Report 3 Operations and Maintenance Systems
Report 3 Operations and Maintenance Systems
PREFACE
1) In view of the rapid urbanization and growing economy, the country has been
moving on the path of accelerated development of urban transport solutions in cities.
The cities of Kolkata, Delhi and Bangalore have setup Metro Rail System and are
operating them successfully. Similarly the cities of Mumbai, Hyderabad and Chennai
are constructing Metro Rail system. Smaller cities like Jaipur, Kochi and Gurgaon
too are constructing Metro Rail system. With the new policy of Central Government
to empower cities and towns with more than two million population With Metro Rail
System, more cities and towns are going to plan and construct the same. It is
expected that by the end of the Twelfth Five Year Plan, India will have more than
400 Km of operational metro rail network (up from present 223 Km Approximate).
The National Manufacturing Competitiveness Council (NMCC) has been set up by
the Government of India to provide a continuing forum for policy dialogue to
energise and sustain the growth of manufacturing industries in India. A meeting was
organized by NMCC on May 03, 2012 and one of the agenda items in that meeting
was “Promotion of Manufacturing for Metro Rail System in India as well as formation
of Standards for the same”. In view of the NMCC meeting and heavy investments
planned in Metro Rail Systems, Ministry of Urban Development (MOUD) has taken
the initiative of forming a Committee for “Standardization and Indigenization of Metro
Rail Systems” in May 2012.
The committee had a series of meetings in June- August 2012 and a Base paper
was developed. With a view to promote domestic manufacturing for Metro Rail
Systems and formation of Standards for such systems in India, Ministry of Urban
Development has constituted various Sub-Committees on following topics:-
- Traction System
- Rolling Stock
- Signaling System
- Fare Collection System
- Operation & Maintenance
- Track Structure
- Simulation Tools
4) The Sub-Committee has since completed the assigned task, which effort has
culminated in the production of this report. The report covers the following:
i) Study of the Operation and Maintenance Practices on Metro Railways in
Delhi, Bangalore, Hyderabad, Chennai and Gurgaon
ii) Operation and Maintenance Practices in Foreign Metros
iii) Safety, Security and Disaster Management.
iv) Indigenization of Spares & Consumables.
v) Manpower and M&P Resources Deployed in Metros
vi) Operation &Maintenance cost.
vii) Outsourcing Complete O&M services – Experience in India
viii)Analysis of the study with Key findings &Recommendations.
The Sub-Committee would like to thank Dr. Sudhir Krishna (Secretary/MOUD), Shri. SK
Lohia (OSD/MOUD),Shri.IC Sharma (NPM/SUTP) and officials of Ministry of Urban
Development for undertaking this seminal work.
TABLE OF CONTENTS
0.0 EXECUTIVE SUMMARY: ........................................................................................................ 9
1.0 INTRODUCTION .................................................................................................................... 11
1.1 Background ........................................................................................................................ 11
1.2 Proceedings of Sub-Committee ......................................................................................... 11
2.0 OPERATION AND MAINTENANCE PRACTICES ................................................................ 13
2.1 Delhi Metro ......................................................................................................................... 13
2.2 Bangalore Metro ................................................................................................................. 18
2.3 Hyderabad Metro (LTMRHL).............................................................................................. 22
2.4 Rapid MetroRail Gurgaon Limited (RMGL) ........................................................................ 26
3.0 OPERATION & MAINTENANCE PRACTICES IN FOREIGN METROS .............................. 28
3.1 Singapore Metro (SMRT) ................................................................................................... 28
3.2 Seoul Metro: ....................................................................................................................... 29
3.3 Bangkok Metro (MRT): ....................................................................................................... 29
3.4 Key Performance Indicators – Foreign Metros .................................................................. 30
3.5 Nova and CoMET Key Performance Indicator System ...................................................... 31
4.0 SAFETY, SECURITY AND DISASTER MANAGEMENT ...................................................... 34
4.1 Delhi Metro ......................................................................................................................... 34
4.2 Bangalore Metro ................................................................................................................. 35
