Revised Geotechnical Report PDF
Revised Geotechnical Report PDF
P
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
TABLE OF CONTENTS
Page
1. INTRODUCTION .................................................................................................. 1
2.1 Drilling............................................................................................................ 5
2.2 Drilling Equipment and Operation.................................................................. 5
2.3 Testing and Sampling...................................................................................... 6
2.3.1 Field Testing .................................................................................. 6
2.3.2 Sampling ....................................................................................... 8
2.3.3 Laboratory Testing ........................................................................ 8
5. CONCLUSION ...................................................................................................... 19
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
List of Tables
List of Figures
Appendices
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
BH - Boreholes
BS - British Standards
m - Meters
kPa - Kilo-Pascal (kN/m2)
GWL - Ground water level
N-value - Number of blows for 300mm penetration
NMC - Natural moisture content
LL - Liquid limit
PI - Plasticity index
PL - Plastic limit
UCSC - Unified soil classification system
FS - Free Swell
D - Disturbed sample
UDS - Undisturbed sample
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
1. INTRODUCTION
This report presents the results of the geotechnical investigation work for
building project which is located in Oromia Liyu zone, Legetafo. The proposed
development consists of the construction of two story building with ground floor
(G+2).
The field work of the geotechnical site investigation was conducted from
December 31, 2017 to January 02, 2018.
The site investigation has been carried out by drilling three exploratory bore
holes to a depth of 10.00m (BH-1 and BH-2) and 12.00m (BH-3) at the proposed
locations shown in the attached site plan (Appendix 3). Laboratory tests were
performed on selected soil samples to identify and determine their properties.
The results of laboratory tests are included in Appendix 4 of this report.
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
1.4 Location
The project site is located in Oromia Region, Legetfo. Based on the area to be
covered by structure; three boreholes were selected for the investigation. The
project site is generally characterized by nearly flat topographic feature.
The co-ordinates of the boreholes measured using hand-held GPS (UTM Adindan
Datum), are tabulated as follows
Addis Ababa city is situated in the western margin of the Main Ethiopian Rift and
represents a transition zone between the Ethiopian Plateau and the rift with
poorly defined escarpment.
Addis Ababa basalt extensively crops out along Akaki, Kebena, and Dukem rivers
at the east to southeastern part of Addis Ababa, and represents the oldest unit
of the area. It consists of essentially sub-horizontal lava flows with thickness
ranging from few meters up to 20m. Maximum exposed thickness was found
east of Addis Ababa, along the Kebena River. Addis Ababa basalt is
predominantly constituted by alkaline and olivine basalts with three main
textural attributes, that is, porphyritic, aphyric, and sub-aphyric.
Addis Ababa Ignimbrite is exposed close to Addis Ababa along the Akaki and
Kebena rivers. It overlies the Addis Ababa basalt and locally covers the products
of the composite central volcanoes of Wechecha and Furi. The sequence is
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
Central volcanoes unit includes the Yerer volcano and the product of the two
composite volcanoes wechecha and Furi west and southeast of Addis Ababa,
respectively. Wechecha and Furi volcanoes are two large edifices composed by
predominant trachyte with minor pyroclastics. Yerer represents the largest
volcanic edifice in the region, with a relief of 1000m from the plain and 14km
wide along east-west direction. Products mainly consist of trachytes, even if
pyroclastics are widespread mainly in the central part eastern sector. The highest
part of Yerer volcano was affected by a more recent volcanic activity that
produces spatter cones and associated basalt.
Akaki unit crops out east of Addis Ababa and consists of scoria and spatter cones
with associated tabular lava flows and phreato- magmatic deposits. Alluvial
deposits covering these units consists of regolith, reddish brown soils, talus and
alluvium with maximum thickness of about two meters.
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
The upper most layer of the project site is backfill material that has an average
thickness of 50cm. Beneath a backfill material a residual soil found which is
characterized by stiff to very stiff, light gray, high plastic silty CLAY/ clayey SILT
(Expansive) soil and extends up to a depth of 8.30m in BH-1 and 9.10m in BH-
2 and BH-3 from existing ground level of the project site. Beneath the expansive
soil layer is extremely weak, variegated color, moderately weathered TUFF rock
layer and extends up to end of investigation depth in all boreholes.
The detailed geological strata are presented in the borehole logs attached with
this report (Appendix 1) and generalized ground profile is shown below.
