agree that such cause should be regarded as Force Majeure”.
Frequency Bias Setting: A value, in MW/0.1 Hz, set into a Control Area’s AGC
Equipment to represent a Control Area’s response to deviation from scheduled frequency.
Hourly Value: Data measured on a clock-hour basis. When related to energy or similar data,
it is the value accumulated during the sixty (60) minute interval ending at the hour which is
specified.
Inadvertent Energy Flow: Inadvertent Energy Flow shall mean the difference between
the net scheduled energy delivered and the actual net energy delivered in any specific hour.
Interconnection: When starting with a capital letter, it shall mean high voltage
transmission lines and substations making up international backbone of the Southern Africa
Grid. When not starting with a capital letter, it shall mean the facilities that connect two
adjacent Systems or Control Areas.
Leap Second: A second of time added occasionally by the Bureau of Standards to correct
for the offset between the clock-hour day and the solar day.
Load: The amount of electric power delivered or required at any specified point on a
system.
Mothballing: Mothballing plant stored for longer than one (1) year; the plant is dry stored
and may be partially dismantled and specifically protected.
Net Energy for load: Net system generation plus interchange received minus interchange
delivered in a time interval.
Operating Reserve: The un-used capacity above System Demand which is required to
cater for regulation, short-term load forecasting errors, and unplanned outages. It consists
of Spinning and Quick Reserve.
Operating Security: The ability of a power system to withstand or limit the adverse effects
of any credible contingency to the System including overloads beyond emergency ratings,
excessive or inadequate voltage, loss of stability or abnormal frequency deviations.
Planned Outage: Unless otherwise agreed and confirmed in writing between all relevant
Control Centres, planned Outages shall mean outages which are scheduled with at least
two weeks notice and agreed in writing between the Control Centres.
Quick Reserve: Quick Reserve is interruptible load or capacity readily available from
Cold Reserve which can be started and loaded within ten (10) minutes to meet the system
demand. This includes hydro plant, gas turbines, pumped storage and interruptible load.
Reserve Storage: Reserve Storage is plant that is stored for more than three (3) months in
a wet or dry stored condition. Some auxiliary plant may be run periodically.
Regulating Margin: The on-line capacity that can be increased or decreased to allow the
system to respond to all reasonable demand changes in order to comply with the Control
Performance Criteria.
Service Schedules: Service Schedules shall mean schedules governing various types of
transactions that may be entered between Operating Members to reduce costs or improve
reliability of supply.
-Page 19 -
Slow Reserve: Slow Reserve is capacity available from Cold Reserve and considered
to be ready for synchronization to the system within twenty-four (24) hours. The purpose of
slow reserve is to replace any generating units on unplanned outages or to meet forecasted
demand.
Special Protection System (SPS) :Shall mean a protection scheme designed to perform
functions other than the isolation of electrical faults; it is also called “remedial action
scheme”. See Guideline II “Relay Co-ordination”.
Spinning Reserve: Spinning Reserve shall mean the unused capacity which is
synchronized to the System and which can be delivered immediately without manual
intervention.
Station Service: Shall mean electric supply to ancillary equipment used to operate a
generating station or substation.
Station Service Generator: Shall mean a generator used to supply electrical energy to
station service equipment.
Supervisory Control and Data Acquisition (SCADA): Shall mean a system of remote
control and telemetry used to monitor and control the transmission system.
Unplanned Outage: Unless otherwise agreed and confirmed in writing between all
relevant Control Centres, Unplanned Outages shall mean outages which are not scheduled
with the advance notice of two weeks and agreed in writing.
Wheeling: Wheeling shall mean transmitting a contractual amount of power over specified
time periods through the System of an Operating Member who is neither the Seller nor the
Buyer of this power.
---oOo---
-Page 20 -
A. GENERATION CONTROL…
Criteria:
Each Control Area shall operate sufficient generating capacity under Automatic Generation
Control (AGC):
(1) to continuously balance its generation and interchange schedules to its load,
Requirements:
(i) total net actual interchange adjusted for actual frequency and;
to determine the Control Area’s Area Control Error (ACE) and respond by returning
the ACE to zero.
2. Each Control Area shall provide an amount of Spinning Reserve responsive to AGC,
which is synchronized to the interconnection. This amount shall be raised or lowered
by AGC to provide adequate system regulation and satisfy Control Performance
Criteria.
3. Each Control Area shall operate its AGC on tie-line bias mode, unless such operation
is adverse to System or Interconnection reliability. The requirements for tie-line bias
control are as follows:
3.1 The Control Area shall set its frequency bias (expressed in MW/0,1 Hz) as
close as practical to the Control Area’s frequency response characteristic.
Frequency bias may be calculated in several ways:
3.1.1 A fixed frequency bias value may be used which is based on a fixed,
straight-line function of tie-line deviation versus frequency deviation.
-Page 21 -
3.2.1 In no case shall the monthly average frequency bias be less than 1%
of the Control Area’s estimated yearly peak demand per 0.1 Hz.
3.3 Each Control Area shall review its frequency bias settings by 1 January of
each year and shall recalculate its settings to reflect any change of frequency
response characteristic in the Control Area.
3.3.1 The bias setting or the method used to determine the setting may be
changed whenever any of the parameters listed in Clause 3.1.2 above
changes.
3.4 Each Control Area must be able to prove to the Operating Sub-Committee
that its frequency bias settings closely match its frequency response
characteristic.
3.5 Each Control Area shall communicate its frequency bias setting and the
method for determining that setting to the Operating Sub-Committee.
Recommendations:
1. AGC should be in service all the time and when not possible, arrangements must be
made to include the System in an established Control Area or to switch over to
temporary manual control.
2. Turbine governors and other control systems, including AGC and HVDC control
systems should be tested periodically to verify their correct operation. The maximum
intervals between such tests shall be specified by the Operating Sub- Committee.
-Page 22 -
3. Turbine governors and HVDC controls, where applicable, should respond to system
frequency deviation, unless there is a temporary operating problem.
4. Each Member should establish normal and emergency rates of response for
each generator and each HVDC terminal.
5. Load –limiting devices should be applied only when the rate of load change
has an adverse effect on the generators or when it can jeopardize
transmission security.
7. Each Control Area should schedule its generation so as to comply with the
Control Performance Criteria for any expected change in load characteristics
and daily load patterns.
Background:
Accurate and adequate generator control helps reduce time error, frequency
deviations, and Inadvertent Energy interchanges.
Each Control Area will respond to frequency deviations in accordance with the
response characteristics of its own System. Most of this response will be
reflected in the Control Area’s net interchanges. By monitoring the interchange
deviations from schedule, the frequency deviation from schedule, and by using
the Control Area’s frequency response characteristic, it is possible to determine
through the AGCs, whether the imbalance between load and generation is
internal or external to the Control Area. If internal, the AGC will adjust the
generation to correct the imbalance. If external, no AGC action should occur.
