Basis of Design - Pipeline System Trunkline
Basis of Design - Pipeline System Trunkline
Basis of Design - Pipeline System Trunkline
TABLE OF CONTENTS
Page
1.0 SCOPE............................................................................................................................................. 3
2.0 CODES, STANDARDS AND SPECIFICATIONS ........................................................................ 3
3.0 GENERAL REQUIREMENTS....................................................................................................... 3
4.0 SYSTEM DESCRIPTION .............................................................................................................. 3
5.0 DESIGN REQUIREMENTS........................................................................................................... 5
6.0 DESIGN DATA .............................................................................................................................. 7
7.0 DOCUMENTATION ...................................................................................................................... 9
Page 2 of 10
TRUNKLINE SP XI - SPU PROJECT
PT. PERTAMINA EP – FIELD LIMAU
1.0 SCOPE
This document covers the Basis of Design for the Trunkline SP XI - SPU Project for the detailed
design of onshore pipelines.
Page 4 of 10
TRUNKLINE SP XI - SPU PROJECT
PT. PERTAMINA EP – FIELD LIMAU
The SP XI - SPU pipeline shall be isolated prior to the tie-in. A remote controlled
mechanical isolation plug or similar equipment approved by COMPANY shall be set into
position just past a removable spool.
After hydrotest and pre-commissioning, the liquids pipeline shall be left filled with treated
water ready for commissioning.
4.4 Pipeline Tie-in
In the absence of specific information from the pipeline operator, the following assumptions
have been made:
1. The pipeline operator from CONTRACTOR is responsible for the pipeline section
from the downstream outlet flange.
2. The pipeline operator from CONTRACTOR will install the tie-in into the existing
pipeline. The valves may be fitted either at the tie-in point or at the downstream
flange.
3. The pipeline operator from CONTRACTOR will be responsible for all costs
associated with providing the tie-in process.
4. COMPANY will operate the proposed pipeline system within the range 100 to 300
psi.
5. Both pipelines shall be rated to the same Maximum Allowable Operating Pressure
(MAOP) of 1,000 psig. The pipeline operator from CONTRACTOR and
COMPANY will ensure that the pipeline pressure protection devices on both
pipelines are set so that the pipeline pressure cannot exceed 110% of the MAOP (ie
1100 psig).
Page 7 of 10
TRUNKLINE SP XI - SPU PROJECT
PT. PERTAMINA EP – FIELD LIMAU
Drag Coefficient CD = 1.2
Lift Coefficient CL = 1.5
Inertia Coefficient CI = 3.29
6.5.2 Hydrodynamic Coefficients for Pipeline Spanning Design and Support Clamp
Spacing Design
The following numbers are hydrodynamics coefficients used for spanning design:
Drag Coefficient CD = 1.2
Inertia Coefficient CI = 3.29
6.6 Material Properties
6.6.1 Pipeline / Support Material Properties
The line pipe material properties are for the Trunkline SP XI - SPU Project is
presented in table below:
Table 6.5
Pipeline / Support Material Properties
Page 8 of 10
TRUNKLINE SP XI - SPU PROJECT
PT. PERTAMINA EP – FIELD LIMAU
7.0 DOCUMENTATION
7.1 Design Report
A complete design report shall be prepared which includes the following as a minimum, plus
any other documentation required:
(1) Detail description of the analysis procedures
(2) Wall thickness calculations
(3) Calculations for on-bottom stability analysis
(4) Pipeline expansion analysis
(5) Crossing span analysis
(6) Constructability analysis
(7) Upheaval and lateral buckling
(8) Impact and dropped object analysis
Page 9 of 10
TRUNKLINE SP XI - SPU PROJECT
PT. PERTAMINA EP – FIELD LIMAU
7.2.4 The calculations shall be made in U.S. Customary Units (i.e. foot, inch, and
pound).
7.2.5 The calculations shall be archived by CONTRACTOR for the life of the facility,
and shall not be destroyed without prior written COMPANY approval.
7.3 Drawings
7.3.1 Drawing title blocks shall be agreed upon prior to start of drafting.
7.3.2 Drawings shall be to scale and in U.S. Customary Units with the exception of
Survey and positioning which shall be scale in SI units. Material and section
callouts shall be in accordance with American Institute of Steel Construction
(AISC).
7.3.3 Drawings shall be to the detail as defined by COMPANY.
7.3.4 A summary of the design criteria shall be shown on a general information and
index drawing.
7.3.5 During construction, as-built revisions shall be kept on a set of Construction
Drawing prints. At the completion of construction, the original drawings shall be
revised to "As-Built Drawings" and reissued to COMPANY.
7.3.6 Drawings shall be numbered in accordance with Field Limau Drawing Numbering
System.
Page 10 of 10