ITP For Painting Works
ITP For Painting Works
1. General
Visual /
Prior to Start of
1.1 Approval of documents Document
work
Review
Visual /
Material Receiving Inspection and MTC On Delivery to
2.1 Document
Review site
Review
3. Internal Surface Painting- Internal walls, Ceiling, soffits and Steel doors, frames
INSPECTION AND TES
INTERNAL AND EXTER
Mock Up
Internal Painting - 600 x 600 mm or larger,
Pior to Start of
3.1 applied in-situ walls, for QP selection and Visual
the Activity
approval (adherence to below procedure)
Surface prepration
1)Concrete surfaces:Removal of loose
and damaged paint, sanding on existing
paint/plastered/rendered surfaces as
recommended by selected paint
manufacturer/painting system.
3.2 Visual Each work area
INSPECTION AND TES
INTERNAL AND EXTER
Primer Application
1) Concrete surfaces- For water based
surface : 1 coat Acrylic Primer
-For oil based surface : 1 coat
Enamel Primer
Stucco application
-For water based surface : 2 coats stucco
3.4 Visual Each work area
-For oil based
surface : 2 coat stucco
Paint Application
1. Concrete surfaces – 2 coats Washable
acrylic silk emulsion paint
Surface prepration
Remove existing painting on external
4.2 plastered/rendered surfaces as Visual Each work area
recommended by selected paint
manufacturer/painting system.
Primer Application
4.3 1 coat Acrylic Primer/Sealer Visual Each work area
INSPECTION AND TES
INTERNAL AND EXTER
Paint Application
4.4 2 coats Acrylic emulsion exterior paint, Visual Each work area
elastomeric, anti-carbonation
5. Final Inspection
W=WITNESS CHECK : RFI to be issued for client approval. Work may proceed beyond ‘W’ if Client Representative does not attend.
H=HOLD POINT : RFI to be issued for Client approval. No work shall proceed beyond ‘H’ point without approval.
INSPECTION AND TES
INTERNAL AND EXTER
S= SURVEILLANCE : Client / Others may carryout surveillance of work in progress on an unscheduled basis. No notification required.
R=REVIEW : The document to be submitted to client for review and approval.
SPECTION AND TESTING PLAN (ITP) FOR
ERNAL AND EXTERNAL PAINTING WORKS
ISO 9001,ISO 14001 &OHSAS 18
ontrol Tower and Systems at RLIC COMPAN
REV
Site Engineer,
Compliance with Project Approval for MAR- material
Project Specifications QA/QC
Specs and source
Engineer
MIR
Site Engineer,
Compliance with MAR and (AMC/LC17100200/MIR/001,
Approved MAR QA/QC
Material Delivery note Rev. 0/ 20.03.2018), Delivery
Engineer
note,(MTC if applicable)
SPECTION AND TESTING PLAN (ITP) FOR
ERNAL AND EXTERNAL PAINTING WORKS
ISO 9001,ISO 14001 &OHSAS 18
ontrol Tower and Systems at RLIC COMPAN
REV
RFI
AFC drawings,Approved (AMC/LC17100200/RFI/001, Site Engineer,
Compliance with Project
MS and QCS 2014 Rev. 0 , Issued Date: QA/QC
Specs
Section 26 06.03.2018), Engineer
Painting Check List
RFI
Suitable finish for application (AMC/LC17100200/RFI/001,
of primer, Moisture Rev. 0 , Issued Date:
Content<12% 06.03.2018),
Painting Check List
Approved MS, drawings Site Engineer,
and QCS 2014 Section 26 QA/QC
