OPER2p91 - Chapter 15
OPER2p91 - Chapter 15
1) Which of the following is NOT a key direct benefit from effective internal or external scheduling?
A) lower cost
B) greater use of assets
C) more dependable delivery
D) higher quality
E) added flexibility
10) Which of the following is NOT required to be known in order to schedule process-focused facilities?
A) the sequence of work
B) which workers are assigned to each work center
C) the time required for each item
D) the capacity of each work center
E) the availability of each work center
11) A work center had actual input of 280 hours and actual output of 270 hours. What is the change in
backlog?
A) 10
B) -10
C) 0
D) 1.037
E) Unable to determine with the given information
12) A work center had planned outputs of 10, 15, 13, and 20 hours with actual outputs of 12, 14, 13, and 18
hours. What is the cumulative deviation in output?
A) 0
B) 1
C) -1
D) 58
E) Unable to determine with the given information
2
Copyright © 2017 Pearson Education, Inc.
14) What is a scheduling technique used to achieve an optimum, one-to-one matching of tasks and
resources?
A) the assignment method
B) Johnson's rule
C) the CDS algorithm
D) the appointment method
E) the reservation method
15) There are two jobs to be assigned to two workers. The profit for worker A on job 1 is $5 and on job 2 is
$8. The profit for worker B on job 1 is $10 and on job 2 is $12. How should the work be divided using the
assignment method?
A) worker A assigned to job 1 and worker B assigned to job 2
B) worker A assigned to job 2 and worker B assigned to job 1
C) worker A gets both jobs 1 and 2
D) worker B gets both jobs 1 and 2
E) unable to determine
16) If job 5 takes 3, 4 or 5 hours to be completed by workers A, B, and C, respectively, what would the row
values for job 5 be after performing Step 1A of the assignment method?
A) 3, 4, 5
B) 8, 9, 10
C) 0, 1, 2
D) 6, 7, 8
E) 1, 4/3, 5/3
3
Copyright © 2017 Pearson Education, Inc.
20) Three jobs are to be assigned to three machines. Cost for each job-machine combination appears in the
table below. Perform the first two steps of the assignment method (subtract the smallest number in each
row and subtract the smallest number in each column; then cover with straight lines). At this point in the
problem-solving process:
21) The jobs listed below need to be completed. Assume that it is now day 140. If the jobs are sequenced
according to the longest processing time rule, what is the lateness of job A?
Processing Job due date
Job Time (days) (days)
A 20 180
B 30 200
C 10 175
D 16 230
E 18 210
A) 0.0 days
B) 24.0 days
C) 7.4 days
D) 9.0 days
E) 11.6 days
22) The jobs listed below need to be completed. Assume that it is now day 140. If the jobs are sequenced
according to the shortest processing time rule, what is the average completion time?
Processing Job due date
Job Time (days) (days)
A 20 180
B 30 200
C 10 175
D 16 230
E 18 210
A) 47.6 days
B) 60.2 days
C) 94.0 days
D) 2.5 days
E) 238.0 days
4
Copyright © 2017 Pearson Education, Inc.
23) EDD stands for what?
A) earliest due date
B) earliest design date
C) earliest detrimental date
D) earliest decision date
E) economic date determination
24) Using LPT priority would result in what sequence for Jobs A, B, C, and D if their process times are 4,
6, 5, and 2 respectively?
A) ABCD
B) DCBA
C) DACB
D) DABC
E) BCAD
25) Orders are processed in the sequence in which they arrive if (the) ________ rule sequences the jobs.
A) earliest due date
B) slack time remaining
C) first come, first served
D) critical ratio
E) Johnson's
26) Which of the following dispatching rules ordinarily gives the best results when the criterion is
quickest time for completion of the full sequence of jobs?
A) shortest processing time (SPT)
B) critical ratio (CR)
C) first in, first out (FIFO)
D) first come, first served (FCFS)
E) longest processing time (LPT)
27) Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the
shortest processing time dispatching rule, in which order should the jobs be processed?