4.3 Rapid Metrorail Gurgaon Ltd (RMGL) ................................................................................ 37
5.0 INDIGENISATION OF SPARES & CONSUMABLES ........................................................... 38
5.1 Delhi Metro ......................................................................................................................... 38
5.2 Bangalore Metro ................................................................................................................. 38
6.0 MANPOWER AND M&P RESOURCES DEPLOYED IN METROS ...................................... 39
6.1 Delhi Metro ......................................................................................................................... 39
6.2 Bangalore Metro ................................................................................................................. 41
6.3 Hyderabad Metro ............................................................................................................... 42
6.4 Rapid Metrorail Gurgaon Ltd (RGML) ................................................................................ 42
7.0 OPERATION AND MAINTENANCE (O&M) COST ............................................................... 43
7.1 Delhi Metro ......................................................................................................................... 43
7.2 Bangalore Metro ................................................................................................................. 44
7.3 Rapid Metrorail Gurgaon Ltd (RGML) ................................................................................ 44
7.4 Hyderabad Metro (LTMRHL).............................................................................................. 44
7.5 Foreign Metros ................................................................................................................... 44
8.0 OUTSOURCING COMPLETE O&M SERVICES–EXPERIENCE ......................................... 45
8.1 Background ........................................................................................................................ 45
8.2 Scope of O&M Services ..................................................................................................... 45
ABBREVIATIONS
AFC Automatic Fare Collection System
AMS Asset Management System
APTA American Public Transportation Association
ATC Automatic Train Control
ATO Automatic Train Operation
ATP Automatic Train Protection
ATS Automatic Train Supervision
BMRCL Bangalore Metro Rail Corporation Limited
BMS Building Management System
CATC Continuous Automatic Train Control
CBTC Communication Based Train Control
CCTV Close Circuit Television
CISF Central Industrial Security Force
CMRL Chennai Metro Rail Limited
CMRS Commissioner of Metro Rail Safety
COD Commencement Date
CoMET Community of Metros
CRA Customer Relation Assistant
CSIR Council of Scientific and Industrial Research
DAMEL Delhi Airport Metro Express Limited
DBFOT Design Build Finance Operate and Transfer
DCC Depot Control Centre
DDMA Delhi Disaster Management Authority
DG Diesel Generator
DLP Defect Liability Period
DMP Disaster Management Plan
DMRC Delhi Metro rail Corporation
DPR Detailed Project Report
ERP Enterprise Resource Planning
GoAP Government of Andra Pradesh
GOI Government of India
GoK Government of Karnataka
IFA International Finance Advisory
IISc Indian Institute of Science
IIT Indian Institute of Technology
ISA Independent Safety Assessor
KISF Karnataka Industrial Security Force
KMRC Kolkata Metro Rail Corporation
KPI Key Performance Indicator
LTA Land Transport Authority
1.0 INTRODUCTION
1.1 Background
Ministry of Urban Development formed a Sub-Committee for Standardization of
O&M Practices for Metro Rail Systems vide letter no. K-14011/26/2012-
MRTS/Coord dated 25.07.2012 (Annexure-1). The terms of reference of the Sub-
Committee are as under:
Study of the Operation and Maintenance practices adopted by DMRC,
BMRCL and Kolkata Metro
Study of the Operation and Maintenance practices adopted by metros
outside India
Study of currently imported spares / consumables which can be
considered for indigenization
Detailed study of manpower, M&P, resources deployed by DMRC /
BMRCL for different systems and civil infrastructure maintenance
Report of study, analysis and recommendations duly suggesting
standardization / benchmarking of maintenance practices
The members of the Sub-Committee are as under:
(a) Shri DD Pahuja, Director (RSE)/BMRCL – Convener
(b) Shri AK Gupta, CGM, DMRC
(c) ShriSKSinha, GM(HR), DMRC
(d) Shri Prakash Singh, Director MRTS/MOUD
(e) ShriDeenDayal, Under Secretary (MRTS)/MOUD
(f) ShriSalabhTyagi, Director (PE)/RDSO
(g) ShriSujit Mishra, Director (TI)/RDSO
(h) ShriAlokKatiyar, Director (Signaling) / RDSO
(i) Director (Track / Bridges) / RDSO
(j) Shri Anil Kumar Saini, System Head, L&T HMRL
(k) Shri Anil Jangid, Professional Consultant
(l) Shri Parveen Kumar, Sr. V.P. RMGL
(m)ShriKeshava Prasad, GM/Rail System Siemens/FICCI
(n) Shri R. Satish Director / CII
(o) Shri D.S Rawat Secretary / ASSOCHAM
Gupta, CGM, DMRC, Shri Anil Jangid, Professional Consultant and officers from
O&M wing of BMRCL.