Part 2 Clause 2.3.1 Engineer
SPECTION AND TESTING PLAN (ITP) FOR
ERNAL AND EXTERNAL PAINTING WORKS
ISO 9001,ISO 14001 &OHSAS 18
ontrol Tower and Systems at RLIC COMPAN
REV
RFI
Dry flim thickness of 30 (AMC/LC17100200/RFI/001,
micron, min 24 hours drying Rev. 0 , Issued Date:
time for each coat 06.03.2018),
AFC drawings,Approved Painting Check List
Site Engineer,
MS and QCS 2014
QA/QC
Section 26 Part 3 Clause
Engineer
3.2
SPECTION AND TESTING PLAN (ITP) FOR
ERNAL AND EXTERNAL PAINTING WORKS
ISO 9001,ISO 14001 &OHSAS 18
ontrol Tower and Systems at RLIC COMPAN
REV
RFI
AFC drawings,Approved
Dry flim thickness of 100 (AMC/LC17100200/RFI/001, Site Engineer,
MS and QCS 2014
micron/coat, min 24 hours Rev. 0 , Issued Date: QA/QC
Section 26 Part 3 Clause
drying time for each coat 06.03.2018), Engineer
3.4.1
Painting Check List
RFI
AFC drawings,Approved (AMC/LC17100200/RFI/001, Project Engineer,
Compliance with Project
MS and QCS 2014 Rev. 0 , Issued Date: QA/QC
Specs
Section 26 06.03.2018), Engineer
Painting Check List
SPECTION AND TESTING PLAN (ITP) FOR
ERNAL AND EXTERNAL PAINTING WORKS
ISO 9001,ISO 14001 &OHSAS 18
ontrol Tower and Systems at RLIC COMPAN
REV
RFI
Approved MS, drawings Suitable finish for application (AMC/LC17100200/RFI/001, Project Engineer,
and QCS 2014 Section 26 of primer, Moisture Rev. 0 , Issued Date: QA/QC
Part 2 Clause 2.3.1 Content<12% 06.03.2018), Engineer
Painting Check List
RFI
AFC drawings,Approved
Dry flim thickness of 35 (AMC/LC17100200/RFI/001, Project Engineer,
MS and QCS 2014
micron, min 24 hours drying Rev. 0 , Issued Date: QA/QC
Section 26 Part 3 Clause
time for each coat 06.03.2018), Engineer
3.2
Painting Check List
SPECTION AND TESTING PLAN (ITP) FOR
ERNAL AND EXTERNAL PAINTING WORKS
ISO 9001,ISO 14001 &OHSAS 18
ontrol Tower and Systems at RLIC COMPAN
REV
RFI
AFC drawings,Approved Dry film thickness of 140 (AMC/LC17100200/RFI/001, Engineer,
MS and QCS 2014 Part 3 micron/coat, min 24 hours Rev. 0 , Issued Date: QA/QC
Clause 3.4.1 drying time for each coat 06.03.2018), Engineer
Painting Check List
Date: 12/09/2018
INSPECTION
INTERVENTION POINTS
AMC TPL QP
H - W/R
H - W/R
&OHSAS 18001 CERTIFIED GRADE A
COMPANY
Date: 12/09/2018
INSPECTION
INTERVENTION POINTS
AMC TPL QP
H - H
H - W
&OHSAS 18001 CERTIFIED GRADE A
COMPANY
Date: 12/09/2018
INSPECTION
INTERVENTION POINTS
AMC TPL QP
H - W
H - W
&OHSAS 18001 CERTIFIED GRADE A
COMPANY
Date: 12/09/2018
INSPECTION
INTERVENTION POINTS
AMC TPL QP
H - W
&OHSAS 18001 CERTIFIED GRADE A
COMPANY
Date: 12/09/2018
INSPECTION
INTERVENTION POINTS
AMC TPL QP
H - W
H - W
&OHSAS 18001 CERTIFIED GRADE A
COMPANY
Date: 12/09/2018
INSPECTION
INTERVENTION POINTS
AMC TPL QP
H - W
H - H
&OHSAS 18001 CERTIFIED GRADE A
COMPANY
Date: 12/09/2018
INSPECTION
INTERVENTION POINTS
AMC TPL QP
H - W
H - W
&OHSAS 18001 CERTIFIED GRADE A
COMPANY
Date: 12/09/2018
INSPECTION
INTERVENTION POINTS
AMC TPL QP
H - W
H - H
&OHSAS 18001 CERTIFIED GRADE A
COMPANY
Date: 12/09/2018
INSPECTION
INTERVENTION POINTS
AMC TPL QP