Project Risk Management Report: The Global Partnership On Output-Based Aid
Project Risk Management Report: The Global Partnership On Output-Based Aid
Project Risk Management Report: The Global Partnership On Output-Based Aid
Submitted by Group 5:
2B4033 - Myat Thada Kyaw
2B4059 - Yem, Socheath
2B5056 - Suos, Kumpina
2B5010 - Bist, Stuti
2B5015 - Dubey, Alok Kumar
2B4026 - Kipkoech, Robin Pik
2B4031 - Mi Kyi Kyi Han
II. Background
The International Network Connectivity in Cambodia was re-established in 1987 with Satellite
which supported by Soviet Unions. Between 1997 and 1999 the first fiber optical network
backbone was connected three countries – Cambodia, Thailand and Vietnam. Between 2007 and
2009 another project called Great Mekong Sub-region Information Highway was expanded
these three countries to Laos through four provinces in Cambodia.
Even the telecommunication network for this country, Cambodia, have been developed rapidly,
some rural and remote areas were facing with poor communication. Therefore, the development
of ICT, which is the key factor for economic development, consist of a very hug gap between
urban and rural.
The Global Partnership on Output-Based Aid (GPOBA), World Bank Agency, was assumed this
issue, rural communication accessing, as a key challenge. Among 14.4 millions of population in
2008, there were 18 percent were living in urban and the rest in rural area. Furthermore, based
on the National Institution of Statistic (NIS) reported that 28.1 percent of households in City
were connecting fixed line phone whereas there are only 5.8 percent were accessing fixed line
phone in rural areas.
The economy for those remote area were lag far behind the urban due to the operation process
were costly including communication and transportation. In 2008 the Optical Fiber Network
were under construct while the satellite link was cost efficient.
As a result there were five provinces were setting as the project target, see Exhibit 1.
SUBMITTED BY GROUP 5: 1
GPOBA Improved Access to communications in Rural Cambodia
The project was named Improved Access to Communications in Rural Cambodia with ID
P102475.
2. Project Objective
The first objective of the project was to access voice telephony service for low income families
in rural area. The second object was to demonstrate a private public partnership through the
GPOBA.
The target for this project was low income and remote area families and located in north and
4. Project Scope
The scope of this project was detailed in form of project scope statement as following:
Project Output/Deliverables: based on the above acceptance criteria, the project can
SUBMITTED BY GROUP 5: 2
GPOBA Improved Access to communications in Rural Cambodia
There are also three deliverables based on the basic access service:
1. Access points are required to access at least 80% villages in targeting areas.
2. The service for access point is ranged 8 hours a day and 5 days a week.
From additional service to be offered by Service Provider, it not only increases the
revenue, but the service provider may also offer and reduce the number of subsidy.
Project Scale: the following table show the number of target and the expected number of
1. Project Cost: The total investment fro was estimated at USD $4,751,914. And there are
other two funding windows; window 1 is USD $491,737 and window 3 is USD
$2,625,595.
3. Human Resource: The project was prepared and run by GPOBA and Ministry of Posts
SUBMITTED BY GROUP 5: 3
GPOBA Improved Access to communications in Rural Cambodia
Core Team:
Name Title Unit
Natasha Beschorner Task Team Leader, Senior ICT Policy Specialist CITPO
Cledan Mandri-Perrott Sr. Infrastructure Specialist FEU/GPOBA
Naomi Halewood Co-TTL, Operations Analyst CITPO
Joshua Gallo Infrastructure Specialist FEU
Arturo Muente Kunigami ETC (rural telecommunications specialist) CITPO
Juan Navas-Sabate Senior Telecommunications Specialist CITPO
Rajendra Singh Senior Regulatory Specialist CITPO
Kashmira Daruwalla Senior Procurement Specialist CITPO
Ahsan Ali Senior Procurement Specialist EAPCO
John Richardson Governance Specialist (Consultant) EAPCO
Sokunthea Sok Procurement Assistant EAPCO
Kannathee Danaisawat Financial Management Specialist EAPCO
Bunlong Leng Environmental Specialist EASES
Vanna Nil Social Development Specialist EASSO
Roch Levesque Senior Counsel LEGEA
Maria Lourdes Pardo Consultant LEGES
Gilbert +Tobin Telecommunications Consulting Law Firm External
Advisory Team:
Name Title Role Unit
SUBMITTED BY GROUP 5: 4
GPOBA Improved Access to communications in Rural Cambodia
5. Project Milestones
The project was documented in April 9, 2008 and estimated to close in 2010. Here are the key
milestones if this two-year project (see exhibit 4).
