FIDIC Comparison PeterAtkinson
FIDIC Comparison PeterAtkinson
FIDIC Comparison PeterAtkinson
An Overview
by
Edward Corbett
Corbett & Co
London
Corbett & Co
International Construction Lawyers
George House
2 Claremont Road
Teddington TW11 8DG
Tel: 44+20 8614 6200
Fax: 44+20 8614 6222
[email protected]
www.corbett.co.uk
FIDIC’s 1999 Rainbow – An Overview
of the Red, Yellow, Silver and Green Books
by
Edward Corbett
Corbett & Co, London
Introduction
The first comment to make is that the standard format of the three major forms is welcome. They
all have 20 clauses, 17 common clause titles and much wording and many definitions and
concepts in common. Although it may be thought that the desirability of this commonality has
led the draftsmen into error with the Silver book, a suite of contracts such as these is a great
improvement over the needless variations in the earlier forms. The Green Book has just 15
clauses covering 10 pages.
One effect of the 1999 issues is to make redundant the popular but troublesome Orange Book of
1995. The Yellow Book is in some ways the second edition of the Orange Book and is an
improvement, in this writer’s view. It is also intended to supercede the 3rd Edition of the Yellow
E&M form, published in 1987.
The old Red form was for civil works and the old Yellow for E&M work. The 1999 forms divide
as to responsibility for design, irrespective of the work type. The decision to divide the forms by
design responsibility rather than work type is debatable. The UK Institute of Civil Engineers’
New Engineering Contract demonstrates (as to a lesser extent does FIDIC’s Short Form) that
there is no fundamental difficulty in providing for contractor design as an alternative in a contract
The decision to depart from FIDIC’s traditional balanced risk philosophy may be viewed with
alarm by some readers of the Silver Book. Should FIDIC be endorsing the practice of dumping
risk on contractors? Of course it happens and for sufficient commercial reasons in projects with
non- or limited recourse project financing where price certainty is considered paramount. But
what will be the effect elsewhere in the market? If FIDIC say it is accepteble to place ground
conditions risk on contractors in the Silver Book, how often will we see the Silver Book clause
4.12 replacing its equivalent in the Red and Yellow Books?
Common features
Employers and funders will be pleased to see the following new features in all three 1999 books:-
• Sample on-demand bonds are now included with the conditions, FIDIC having overcome its
distaste for these instruments to recognise international practice.
• Progress reports are required by clause 4.21 and must be included with the supporting
documents accompanying applications for payment – clause 14.3. The next step to payment
occurs (clause 14.6)
• Termination for convenience is provided for at clause 15.5 upon 28 days’ notice. The
Contractor is paid for work done and demobilisation but receives no compensation.
• The Defects Notification Period, as it is now called, may be extended for up to 2 years
“… if and to the extent that the Works, Section or a major item of Plant … cannot be used
for the purposes for which they are intended by reason of a defect or damage”, clause
11.3.
“… the Time for Completion shall not be extended, the Contractor shall not be entitled to
additional payment, and the Employer shall be discharged from all liability in connection
with the claim.”
This contrasts with FIDIC policy hitherto which stopped well short of barring contractors’
claims for lack of notice. Contractors may think that the 42-day limit for the response to the
claims (clause 20.1) is scant compensation for the very real danger that this clause represents.
One result may be the appearance on site of claims managers more frequently and at an
earlier stage in the life of a project.
Contractors will be pleased to see the following in all three major contracts:-
“(a) which is beyond a Party’s control, (b) which such Party could not reasonably have
provided against before entering into the Contract, (c) which, having arisen, such Party
could not reasonably have avoided or overcome, and (d) which is not substantially
attributable to the other Party …”
The normal list of examples is provided but the above definition may provide some surprises.
Equally important are the consequences set out at clause 19.4, which are that the Contractor
receives both time and reimbursement of costs that results from the event, a far cry from
traditional force majeure.
“reasonable evidence that financial arrangements have been made and are being
maintained which will enable the Employer to pay the Contract Price …”, clause 2.4.