However, the frequency response to the interchange deviations through the
governors, should be allowed to continue until the external system with the
generation surplus or defiency corrects its imbalance and returns the frequency
to schedule.
bias matches the actual system frequency response, the better AGC will be able
to distinguish between internal and external imbalances and reduce the number
of unnecessary control actions. Therefore, the basic requirement of tie-line
frequency bias is that it matches the actual system response as closely as
practicable.
B. VOLTAGE CONTROL….
Criteria :
Each System and Control Areas shall maintain system and Interconnection voltages
within agreed upon high and low limits by operating suitable capacitive and reactive
resources. Reactive generation scheduling, transmission equipment switching and
load shedding if necessary, shall be implemented to maintain voltage levels under
credible contingency conditions.
Requirements:
2.2 Transfer limits shall take into account voltage or reactive power
restrictions. These restrictions should be clearly displayed in each
Control Centre.
2.3 Control Centres shall monitor and keep reactive power flows within
agreed upon limits on the interconnectors between neighbouring
countries.
Recommendations:
5. Systems with HVDC transmission facilities shall utilize the power resources
associated with the DC converters.
Criteria:
Operating limits for frequency deviation and time error shall be established with
Interconnection reliability as first priority.
One Control Area shall be selected every year to monitor the time error of the
Interconnection and to issue time error correction orders.
Requirements:
1. Every year the Operating Members shall designate a Control Area ( the
Monitor) which shall monitor time and initiate or terminate corrective actions
when time error reaches +/- 10 seconds.
2. Time error corrections shall start and end on the hour, a notice shall be given at
least thirty (30) minutes before the time error correction is to start or stop.
4. The offset to carry out the time error correction shall be implemented as
follows:
-Page 25 -
4.1 The frequency scheduled may be offset by 0.02 Hz, leaving the
frequency bias unchanged , or
4.2 If the normal frequency (50 Hz) cannot be offset, the net interchange
schedule (MW) may be offset by an amount corresponding to a 0.02
Hz frequency deviation (i.e 20 % of the frequency bias setting).
4.3.3 AGC offset may be made by either offsetting the frequency schedule
up to 0.02 Hz, leaving the bias setting normal or offsetting the net tie-
line schedule by up to 20 % of the Control Area’s bias or 5 MW,
whichever is greater.
4.3.4 Inadvertent pay-back shall end when either the time error is zero or
has changed signs, the accumulation of inadvertent interchanges has
been corrected to zero, or a scheduled time error correction begins,
which takes precedence over offsetting frequency schedule to pay-
back inadvertent.
6. The Monitor shall periodically issue a notification of time error, accurate to within
0.1 second, to Members to ensure uniform calibration of time standards.
7. Each Control Area shall, at least annually, check and calibrate its time error and
frequency devices against a common reference.
8. When one or more Control Areas have been separated from the interconnection,
upon reconnection, they shall adjust their time error devices to coincide with the
Interconnection by one of the following methods:
-Page 26 -
Before connection, the separated area may institute a Time Error Correction Procedure to
correct its accumulated time error to coincide with the indicated time error of the Monitor, or
After interconnection, the time error devices of the previously separated area may be
corrected to coincide with the indicated time error of the Monitor. A notification of adjustment
time error shall be passed through the Monitor as soon as possible after interconnection.
Recommendations:
1. The Control Areas may implement automatic time error control as part of their
AGC scheme.
1.1 If automatic time error correction is used, all Control Areas should
participate.
2. Systems using time error devices that are not capable of automatically
adjusting for leap-seconds should arrange to receive advance notice of the
leap-second and make the necessary manual adjustment in a manner that
will not introduce a disturbance into their control system.
Background:
The difference between load and generation results in frequency deviations from 50
Hz, and the integrated deviation appears as a departure from standard time.
Criteria:
The net amount of interchange scheduled between Control Areas shall not exceed
the mutually agreed transfer limits of the common interconnections and alternate
paths which have been arranged for between the parties. When establishing normal
and emergency transfer limits, the sending, wheeling, and receiving Control Areas
shall consider the effect of power flows through their own and other parallel Systems
or Control Areas based on mutually acceptable reliability criteria. In no case shall the
scheduled power transfers between two Control Areas exceed the total installed
capacity of own or pre-arranged transmission facilities between the two Control
Areas.
Schedule changes shall be made at a time and rate agreeable to both the supplier
and receiver and within the capacity of each Party to control the change.
Requirements:
2.1 When Control Areas are interconnected in such a way that parallel flows
present reliability problems, the affected Control Areas shall develop multi-
Control Area interchange monitoring techniques and pre-determined corrective
actions to mitigate or alleviate potential or actual transmission system overloads.
3. The maximum net scheduled interchange between two Control Areas shall not
exceed the lesser of two values:
3.1 The total capacity of the transmission facilities in service between the two
Contorl Areas owned by the them or available to the under wheeling
arrangements, contracts, or mutual agreements, or
-Page 28 -
3.2 The mutually established transfer capacity between two Control Areas
considering other transmission facilities available to them under wheeling
arrangements. (Transfer Capacity is defined in Appendix I.B “Transfer Capacity”).
4. The sending, wheeling and receiving Control Areas that are parties to an
interchange transaction shall agree on the following:
4.2 A change of schedule must be entered five (5) minutes before the hour and
must reach the full magnitude on the hour.
Background:
Criteria:
Requirements:
1. Two criteria shall be used to continually monitor control performance during normal
conditions (see Section 2.1 in the “Control Performance Criteria Training
Document”).
A1 Criteria- The Area Control Error (ACE) must return to zero at least every ten (10)
minutes. Violations of this criteria are counted for each subsequent ten (10) minute period
that the ACE fails to return to zero.
A2 Criteria- The average ACE for each of the 6 ten (10) minute periods during the hour (i.e
for the ten (10) minute periods ending at 10, 20, 30, 40, 50, and 60 minutes past the hour)
must not exceed specific limits, referred to as Ld. These limits are determined from the
Control Area’s rate of change of demand characteristics. (See Section 2.1.2.1 in the “Control
Performance Criteria Training Document” appended to these Guidelines for the methods for
calculating Ld).
B1 Criteria- The ACE must return to zero within ten (10) minutes following
the start of the disturbance.
B2 Criteria- The ACE must start to return to zero within one (1) minute
following the start of the disturbance.
3. The ACE used to determine compliance to the Control Performance Criteria shall
reflect its actual value, and exclude short excursions due to transient telemetering
problems or other influences such as control algorithm action.
4. All Control Areas shall respond to control performance surveys that are requested
by the Operating Sub-Committee.
Recommendations
1. Each Control Areas should comply with the A1 and A2 Criteria . A1 Criteria should be
met at least 90% of the time and A2 Criteria on average 80% for each month.