Based on the inputs collected/made available so far, this study report has been
prepared.
The first section, on the Red Line, Shahdara to Tis-Hazari of 7 RKM opened in25
December 2002, followed by the Yellow Line in 2004, the Blue Line in 2005, its
branch line in 2009, the Green and Violet Lines in 2010, and the Delhi Airport
Metro Express in 2011, and is being operated & maintained by a private
concessionaire M/s Reliance Infra for a period of 30 years.
The Delhi Metro is being built in phases, Phase 1 completed 65.11 RKMwith59
stations and the inauguration of the Dwarka-Barakhamba Road corridor of the
Blue Line marked the completion of Phase 1in October 2006.
Phase 2 of the network comprises 128 RKM with 79 stations, and is fully
completed, with the first section opened in June 2008 and the last line opened in
August 2011.
2.1.4 The Operation and Maintenance of major assets generally undertaken in-house
is as under:
(e) Passenger Earning: Total revenue from Fare Box collection. Rs 1,061,679,660
(for January, 2013)
(f) Passenger KM: Total distance travelled by each passenger on metro trains,
summed-up for all passengers. 885,980,174 (for January, 2013)
(g) Car Hours: Actual time in which each car is operating in revenue (passenger
carrying) service, summed-up for all cars.19,888,732.9 (Jan 2013)
(h) De-boarding: Train withdrawn from service and passengers need to be de-
boarded en-route from the train due to failure. 2 Trains (for January, 2013)
(i) Trips run on time: Number of trips run as per scheduled time. 80,875 (Jan 2013)
DMRC have not yet started following the KPI as per international benchmarks
and they are in the process of implementing such system.
2.1.7.2 DMRC has recently started monitoring the following KPIs on monthly basis:
SN Key Performance Indicator For the Month
- Jan 2013
1 Staff Cost (Rs. in lacs) 2276.80
1a No. of Staff 5870.00
1b No. of Route Km. 166.29
1c a) Staff/Route Km. 35.3
1d b) Avg. Cost/Staff (Rs. in lacs) 0.39
4 Operation 170.12
4.1 Cost of Ticketing ( Exp. on TOM Operators) 170.12
(Rs. in lacs)
4.2 Cost of Ticketing per station (Rs. in lacs) 1.24
4.3 Avg.No. of TOM Operators 812
4.4 Cost per operator (Rs. in lacs) 0.21
6 S&T 568.72
6.1 Repair & Maintenance cost (Rs. in lacs) 568.72
Repair & Maintenance cost per station (Rs.
6.2 4.15
in lacs)
Annexure-4F Maintenance Schedule, Down time and man hours for AFC
System
Annexure-4G Maintenance Schedule, Down time and man hours for Civil
Structures and Works
Annexure-4H Maintenance Schedule, Down time and man hours for
M&P
Annexure-4I Maintenance Schedule, Down time and man hours for Lifts,
Escalators and D.G. Sets.
The comparison of maintenance periodicity, down time and man hours required,
between DMRC and BMRCL for rolling stock is as under:
SN DMRC BMRCL
1 Daily check (30 min, 2 staff=1 Daily check (30 min, 2 staff=1
man hour) man hour)
2 5,000km / 15 days (2 Hrs, 4 staff 6,000km / 15 days (1.5 Hrs, 4
= 8 man hours) staff = 6 man hours)
3 15,000km / 45 days (8 Hrs, 7 18,000km / 45 days (4 Hrs, 8
staff = 56 man hours) staff = 32 man hours)
4 30,000km / 90 days (8 Hrs, 7 36,000km / 90 days (6 Hrs, 8
staff = 56 man hours) staff = 48 man hours)
5 60,000km / 180 days (8 Hrs, 12 72,000km / 180 days (12 Hrs, 8
staff = 96 man hours) staff = 96 man hours)
6 1,20,000km / 360 days (16 Hrs, 15,0000km / 1 Year (20 Hrs, 8
13 staff = 208 man hours) staff = 160 man hours)
7 2,40,000km / 720 days ((16 Hrs, 3,00,000km / 2 Years (28 Hrs, 8
13 staff = 208 man hours) staff = 224 man hours)
8 4,20,000km / 3.5 years (3096 5,20,000km / 3.5 years (10 days,
man hours) 4 staff per car)
9 8,40,000km / 7 years (7910 man 10,40,000km / 7 years (20 days,
hours) 4 staff per car)
The project is under construction and is likely to commence operation in the year
2015-2016.