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
2. METHODOLOGY OF INVESTIGATION
The site investigation was conducted by deploying one Spindle type China made
XY-200 core drilling rig having the capacity to perform boring operations to the
required standard and quality.
The main tasks undertaken as per the requirements for the geotechnical
investigation are:
2.1 Drilling
For the top soil formation dry drilling method has been utilized using single core
barrels fitted with appropriate size tungsten carbide bits at the bottom in order
to achieve good quality core recovery. Telescopic drilling was used whereby the
drilling size was reduced progressively starting from 108mm hole-diameter
through 89mm and remains till the completion depth.
The core drilling was carried out by using spindle type rotary core drilling rig.
Equipment to conduct in-situ testing and sampling, such as SPT apparatus
including split spoon sampler, water pump, rods, casings and a wide range of
heavy-duty tools were used during the drilling operation.
Core samples recovered from core barrels were arranged in partitioned wooden
core boxes having 1.0 m length, and are properly labeled indicating project
name, client, borehole designation, depth, etc. The cores inside core boxes were
logged and photographed (colored) and kept as part of the report document.
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
Field investigation
Drilling
BH-1 m 10.00
BH-2 m 10.00
BH-3 m 12.00
- Standard penetration test, SPT No. 14
Laboratory Tests
Atterberg Limit No. 7
Grain size analysis No. 7
Specific gravity No. 5
Free swell No. 7
Natural moisture content No. 4
The Standard Penetration Test (SPT) utilizes a 51mm external diameter and
450mm long thick-walled split spoon tube sampler driven into the ground under
the impact of semi-automatic sliding hammer weighing 63.5kg through a free
fall height of 760mm in accordance with test procedure mentioned in test No.
19 of BS 1377; 19750. The 'N' value, which is the measure of the density or
consistency of the ground under testing, is recorded as the number of hammer
blows required to achieve penetration of the last 300mm. The initial blows
required to penetrate the first 150mm are normally regarded as seating blows to
allow for any disturbed materials at the bottom of the borehole, and are
discarded. Upon completion of the test, the sampler tube is removed and
disassembled to obtain 'disturbed' but representative sample of the tested
ground.
The N-values of the SPT are an indication of the relative density of cohesion less
soils and the consistency of cohesive soil. General N-value ranges are correlated
with relative density and consistency as shown in table 3 below. It is emphasized
that for gravels and clays the correlations to relative density and consistency
should serve only as general estimates.
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
Standard Penetration Testing (SPT) in the borehole was conducted starting from
a depth of 1.50m below the ground level. The following table summarizes the
representative SPT N-value.
5.00
7.50 – 7.95 6/7/9 6.00
7.00
Extremely weak, variegated
9.00 – 9.45 R 8.00 color, moderately
9.00 weathered TUFF rock
SPT N Value per 300mm
2.00 – 2.45 2/4/5 7 9 11 13 15 17 19
1.00
2.00
4.00 – 4.45 5/7/8 3.00
Stiff to very stiff, light gray,
Depth (m)
4.00
5.00
BH-2 6.00 high plastic silty CLAY/
7.00
6.00 – 6.45 6/6/8 8.00 clayey SILT (Expansive) soil
9.00
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
Depth (m)
6.00 – 6.45 5/6/9 5.00 clayey SILT (Expansive) soil
6.00
7.00
8.00 – 8.45 6/7/10 8.00
9.00
2.3.2 Sampling
Seven disturbed soil samples were taken from the boreholes for laboratory
determinations of specific gravity, gradation, Atterberg limits and free swell tests
to characterize the types of soil in the profile.
Representative soil samples were selected and tested in ARCON Soil and
Construction Materials Laboratory, to check field classification and to determine
pertinent engineering properties. Summary of laboratory test results are shown
in summary table of Appendix 4.
