Summary RT MultiSystem
Summary RT MultiSystem
PT. BILL EMAS SARNO Powerplant Project (Turbine) - PT. Multi System Production (P. Bulan)
Thk Report
Line No Identification/ Description Joint No DIA ø Loc Test Date R1 R2 RSC Status FILM D7 FILM D7 Remark
(mm) No
4"x10" 4"X15"
1 CEP ( 1,2 ) suction from surface condenser 1 6" 7.11 0-7 14-0 19-Nov-18 18 √ ACC 2
1 CEP ( 1,2 ) suction from surface condenser 3 6" 7.11 0-7 7-14 14-0 19-Nov-18 18 √ ACC 3 Por 7-14; Por 14-0
2 CEP (1,2 ) discharge to Ejector inlet 1 4" 6.02 0-5 5-10 10-0 19-Nov-18 18 √ ACC 3 Por; Por; Por
2 CEP (1,2 ) discharge to Ejector inlet 2 3" 5.49 8-0 19-Nov-18 18 √ ACC 1
3 GVC outlet to LP heater 1 3" 5.49 8-0 16-Nov-18 17 √ ACC 1
3 GVC outlet to LP heater 2 3" 5.49 8-0 16-Nov-18 17 √ ACC 1
3 GVC outlet to LP heater 3 3" 5.49 0-4 4-8 16-Nov-18 17 √ ACC 2
3 GVC outlet to LP heater 4 3" 5.49 0-4 4-8 8-0 16-Nov-18 17 √ ACC 3
3 GVC outlet to LP heater 5 3" 5.49 4-8 8-0 16-Nov-18 17 √ ACC 2
3 GVC outlet to LP heater 6 4" 6.02 0-5 5-10 19-Nov-18 18 √ ACC 2 Por 0-5
4 Re-circulation line from LCV to surface condenser 3 2" 3.91 AB 19-Nov-18 18 √ ACC 2
5 Air evacuation line (condenser to vacuum pump) 1 4" 6.02 0-5 5-10 10-0 19-Nov-18 19 √ ACC 3
5 Air evacuation line (condenser to vacuum pump) 2 6" 7.11 0-7 14-0 19-Nov-18 19 √ ACC 2 Por 0-7
13 Oil filter outlet to Turbine Skid 1 2" 2.65 AB 22-Nov-18 22 √ ACC 2
14 Alternator inlet 1 1 1/2" 3.68 ABC 22-Nov-18 22 √ ACC 3
15 Alternator oil outlet 1 3" 5.49 0-4 4-8 22-Nov-18 22 √ ACC 2 Por 0-4; Por 4-8
19 Turbine bleed to LP heater inlet 1 3" 5.49 0-4 4-8 8-0 15-Nov-18 17 √ ACC 3 Por 4-8
19 Turbine bleed to LP heater inlet 2 4" 6.02 5-10 15-Nov-18 17 √ ACC 1
19 Turbine bleed to LP heater inlet 3 4" 6.02 0-5 10-0 15-Nov-18 17 √ ACC 2
19 Turbine bleed to LP heater inlet 4 4" 6.02 0-5 5-10 15-Nov-18 17 √ ACC 2 RC 0-5
19 Turbine bleed to LP heater inlet 5 2" 3.91 AB 15-Nov-18 17 √ ACC 2
19 Turbine bleed to LP heater inlet 6 4" 6.02 0-5 10-0 21-Nov-18 20 √ ACC 2
19 Turbine bleed to LP heater inlet 7 4" 6.02 0-5 5-10 10-0 21-Nov-18 20 √ ACC 3
19 Turbine bleed to LP heater inlet 8 4" 6.02 0-5 15-Nov-18 17 √ ACC 1
19 Turbine bleed to LP heater inlet 9 4" 6.02 0-5 10-0 15-Nov-18 17 √ ACC 2
19 Turbine bleed to LP heater inlet 10 4" 6.02 0-5 5-10 10-0 15-Nov-18 18 √ ACC 3 Profile 5-10; Profile 10-0
19 Turbine bleed to LP heater inlet 11 4" 6.02 0-5 10-0 21-Nov-18 20 √ ACC 2
19 Turbine bleed to LP heater inlet 12 4" 6.02 0-5 15-Nov-18 18 √ ACC 1
20 Dump steam line 1 12" 10.31 0-25 25-50 50-75 21-Nov-18 20 √ ACC 3 CP 0-25; Por 25-50; Por 50-75
20 Dump steam line 1 12" 10.31 75-0 21-Nov-18 20 √ ACC 1
20 Dump steam line 2 12" 10.31 25-50 75-0 14-Nov-18 15 √ ACC 2
20 Dump steam line 3 12" 10.31 25-50 21-Nov-18 20 √ ACC 1 SI+Por 25-50
20 Dump steam line 5 12" 10.31 0-25 25-50 50-75 14-Nov-18 15 √ ACC 3
20 Dump steam line 6 12" 10.31 50-75 75-0 14-Nov-18 15 √ ACC 2
20 Dump steam line 7 12" 10.31 0-25 25-50 50-75 75-0 14-Nov-18 15 √ ACC 4
20 Dump steam line 8 12" 10.31 0-25 25-50 75-0 14-Nov-18 15 √ ACC 3
20 Dump steam line 9 12" 10.31 0-25 25-50 50-75 75-0 21-Nov-18 21 √ ACC 4
20 Dump steam line 10 12" 10.31 25-50 14-Nov-18 16 √ ACC 1
20 Dump steam line 13 6" 7.11 14-0 14-Nov-18 16 √ ACC 1
21 Warm up vent line 1 4" 6.02 0-5 5-10 22-Nov-18 22 √ ACC 2
21 Warm up vent line 2 4" 6.02 0-5 5-10 10-0 22-Nov-18 22 √ ACC 3
21 Warm up vent line 3 4" 6.02 0-5 22-Nov-18 22 √ ACC 1 SI 0-5
21 Warm up vent line 4 2" 3.91 AB 22-Nov-18 23 √ ACC 2
21 Warm up vent line 5 2" 3.91 AB 22-Nov-18 23 √ ACC 2
TOTAL FILMS 69 24