2.3.3 Approach and Methodology of operation & maintenance:
L&T Metro Rail Hyderabad Limited shall operate and maintain the Project in
accordance with the Concession Agreement. For this, LTMRHL has entered into
an operation and maintenance agreement and engaged a professional Operator
to operate and maintain the system. Tenders based on International Competitive
Bidding were called for the selection of OMC (Operation and Maintenance
Contractor) for performing the O&M deliverables. The objective of LTMRHL is to
engage a world class metro operator with a credible operating track record.
Keolis SA (a subsidiary of SNCF France) has been selected as the O&M
Operator for 5 years from amongst Keolis, SMRT, Veolia-RATP, Serco and
Seoul Metro.
Keolis SA has the experience, expertise, capability and know-how to ensure that
the O&M deliverables are executed in accordance with the terms of the O&M
Agreement in a timely, safe and environmentally responsible manner.
The security of the Metro Rail Project is the responsibility of GoAP, who would
provide all staff, resources and equipment required for security arrangements
except that fixed security equipment at stations will be provided by LTMRHL as
part of station works.
2.3.3.1 Scope of O & M Contractor (OMC):
Keolis SA shall act as the Operation and Maintenance consultant in the start-up
phase as part of early Operator involvement and thereafter operate and maintain
the MRTS project upon its commissioning in various stages. The scope of work
of Keolis SA is divided into three phases:
(1) Consultancy phase
(2) Pre-Operation phase
(3) Operation & Maintenance phase
The detailed scope of work of OMC in each of the above phases is given in the
Annexure-6.
b. A detailed plan to describe how the OMC is going to achieve each KPI
requirement;
c. A database and the methodology to capture the required KPI in the system.
iii. Operation has large & complex external interfaces and, for a small
system, perceived risks by external agencies generally do not fit
economies of scale.
i. Station Security
ii. House Keeping and Cleaning activities
iii. Ticket Vending
iv. Maintenance of Telecommunication, Automatic fare collection, Track
and Building infrastructure.
RMGL are likely to commence operations in the year 2013-2014.
The first section of the Blue Line between Hua Lamphongand Bang
Sue has 18 operational stations along 27 Km of underground track with a
fleet of 19 trains.
The MRT Purple Line is under construction and It will connect Bang
Sue with Nonthaburi in the north-west, and will be the first public transit
line outside the Bangkok Metropolitan Administration.
3.4.3 Direction level, lagging KPIs shall be derived from the Organization values and
objectives, O&M Agreement and Quality and Performance Module.
3.5.4.3 Customer
Capacity Provision & Utilization
C1 Capacity km / Route km
C2 Passenger km / Capacity km
3.5.4.4 Service Quality
C3 Passenger Hours' Delay / Passenger Journey
C4 Passenger Journeys On Time / Passenger Journey
C5a/b Trains On Time / Total Trains (scheduled + actual)
C6 Train Hours Operated / Hours of Train Delay
3.5.4.5 Internal Processes
Reliability & Availability
P1a/b % of Cars Available & Used in Peak Hour
P2a/b Car km / hours between Incidents (by category)
3.5.4.6 Efficiency
P3 Passenger Journeys / Staff + Contractor hours
P4a/b Capacity & Car km / Staff + Contractor hours
P5 Train hours / Driver Hours
P6 % Employee Absenteeism
P7 Traction Energy Consumed / Car km
P8a/b Total Energy Consumed / Passenger Journey & km
3.5.4.7 Safety & Security
S1 Total Fatalities / Passenger Journeys
S1a Deaths from Suicide / Passenger Journeys
S1b Deaths from Accidents / Passenger Journeys
S1c Deaths from Illegal Activity / Passenger Journeys
S2 Incidences of Crime / Passenger Journeys S3a/b Staff Lost Time through
Accidents / Staff Hours
3.5.4.8 Environment
E1 CO2 per Passenger km
5.1.2 The suggestions of DMRC for such currently imported items, which can be
developed through indigenous sources, are also provided in Annexure-9.
5.2.2 The suggestions of BMRCL for such currently imported items, which can be
developed through indigenous sources, are also provided in Annexure-10.
6.1.2 The current O&M manpower in DMRC, including managerial and supervisory
staff is as under (as on 1.11.2012):
No.