Atterberg
Lab. Limit FS, % % %
BH ID Depth(m) Gs, USCS
Description LL, PI, (%) Gravel Sand Fine
(%) (%)
High Plastic
114 73 160 2.31 NIL 1 99 CH
BH-1 3.00 – 3.50 silty CLAY
5.50 – 6.00 High Plastic 90 38 140 2.51 2 98
NIL MH
clayey SILT
High Plastic
3.00 – 3.50 121 70 130 2.38 NIL 1 99 MH
clayey SILT
BH-2
High Plastic
5.50 – 6.00 108 64 140 2.32 NIL 2 98 CH
silty CLAY
High Plastic
BH-3 2.50 – 3.00 119 69 150 2.32 NIL 1 99 MH
clayey SILT
High Plastic
4.50 – 5.00 116 70 160 - NIL 1 99 MH
silty CLAY
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
High Plastic
7.50 – 8.00 121 71 140 - NIL 3 97 MH
clayey SILT
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
3. GEOTECHNICAL CHARACTERISTICS
Descriptive analysis was made on the soil samples derived from the three
boreholes. This was used together with the classification tests and relative
compactions as indicated from the SPT tests, and the following generalized geo-
technical layers are identified. Details on type and extent of the geotechnical
layers are given in Appendix 1 (Borehole logs).
A. Backfill layer
The upper most layer of the project site is backfill material which extends to a
depth of 0.50m, 0.40m and 0.55m below existing ground surface around BH-1,
BH-2 and BH-3 respectively.
B. Stiff to very stiff, light gray, high plastic silty CLAY/ clayey SILT
(Expansive) soil layer
This layer is characterized by stiff to very stiff, light gray, high plastic clayey SILT
(Expansive) soil layer and extends up to a depth of 8.30m in BH-1 and 9.10m in
BH-2 & BH-3 from existing ground level of the project site.
SPT tests were conducted and the reading ranging from to 8 to17blows/300mm
shows stiff to very stiff degree consistency.
Representative disturbed soil samples were taken and lab tests were conducted.
From test results, the percentage of materials passing through 0.075mm sieve is
97% to 99%. The soil consistency test results for the strata shows Plasticity Index
and Liquid Limit values are ranging 38% to 73% and 90% to 121% respectively.
Recorded maximum free swell is 160%. These results indicate that the soil in this
layer is high plastic fine grained with high degree of expansion potential.
C. Extremely weak, variegated color, moderately weathered TUFF rock
layer
Standard penetration test was conducted in this layer at one point and gives
refusal.
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
Ground water was not encountered during the course of drilling. However,
variation in location of the long-term water table may occur as a result of
changes in precipitation, evaporation, seepage and other factors not
immediately apparent at the time of this exploration.
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
4. FOUNDATION RECOMMENDATION
For the study area, isolated footing foundation on natural soil (Option-I) and
on 1.50m select fill(Option-II) are proposed options which can support the given
structure based on the site geologic setting and anticipated load.
Allowable bearing capacity for the selected foundation type shall be calculated
from SPT data, then, all the necessary adjustments are made to determine the
actual SPT values.
SPT values will be used to calculate the bearing capacity of the geotechnical layer.
The depths at which the SPT N-values are obtained, the SPT N-values and the
adjusted N-values (i.e., N’55) are given below and they are considered for
determining the design N-values.
Before using in-situ SPT values, the site N-values shall be adjusted to N55 standard
energy ratio value using the following formula (Bowles, 1988).
,
𝑁55 = 𝐶𝑁 ∗ 𝑁 ∗ 𝜂1 ∗ 𝜂2 ∗ 𝜂3 ∗ 𝜂4
,
Where 𝑁55 = adjusted N
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
𝑃 ′′
𝐶𝑁 = adjustment for overburden pressure =( 𝑃𝑂, )1/2
𝑂
𝑃𝑂, =overburden pressure
𝑃𝑂′′ = reference overburden pressure (95.76 kPa or
1.0kg/cm2)
𝜂1 = 𝐸𝑟 /𝐸𝑟𝑏 (where 𝐸𝑟 is average energy ratio that depends
on the drill system and 𝐸𝑟𝑏 is the standard energy
ratio). 𝐸𝑟 is taken as 50 and 𝐸𝑟𝑏 as 55.
𝜂2 = Rod length correction
Rod length > 10 m = 1,
Rod length 6-10 m = 0.95,
Rod length 4-6 m = 0.85,
Rod length 0-4 m = 0.75
𝜂3 = sampler correction (1.00 in our case)
𝜂4 = borehole diameter correction (1.00 in our case)
After adjusting the N-values, a design N-values are chosen from consecutive
depths where the test is performed. The design N-values are taken as the average
of adjusted N-values which are found in between ½ B above and 2B below the
proposed footing depths where B is the width of the foundation.
