Golden Success College Renovation and Expansion With ADDITIONAL FLOORS (Foundation To 3 Floor Column Dowels ONLY)

This document provides details of construction work done at Golden Success College in Cebu City, Philippines on May 27, 2017. It describes the scope of work completed that day which included preparing gravel beds, installing formworks for footings, fabricating footing formworks, adding spacers to the footing forms, and demolishing an existing wall. It notes that the building permit has not yet been released which is required for other permits and requests rerouting of high tension wires for safety.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
73 views3 pages

Golden Success College Renovation and Expansion With ADDITIONAL FLOORS (Foundation To 3 Floor Column Dowels ONLY)

This document provides details of construction work done at Golden Success College in Cebu City, Philippines on May 27, 2017. It describes the scope of work completed that day which included preparing gravel beds, installing formworks for footings, fabricating footing formworks, adding spacers to the footing forms, and demolishing an existing wall. It notes that the building permit has not yet been released which is required for other permits and requests rerouting of high tension wires for safety.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

RSG Construction & Development

Address: Sitio Tambisan, Brgy. Tisa, Cebu City


Cellphone No.: 09206221433/09420075631

GOLDEN SUCCESS COLLEGE RENOVATION AND EXPANSION WITH


ADDITIONAL FLOORS (Foundation to 3rd floor Column Dowels ONLY)

Golden Success College


1297 V. Rama Ave., Cor. Singson St., Guadalupe
Cebu City 6000, Philippines

Date: May 27, 2017


Weather: 8:00 am – Sunny; 1:00 am – Sunny
Project-in-charge:
 Arielle Nicole Tambanillo
 Sarah Emily Gudia
 Andrew Baydid

Manpower:

 Foreman – 1
 Electrician – 1
 Skilled Workers – 6

Scope of Works:

1. Gravel Bed Preparation

Fig 1: Footing half filled with gravel (Grid 1 – B) Fig 2: Finished gravel bed (Grid 1 – B & C)
RSG Construction & Development
Address: Sitio Tambisan, Brgy. Tisa, Cebu City
Cellphone No.: 09206221433/09420075631

2. Installation of Formworks

Fig 3: Workers installing formworks of footing Fig 4: Installed formworks on Grid 1 – B & C

3. Fabrication of Formworks for Footing

Fig 5: Workers building formworks for footing Fig 6: Finished formworks for footing

4. Spacers for Footing

Fig 7: Removal of spacers in forms Fig 8: Finished spacers for footing & column
RSG Construction & Development
Address: Sitio Tambisan, Brgy. Tisa, Cebu City
Cellphone No.: 09206221433/09420075631

5. Demolition of Wall

Fig 9: Worker demolishing the remaining wall Fig 10: Progress on demolition of wall

REMARKS:

 Building permit not yet released.


 Building permit is a requirement to get hauling permit.
 Building permit is a requirement to get fencing permit.
 Building permit is a requirement to get demolition permit.
 Request VECO to reroute high tension wires for safety. (Building permit is a requirement.)
 Ventilation on the side of the building not yet removed.