Project Cost Control Jul 02
Project Cost Control Jul 02
Project Cost Control Jul 02
CONTROL
2002
INDEX
SUBJECT Page
Introduction 3
Characteristic of a Project Control System 5
Work Breakdown Structure 7
Organization Breakdown Structure 8
Variances 10
BCWS, BCWP, ACWP 10
Cost Variance 11
Schedule Variance 12
At completion Variance 13
Performance Ratios 14
Measuring and Forecasting Completion 15
Engineering Measurement 15
Procurement Measurement 19
Construction Progress Measurement 22
References 25
2
Introduction
Controls are systems for guiding work processes toward some objectives.
Planning performance
Measuring performance
Contracting administration
If it has to be said in two words what this chapter is all about they would be cost control.
3
The contrast between a project running with a cost control system and one without it may
be illustrated by considering two different ways of building a warehouse.
One approach is to hire masons, mechanics, electricians, plumbers, laborers and the like
and put them to work. They will make decisions and order supplies as the needs arise. The
owner will check periodically to see if all goes right. As problems surface, rework has to
be done if spotted on time, otherwise the owner has to live with the mistake.
The final result: cost and time overruns, labor disputes, and frustration for all project
participants.
The other approach is utilizing modern project management techniques. It will not prevent
all problems but it will minimize them. All resources available will be organized and
controlled and most situations anticipated. Benefits may be summarized as:
Basis for problem solving, decision making, and corrective action available at
all times
4
When designing a project control system, it is important to consider the following
characteristics:
1.- Objective.
Priorities
Plans
2.- Flexibility.-
Project control systems must be flexible enough to adapt to different project sizes and
different users.
3.- Simplicity.
Control system simplicity is required to avoid users directing their attention to the
mechanics of the system rather than to working and getting results.
The control system must be the one requiring the smallest effort and producing the
required results.
Standing control systems should be examined periodically and carefully to see if each piece
of information is really necessary.
4.- Response.
Control data must result in immediate action to be effective. The right data must go to the
right people. To get good response from a project control system it is necessary to know
who is responsible for action, what are the control requirements, what controls are needed
to meet this requirements, and how control data may be best presented
5.- Timelyness.
5
Information may not be effective if it does not come at the right time. Making project data
available on time requires avoiding delays between data collection and its presentation and
time-framing reports frequency to the individuals. For instance, the time frame for cost
reports for a cost engineer may be a week while that of a project manager might be two to
four weeks.
A control system will be utilized by people so it must be designed for people. It must be:
User friendly
Simple
Flexible
Fool proof
6
WORK BREAKDOWN STRUCTURE
The essential tool for building a control system is breaking the work down to
comprehensive activities.
The work breakdown is the division of work into a number of more manageable
pieces.
A project may be broken down into smaller pieces called Job orders; Job orders can then
be divided into smaller work efforts called phases, then phases may be separated into work
packages, and work packages parted into work items or activities.
Reduction of complexity
The work breakdown structure (WBS) of a project is almost like a bill of materials. It
divides the project into tasks of manageable size which makes estimating a relatively easy
process. The figure below gives an idea of how to start breaking down a project.
HOUSE CONSTRUCTION
The subdivision of project tasks is often a continuing process and as the project develops,
the more general tasks at higher level are divided up into more specific tasks at lower
levels.
7
Paralleling the WBS there is an organization breakdown structure or OBS. The
organization breakdown structure may incorporate contractors and subcontractors and
shows how these units fit into the hierarchical organization structure. The figure shows an
example of an incipient Organization Breakdown Structure.
The WBS is a product oriented breakdown of the project plans, whereas the OBS is a
functional reporting breakdown and shows the hierarchy of the organizational units
responsible for performing the work on the project. As with the WBS, the OBS can be
broken down into various hierarchical levels.
The WBS and the OBS are independent of each other, but at the lower levels they
intersect and form a matrix or grid of valid cost collection points called COST
ACCOUNTS. A department can work on multiple tasks, and a task can be worked on by
multiple departments.
COST ACCOUNT
Budget No.: 300
Work Packages
Planning
Packages
8
Once the detail level tasks have been created, departments should be allocated to each
one. Each detail task must have at least one department responsible for performing the
work. Each time a department is assigned to a task, a cost account is created.
These cost accounts can then be divided into work packages which represent the detail
work involved. A cost account may contain multiple work packages spanning different
periods of time.
General types of control items are usually referred to as elements of cost, they are like the
resource requirements of an activity in a critical path network.
The cost control system utilizes the project breakdown structure to collect information,
develop reports, generate variances and produce plan revisions.
