Onshore Operation Daily Maintenance Report: H2S Support Engineer

Cascade Air Lines provides daily maintenance reports for its offshore drilling rig, SLR-215. The report details the completion of regular inspections of breathing air equipment, safety gear like self-contained breathing apparatuses, and gas monitoring systems. It also records H2S safety training conducted and monitoring of rig operations that occurred over the past 24 hours.

Uploaded by

shahzad sultan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
65 views1 page

Onshore Operation Daily Maintenance Report: H2S Support Engineer

Cascade Air Lines provides daily maintenance reports for its offshore drilling rig, SLR-215. The report details the completion of regular inspections of breathing air equipment, safety gear like self-contained breathing apparatuses, and gas monitoring systems. It also records H2S safety training conducted and monitoring of rig operations that occurred over the past 24 hours.

Uploaded by

shahzad sultan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

CASCADE Air Lines

DATE VERIFIED
ONSHORE OPERATION DAILY MAINTENANCE REPORT
Company man Name Syed Mehmood ul hassan shah
RIG NAME SLR-215

EEBA
SABA

SCBA
LOCATION Maino 28 WELL No.: 1
USL H2S Support Engineer Shahzad Sultan STATIONS
DATE 19-Nov-18

Status
11/19/2018
Monkey Board 1 1 11/19/2018
DAILY REQUIREMENTS Rig Floor 5 6 11/19/2018
Dog house 1 1 11/19/2018
Carried out regular inspection for all mesh guard devices overall around of RIG's H2S Office 1 11/19/2018
Regulary monitoring and inspect all Breathing Air supply - all HP & LP gauges, lines, manifolds, regulators, fittings, cascade racks for leaks and appropriate pressure readings. Shale shakers 2 3 11/19/2018
To Check fixed gas monitoring system for all stations . Muster station A 4 11/19/2018
To inspect & maintain all SCBAs & SABAs. Muster Station B 4 11/19/2018
Conducting, H2S awarness training as mandatory requirements for new commer, Visitor Orientations & H2S Refresh Trainings as required - and recorded accordingly Mud logging unit 11/19/2018
Actively monitoring the RIG operation Medic 2 11/19/2018
#REF! Company man office 2 11/19/2018
Rig manager office 2 11/19/2018
Cementing unit dowel 2 11/19/2018
Mud pits 2 3 11/19/2018
ACTIVITIES FOR 24 HOURS : DAY & Night shahzad sultan Pump room 11/19/2018
Sack area 1 2 11/19/2018
* 5 persons were given trainin today to refresh on donning of breathing air packs and response planning * Training Room 1 11/19/2018
* 2 person were given full training on theory and practic. * Choke manifold 1 3 11/19/2018
* Inspected system and detectors, radio communication. * Client HSE 1 11/19/2018
* Assured that breathing air pressure is good at all points. * Rig HSE 1 11/19/2018
* checked LP and HP lines around location for vulnerable points. * Step oil tool 2 11/19/2018
* Inspected manifolds and high pressure regulators and pressure. * Enviromental office 11/19/2018
* walked around location to monitor activities and operations * Material man office 1 11/19/2018
* Mud engineer 1 11/19/2018
security 1 11/19/2018
Geologist 1 11/19/2018
Rig ware house 1 11/19/2018
PMS office 2 11/19/2018
Radio Room 1 11/19/2018
Mud logger 4 11/19/2018
US unit 1 11/19/2018
Engine area 2 11/19/2018
Well head area 2 11/19/2018
Welding Work Shop 1 11/19/2018
DD unit 2 11/19/2018
wireline unit 1 11/19/2018

MONTHLY REPORTS & SUBMISSION Fire, Abandon & H2S Drill


Last H2S drill was conducted on 13 November 2018
Mesh Guard calibration was done on 24 october 2018 & next due on 24 nov.
Gas alert micro 5 & single gas clip bump tested on 24 oct. 2018 & next due on 24 nov.2018.

TOTAL : 14 16 23 22

QUARTERLY ACCOMMODATIONS*
Cabin # Occupy N0. Cabin # Occup.N0. Cabin # Occup.N0

TOOLS & EQUIPMENT ONBOARD DETECTION SYSTEM Fixed sensors, ITX & GAS badges sensor calibration
NO. ITEMS QTY SERIAL NO. Station QTY TYPE LAST DATE NEXT DATE
Wire Brush 1 Main Deck 1 H2S 24-Oct-18 24-Nov-18
Bug Blowers - 30 inches in size 2 Rig Floor 1 H2S 24-Oct-18 24-Nov-18
Bull Hornes 1 Shale Shakers 1 H2S 24-Oct-18 24-Nov-18
Windsock w/Poles - Windsocks & Poles 2 Mud Pits 1 H2S 24-Oct-18 24-Nov-18
Intrinsically safe Torches - Flash Lights Well Head 1 H2S 24-Oct-18 24-Nov-18
Screw drivers 1 Choke Manifold 1 H2S 24-Oct-18 24-Nov-18
Rescue Stretcher
Oxygen Resuscitator
Air analysis Kit 1
Air analysis Test tubes 1
Digital Anometer 1
Allen Key Set 1
Cutter 1 Single Gas Clip 12 H2S 10-Oct-18 24-Nov-18
Pliers 1 Multi Gas Detector 3 H2S,LEL,CO,O2 10-Oct-18 24-Nov-18
Crescent Wrench 1 Rae Pump 2 Multi Tubes Nill Nill
Tool Bag 1
Printer 1
Voice amplifiers 3

PENDING ISSUES ACTION TAKEN

* POB in Chambers:
POB Total onboard = 137 Max. allowable POB =

BA on board & operational ( SCBA 2216psi & SABA 4500psi )


DAILY OPERATIONS SUMMARY MISCELLANEOUS / OTHER Cascade racks 3 ( With 6 cylinders)
Cascade Air Lines 23

Day Shift Rescue Team : Night Shift Rescue Team :


Crane C
Team # 1: Rig Manager, Roustabouts Team # 2: Doctor, Electrician, Mechanic
Rig : completed wireline, RIH to clean hole.

Shahzad Sultan
H2S Support Engineer