In view of the fact that failure to comply with Sub-Clause 2.4 is treated as a default by the
Employer which by clause 16.1 entitles the Contractor to suspend all or part of the Works or
• Suspension for late payment and late certification under clause 16.1
“above the discount rate of the central bank in the country of the currency of payment”
which provision (clause 14.8) may or may not provide an incentive for the Employer to pay
promptly.
• Ground conditions claims are alive and well at clause 4.12 in the Red and Yellow Books with
the proviso that a claim may be reduced where
“other physical conditions in similar parts of the Works (if any) were more favourable
than could reasonably have been foreseen when the Contractor submitted the Tender.”
Employers faced with ground conditions claims will no doubt be looking for reductions and
the meaning of “similar parts” and “more favourable” will come under close scrutiny.
• The Employer must comply with a claims clause (Clause 2.5) and may not make arbitrary
deductions from sums otherwise payable. Whereas a general right to set off from sums
certified was preserved in previous forms, here the Engineer’s determination function is
intended to cover all the Employer’s entitlements so that any attempt to set off could result in
suspension or termination by the Contractor.
Construction lawyers will be pleased (or at least kept busy) by the extended use of the terms
“reasonable” and “Unforeseeable”, the latter term being defined at clause 1.1.6.8 in the Red and
Yellow Books as
Equally, the term “reasonable evidence” of ability to pay, combined with the dramatic sanctions
available to the Contractor who considers that such evidence has not been forthcoming, seems
sure to be the subject of much debate. (A similar clause caused much trouble on a recent Asian
project to this author’s knowledge.) Nevertheless, the clause is right in principle in this writer’s
view, as any contractor caught up in a project in a collapsing economy will testify.
Generally welcome will be the replacement of the Engineer’s decision with a Dispute
Adjudication Board as the first step in the dispute process set out in clause 20. These Boards,
which may be of one or three members, have proved their worth on a variety of projects and
should substantially reduce the duration of disputes. Their decisions will have interim binding
effect, unlike World Bank dispute review boards who make recommendations only.
“The decision shall be binding on both Parties, who shall promptly give effect to it unless
and until it shall be revised in an amicable settlement or an arbitral award …” Clause
20.4
The debate within FIDIC and beyond on the role of the Engineer appears not to be over and an
uneasy compromise appears to have been reached. Clause 3.1(a) declares that
Clause 3.5 requires him to make “a fair determination in accordance with the Contract, taking
due regard of all relevant circumstances” where the conditions refer to clause 3.5. The claims
clause refers to clause 3.5; the payment and variations clauses do not. In the Silver Book, the
Employer is also required to be fair in certain specific instances.
The Engineer may now be replaced by the Employer, subject to a right of reasonable objection by
the Contractor “with supporting particulars” (clause 3.4). It will be interesting to see how this
works in practice.
As mentioned above, clause 12 lives on in clause 4.12 of these books, except that recovery may
be reduced if more favourable conditions than could have been expected are encountered
elsewhere in “similar parts of the Works”. What is a similar part will inevitably cause difficulty.
Overall, the risk allocation has moved slightly in the contractor’s favour. The definition of force
majeure has broadened beyond the impossible or illegal basis of the Orange Book. Now it must
be beyond a party’s control, something against which he could not reasonably have provided and
which he cannot now reasonably avoid or overcome and for which he cannot blame the other
party. The illustrative list now includes
The increased power of the Contractor in relation to the Employer’s ability to pay and actual
payment is a significant and entirely justified shift in commercial risk, in this writer’s view.
Financing charges and suspension for non-payment and suspension for late interim payment
certificates all serve to increase the pressure on Employers to have their financing properly
These beneficial moves for contractors are balanced to some extent by the termination for
convenience option (clause 15.5) which provides no profit for the Contractor.
The potential severity of the 28-day notice provision for claims and the consequences of a failure
to give the right notices and particulars represents a danger to the Contractor and may well have
the undesirable consequences of shortening the project honeymoon, of increasing the claims staff
on projects and causing disputes to arise early in the life of a project.
One feature deserves special mention. There is a value engineering clause at clause 13.2 of the
Red Book which gives the Contractor the opportunity and incentive to suggest cheaper or quicker
ways of executing the project. The reward is 50% of the net benefit to the Employer, i.e. half the
cost saving less any diminution in the value of the project. Thus a cheaper turbine may mean
increased maintenance so the net benefit of the alternative may be less than the saving in capital
cost.