Background:
Control performance is the degree to which a Control Area succeeds in matching its
generation to its demand plus scheduled power interchanges taking into account the
effects of frequency bias. The Control Performance Criteria (CPC) establishes minimum
standards for control performance and provide a means for measuring the relative
control performance of each Control Area. While these standards define the minimum
-Page 30 -
acceptable performance, each Control Area shall meet and strive to exceed these
standards.
Criteria:
Each Control Area shall, through daily schedule verification and the use of reliable
metering equipment, accurately account for Inadvertent Energy interchanges.
Recognising generation and load patterns, each Control Area shall do its best to
prevent inadvertent interchange accumulation. Each Control Area shall reduce
accumulated Inadvertent Energy.
At least a common MWh- meter, with readings provided hourly to the relevant
Control Centres shall measure the power transfers at each Point of Interconnection
between two Control Areas.
Inadvertent Energy is defined to be the difference between the net scheduled energy
on the tie-lines in a Control Area and net actual energy delivered on the tie-lines in
that Control Area.
Requirements:
The other Control Area must have an inadvertent accumulation in the opposite direction.
The scheduled amount of inadvertent pay-back shall be agreed upon by all Control Areas
involved.
-Page 31 -
If time is slow and there is a negative accumulation (under generation), the AGC may be
offset to over-generate and pay-back inadvertent interchange accumulation and reduce time
error.
If time is fast and there is a positive accumulation (over-generation), the AGC may be offset
to under-generate and pay-back inadvertent interchange accumulation and reduce time
error.
AGC offset may be made either offsetting the frequency schedule by up to 0,02 Hz, leaving
the bias setting normal or offsetting the net tie-line schedule by up to 20% of the Control
Area’s bias or 5 MW, whichever is greater.
Inadvertent pay-back shall end when the time error becomes zero or has changed signs, the
accumulation of inadvertent interchange has been corrected to zero, or a scheduled time
error correction begins, because this action takes precedence over offsetting frequency
schedule to pay-back inadvertent.
Control Areas using automatic time error control techniques shall not use Method 2 to
reduce their accumulations of inadvertent. Method 1 is the only acceptable way for these
Control Areas to reduce their accumulations of inadvertent.
Inadvertent Energy summaries shall include at least the previous accumulation, net
accumulation for the month, and final net accumulation, for both on-peak and off-peak
periods.
Each Control Area shall submit its monthly summary report to the Operating Sub-Committee
representative who will prepare a composite tabulation for distribution to all other Operating
Sub-Committee representatives.
Background:
Inadvertent Energy is the difference between the Control Area’s net actual
interchange and net scheduled interchange. Interchange is partially due to the
frequency deviations occurring on the Interconnection. Unintentional Inadvertent
Energy interchanges are due to instrument and control errors, improper control
settings, poor generator response time, fluctuations in demand, etc.
G. CONTROL SURVEYS….
Criteria:
Requirements:
An Area Control Error survey to determine the Control Areas’ interchange error(s) due to
equipment failures, improper scheduling operations, or improper AGC performance.
A Control Performance Criteria survey to monitor the Controls Area’s control performance
during normal conditions and during disturbances.
Criteria:
The control equipment of each Control Area shall be designed and operated
to enable the Control Area to continuously meet its System and
Interconnection control obligations and measure its performance. The control
equipment shall be designed and operated in accordance with accepted
industry norms.
The Control Centre displays and consoles shall present a clear and
understandable picture of Control Area parameters. This shall include the
necessary information from the Control Area itself as well as all the necessary
information from other Control Areas.
Requirements:
1. Each Control Area shall perform control error checks at the end of
every hour using tie-line MWh meters to determine the accuracy of
its control equipment.
--oOo--
APPENDIX 1.A : TIME ERROR CORRECTION PROCEDURES
-Page 34 -
1. A time correction may be terminated after five (5) hours or after any hour in which a
time correction of 0.5 seconds has NOT been achieved. A time correction may be
extended beyond five (5) hours if the average correction has exceeded 0.5
seconds per hour.
2. After the termination of a time correction because of the “5-hour rule” above, or
failure to make a correction of 0.5 seconds per hour, slow time correction may be
reinstated after the frequency has returned to 50 Hz or above for a period of sixty
(60) minutes. At least one (1) hour should elapse between the termination and re-
initiation notices.
4. The time reference for the Southern African Power is UTC (Universal Time Co-
ordinated) plus two (2) hours.
---oOo---
1. STUDY METHOD….
The transfer limits must be determined for normal operation and emergency
condition using steady state, stability and voltage collapse models. This must be
done using, as far as possible, the N-1 criteria. These limits must be identified and
the limit which have the most severe consequences if exceeded, should be
recommended as the transfer limit to the appropriate Control Centres. If an operating
condition in a system creates a problem, it shall be reflected in the calculation of the
transfer limit of the tie-line.
2. CONTINGENCIES….
Steady State:
Loss of any transmission line having an impact on the loading of the tie-lines
System intact:
3. RESULT ANALYSIS….
The results of the above studies must show the following criteria are met:
Normal operation:
The voltage at the following power stations must remain within the following
bands:
For a N-1 criteria the voltage at Kariba South must remain within the following
band:
Following the first swing, the busbar voltages on the Interconnection should not
be lower than the values specified in the table below for more than 100 msec:
400 KV -10 %
330 KV -10%
275 KV -10%
220 KV -10%
132 KV -10%
4. GENERAL….
The system to be studied should be clearly defined as well as the year to study;
The transfer limits should be studied for peak and minimum load conditions;
During emergencies, the Control Centres can operate the lines at a higher loading than
the transfer limits. During such conditions, the Control Centres must realize that they
could experience severe voltage dips, should a fault occur. These risks must be
accepted if transfer limits are exceeded.
A report has to be issued by the study group and evaluated by the OSC. The transfer
limits shall be updated once the OSC accepts new results and recommendations.
---oOo---
A. INTRODUCTION….
Uniform accounting practices will help to identify and eliminate errors. They will also
highlight poor control performances that contribute to the accumulation of inadvertent
interchanges.
These practices outline the methods and procedures required to reconcile energy
accounting and inadvertent interchange balances.
The Control Areas must adhere to the Operating Guidelines to properly monitor and
account for inadvertent interchanges.
B. SCHEDULES….
All hourly schedules and schedule changes shall be agreed to between the relevant
Control Areas prior to implementation. The Agreement shall cover magnitude, rate of
change and common starting time.
C. ACCOUNTING PROCEDURES….
1. Daily accounting- Each Control Area shall agree with adjacent Control Areas upon
the following quantities for each hour and on a daily basis:
2. Adjacent Control Areas shall agree upon the differences described above
and shall assign the relevant corrections to the on-peak and off-peak hours.