9
VARIANCES
Variances are used by management to verify cost and scheduling plans. Cost and
scheduling variances must be established together because:
1.-Cost variances alone only provide a deviation measurement from the budget without
considering work accomplished and its planned sequence. A project cost reported
performing exactly as planned only indicates that work for that amount has been
performed regardless of schedule sequential performance, which in time it may mean that
the project is getting late.
2.-Scheduling variances alone provide only a comparison between the work planned and
the one performed.
A project apparently on schedule may only indicate that additional costs have been
incurred to be on time.
VARIANCE DEFINITIONS
Some new concepts have to be introduced before the cost and schedule variances may be
defined. (see figure next page)
BCWS
The BCWS, also called the baseline, is the budgeted cost of the project and the curve in
the graphic next page shows how it is expected to be spent during the duration of the
project.
BCWP
The BCWP, also called the earned value, may be defined as the cost value resulting from
the difference between the original budget for any given cost account and the current
required budget to finished the cost account work.
ACWP
The ACWP, also called actual cost, is the accountability of all expenditures payed to date,
regardless what they are being applied to different accounts and schedule implications.
10
% COST % COST
REPORT DATE
(BAC)
BUDGETED COST AT COMPLETION FORECAST OVERRUN
BCWS
(BASELINE)
ACWP
(ACTUAL COST)
TIME
OVERRUN
BCWP
(EARNED VALUE)
TIME
COST VARIANCE
Cost variance (CV) is defined by,
CV = BCWP - ACWP
11
% COST % COST
REPORT DATE
EAC
BCWS BAC
ACWP AV
CV
SV
Legend:
AV = Account Variance
BCWP SV = Schedule Variance
CV = Cost Variance
TIME
SCHEDULE VARIANCE
Schedule variance (SV) is defined by,
SV = BCWP - BCWS
12
AT-COMPLETION VARIANCE
At-Completion variance (ACV) is defined by: ACV = BAC - EAC
Or, the difference between the budgeted cost at completion (BAC) and the estimated cost
at completion (EAC). Analysis of ACV will identify problems on,
Careful analysis of all variances should provide project management the tools to determine
problem areas, identify culprits, and take corrective action in a timely manner, as long as
the control systems and documentation is kept updated periodically and professionally.
13
PERFORMANCE RATIOS
Cost performance ratio.-
The cost performance ratio (CPR) measures the cost efficiency of the work accomplished.
CPR is defined as the ratio of the cumulative, budgeted cost of work performed over the
cumulative actual cost of work performed.
For instance, a CPR of 0.90 (90%) means that 90 contract-dollars worth of planned
work has been completed for every 100 dollars spent.
Schedule-performance ratio.-
The schedule performance ratio (SPR) indicates the schedule efficiency of the work
completed to date. SPR is the ratio of the cumulative budgeted cost of work performed
over the cumulative budgeted cost of work scheduled.
For instance a SPR of 0.80 (80%) means that only $80 worth of work has been
accomplished to date for each $100 worth of work scheduled.
14
MEASURING AND FORECASTING COMPLETION
One of the most important functions of project controls is to accurately evaluate the
physical progress of engineering, procurement and construction activities.
The following guidelines offer an objective method of determining physical progress for
each phase of a project from start of design to project completion.
Progress by drawing
Progress by discipline
Total engineering progress
Estimate
Prior to implementing a system for progress evaluation an estimate must be developed for
both manhours and quantities of drawings for each engineering discipline. For these
guidelines we will assume the estimate shown in Table 1 next page.
Progress Evaluation
Actual physical progress is measured against the drawings only. The progress
measurement for each engineering discipline and for the total engineering effort is a
function of the progress against each individual drawing.
15
DISCIPLINE ESTIMATED BUDGETED DISCIPLINE
DRAWINGS MANHOURS WEIGHTED
VALUE (%)
To objectively determine the physical progress against each drawing a series of milestones
are established to give credit for incremental work accomplished. The following is an
example of typical drawing milestones and their related values to the completed drawing:
Drawing Milestones
Start draft (20%) Layout and design completed and actual line work visible. Rough draft
of specification is completed ready for draft typing.
Draft complete (65%) Drawing has been completed by drafting, checked by chief
draftsman, and issued to engineering for checking. Specification is ready for checking.
Office check (80%) Engineering has reviewed the drawing and pertinent corrections has
been incorporated by draftsmen and engineers.
Owner review (85%) Drawing and specification have been reviewed by the owner and
returned with comments.
Final draft (90%) All engineering and owner comments have been incorporated and
drawing and specification have been issued to owner for approval.
Approval with holds (95%) Drawing and specification have been approved by owner
and are ready to be issued for construction with the exception that some portion(s) of the
drawing has "holds", waiting for final resolution.
