Core Cutter Test

The document summarizes soil test results from 3 test locations for a proposed 1132/11.5 kV grid station and transmission line project in DHA Phase VIII, Lahore. Test details include the weight and volume of sand used, wet and dry density measurements, moisture content, and percentage compaction compared to the maximum lab density. Signatures from contractor and consultant representatives are included to verify the test results.

Uploaded by

Mian M Khurram
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
121 views

Core Cutter Test

The document summarizes soil test results from 3 test locations for a proposed 1132/11.5 kV grid station and transmission line project in DHA Phase VIII, Lahore. Test details include the weight and volume of sand used, wet and dry density measurements, moisture content, and percentage compaction compared to the maximum lab density. Signatures from contractor and consultant representatives are included to verify the test results.

Uploaded by

Mian M Khurram
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 6

1132 kV (AIS) Grid Station Minchanabad

Client: MEPCO Height from Zero Level _______________


Contractor: PEL Date _______________
Consultant: BARQAAB Area _______________
Test Method Core Cutter Lab Dry Density 2.1
Test Location Detail:
Sr. No. Description Notation Unit Test-1 Test-2

Volume of Mould-
1 V cm^3 1025.061 1025.061
[{(3.14xDxD)/4]xH}/1000^3]

Weight of wet sample plus


2 W1 g 3450 3465
Mould

3 Weight of Mould W2 g 1200 1200

Weight of Wet Sample -


4 W3 g 2250 2265
(W1-W2)

Moisture Content from


5 m % 8.0% 9.0%
Speedy Moisture

Weight of dry sample-[W3/


6 W4 Kg 2083.34 2077.99
{(1+(m/100)}]

7 Density of Sample-(W4/V) D g/cm^3 2.033 2.028

Percentage Compaction-
8 C % 96.81% 96.57%
(D/Lab Dry Density)x100

9 Remarks - -

Contractor Representative Consultant Represen

Name: ___________________ Name: ________________

Designation ___________________ Designation ________________

Signature: ___________________ Signature: ________________

Date: ___________________ Date: ________________


Grid Station Minchanabad

____________________
____________________
____________________
g/cm3

Test-3

1025.061

3458

1200

2258

8.5%

2081.11

2.031

96.71%

Consultant Representative

____________________

____________________

____________________

____________________
1132/11.5 kV (AIS) Grid Station Including Allied Transmission Line (CBW Sajpal) DHA, Phase-
VIII, Lahore Height from Zero
Client: Level____________________
Contractor: Date ____________________
Consultant: Area____________________
Lab Dry Density____________________
Test Location Detail:
Sr. No. Description Notation Unit Test-1 Test-2 Test-3
1 Total Weight of Sand +cone+Bottal V m^3 0.00410024

2 Weight of sand +Bottal after pouring

3 Sand used in Hole and Cone (1-2) W1 Kg 2000

4 Weight of sand used in Cone W2 Kg

5 Weigh of sand used in hole (3-4) W3 Kg

6 Unit weight of Sand m %

7 Volume of Hole

8 Weight of Soil W4 Kg

9 Wet Density (8/7)

10 Moisture Content (m.c/100+1) D Kg/m^3

11 Dry Density (9/10) C %

12 Max Lab Density

13 Compaction % (11/12x100) - -
Contractor Representative Consultant Representative

Name: ___________________ ___________________ Name:____________

Designation ___________________ ___________________ Designation____________

Signature: ___________________ ___________________ Signature:____________

Date: ___________________ ___________________ Date:____________


1132/11.5 kV (AIS) Grid Station Including Allied Transmission Line (CBW Sajpal) DHA, Phase-
VIII, Lahore Height from Zero
Client: DHA Level____________________
Contractor: DESCON Date ____________________
Consultant: ENMASSE Area____________________
Lab Dry Density____________________
Test Location Detail: ____________________
Sr # Description Test 1 Test 2

1 Total Weight of Sand +cone+Bottal

2 Weight of sand +Bottal after pouring

3 Sand used in Hole and Cone (1-2)

4 Weight of sand used in Cone

5 Weigh of sand used in hole (3-4)

6 Unit weight of Sand

7 Volume of Hole

8 Weight of Soil

9 Wet Density (8/7)

10 Moisture Content (m.c/100+1)

11 Dry Density (9/10)

12 Max Lab Density

13 Compaction % (11/12x100)

Contractor Representative Consultant Representative Consultant Representative

Name: ___________________ Name: ___________________ Name:____________

Designation ___________________ Designation: ___________________ Designation____________

Signature: ___________________ Signature: ___________________ Signature:____________

Date: ___________________ Date: ___________________ Date:____________