---oOo---
Criteria:
Each Control Area shall operate its active power resources so as to ensure a level of
operating reserve sufficient to account for such considerations as errors in
forecasting, generation or transmission equipment unavailability, loss of generating
units, forced outage rates, maintenance schedules, regulating requirements and load
diversity between Control Areas. Following the loss of load or of active power
resources, the Control Area shall take appropriate steps to reduce its Area Control
Error to zero within ten (10) minutes and to protect itself against the next
contingency.
The Operating Sub-Committee shall specify the operating reserve policy in terms of:
1. Requirements:
The System Controller shall be kept informed of all generation and transmission resources
available for use.
The System Controller shall have all the necessary information, including weather forecasts
and past load patterns, to predict the system’s near-term load pattern.
An additional amount of Operating Reserve sufficient to reduce the Area Control Error to
zero within ten (10) minutes following the loss of generating capacity which would result
from the most severe single contingency. Interruptible load may be included in Quick
Reserve provided that it can be interrupted in less than ten, (10) minutes and remain
disconnected until replacement generation can be brought to service.
In order to ensure compliance with Clause 1.3 above, the Operating Reserve shall be
sufficiently dispersed throughout the system, shall take into account the effective
contribution of unused generating capacity in an emergency, the time required for these
contributions to be effective, the transmission limitations at the time and all the local
requirements that may exist.
All Operating Members shall from time to time, review the adequacy of their Operating
Reserve policy by evaluating the impact of all relevant contingencies.
The above shall establish the minimum amount of Operating Reserve that
each Operating Member will be obliged to carry and indicates the level below
which a Member is at fault.
Each Member shall declare its annual peak demand and its largest unit that is
in service, everytime these values change.
where:
-Page 42 -
Recommendations:
The effect of station service generators on area security should be considered before
their shut down for economic reasons.
Criteria:
Each Control Area shall supply its own reactive power requirements and shall keep
appropriate reserves to maintain voltage levels during a contingency. This includes the
Control Area’s share of the reactive power required by the interconnections between
-Page 43 -
Members’ Systems. The reserves shall be located electrically where they can be applied
effectively and timeously when a contingency occurs.
Control Areas shall co-ordinate the use of voltage control equipment to maintain
transmission voltages and reactive power flows at levels consistent with the Interconnection
security.
Requirements:
1. The System Controller shall receive all the necessary information on available
generation and flows of reactive power.
3. Reactive energy sources shall be dispersed and located in such a way that they can
be applied effectively and quickly when contingencies occur.
4. Prompt action shall be taken to restore reactive energy resources if these drop below
acceptable levels.
5. The System Controller shall take all necessary actions, including load reductions, to
prevent voltage collapse when reactive energy sources are insufficient.
Recommendations:
C TRANSMISSION OPERATION….
Criteria:
When line loadings, equipment loadings or voltage levels deviate from the ratings or
are excepted to exceed emergency ratings following a contingency, with the result
that the reliability of the Interconnection is at risk, Control Areas experiencing or
causing the condition shall take immediate steps to remedy the situation. These
steps include informing other Systems, adjusting generation, changing schedules
-Page 44 -
between Control Areas, initiating load relief measures and taking every action that
may be required.
Requirements:
1. System Controllers shall monitor all critical transmission system loadings and
shall check that voltage limits and emergency ratings are not exceeded.
2. Transmission Planned Outages shall be co-ordinated with other Systems that are
likely to be affected.
5. Each Control Area shall use appropriate, up-to-date studies as reference for
establishing transmission operation procedures.
Recommendations:
D. RELAY CO-ORDINATION….
Criteria:
Systems and Control Areas shall co-ordinate the application, and maintenance of
protective relays. They shall develop criteria which will enhance system reliability
with minimum adverse effects on the Interconnection.
System Controllers shall be familiar with the intended operation of protective relays
and shall have access to the information relating to the operation of these relays.
Requirements:
-Page 45 -
2. System Controllers shall be familiar with the purpose, operation and limitations of
protection schemes.
4. All new protective schemes and all modifications to existing protective schemes
shall be co-ordinated between neighbouring Systems if these neighbouring
Systems are affected by the change.
7. The Control Centres shall monitor the status of every Special Protection System
(SPS) and notify all affected Systems of each status change.
Recommendations:
High speed relays, high speed circuit breakers and automatic reclosing
should be used where studies indicate their application will enhance
stability margins. Single pole tripping and reclosing may be appropriate
on some lines.
-Page 46 -
The adequacy of the communication channels used for line and other
protections, should be assessed periodically. Automated channel
monitoring and failure alarms should be provided for protection
communication channels if such failure can cause loss of generation,
loss of load or cascading outages.
The Control Centres shall monitor the status of each Special Protection System (SPS) and
notify all affected Members of any change in status.
SPS should be designed for periodic testing without affecting the integrity of the protected
System. They should normally achieve at least the same level of reliability as that provided
by other protection schemes.
SPS should be designed with inherent security to minimize the probability of mal-operation,
even with the failure of a primary component.
Each SPS should be reviewed periodically to determine if it is still required and if it will still
perform the intended functions. Seasonal changes in the SPS or its relay settings and the
concerned Member shall then inform the other Members about the new settings.
Every time an SPS operates, the incident should be reviewed and analysed for correctness.
Background
Special Protection Systems also known as Remedial Action Schemes, are relay
configurations designed to perform functions other than isolation of electrical faults.
These schemes are usually installed to maximize transfer capability. However, they
may be used to maintain system or generator stability or to control active and
reactive power flows on critical components immediately following a disturbance, or
to split a system or open an interconnection at preplanned locations to prevent
-Page 48 -
cascading. The general design objective for any SPS shall be to perform its intended
function(s) in a dependable manner while refraining from unnecessary operation. An
SPS can expose a System to a greater reliability risk. The integrity of a whole
System may depend on its correct operation.
Criteria:
Each System and Control Area shall continuously monitor those parameters (such as
MW, Flow, MVAr flow, frequency, voltage, phase angle, etc.), internal and external to
its System or Control Area, that indicate the condition of the Interconnection.
The Control Centres shall be provided with adequate equipment to accomplish this
objective. Measuring instruments of suitable range and reliability for both normal and
emergency conditions shall be installed and maintained at strategic points.
Requirements:
2. Each Control Area shall use sufficient instruments of suitable range, accuracy
and sampling rate to ensure accurate and timely monitoring of the
Interconnection under normal and emergency situations.
3. Control Centres shall monitor transmission line status, MW and MVAr flows,
voltages, Load Transfer Capability (LTC), settings and status of rotating and
static reactive resources.
12. Voltage schedules shall be co-ordinated from a central location within each
Control Area and co-ordinated with adjacent Control Areas.
13. All tie-line SCADA metering between Control Areas, shall be available to all
the Operation Members’ Control Centres.
Background:
The System Controllers must have information available to them at all times so that
they can accurately assess the status of the system under normal operating
conditions, make the correct decisions following the occurrence of a contingency and
rapidly restore system integrity after a disturbance.
