CNG Schedule

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

ID Task Task Name Duration Start Finish Predecessors Resource Names 09 Sep '18 23 Sep '18 07 Oct '18

Resource Names 09 Sep '18 23 Sep '18 07 Oct '18 21 Oct '18 04 Nov '18 18 Nov '1
Mode T S W S T M F T S W S T M F T S W S
1 Order finalisation for 23 days Sat 15-09-18 Mon 08-10-18
Compressors and Cascades
2 Mobilisation of Civil 30 days Mon 01-10-18 Wed 31-10-18
contractor
3 Site Preparation 3 days Mon 01-10-18 Thu 04-10-18
4 Compressor Foundation (with 21 days Thu 04-10-18 Thu 25-10-18
Curing)
5 PCC for loading Bay & Fill post 10 days Mon 15-10-18 Thu 25-10-18
6 Chain Link fencing & Fixing of 6 days Thu 25-10-18 Wed 31-10-18
Gate
7 Construction (Mechanical 23 days Mon 08-10-18 Wed 31-10-18
and E & I)
8 Suction Piping 12 days Mon 08-10-18 Sat 20-10-18
9 Compressor A Installation ( 1 3 days Mon 22-10-18 Thu 25-10-18
Nos)
10 Compressor B Installation ( 1 4 days Sat 27-10-18 Wed 31-10-18
Nos)
11 Receipt of Cascades at site( 2 5 days Mon 22-10-18 Sat 27-10-18
Nos)
12 Discharge Tubing/piping Work 6 days Thu 25-10-18 Wed 31-10-18
13 Cabling & Termination Works 9 days Mon 22-10-18 Wed 31-10-18
14 Lighting & Earthing Works 16 days Mon 15-10-18 Wed 31-10-18
15 Commissioning, 42 days Mon 01-10-18 Mon 12-11-18
Stabilisation and Operation
16 Statutory Permissions 1 day Mon 01-10-18 Tue 02-10-18
17 PESO Application for 7 days Mon 01-10-18 Mon 08-10-18
Construction ( CCOE, Nagpur)
18 Receipt of Approval from 10 days Tue 09-10-18 Fri 19-10-18
PESO
19 NOC from Panchayat 3 days Fri 19-10-18 Mon 22-10-18
20 Application to PESO for 2 days Mon 22-10-18 Wed 24-10-18
License ( CCOE, Nagpur)
21 Receipt of License (from 13 days Wed 24-10-18 Tue 06-11-18
CCOE, Nagpur)
22 Site Inspection by CCOE 3 days Fri 09-11-18 Mon 12-11-18
Kolkata and Endorsement of
License by Kolkata

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: CNG Schedule Split External Tasks Inactive Summary Manual Summary Progress
Date: Fri 05-10-18 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 1

You might also like