Activities Indicative Schedule
GPOBA provides subsidy commitment April 2008
Documentation to government for review, including Grant Agreement May 2008
Bidding documentation to government for review August 2008
Signature of GPOBA Grant Agreement August 2008
Launch of Bid September 2008
Contract Award December 2008
Project Implementation and Subsidy Disbursement begins December 2008
Recruitment of Independent Verification Agent August 2009
Mid-Term Review June 2010
Recruitment of Independent External Auditor October 2010
GPOBA Subsidy disbursement ends December 2011
Source: GPOBA commitment paper of Cambodia Project, 2008
Exhibit 5: The key milestones of the project
Institutions Responsibilities
MPTC 1. Project coordination
2. Operations manual
3. Providing technical inputs/specifications/designs for bidding document
4. Providing term of reference for consulting service
5. Formation of procurement review committees, and
6. Contracting administration and execution
SUBMITTED BY GROUP 5: 5
GPOBA Improved Access to communications in Rural Cambodia
V. Financial Management
1. Procurement Contractual Agreement
Almost procurement processes were responded by Independent Procurement Agent (IPA).
Somehow, the contract with MPTC (Ministry of Posts and Telecommunication of Cambodia)
were required for some technical and design support. Exhibit 6 show the process of contractual
agreement and funding flow.
GPOBA
MPTC
SUBMITTED BY GROUP 5: 6
GPOBA Improved Access to communications in Rural Cambodia
2. Project Funding
Total
Component US$ million
US$ million
Project Subsidy: Voice telephony (Window 3) $2,375,957 $2,375,957
Consulting Services:
SUBMITTED BY GROUP 5: 7
GPOBA Improved Access to communications in Rural Cambodia
Cost_003 Exchange rate in Cambodia base one USD Low Not likely
dollar
Scope_001 Scope would be change if High Not likely
telecommunication regulation would be
released
Scope_002 Measure and monitoring of service quality Medium Likely
and access availability
Scope_003 Selection of distribution channel(s) Low Likely
Policy_001 The ICT policy will be changed High Not likely
Schedule_001 Funding delay High Not likely
Environment_001 3 months of reason in Cambodia can slow Medium Almost certain
down installing speed
2. Risk Matrix
Based on the Risk matrix, Environment_001 which causes by three months of the heavy rain in
Cambodia can be medium impact with almost certain on project; therefore, this risk cannot be
ignored - it should be mitigate in effective way.
3. Schedule Estimation
3.1. Gantt Chart
SUBMITTED BY GROUP 5: 9
GPOBA Improved Access to communications in Rural Cambodia
Histogram Plot
Simulation Name Simulation #1
Seed 110855032
Statistic Plot
Variable Name Total duration Total duration
Location
SUBMITTED BY GROUP 5: 10
GPOBA Improved Access to communications in Rural Cambodia
# of Errors 0 5000
# of Filtered 0 0
Spread
Shape
Percentiles
1.00% 972.3277112
3.00% 972.8295882
5.00% 973.0985932
8.00% 973.3449308
10.00% 973.4752817
15.00% 973.7614126
20.00% 973.9654854
25.00% 974.1984176
30.00% 974.360514
35.00% 974.5223291
40.00% 974.6932543
45.00% 974.8446197
50.00% 974.9797315
SUBMITTED BY GROUP 5: 11
GPOBA Improved Access to communications in Rural Cambodia
Failure of the subsidy Issue the bidding Consultations with After 10 days Operator
bidding publicly thought winning bidders on other still no bidding
multi-channel sites to recognize their
reasons for not offering to
1 bid on the ignored sites,
and what is required to
stimulate their
participation in a
re-bidding.
MPTC has no A qualified MPTC World Bank to provide After World
experience with Bank staff may be training on Bank policy launching the Bank and
funding project appointed to and procedures on project MPTC
2
handle both financial management and
administrative and disbursement during
finance tasks project launch workshop.
Weak financial control All payments will An independent auditor to Immediately GPOBA
3 environment as limited be made via direct be appointed to audit the after reported
segregation and duties payments with full Project Financial from internal
SUBMITTED BY GROUP 5: 12
GPOBA Improved Access to communications in Rural Cambodia
SUBMITTED BY GROUP 5: 13