Criteria
Requirements:
Recommendations:
Criteria:
Requirements:
1. Major operating problems that could affect other Systems shall be reported
as soon as possible to neighbouring Systems. These could include loss of
generation, of load or of facilities
Recommendations:
Background :
H. MAINTENANCE CO-ORDINATION….
Criteria
Requirements:
1. Planned generator and transmission Outages that may affect the reliability
of Interconnected operations, shall be planned and co-ordinated
(notification of cancellation at least twenty-four (24) hours in advance)
between the affected Systems and Control Areas. Special attention shall
be given to the results of pertinent studies. A Planned Outage shall be
advised at least two (2) weeks in advance and confirmed in writing. Each
Control Area must be advised of any return of equipment to service.
---oOo--
Criteria:
its generation and interchange schedules to its load without regard to cost , to avoid
excessive use of the assistance provided by interconnection frequency bias. The
reserve inherent to frequency deviation is intended to be used only as a temporary
source of emergency energy and is to be promptly restored to enable the
interconnected Systems to withstand the next contingency. A Control Area unable to
balance its generation and interchange schedules to its load shall shed sufficient
load to ensure that its Area Control Error (ACE) is corrected.
Requirements:
2.2 The deficient System shall schedule all available assistance that is
required with as much advance notice as possible.
2.3 The deficient System shall use the assistance provided by the frequency
bias only for the time needed to accomplish the following:
3. If all other steps prove inadequate to remedy the situation, the deficient
system shall take immediate action which includes, but is not limited, to the
following:
-Page 55 -
Recommendations:
2.3 Identify and address the problems that could delay the restoration of the
System.
Criteria:
Requirements:
C. LOAD SHEDDING….
Criteria:
After taking all other remedial steps, a System or Control Area whose integrity is
In jeopardy due to insufficient generation or transmission capacity shall shed
customers rather than risk an uncontrolled failure of components making up the
Interconnection.
Requirements:
generator tripping or isolation, shunt capacitor tripping, and other automatic actions
which occur during abnomal frequency or voltage conditions.
2. Automatic load shedding shall be in steps and initiated by one or more of the
following parameters: frequency, rate of frequency decay, voltage level, rate of
voltage decay or power flow. See table in Appendix III.A “Automatic Under
frequency Load Shedding in the SAPP”.
Recommendations:
1. Voltage reduction for load relief should be restored to in the distribution networks.
Voltage reductions on the sub-transmission or transmission system may be
effective in reducing load; however, voltage reductions should not be restored to on
the high voltage transmission system unless the system has been isolated from the
Interconnection.
D. SYSTEM RESTORATION….
Criteria:
After a system collapse, restoration shall begin as soon as possible, provided it can
proceed in an orderly and secure manner. Systems and Control Areas shall co-
ordinate their restoration actions. Priority shall be given to the auxiliary supply of
power stations and of transmission sub-stations. Even though the restoration is to be
expeditious, Control Centres shall avoid premature action to prevent another
collapse of the System.
Requirements:
Each Control Area shall identify interconnections with adjacent Control Areas
that may be used to restore power and obtain agreement for their use.
2. Following a disturbance in which one or more areas are isolated, steps shall
immediately be taken to return the system to normal:
The Control Centre shall determine the extent and condition of the isolated
area(s).
The System Controller shall then take the necessary action to restore system
frequency to normal, including adjusting generation, placing additional
generators on line, or shedding load.
When voltage, frequency and phrase angle permit, the Control Centre may re-
synchronise the isolated area(s) with the surrounding area(s), properly
notifying adjacent Systems of the size of the area being reconnected and the
capacity of transmission lines effecting the reconnection.
Criteria:
Requirements:
-Page 59 -
1. A System shall inform neighbouring Systems and Control Areas within the
SAPP, through pre-determined communication channels, whenever the
following situations are anticipated or arise:
The System is unable to purchase capacity to meet its load and reserve
requirements on a day-ahead basis or at the start of an hour.
The System’s line loadings and voltage/reactive power levels are such
that a single contingency could threaten the reliability of the
Interconnection.
Criteria:
Because the facilities of each System may be vital to the secure operation of the
Pool, Systems and Control Areas shall make every effort to secure the
Interconnection. However, if a System or Control Area establishes that it is
endangered by remaining interconnected, it may take such action as it deems
necessary to protect its network.
Requirements:
Recommendations:
Criteria:
Each Control Area shall have a plan to continue its operations in the event that its
Control Centre becomes inoperable.
Recommendations:
--oOo--
Mandatory
ZESA Mandatory
BPC Mandatory
SNEL
EDM No scheme
LEC No scheme
SEB No scheme
Criteria:
-Page 63 -
Each System Controller shall be delegated sufficient status and authority to take any
action necessary to ensure that the System or Control Area for which he is
responsible, is operated in a stable and reliable manner.
Requirements:
1. Each Control Area and Control Centre shall provide its System Controllers
with a clear definition of their authority and responsibilities.
2. Each Control Area and Control Centre shall advise the other Control Centres
of the authority and responsibilities of its own System Controllers.
B. SELECTION….
Criteria:
Each Control Centre Area shall selects its System Controllers using criteria likely to
promote reliable and safe operation.
Recommendations:
B. SELECTION (CONTD)….
Physical examination.
C. TRAINING….
Criteria:
Each System and/or Control Area shall provide its personnel with training that is
designed to promote reliable and safe operation.
Requirements:
1. Each Control Area shall provide its System Controllers with guidelines to
resolve those problems that can be caused by realistic contingencies and
known restrictions on equipment.
Recommendations:
1. Each System should implement a training program for its Control Centre
personnel.
C. TRAINING (CONTD)….
3. Each System should consider the list of items in Appendix IV. A for inclusion in
their training program.
-Page 65 -
Background:
Criteria:
The operating personnel of each System and Control Area shall be responsive to
requests for information emanating from other Systems or Control Areas and from
the Operating Sub-Committee.
Requirements:
1. The operating personnel of Systems and Control Areas shall be aware of the
operating information required by other Systems or Control Areas and by the
Operating Sub-Committee.
Background:
-Page 66 -
---oOo---
This Appendix lists the items that should be included in a training course for System
Controllers.
-Page 67 -
A. NORMAL OPERATIONS….
Generation
Transmission
Transformation
Loads and effect on system
Phase angle
Phase shifting transformers
Reactors
Capacitors
Parallel flows
Transmission
Interconnections
2. Voltage Control:
Load characteristics
Standards
Schedules
Cause for voltage deviations
Generation excitation
Transformer taps
Reactive sources e.g
Generators
Synchronous condensers
Capacitors
Reactors
Static VAr compensators
Operating Reserve
-Page 68 -
Dispatching techniques
Generators AGC’s and Governors
Area Control Error (ACE)
Interchange control
Inadvertent interchange
Special operating programme(s)
4. Economic Operation:
Dispatching techniques
Heat rates
Fuel costs
Start-up and shutdown costs
Pumped storage costs
Unit commitment
Economic loading
Effects of Transmission losses
Reactive flows
Utilisation of limited energy capacity
Pumped storage capacity
Incremental and decremental costs
Accounting procedures
Operating Manual
Operating Guidelines
Control Performance Criteria
Reliability Criteria for Interconnected Systems Operation
Contingency assessment.