The bearing capacity for isolated footing can be calculated from the SPT N-
values using Meyerhof’s equation as follows (Bowles, 1997): -
𝑁,
𝑞𝑎𝑙𝑙 = ∗ (1 + 𝐹3 /𝐵)2 ∗ 𝐾𝑑 … … … … … … … … … 𝐵 > 𝐾𝑑
𝐹2
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
Where
𝑞𝑎𝑙𝑙 = Allowable bearing pressure for settlement limited to 25 mm.
B > F4
𝐾𝑑 = 1+0.33D/B, ≤ 1.33
𝐹2 = 0.08
𝐹3 = 0.3
𝐹4 = 1.2
𝐵 = Width of foundation
𝐷 = Depth of foundation
The following allowable bearing capacities are computed for isolated footings
placed at a depth of 3.00m below the lowest ground level. Foundation widths
are varied from 1.50m to 3.50m. A settlement of 25mm is assumed for the
allowable bearing capacity computation. The table below illustrates the
computations made.
340
BH-1 & BH-3
325
BH-2
310
Bearing Capacity (kPa)
295
280
265
250
235
220
205
190
1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5
Width of footing (m)
From the above analysis, the allowable bearing capacity range in values from
234kPa to 311kPa around BH-1 & BH-3 and 216kPa to 287Ppa around BH-2 on
natural ground layer based on various footing width.
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
Different building codes set the limiting settlement for the type of the structure
and foundations. The proposed foundation types shall also meet this criterion.
For saturated fine grained soils, the major part of the settlement is contributed
by the consolidation settlement. Hence, the calculation of consolidation
settlement is presented below.
Cc = -0.156+0.411e0 + 0.00058WL
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
consolidation settlements are checked for the high plastic clayey SILT/ clayey SILT
soil layer.
150
140
130
120
settelment (mm)
110
100
90
80
70
60
50
40
30
1 1.5 2 2.5 3 3.5 4 4.5
Width of Isolated Fotting (m)
For this option, depth of foundation is considered at 3.00m below the lowest
ground level of the project site and shall rest on 1.50m thick compacted selected
fill. In this case, total excavation at the foundation locations shall be up to 4.50m
below the lowest ground level and the excavated area shall be back-filled by
compacting 1.50m thick suitable material progressively upwards up to the
foundation level layer by layer.
The allowable bearing capacity value for various foundation width on 1.50m
well compacted selected fill is presented in below figure below.
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
415
400
385
370
Bearing Capacity (kPa)
355
340
325
310
295
280
265
250
235
220
205
190
1 1.5 2 2.5 3 3.5 4 4.5
Width of footing (m)
Fig 5: Plot of Allowable Bearing Capacity Values Vs. Width of Isolated Footing
Foundation on 1.50m thick selected fill
From the above analysis, the allowable bearing capacity range in values from
208kPa to 383kPa based on various widths of footings.
Appropriate granular material with few fines, i.e. Gravel – sand mixtures with
few silt/clay– GW-GC/SW-SC, etc shall be used for fill. The granular fill material
shall have a minimum soaked Californian Bearing Ratio (CBR) of not less than
30%. The Californian Bearing Ratio (CBR) shall be determined at a density of
95% of the maximum dry density determined in accordance with the
requirements of AASHTO T-180 method D.
The moisture content of fill material at the time of compaction shall be the
optimum for the equipment being used and not more than 2% above the
optimum for the material determined in accordance with the requirements of
AASHTO T-180. Each layer of fill shall be compacted to not less than 95% of
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
Note:
1. During the selection of appropriate option, the bearing layer shall be get
emphasized as one of selection criteria since the bearing layer is expansive
soil.
4. It is advisable that foundations constructed soon after the pits are opened
and the necessary preparations are made. Foundation trenches may
generally not be left open for a long time after excavation.
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
5. CONCLUSION
Backfill layer;
Stiff to very stiff, light grey, high plastic silty CLAY/ clayey SILT (Expansive)
soil layer and
Extremely weak, variegated color, moderately weathered TUFF rock
layer.
Recommendations are made on the type, depth and allowable bearing capacity
values under section 4.3 of this report according to Ethiopian standards – Based
on European Norm, Geotechnical Design ES EN 1997-1:2015 and ES EN 1997-
2:2015.The foundation designer can use any of the recommended values
depending on the superstructure loads.
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
APPENDICES
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
Appendix 1
Borehole Logs
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
Appendix 2
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
Appendix 3
Borehole Locations
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
Appendix 4
December 2018
Geotechnical Investigation and Foundation Recommendation Report for G+2
Office and Warehouse
Appendix 5
December 2018