Total
SL of No. of
Staff
N Post staff staff
Line
o Line- Line-2
1&2
1
Senior Section Engineer
1 46 62 108
(SSE)/Section Engineer (SE)
Asst. Section Engineer (ASE) /
2 106 145 251
Junior Engineer (JE)
Sr. Maintainer/ Maintainer/
3 309 437 746
Customer Relation Manager CRM)
4 Unskilled 6 13 19
5 Track Maintainer 9 12 21
6 Track Men 20 26 46
7 Station Controller 65 72 137
8 Train Operator 102 152 254
9 Finance , HR ,Stores 18 24 42
Total 681 943 1624
6.2.3 There were initial cases of wheel flat in BMRCL. Thereafter, BMRCL resorted to
mill scale grinding of rails (by borrowing grinding machine from DMRC ). Rail
grinding has helped BMRCL achieving better rail wheel interaction, squeaking
noise has reduced, rail profile is better, current collection is better, wheel re-
profiling has reduced.
The project is under construction and is likely to commence operation in the year
2013-2014.
(Rs In Lakh)
SN Year Network Total O&M Total O&M O&M Cost O&M
Size (km Cost Revenue / RKM Revenue/RKM
1 2007-08 65.10 20035.44 31701 307.76 486.96
2 2008-09 74.56 22807.27 39287 305.89 526.92
3 2009-10 95.80 28898.64 52720 301.66 550.31
4 2010-11 160.87* 48890.63 93865 303.91 583.48
5 2011-12 166.76* 62784.90 128157 376.50 768.51
DMRC confirmed that out of total energy, 54-56% is on account of traction and
remaining on account of auxiliary systems. This is based on the actual data of
past 5 years.
8.4.6 Converting the Concessionaire‟s cost estimate into a Public Sector Comparator
(PSC)
To accurately compare the Concessionaire‟s cost estimate with the
Financial proposals received for the Metro Rail System O&M Contract
tender, the Concessionaire estimate should be adjusted using the
methodology for developing a PSC, namely:
Appropriate costing of all the risks that are transferred to the Operator
under the O&M contract and inclusion within the PSC.
Application of competitive neutrality principle with regards to tax.
Then a VFM calculation can be made to determine if the private approach
yields value for Concessionaire.
I. Adjustments were applied to the Concessionaire‟s O&M Cost estimate of
Rs. 1127 Cr for KPI risks, Electricity risks, Pre-operation cost risks, O&M
cost risks and Inflation risks as per details given below.
II. Risk allowance summary
Elements Details INR in Cr
Pre-operation period 103.4
Operations Period 1023.6
Concessionaire Base O&M Cost 1127.0
Estimate (DMRC and BMRCL
experience as the basis)
IFA recommended risk allowances
KPI risk 5% of 1024 Cr +51.2
Electricity Risk 60% of 234 Cr +140.4
Extended pre-operation risk 50% of 103.39 +51.7
Cr
O&M cost overrun risk 10% of 790 +79.0
Inflation risk See table +59.2
Revised Concessionaire PSC 1508.5
8.4.7 Since the lowest bid was found near the revised Metro Rail System PSC, the bid
was recommended for acceptance by IFA.
8.5 Decision Making
8.5.1 The Board of Directors of Metro Rail System appointed a sub-committee of
Directors to analyze the key findings presented by IFA and to submit their
recommendation on the following:
The responsibility for getting the constructed system certified fit for safe
carriage of passengers from CMRS rest with the Concessionaire. As per
the current practice and rules the agency to whom operations and
maintenance is outsourced cannot approach directly CMRS for safety
certification process.
The operating and maintaining staff either employed by the
Concessionaire or O&M Service contractor, being part of certification
process can be given competency certificate by the Concessionaire
only. As per the past experience CMRS did not accept competency
certification of drivers and other personal by DAMEL in case of Delhi
Airport line. This can be perhaps handled by setting up an accredited
training institute authorized to train and issue competency certificate to
O&M personal of belonging to the Concessionaire or O&M service
contractor. The competency certificate issued by accredited institute
should be acceptable to CMRS.
For any accident/unsafe operations due to fault of personal, the
responsibility and liability rest with the O&M service contractor as per
the conditions of contract agreement between the Concessionaire&
Contractor. However, the owner will be held responsible to CMRS as
well as other government authorities in respect of all safety related
issues.
Apart from the above there were certain more legal complications in the
financial bids having different interpretations and opinions from legal
experts.