“When completed, the Works shall be fit for the purposes for which the Works are
intended as defined in the Contract” (clause 4.1).
This formula is similar to the old Orange Book and is not popular with contractors. How the
purpose should be defined in the contract is and will remain a subject for debate.
FIDIC have tried to tackle the confusion in the Orange Book about responsibility for errors in the
Employer’s Requirements. Results are not good. The Contractor is supposed to state in his tender
letter that he has “ascertained that [the Employer’s Requirements etc.] contain no errors or other
“… an experienced contractor exercising due care would have discovered the error
…before submitting the Tender.”
After the period has expired, any errors found later will give rise to time and money only if that
experienced contractor would not have spotted the error in the initial prescribed period.
So who is responsible for errors in the Employer’s Requirements? Well ..... it depends.
Meanwhile, the fitness for purpose obligation remains regardless.
This is intended as a turnkey form for BOT and other similar projects where the risk is placed
largely on the Contractor. So clause 4.12 states that
“(b) by signing the Contract, the Contractor accepts total responsibility for having
foreseen all difficulties and costs of successfully completing the Works”
This is clear but there is an impossibility clause at clause 19.7 which discharges the Contractor
from further performance
“if an event or circumstance outside the control of the Parties … arises which makes it
impossible or unlawful for either or both Parties to fulfil its or their contractual
obligations …”.
This provision may well come under pressure where ground conditions render the works
impossible to achieve as intended.
The fitness for purpose formula in the Yellow Book appears in the Silver Book as well but errors
in the Employer’s Requirements are placed squarely at the door of the Contractor by clause 5.1
with certain exceptions, in particular the definitions of intended purposes and the performance
criteria. The rest must be checked and adopted by the Contractor. It is less clear that the
Where the desire for similarity with the other forms may have led the draftsmen astray is the
degree to which the Employer can interfere with the works and the Contractor’s performance.
This is making contractors reading this form uneasy. If the Contractor is to have so much risk and
responsibility, it is felt that the Employer should leave the Contractor to progress the works and
achieve the performance specification in his own way. The turnkey contract should not, perhaps,
be used where the ability of the Contractor to achieve the result is so much in doubt that constant
supervision is required.
The concept of turnkey in its pure form is that the Employer goes away entirely and returns when
the Contractor has a completed project ready to meet the performance specification. This form
seems to be a long way from that concept. Although the Employer has a legitimate interest to
ensure that the stage payments being made are not being wasted, the ability to instruct, to vary
and to condemn may go too far here. Responsibility for the result is not diminished if the
Employer does choose to interfere and instruct how the work is to be done although the
Contractor can record his objections to a variation under clause 13.1.
The test edition of the Silver book received a rocky reception from some quarters and some
changes were made to address the concerns being raised. It is doubtful that the contracting
community will be satisfied with the 1st Edition and may well fear that the form will be used
outside of the true turnkey situation for which it was intended.
The Green Book started out as a minor works form but evolved, not least when dredging
contractors said that large value but simple contracts for dredging and reclamation might also be
appropriate for the form. It is contained in 15 clauses on 10 pages of large print, the task group
having made every effort to keep the language and concepts simple.
• A similar overall risk philosophy has been adopted as for the Red and Yellow books.
• The contract price would normally be a lump sum
It is understood that there are no plans for a Red book sub-contract so it may be that the Short
Form has a dual life as a subcontract. It should be said, however, that it was not drafted with this
in mind and this writer, at least, has not worked out what pitfalls might exist in any attempt to use
the form in that way.
Conclusion
FIDIC’s 1999 rainbow of forms should be welcomed. There is little reason to doubt that the Red
and Yellow forms will take their place on the international stage in the way that their
predecessors have done. The World Bank has indicated its intention to incorporate the Red Book
into its standard bidding documents and to permit the use of the Yellow Book on appropriate
projects. They are also taking a keen interest in the Short Form for smaller contracts. The 1999
Rainbow therefore seems destined to have a major impact on the international construction
industry.
ECC