CNG Schedule
CNG Schedule
CNG Schedule
Resource Names 09 Sep '18 23 Sep '18 07 Oct '18 21 Oct '18 04 Nov '18 18 Nov '1
Mode T S W S T M F T S W S T M F T S W S
1 Order finalisation for 23 days Sat 15-09-18 Mon 08-10-18
Compressors and Cascades
2 Mobilisation of Civil 30 days Mon 01-10-18 Wed 31-10-18
contractor
3 Site Preparation 3 days Mon 01-10-18 Thu 04-10-18
4 Compressor Foundation (with 21 days Thu 04-10-18 Thu 25-10-18
Curing)
5 PCC for loading Bay & Fill post 10 days Mon 15-10-18 Thu 25-10-18
6 Chain Link fencing & Fixing of 6 days Thu 25-10-18 Wed 31-10-18
Gate
7 Construction (Mechanical 23 days Mon 08-10-18 Wed 31-10-18
and E & I)
8 Suction Piping 12 days Mon 08-10-18 Sat 20-10-18
9 Compressor A Installation ( 1 3 days Mon 22-10-18 Thu 25-10-18
Nos)
10 Compressor B Installation ( 1 4 days Sat 27-10-18 Wed 31-10-18
Nos)
11 Receipt of Cascades at site( 2 5 days Mon 22-10-18 Sat 27-10-18
Nos)
12 Discharge Tubing/piping Work 6 days Thu 25-10-18 Wed 31-10-18
13 Cabling & Termination Works 9 days Mon 22-10-18 Wed 31-10-18
14 Lighting & Earthing Works 16 days Mon 15-10-18 Wed 31-10-18
15 Commissioning, 42 days Mon 01-10-18 Mon 12-11-18
Stabilisation and Operation
16 Statutory Permissions 1 day Mon 01-10-18 Tue 02-10-18
17 PESO Application for 7 days Mon 01-10-18 Mon 08-10-18
Construction ( CCOE, Nagpur)
18 Receipt of Approval from 10 days Tue 09-10-18 Fri 19-10-18
PESO
19 NOC from Panchayat 3 days Fri 19-10-18 Mon 22-10-18
20 Application to PESO for 2 days Mon 22-10-18 Wed 24-10-18
License ( CCOE, Nagpur)
21 Receipt of License (from 13 days Wed 24-10-18 Tue 06-11-18
CCOE, Nagpur)
22 Site Inspection by CCOE 3 days Fri 09-11-18 Mon 12-11-18
Kolkata and Endorsement of
License by Kolkata
Project: CNG Schedule Split External Tasks Inactive Summary Manual Summary Progress
Date: Fri 05-10-18 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only
Page 1