Generator outages
Transmission lines outages
Transformer outages
Busbar Outages
Combination of above
Outages of reactive energy sources
Thermal
-Page 69 -
Voltage / Reactive
Relay
Stability
6 Operating considerations:
Generation
Transmission
Substation
Protection
B. ABNORMAL OPERATIONS….
Transient stability
Oscillations
Relay action
Control-initiated swings
Causes of disturbances
Special Protection System (SPS)
Governor response
Exciter response
Relays and breakers
Under-frequency relays:
Metering
Automatic controls:
Plant
AGC
Voltage
Generator and load tripping
System separation
Loss of load
Breaker operation
Line fault
Generator trip
Frequency deviation
Interchange deviation
Voltage level
System separation
Communication with power stations, substations and other utilities
Parallel flows
4. Remedial Action:
Islanding
Load shedding
Generator dropping / trips
Shifting generation
Switching generation
Isolated system operation
High-and-low –frequency operation
High-and-low-voltage operation
5. Recovery:
Sectionalising
Load pickup priorities and problems
Synchronising within a System and at the Points of Interconnection
C. COMMUNICATIONS….
1. Facilities Available:
2. Information Exchange:
Standard terminology
Neighbouring Systems
Power Plants
Substations
Management
News Media
Governmental agencies
2. Philosophy of Operation:
Benefits
Obligations
Responsibilities
Authority
Frequency
-Page 72 -
Interchanges
Reserves
Mutual assistance
Pooling arrangements
Communications
4. Abnormal Operations:
Responsibilities
Actions required
1. Equipment:
Man-machine interface
Supervisory control
Data acquisition
Fail over and restart
Economic dispatch
AGC
Unit commitment
Operator load flow
Contingency analysis
Corrective strategies
State estimation
Interchange accounting
-Page 73 -
Transmission evaluation
Automated billing
F. SUPERVISORY SKILLS….
1. Personnel supervision
2. On-the-job training, preparation of
3. Verbal communication
4. Decision - making
5. Influence of stress
---oOo---
A. NORMAL OPERATIONS….
Criteria:
-Page 74 -
Each Control Area shall plan its future operations in-co-ordination with other affected
Control Areas to ensure that normal operation on the Interconnection proceed in an
orderly and efficient manner.
Requirements:
1. Each Control Area shall schedule its plant and interchanges so as to meet the
daily load pattern and the changes in load characteristics.
2. The results of studies dealing with the operation of the System shall be
available to System Controllers.
Recommendations:
5. Each Control Area should determine the power transfer capabilities of its
transmission system and identify potential problems by conducting simulation
studies.
-Page 75 -
Thermal and stability limits, previous short-and long term loading, voltage
limits and seasonal (temperature) characteristics should be considered
when determining the capability of transmission facilities.
6. Computer models and data utilized for analysis and planning system operations
should be updated and replaced as necessary to ensure that they can
accurately and adequately represent the System. The same software and
computer platforms should be used throughout the SAPP. (It is recommended to
move away from main frame computers to personal computers).
7. Neighbouring systems should use uniform line identifiers and ratings when
referring to transmission facilities being part of an interconnected network.
Criteria:
Requirements:
Recommendations:
Criteria:
-Page 76 -
Each System and Control Area shall maintain comprehensive and co-ordinated
procedures to deal with long-term capacity or energy deficiencies.
Recommendations:
1. The SAPP should develop capacity and energy emergency plans that will
enable it to reduce to the fullest extent possible, the impact of a capacity of
energy shortage on its customers.
4. The energy emergency plan should include or consider the following items:
Appeals to the public through the media for voluntary load reductions
and energy conservation including educational messages on how to
accomplish such load reduction and conservation.
A mandatory load curtailment plan will be used as a last resort. This plan
should preserve the loads essential to the health, safety, and welfare of
the community.
A mandatory load curtailment plan will be used as a last resort. This plan
should preserve the loads essential to the health, safety, and welfare of
the community.
Criteria:
Each System and Control Area shall establish a program of manual and automatic
load shedding which is designed to arrest frequency or voltage decays, or extreme
power flows that could result in an uncontrolled failure of components of the
Interconnection. The program shall be co-ordinated throughout the Interconnection to
prevent excessive transmission loadings and voltage deviations.
Requirements:
1. Each System shall establish plans for automatic load shedding and System
Controllers shall have authority to implement manual load shedding when
necessary.
D. LOAD SHEDDING….
Recommendations:
4. Each System and Control Area should consider isolating its generators to protect
them from extended abnormal voltage and frequency conditions. If feasible,
generators should be separated carrying their own auxiliary load.
E. SYSTEM RESTORATION….
Criteria:
-Page 80 -
Each System and Control Area shall develop and periodically update a plan to
restore its electric network in a stable and orderly manner in the event of a partial or
total shutdown. This plan shall be co-ordinated with other Control Areas to ensure a
consistent restoration of the Interconnection.
A reliable and adequate source of black start power shall be provided. Where these
sources are remote from the generating units, instructions shall be issued to expedite
availability. Steps to restore generation, shall be verified by real life testing whenever
possible.
Requirements:
1. Each System and Control Area shall establish a restoration plan with adequate
operating instructions and procedures to cover emergency conditions, including
the loss of vital telecommunication channels.
Recommendations:
4. Load shed during a disturbance should be restored only when doing so will have
an adverse effect on the System or the Interconnection.
Remove shunt capacitors, switch-in shunt reactors or add small blocks of load
to prevent excessive Ferranti effect when energizing long transmission lines or
high-voltage cables at the end of a long, lightly-loaded system.
8. The Control Centres should know the re-synchronising points and procedures.
Procedures should provide for alternative courses of action when there is a lack of
information or loss of communication that would affect re-synchronising.
9. Each power station should have written procedures for orderly start-up and
shutdown of the generating units.
Exercises should be held periodically to ensure that plant operators are familiar
with the procedures.
10. Each power station should have a source of emergency power to reduce the time
required for restarting. Hydro-electric power stations should have built-in restarting
facilities.
11. Back-up voice telecommunication facilities, including emergency power supplies and
alternative telecommunications channels should be provided to ensure co-ordinated
control of operations during the restoration process.
---oOo---
A FACILITIES….
Criteria
Each System and Control Area shall be equipped with adequate and reliable
telecommunication facilities internally and with other Systems and Control Areas to
ensure the exchange of information necessary to maintain the reliability of the
Interconnection. When possible, redundant facilities using alternative routes and
medium, shall be provided.
