Method Statement: Existing Utilities
Method Statement: Existing Utilities
Method Statement: Existing Utilities
Project
Design and Construct New Orbital Highway & Truck Route (P023)
Contract 2: Orbital Highway: Salwa Road to North Relief Road
METHOD STATEMENT
EXISTING UTILITIES
E X W P 0 2 3 0 0 0 2 C U Q B J M T 0 0 0 2 1 C A
Rev.
``
Design & Construct / Orbital Highway & Truck Route Contract: C2 – Salwa Road to North Relief Road (P023)
METHOD STATEMENT
EXISTING UTILITIES
PAGE 1
ISSUE DATE : 23/07/2014 DOC NO. EXW-P023-0002-CU-QBJ-MT-00021 REV: CA
OF 8
APPROVAL RECORD
This document is the property of QDVC-BIN OMRAN JV. Any unauthorized attempt to reproduce it, in any form, is strictly
prohibited.
``
Design & Construct / Orbital Highway & Truck Route Contract: C2 – Salwa Road to North Relief Road (P023)
METHOD STATEMENT
EXISTING UTILITIES
PAGE 2
ISSUE DATE : 23/07/2014 DOC NO. EXW-P023-0002-CU-QBJ-MT-00021 REV: CA
OF 8
This document is the property of QDVC-BIN OMRAN JV. Any unauthorized attempt to reproduce it, in any form, is strictly
prohibited.
``
Design & Construct / Orbital Highway & Truck Route Contract: C2 – Salwa Road to North Relief Road (P023)
METHOD STATEMENT
EXISTING UTILITIES
PAGE 3
ISSUE DATE : 23/07/2014 DOC NO. EXW-P023-0002-CU-QBJ-MT-00021 REV: CA
OF 8
SUMMARY
INTRODUCTION...................................................................................................................4
REFERENCES ........................................................................................................................4
1- CONTRACTUAL DOCUMENTS ................................................................................................................ 4
2- CONTRACTOR DOCUMENTS ................................................................................................................... 4
3- DRAWINGS .................................................................................................................................................. 4
1 RESOURCES ...............................................................................................................4
1.1 HUMAN RESOURCES ........................................................................................................................ 4
1.2 EQUIPMENTS ...................................................................................................................................... 5
This document is the property of QDVC-BIN OMRAN JV. Any unauthorized attempt to reproduce it, in any form, is strictly
prohibited.
``
Design & Construct / Orbital Highway & Truck Route Contract: C2 – Salwa Road to North Relief Road (P023)
METHOD STATEMENT
EXISTING UTILITIES
PAGE 4
ISSUE DATE : 23/07/2014 DOC NO. EXW-P023-0002-CU-QBJ-MT-00021 REV: CA
OF 8
INTRODUCTION:
The purpose of this method statement is to define the procedures to ensure that the
installation of street light foundation and part thereof and workmanship at the above
site are complying with the condition/requirements as stipulate in the Qatar
Construction specifications.
In this document, these items will be present for installation of street light foundation:
REFERENCES
1- CONTRACTUAL DOCUMENTS
Qatari Construction Standards (QCS version 2010)
2- CONTRACTOR DOCUMENTS
QBJ Management Procedures:
Project Health & Safety Plan
Project Quality Plan (PQP)
Construction Environment Management Plane (CEMP).
Permit To Excavate.
3- Drawings
Existing drawings will be provided from the utility authorities (end user).
1 RESOURCES
1.1 HUMAN RESOURCES
The following organisation is required for the existing utilities. Each area will have its
This document is the property of QDVC-BIN OMRAN JV. Any unauthorized attempt to reproduce it, in any form, is strictly
prohibited.
``
Design & Construct / Orbital Highway & Truck Route Contract: C2 – Salwa Road to North Relief Road (P023)
METHOD STATEMENT
EXISTING UTILITIES
PAGE 5
ISSUE DATE : 23/07/2014 DOC NO. EXW-P023-0002-CU-QBJ-MT-00021 REV: CA
OF 8
dedicated team for working hours. These quantities will be adjusted according to the
different areas.