Final owner Approval (100%) Drawing and specification have been approved by the
owner and they are ready to be issued as approved for construction with no "holds".
In order to control the drawing process and effectively monitor the accomplishment of the
above-mentioned milestones, a drawing control log should be maintained to record the
accomplishment of each milestone and identify the location of each in-process drawing.
16
Progress by Discipline
Now that the estimated number of drawings for each engineering discipline has been
established and the drawing milestones have been defined and assigned a weighted value,
the physical progress for each discipline can be evaluated.
For example, assume the work status shown in Table 2 for the 50 piping drawings
referenced in Table 1.
The progress for each of the other engineering disciplines could be calculated in the same
manner.
17
Total Engineering Progress
As each drawing milestone represents a portion of the total drawing, so does each
engineering discipline represent a portion of the total engineering effort.
Because certain disciplines may require more manhours per drawing than others,
depending on the nature and complexity of the project, the weighted value of each
discipline is determined by the engineering manhours budgeted to the project
To calculate total engineering physical progress, the percentage of drawing completion for
each discipline, would be multiplied by that discipline's weighted value. The product of this
calculation would be the discipline's contribution to total engineering progress.
For example:
The piping discipline, was calculated to be 65.5% completed. Let us assume the
percentages of completion for the remaining disciplines and the total engineering physical
progress would be calculated as shown on Table 3.
18
PROCUREMENT MEASUREMENT
Normally for a major project, the procurement of long lead technical equipment and
materials is a function of the engineering effort and it is included in the Engineering budget
as a separated item.
Material take-offs
Purchase requisitions
Purchase orders
To measure physical progress of the procurement effort, each of the three functions should
be weighted as a percentage of the total procurement effort. This weight factor should be
based on the budgeted manhours for each function relative to the budgeted manhours for
the total procurement effort. (see Table 4)
TOTAL 100
PROCUREMENT
VALUE
TABLE 4
Material Take-offs
Physical progress measurement for material takeoffs is based on the estimated number of
drawings requiring material takeoffs versus the number of drawings for which takeoffs
have been completed.
For example:
19
Drawings with takeoffs complete = 75
Purchase Requisitions
Physical progress measurement for purchase requisitions is based on the estimated total
number of purchase requisitions versus the number of requisitions approved for purchase.
For example:
Purchase Orders
Progress should be based on both the quantity of purchase orders placed and the
cumulative dollar value of materials shipped from the manufacturer's plant (explanted).
The quantity of purchase orders placed will contribute 50 percent progress and the dollar
amount of total material value explanted will contribute the remaining 50 percent.
For instance, the purchase order quantity is 100 with 28 purchase orders placed. The total
cost of purchase materials is estimated at 100 million dollars and from this amount
approximately 1 million dollars of materials has been explanted. Progress would be
calculated as follows:
20
Total Procurement Progress
By evaluating the physical progress of each major procurement function, the total
procurement progress can be determined (see Table 5).
TOTAL 29.0
PROCUREMENT
PROGRESS
TABLE 5
TABLE 6
21
CONSTRUCTION PROGRESS MEASUREMENT
There are two basic methods of determining physical progress for the construction phase
of a project, they are:
Intermediate Milestone
Percentage Complete
The approach to performing the construction phase of a project can vary considerably
from one project to another and from one contractor to another. Because of this fact, it is
very important that the activities and/or milestones selected as progress measurement
criteria reflect the contractor's approved work plan and schedule.
This means that even if the contractor has already started piping and electrical
construction, he receives no credit for physical progress until the corresponding milestones
are completed.
In the percentage complete method, credit is allowed for incremental work accomplished
against each activity based on the activity's estimated percentage of completion. The
22
estimated percentage of completion for an activity can be determined by two methods, as
follows:
Credit by units installed: Using this method of credit, the percentage of completion
for each activity is based on the units of work installed (e.g.: cubic yards, tons, linear feet)
for the activity versus the total estimated units required for completion.
Credit by earned manhours: This method is applied to activities for which a specific
unit of measure, other than manhours earned, would be misleading or difficult to identify.
This method also compensates for varying degrees of difficulty in installing similar units,
ie.: a squared foundation requiring 25 cubic yards of concrete would require much less
effort than a 5 cubic-yard specially shaped foundation yet, by the "units installed" method,
the one squared foundation would receive the same credit as the 5 shaped foundations.
For instance:
An activity is estimated to require 2000 manhours. To date, 1500 manhours have been
expended performing the activity.Project personnel estimate that it will require 1000
manhours to complete the remainder of the activity.
23
The actual manhours expended are not considered in the calculation of earned manhours.
Table7 next page, represents a condensed example of a list of weighted activities.
24
REFERENCES
25