Requirements:
Background:
Criteria:
Requirements:
C. LOSS OF TELECOMMUNICATION….
Criteria:
Requirements:
Each Control Area shall have operating instructions and procedures to enable
continued operations during the loss of telecommunication facilities.
---oOo---
INTRODUCTION….
-Page 85 -
These Operating Guidelines shall be based on good logic, scientific reasoning and
operating experience. The Guidelines shall be correct, practical and highly
considered by all System Controllers. System Controllers shall contribute to the
updates and development of the Guidelines to ensure a practical operator’s
perspective.
The operating policies embodied in the Guidelines shall leave an adequate margin
for contingencies. The Directives of the Operating Sub-Committee shall be focused
towards interconnected system operations and shall set the pattern for future SAPP
and system policies.
REVISION PROCEDURES….
1. Any SAPP Member can recommend revisions to the Guidelines through its
representative at the Operating Sub-Committee.
The proposal for revision must be in writing, and must consider the
content of the other Guidelines to ensure compatibility and consistency.
The language of the revision shall agree with the purpose. That is,
Criteria and Requirements are obligations, while Recommendations and
Background statements simply describe good operating practices.
3. The Sub-Committee may vote on the revision directly, or refer it to one or more
Work Groups for review or improvement.
4. If the revision is referred to a Work Group and the Work Group believes a new or
revised Guidelines is needed, it will prepare a draft for the Operating Sub-
Committee’s consideration.
5. If the Work Group rejects the proposed revision, the Operating Member can
appeal directly to the Operating Sub- Committee through its representative.
SIGNATORIES….
-Page 87 -
IN WITNESS whereof the said Operating Members have here to set their hands:
OF___________________________________1996
OF___________________________________1996
OF___________________________________1996
OF___________________________________1996
OF___________________________________1996
OF___________________________________1996
OF___________________________________1996
OF___________________________________1996
OF___________________________________1996
OF___________________________________1996
OF___________________________________1996
OF___________________________________1996
--oOo--
-Page 91 -
APPENDIX 1….
This document provides the Survey Co-ordinator of the SAPP Control Area Performance
Criteria with specific instructions to organize and report on the survey using forms contained
in the document as Tables A, B and C of this document.
The Control Area may use one of two methods for reporting its control performance:
With the first method, the Control Area measures its compliance to A1 and A2 criteria for a
twenty-four (24) hour period selected at random each month by the Performance Sub-
Committee Chairperson. With the second method, the Control Area continuously monitors
its compliance to A1 and A2 criteria and reports its result at the end of each month. This
training document explains both methods of reporting in detail.
The basis for the calculation of control performance of a Control Area against the
Control Performance Criteria (CPC) is the Area Control Error (ACE). The value of
ACE to be used throughout the calculation should reflect an actual, unfiltered
quantity as displayed to the System Operator in the control room, but obviously
wrong values such as “spikes” due to telemetering error or other spurious influence
should be excluded from the calculation.
There are two (2) measures of the performance of ACE: they are referred to as A1
(Zero Crossing) and A2 (Ld Compliance as defined in Section 2.1.2). These
measures provide the System Operator with a convenient visual indication of how
well the Control Area has kept to minimum accumulation of un–intentional
inadvertent interchange.
Normal Conditions:
The A1 and A2 criteria are the control performance standards for normal
operating conditions.
A2 Criteria – Ld Compliance
The A2 Criterion requires that the average ACE for each of the twelve
(12) Intervals of six (6) minutes making up the hour, be within specific
limits, referred to as L d. This criterion complements the A1 Criterion
by establishing an upper bound for the average value of a Control
Area’ s ACE.
Ld Calculation:
Ld = (0,025)L + 5 MW
Disturbance Conditions:
During disturbance, controls cannot maintain ACE within the Criteria for normal
condition. This requires that a disturbance condition be defined. A disturbance is
said to have occurred when a sampled value of ACE exceeds the limit called L m
due to a sudden loss of generation or load. The value of Lm has been selected
as a function of Ld specifically.
Lm = 3Ld
Normal load and generation excursions (e.g. pumped storage hydro, arc furnace,
rolling steel mill, etc.) that cause the ACE to exceed L m are not included in the
definition of disturbance condition.
When a disturbance condition arises, other criteria apply in addition to the A1 and
A2 Criteria explained earlier.
The B1 Criteria requires ACE to return to zero within ten (10) minutes,
following the start of a disturbance. Following the step change in ACE
attributed to a disturbance (as defined above), the ACE must recover and
achieve a zero reading in period not to exceed ten (10) minutes. Every
system should maintain sufficient reserve capability to restore control
completely and return to normal operation within ten (10) minutes.
The B2 Criteria requires that the ACE stops increasing and begins to
return to zero within one (1) minute following the start of the disturbance
(as defined above) ACE is permitted to evolve in the same direction as
the step change for a period not exceeding one (1) minute. A system
should maintain sufficient reserve capability such that after the initial
allowance of one (1) minute ACE will begin its recovery and tend towards
zero.
-Page 94 -
3. CALCULATION OF CRITERIA…
3.1 A1 Criterion:
And Tal is the maximum number of non-compliant ten (10) intervals recorded
during the reporting period.
Once the ACE recording is initiated, if a ten (10) minute interval expires
before conditions arise which would result in the termination of the
timing interval, an incident of non-compliance is recorded. The incident
is recorded in the hour during which the interval expired. The total
number of such incidents of non-compliance recorded during a reporting
period is equal to Tal.
3.1.3 Termination conditions for the ten (10) minute timing interval.
In practice, there are five (5) conditions which can arise that would
cause the current ten (10) minute timing interval to terminate and a new
ten (10) minute interval to initiate. As will be explained, only one of
these five (5) conditions, namely the expiration of the ten (10) minute
timing interval, represent an incident of non-compliance.
3.2 A2 Criteria:
Compliance with the A2 Criteria requires that the absolute value of the
algebraic mean of the ACE signal (d 2) for a ten (10) minute period does not
exceed the Control Area’s allowance limit, Ld (see Section 2.1.2.1). As was true
for the A1 Criterion, to calculate A2, it is necessary to identify the number of
incidents of non-compliance.
Since the A2 Criteria requires the ACE be averaged over a discrete time
period, the same factors that limit Ta2 will limit Tm. The calculation to Tm and
Ta2, must be discussed jointly.
Each twenty-four (24) hour period beginning at 00:00 and ending at 24:00
contains 144 discrete ten (10) minute periods.