8.5.3 The Board of Directors of Metro Rail System have decided to discharge this
tender. And it is learnt that Metro Rail Authority is planning to take up O&M
activity on the lines of Delhi Metro and Bangalore Metro.
F.No.K-14011/26/2012-MRTS/Coord
Government of India
Ministry of Urban Development
(MRTS CELL)
ORDER
The undersigned is directed to: say that with a view to promote the
domestic mar.lUfacturimm for
.
Met.ro Syst~ms
'; .
and formati9n'.;of
.
standards for
such systems in India, th;-S Ministry lhas constituted' a Group"fqr prep'aning a
Base paper on Standardization and 'l(;Idigel'lization of Metro Railway Systems
vide Order'ofeven number dated 3.(jth ·May, 2012 (copy enclosed).
and industries associated with rail based systems / Metro Railway Systems.
1
Issues Terms of Reference Members of Sub-Committee 1,"
~ Standardi?ation of {;\. Study . of the Shri D.O. Pahuja, Director
maintelilalilce U maintenance and (Rolling ~tock &
practices; eDf metro operating signalling), BMRC -
infrastrpctClFe, practices adopted Convener
systen:)s and by DMRC, BMRCL
rolling stoc~ and Kolkata Metro Shri Prakash Singh,
Director(MRTS), MoUD
~ Identification of- Study of the
sub. maintenance and Shri Deen Dayal, US
systems/compone o~erating (MRTS) Coord , MoUD
nts items for practices adopted
sustainable by metros outside Shri Salabh Tyagi, Direct,..·-·
operation & India (PE) , RDSO, Lucknow
maintenance (over
and above the list - Study of currently Shri Sujit Mishra, Director
already identified imported spares / (TI), RDSO , Lucknow
by consumables
DMRC/BMRCL) which can be Director/Signalling - RDSO,
considered fo r Lucknow
indigenization
DirectorlTracklBridge -
- Detailed study of RDSO, Lucknow
manpower, M&P ,
resources One officer to be nominated
deployed by by MDtDMRC
DMRC / BMRCL
for different Shri Anil Jangid
systems al'ld civil (Professional already .
infrastructure associated with Committf
maintenance preparing the Base Paper)
2
4. FICCI ! CII / ASSOCHAM will nominate representative only from those
Industries who are having long association with Design / manufacture of Rail
Based rolling stocks . with three phase drive (propulsions), systems! sub
systems infr~~tructu.~~s, i.e. IIGBT based propulsions/signalling systemsfThird
~~ifj6~erheaJi~<;elect~ic tractiom/AFC-ticketimg and Power supply system
spe'ciallY uslcJ;;ih lM~tfO Railways.
6. The Sub-C.omrnitte.e shall summit its Report within one month (by
21 .8.2012) to Secretary (UD), Ministry of Urban Developmentfrom the date of
~
issue of this Order.
)~'1 Ill-
(Deen Dayal)
Under Secretary to the Gov!. of India
Tel. 23~62935 / Fax. 23062594
E-mail : [email protected]
• To
3. Managing Director, Delhi Metro Rail Corporation Ltd ., Metro Shawan, Fire
Brigade Lane, Sarakhamba Road ,. New Delhi-110001 with the request to
norninate one officer"from DMRC.
3
4. Secretary, FICCI, Federation
, House, Tansen Marg, New Delhi 110001 .