Processing Job due date
Job Time (days) (days)
A 4 7
B 7 4
C 8 11
D 3 5
E 5 8
A) A, B, C, D, E
B) C, E, A, D, B
C) B, D, A, E, C
D) D, A, E, B, C
E) C, E, A, B, D
5
Copyright © 2017 Pearson Education, Inc.
28) Sequencing (or dispatching):
A) assigns dates to specific jobs or operations steps.
B) assigns jobs to work centers.
C) specifies the order in which jobs should be done at each center.
D) assigns workers to jobs.
E) assigns workers to machines.
29) Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the
earliest due date dispatching rule, in which order should the jobs be processed?
Processing Job due date
Job Time (days) (days)
A 4 7
B 2 4
C 8 11
D 3 5
E 5 8
A) C, E, A, D, B
B) A, B, C, D, E
C) B, D, A, E, C
D) C, B, A, E, D
E) B, D, A, C, E
31) Which of the following dispatching rules tends to minimize job flow time?
A) FCFS: first come, first served
B) SPT: shortest processing time
C) EDD: earliest due date
D) LPT: longest processing time
E) FCLS: first come, last served
32) Average completion time for a schedule sequence at a work center is the ratio of:
A) total processing time to the number of jobs.
B) total flow time to total processing time.
C) total flow time to the number of jobs.
D) total processing time plus total late time to the number of jobs.
E) total flow time plus total late time to the number of jobs.
6
Copyright © 2017 Pearson Education, Inc.
33) Eight jobs have been sequenced at a single work center. Total processing time for the eight jobs is 34
hours, and total flow time for the sequence is 85 hours. For this schedule, utilization is ________ and the
average number of jobs in the system is ________.
A) 100 percent; 10.625
B) low; .0941
C) 0.400 or 40 percent; 2.5
D) 0.235 or 23.5 percent; 4.25
E) maximized; minimized
34) Five welding jobs are waiting to be processed. Their processing times and due dates are given below.
Using the critical ratio dispatching rule, in which order should the jobs be processed? All dates are
specified as days from today.
Processing Job due date
Job Time (days) (days)
A 4 7
B 2 4
C 8 11
D 3 5
E 5 11
A) B, D, A, E, C
B) C, D, A, B, E
C) C, E, A, D, B
D) E, B, A, D, C
E) B, D, A, C, E
35) Which critical ratio value implies that a job is already late?
A) more than 100
B) 1
C) less than 1
D) 10
E) 3.4
36) What is the priority rule that sequences jobs using the smallest ratio of due date from today to
processing time?
A) critical ratio
B) earliest due date
C) first come, first served
D) longest processing time
E) shortest processing time
37) Which of the following is an advantage of the FCFS dispatching rule when used in services?
A) FCFS maximizes utilization.
B) FCFS minimizes the average number of jobs in the system.
C) FCFS minimizes the average lateness of all jobs.
D) FCFS maximizes the number of jobs completed on time.
E) FCFS seems fair to customers.
7
Copyright © 2017 Pearson Education, Inc.
38) What does the use of the shortest processing time sequencing rule generally produce?
A) maximum average lateness
B) maximum utilization
C) maximum effectiveness
D) minimum average flow time
E) B and D
40) A recent advance in short-term scheduling that makes use of expert systems and simulation in solving
dynamic scheduling problems is:
A) forward scheduling.
B) backward scheduling.
C) infinite scheduling.
D) finite capacity scheduling.
E) progressive scheduling.
41) Which of the following is NOT tracked by scheduling optimization systems used in retail stores?
A) cars parked in the parking lot
B) individual store sales
C) transactions
D) units sold
E) customer traffic
Answers
1. D
2. D
3. A
4. B
5. D
6. E
7. E
8. D
9. C
10. B
11. A
12. C
8
Copyright © 2017 Pearson Education, Inc.
13. C
14. A
15. B
16. C
17. C
18. D
19. A
20. A
21. D
22. A
23. A
24. E
25. C
26. A
27. D
28. C
29. C
30. D
31. B
32. C
33. C
34. B
35. C
36. A
37. E
38. E
39. E
40. D
41. A
42. B
9
Copyright © 2017 Pearson Education, Inc.