Each hour (HH) contains six (6) discrete ten (10) minute periods, where
period 1 spans HH:00 – HH:10 , period 2 spans HH:10 – HH:20, period 3
spans HH:20 -HH:30, period 4 spans HH:30 – HH:40, period 5 spans HH:40
– HH:50, period 6 spans HH:50 –(HH+1) :00. For a system that samples ACE
every four (4) seconds, for example, the average ACE over a ten (10) minute
period would be defined by the algebraic sum of 150 ACE samples (starting
at HH:00:04 and ending at HH:10:00) divided by 150. Systems calculating the
A2 Criterion from the manual review of an ACE chart must sum the products
of visual readings and their respective length and divide that sum by ten (10)
minutes. Consider the example where ACE is visually perceived to average
10 MW for 1 minute, -5 MW for the next 1.5 minutes, -10 MW for the next two
(2) minutes, -15 MW for the next three (3) minutes, and –5 MW for the last
2,5 minutes. The ten (10) minute algebraic mean would equal:
[(10) (1)] + [(-5) (1.5)]+ [(-10)(2)] + [(-15) (3)] + [(-5) (2.5)] = -7.5 MW
_____________________________________________
10
Two (2) conditions may arise which impact the normal calculation of Tm and
Ta2. These conditions are the occurrence of system disturbance as defined in
Section 2.2 and a sustained interruption in the recording of ACE.
For each such disturbance in a twenty-four (24) hour period, the discrete ten
(10) minute interval in which the disturbance occurred and the succeeding ten
(10) minute period interval are omitted from the calculation of A2. Functionally,
both ten (10) minute periods are eliminated from the calculation, thus Tm is
reduced by two (2) to normalize the percentage calculation of A2. Disturbance
conditions are not omitted in the A2 calculation if monthly average reporting is
used.
In order to ensure that the average ACE calculated for any ten (10) minute
interval is representative of that ten (10) minute interval, it is necessary that
ACE remain uninterrupted for a period equal to or greater than five (5) minutes
during that ten (10) minute interval. Should a sustained interruption in the
recording for ACE due to loss of telemetering or computer unavailability result
in ten (10) minute interval not containing a consecutive five (5) minute sampling
of ACE, that ten (10) minute interval is omitted from the calculation of A2.
Functionally, the ten (10) minute interval is assumed complaint and Tm is
reduced by one to normalize the percentage calculation of A2.
-Page 99 -
3.3 Examples:
1. Start of new day- Note that at 00:00, even though ACE equals -12 MW, a new
ten (10) minute timing interval is initiated.
2. Zero crossing (Criteria A1) violation - Note that at 00:12, even though ACE
equals 2 MW, a new ten (10) minute timing interval is initiated. Ten (10)
minutes has expired since the last zero crossing at 00:02 indication a
violation to be recorded in the hour ending 01: 00.
3. Interruption in ACE recording - Note that a ten (10) minute timing interval was
initiated at 23:34 and 23:43 even though ACE equals –2.5 MW in both
instances. According to the chart, there was a zero crossing at 23:32 and
again at 23:47. Although fifteen (15) minutes had expired since the last zero
crossing, a violation is not recorded because the time during which the
interruption of ACE recording occurred is not included in the determination of
the A1 Criterion.
-Page 100 -
Other items are of interest in Figure II. Note the violation that spans the time from
06:25 to 07:02. This violation is recorded in the hour in which the ten (10) minute
timing interval expired. Note also the violation that spans the time 07:20 to 07:30.
ACE reaches to –40 MW during this period and the absolute value is well beyond the
Ld, this period does not represent a disturbance condition to this value of ACE. Since
a disturbance is not recorded during this period and since ACE has not crossed zero,
the ten (10) minute timing interval expire at 07:30 and thus an A1 violation is
recorded.
-Page 101 -
Note that the fifth interval (01:40 – 01:50) has recorded a violation because the
absolute value of the algebraic mean of 15,7 MW exceeds the L d of 10 MW. Since
disturbance conditions are included in the A2 calculation for monthly average
reporting, violations are also recorded for the second and third intervals (01:10 –
01:20 and 01:20 - 01:30) if monthly average reporting is used. For Control Areas
using twenty - four (24) reporting, the algebraic means would not be calculated for
these two (2) intervals. This elimination of the second and third interval from further
Criterion A2 analysis for twenty-four (24) hour reporting is due to the disturbance
condition that occurred at 01:15. The ten (10) minute allotment for the successful
recovery from a disturbance spanned both intervals. For this hour therefore, there
was one (1) violation out of four (4) intervals for twenty-four (24) hour reporting and
three (3) violations out of six (6) intervals for monthly average reporting.
-Page 102 -
Note the pattern of the disturbance condition which began at 01:15. During this
disturbance, both the Criteria B1 and B2 were violated. ACE did not begin to trend to
zero until nearly two (2) minutes after occurrence (violating Criteria B2) and ACE was
not restored to zero until 01:27 (twelve (12) minute interval which violates Criteria
B1).
4. SURVEY PROCEDURES….
Twenty-four (24) hour surveys will be conducted for periods selected by the
Chairman of the Performance Sub-Committee, on his own motion, or in
response to specific request from members of the Sub-Committee.
Each Control Area shall return one completed copy of Table A to the
Sub-Committee member representing his Region.
From a manual review of the ACE chart or using data derived from digital
processing of the ACE signal, a representative from each Control Area will
complete Table A “SAPP Control Performance Criteria Survey - twenty-four (24)
Hour”.
MAX/HR For the hour in which the most violations have occurred
for each criterion, enter the respective number of violations on this
row.
MIN/HR For the hour in which the fewest violations have occurred
for each Criterion, enter the respective number of violations on
this row.
Review for each hour ten (10) minute algebraic means of ACE
(d2) calculated to identify A2 Criterion violations. Consider only
those hours where all six (6) periods are included in the analysis,
Sum the absolute values of the six algebraic means (ignore
signs), / d2 / and identify those hours with the least sum and
highest sum. Those hours are the BEST and POOREST hours,
respectively. Record for these respective hours, the hour, the
absolute value of the six (6) algebraic means / d2 / for the hour,
the TOTAL of the six (6) absolute values, and by dividing the
TOTAL by six (6) record the average absolute value.
-Page 105 -
Using data derived from digital processing of the ACE signal, a representative
from each Control Area will complete Table B. “ SAPP Control Area
Performance Criteria Survey – Monthly Average “.
For each of the twenty- four (24) hourly periods of a day, report the
monthly total number, of A1 Criterion violations, A2 Criterion
violations, and the number of unavailable ten (10) minute intervals.
For example, if there was one violation for hour ending 01:00 every
day of a thirty –one (31) day month, a thirty-one (31) would be entered
for the 01:00 hourly period.
Total sum the number of violations and unavailable ten (10) minute
intervals recorded on the hourly tables and enter the sums on this row
for each column.
4.5.1 Review Table A and Table B data received from each Control Area in
the Region for uniformity, completeness, and compliance to the
instructions. Iterate with Control Area survey co-ordinators where
necessary.
4.5.2 Transfer the data from each Table A and Table B to the appropriate
columns on Table C. Review the comments submitted and if
significant, identify them with the appropriate Control Areas.
The SAPP staff will combine the regional reports into a single summary
report and send one copy to each Sub-Committee member.
---oOo---