Prince2 Foundation User Guide v1.6
Prince2 Foundation User Guide v1.6
Question No: 1
Identify the missing word(s) from the following sentence. A project is a temporary organization that is
created for the purpose of delivering one or more business products according to an agreed?
A. Senior User
B. Business Case
C. Change
D. Cost
Answer: B
Question No: 2
According to PRINCE2, which of the following is a characteristic of a project compared to that of business
operations?
A. Incurs cost
C. Delivers benefits
D. Creates products
Answer: B
Question No: 3
Which of the following is FALSE?
Answer: A
Question No: 4
According to PRINCE2, which of the following are the aspects of project performance to be managed?
Answer: D
Question No: 5
What environment does PRINCE2 assume?
A. Third party
B. Customer/Supplier
C. Fixed-price contract
Answer: B
Question No: 6
A characteristic of a project is that they come with an element of uncertainty. Which of the following
PRINCE2 themes will help with the identification and management of such uncertainty?
A. Quality
B. Risk
C. Change
D. Organization
Answer: B
Question No: 7
Which is a benefit of using PRINCE2?
Answer: B
Question No: 8
Which PRINCE2 principle supports planning only to a level of detail that is manageable and foreseeable?
B. Manage by exception
C. Focus on products
D. Manage by stages
Answer: D
Question No: 9
Which is NOT a PRINCE2 integrated element?
A. The principles
B. The techniques
C. The themes
Answer: B
Question No: 10
Which is a characteristic of a project?
B. Have no uncertainty
D. Are cross-functional
Answer: D
Question No: 11
Which is one of the six aspects of project performance that needs to be managed?
A. Issues
B. People
C. Benefit
D. Tolerance
Answer: C
Question No: 12
Identify the missing words in the following sentence... A principle of PRINCE2 is that a project has defined
and agreed?
Answer: A
Question No: 13
Identify the missing words in the following sentence... A PRINCE2 project is and controlled on a
stage-by-stage basis?
A. Planned, monitored
B. Developed, reported
C. Designed, assigned
D. Planned, produced
Answer: A
Question No: 14
Identify the missing word in the following sentence... A PRINCE2 project has defined for each project
objective to establish limits of delegated authority?
A. Allowances
B. Tolerances
C. Roles
D. Deviations
Answer: B
Question No: 15
Identify the missing word in the following sentence... A PRINCE2 project focuses on the definition and
delivery of, in particular their quality requirements?
A. Benefits
B. Products
C. Activities
D. Outcomes
Answer: B
Question No: 16
Which of the following is a TRUE principle of a PRINCE2 project?
Answer: C
Question No: 17
Identify the missing words in the following sentence... A Project is a that is created for the purpose of
delivering one or more business products according to an agreed Business Case?
A. Temporary organization
B. Skilled environment
C. One-off Endeavour
Answer: A
Question No: 18
Which of the following statements is TRUE?
B. PRINCE2 does not seek to engage with any stakeholders outside of the project environment
D. PRINCE2 assumes the supplier will specify the desired result and probably pay for the project
Answer: B
Question No: 19
Which of the following statements is FALSE? PRINCE2 provides projects with . . .
D. Plans designed to meet the needs of the different levels in the management team
Answer: C
Question No: 20
Which of the following does PRINCE2 recognize as being project characteristics?
1. Projects are the means by which we introduce business change
2. Projects have a defined start and end
3. No project is unique
4. Projects often cross the normal functional divisions within an organization
A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4
Answer: B
Question No: 21
The PRINCE2 principle 'continued business justification' states that a requirement for a pro ject is that...
There is justifiable reason to start the project and justification should remain valid throughout the life of the
project. Which one of the following does PRINCE2 also state for this principle?
Answer: D
Question No: 22
Which of the following PRINCE2 elements are described as being the aspects of project management
that must be addressed continually and in parallel throughout the project?
A. The Principles
B. The Processes
C. The Themes
Answer: C
Question No: 23
Which of the following PRINCE2 elements are described as being the guiding obligations and good
practices which determine whether the project is being managed using PRINCE2?
A. The Principles
B. The Processes
C. The Themes
Answer: A
Question No: 24
Which of the following are the integrated elements which make up the structure of PRINCE2?
Answer: A
Question No: 25
Which of the following are benefits of using PRINCE2?
1. Provides a common vocabulary for all project participants, promoting effective communication
2. Promotes regular progress meetings for senior management
3. Plans are carefully designed to meet the needs of the different levels in the project organization,
improving communication and control
4. Defines a thorough but economic structure of reports
A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4
Answer: C
Question No: 26
The PRINCE2 principle 'focus on products' states that a successful project is which one of the following?
A. Output oriented
B. Activity oriented
C. Benefits oriented
D. Resource oriented
Answer: A
Question No: 27
Effective risk management is a pre-requisite to which of the following principles?
B. Manage by exception
C. Focus on products
Answer: A
Question No: 28
In respect of the project's organization structure, one of the seven principles of PRINCE2 is that every
project must have which one of the following?
A. Defined and agreed roles and responsibilities with an organization structure that engages the business,
user and supplier primary stakeholder interests
B. People allocated to clearly defined management jobs, assigned to them on a one-to-one basis
C. As many stakeholders as possible from the customer environment involved in key decision-making
throughout the project life cycle
D. Stakeholders who are responsible, accountable, consulted and informed throughout every stage of the
project
Answer: A
Question No: 29
Which of the following is NOT a PRINCE2 Principle?
C. Manage by stages
Answer: B
Question No: 30
Which of the following best defines an output?