Day 24

The document provides details of a construction project including the scope of works, manpower involved, and photos of progress. It summarizes work done on the first day including demolition, installation of column and footing spacers and formworks, and preparing gravel beds. Remarks note that building permits are still needed.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
77 views3 pages

Day 24

The document provides details of a construction project including the scope of works, manpower involved, and photos of progress. It summarizes work done on the first day including demolition, installation of column and footing spacers and formworks, and preparing gravel beds. Remarks note that building permits are still needed.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

RSG Construction & Development

Address: Sitio Tambisan, Brgy. Tisa, Cebu City


Cellphone No.: 09206221433/09420075631

GOLDEN SUCCESS COLLEGE RENOVATION AND EXPANSION WITH


ADDITIONAL FLOORS (Foundation to 3rd floor Column Dowels ONLY)

Golden Success College


1297 V. Rama Ave., Cor. Singson St., Guadalupe
Cebu City 6000, Philippines

Date: May 26, 2017


Weather: 7:00 am – Sunny; 1:00 pm – Sunny
Project-in-charge:
 Arielle Nicole Tambanillo
 Sarah Emily Gudia

Manpower:

 Foreman – 1
 Electrician – 1
 Skilled Workers – 6
 Operator – 1

Scope of Works

1. Demolition of Walls

Fig 31: Remaining wall before demolition


RSG Construction & Development
Address: Sitio Tambisan, Brgy. Tisa, Cebu City
Cellphone No.: 09206221433/09420075631

2. Spacers for Column & Footing

Fig 32: Spacers for column & footing in their forms

3. Fabrication of Formworks (Footing)

Fig 30: Cutting of plywood to be used as forms Fig 33: Finished formwork

4. Installation of Formworks (Footing)

Fig 34: Workers lowering down formwork Fig 35: Workers installing formworks
RSG Construction & Development
Address: Sitio Tambisan, Brgy. Tisa, Cebu City
Cellphone No.: 09206221433/09420075631

5. Gravel Bed Preparation

Fig 36: Formwork of footing half-filled with gravel

REMARKS:

 Building permit not yet released.


 Building permit is a requirement to get hauling permit.
 Building permit is a requirement to get fencing permit.
 Building permit is a requirement to get demolition permit.
 Request VECO to reroute high tension wires for safety. (Building permit is a requirement.)
 Ventilation not yet removed.