Section engineer 1 for the section
Site superintendent 3 for the project
Foreman 1 per working area
QA/QC Engineer/Inspector 1 team following a section
Land surveyor 2 teams: 1 for marking out, 1 for dimensional
survey
Safety officer 1 team following all the project
Signage team 1 team for all the project
Banks-men as required for critical points
1.2 EQUIPMENTS
EQUIPMENT NUMBER
General Service Vehicle To be confirmed
Excavator To be confirmed
Crane pick-up To be confirmed
JCB To be confirmed
Single Drum Compactor To be confirmed
Dump-truck or trailer To be confirmed
Hand Tools for Excavation work To be confirmed
Equipment’s will be divided in teams. The selection of the team will be done according to the
nature of the job, the nature of the material, the distance of transport, the availability of
equipment’s and traffic requirements.
2.1 MANPOWER
Safety and Health induction shall be conducted prior to commencement of works to all
personnel involved. All personnel will wear the required Personal Protective Equipment
This document is the property of QDVC-BIN OMRAN JV. Any unauthorized attempt to reproduce it, in any form, is strictly
prohibited.
``
Design & Construct / Orbital Highway & Truck Route Contract: C2 – Salwa Road to North Relief Road (P023)
METHOD STATEMENT
EXISTING UTILITIES
PAGE 6
ISSUE DATE : 23/07/2014 DOC NO. EXW-P023-0002-CU-QBJ-MT-00021 REV: CA
OF 8
(PPE) according to Site Regulations HSES Plan and the CEMP. All works at site will be
carried out in accordance to the HSES and the CEMP Plan.
The Supervisor/Foreman responsible for the work will be present on site during working
hours and Safety officer will monitor all activities. Any incident, injury and near miss will be
reported immediately to the Sub-Contractor’s, Main Contractor’s and Employer’s Safety
Departments.
2.2 EQUIPMENT
All equipment shall be checked by the Plant Department.
The equipment selected for the job shall have all current safety and technical inspection
certificates.
This document is the property of QDVC-BIN OMRAN JV. Any unauthorized attempt to reproduce it, in any form, is strictly
prohibited.
``
Design & Construct / Orbital Highway & Truck Route Contract: C2 – Salwa Road to North Relief Road (P023)
METHOD STATEMENT
EXISTING UTILITIES
PAGE 7
ISSUE DATE : 23/07/2014 DOC NO. EXW-P023-0002-CU-QBJ-MT-00021 REV: CA
OF 8
3 WORK METHODOLOGY
This section reference with QCS 2010.
The following documents are necessary to complete the existing utilities works:
- Approved method of statement.
- As-built drawings.
- Permit to excavate procedure.
3.2 SURVEY
The surveyor will set out the position of the existing utilities and the levels and
associated reference level.
The location of existing utilities will be confirmed from as-built drawings and cat
scanning.
Coordination with concern utility authorities will be done as per required in order to
ensure that the exact location will be identified.
Trial bore holes will be done and slip trenches (excavated by hand) to ensure the depth
and location of existing utilities.
Excavation in the vicinity of any utility will be carried out to the requirements of the
utility authorities and under their permit procedure.
This document is the property of QDVC-BIN OMRAN JV. Any unauthorized attempt to reproduce it, in any form, is strictly
prohibited.
``
Design & Construct / Orbital Highway & Truck Route Contract: C2 – Salwa Road to North Relief Road (P023)
METHOD STATEMENT
EXISTING UTILITIES
PAGE 8
ISSUE DATE : 23/07/2014 DOC NO. EXW-P023-0002-CU-QBJ-MT-00021 REV: CA
OF 8
This document is the property of QDVC-BIN OMRAN JV. Any unauthorized attempt to reproduce it, in any form, is strictly
prohibited.