1. PS to UDM
2. Sr. PPS to Secretary (UD)
3. OSD(UT) & E.O . Joint Secretary
4. Director (UT)
5. Director (MRTS-I)
6. Advisory to OSD (UT)
7. US (MRTS-I) / US (MRTS-II) / US (MRTS-III) / US (MRTS-IV)
~
(Deen Dayal·
Under Secretary to the Govt. of India
4
ANNEXURE-2
ANNEXURE-3A
Maintenance Schedule, Downtime and Man hours for Rolling Stock adopted at
DMRC
Page 1 of 22
ANNEXURE-3A
Study of Operation & Maintenance practices adopted at DMRC
Page 2 of 22
Daily Internal
16 Daily 1 1 1
Cleaning (SBL)
Internal light - - -
17 Weekly
Cleaning
Monthly Heavy
Cleaning (Exterior
18 Monthly 6 8 48
& Interior + Roof
Cleaning)
External Washing
19 Daily(AWP) 2 2 4
(window cleaning)
Pest and Rodent
20 Bi-monthly 01 Hrs 02 02
Control
- - -
21 Air duct cleaning Half yearly
Page 3 of 22
ANNEXURE-3B
Maintenance schedule Down time and manpower for traction power
supply/distribution system adopted at DMRC
Maintenance schedule
(Interval)
Inspection Down
AC Required
quarterly
SL to be done
Monthly
time
weekly
traction man
yearly
yearly
yearly
no with in
half
two
system hour power
interval
Page 4 of 22
checking
Cantilevers
11 and yes 0.5 6
(at grade)
adjustment
Cleaning of
ST and BT Cleaning
12 insulators of and yes 0.25 6
polluted checking
zones
Contact
13 Checking yes 0.25 6
Wire Dia
sea
Tree
14 trimming son 0.3 6
trimming
al
Kite, Thread sea
15 / Bird nest son 0.3 4
removal al
checking
Neutral
16 and yes 1.5 6
Section
adjustment
Bond &
17 Earthing yes 0.3 2
Connection
Mast for
18 graded inspection yes 0.1 2
section
POWER SUPPLY AND INSTALLATION
Maintenance schedule
Do
(Interval)
Inspectio wn
Required
quarterly
SL AC traction n to be tim
Monthly
weekly
man
yearly
yearly
yearly
two
power
interval hou
rs
Power checking
1 transformer and yes 2.5 5
(AT & TT) cleaning
checking
CT/CVT/PT and yes 1 4
2
at RSS cleaning
testing and cleaning yes 24
checking
and yes 1 4
3 Isolator cleaning
testing and
yes 2 4
cleaning
checking
and yes 0.25 4
4 LA
cleaning
testing and yes 0.5 4
Page 5 of 22
cleaning
checking
and yes 2 4
SF6/vacuu
5 cleaning
m CBs
testing and
yes 3 4
cleaning
Control checking
6 panels at and yes 2 4
RSS cleaning
checking
ASS
7 and yes 3 4
cleaning
cleaning
checking
and yes 2 4
8 33 KV CB cleaning
testing and
yes 3 4
cleaning
checking
Dry type
9 and yes 2 4
transformer
cleaning
Battery checking
10 charger and and yes 2 2
battery bank cleaning
AC DB and
DC DB checking
11 maintenanc and yes 1 2
e at RSS cleaning
and ASS
Earth
resistance Measurem
12 yes 0.5 3
measureme ent
nt
Page 6 of 22
ANNEXURE-3C
Maintenance schedule, Down time and Man power for Track adopted at DMRC
Page 7 of 22
Recording
Inspection and
13 Maintenance Yearly 3 1+4 279 93*3=279
of Buffer Stops
Measurement
of Toe
14 Yearly 1 1+3 834 834*1=834
Load(per
30mtrs)
Measurement
of Rail wear(up
15 to 30 Stations) Half yearly 4 0+1 880 110*4*2=880
for Ballasted
track
Measurement Done along with
16 Monthly
of creep Foot inspection
Inspection and
Maintenance Done along with
17 Weekly
of Fastenings Track Patrolling
and Fittings
Maintenance As per requirement -
Once in 2
18 of Ballasted 1+20 staff for 4 hrs. NA NA
yrs.
Track by TTM daily
Greasing of
Once in 3
19 ERC clips (30 5 0+5 23334 70,000/3
Year
clips/man/day)
Greasing of
once in 5
20 outer Rails on 3 0+2 4161 19*3*73=4161
days
curves
Preventive and
need based
21 Rail grinding Yearly 6 1+2 1152 192*6=1152
for operation of
RGM
Attention of
drainage pipes
22 on viaduct / Monthly 3 1+1
via-duct
cleaning
23 REJ Inspection Quarterly 3 1+4
Officers
24 Weekly 4 1+4
Inspection
Joggled Fish
25 Quarterly 3 0+2
plates Maint.
Page 8 of 22
ANNEXURE-3D
Maintenance schedule, Down time and Man power for Signaling Systems
(DMRC)
Page 9 of 22
Details of Maintenance Activity
Schedule
Maintenance of VCC Detector-
1 Checking for Wiring & Contacts in Good Condition
2 Oil in each Hole over the Camshafts
Maintenance of Drives:- Monthly
1 Removing of the Surplus of Old Grease from all axles
2 Greasing of all axles
Maintenance of MJ 81:-
1 Checking for Case, Cover & Gear Box Housing in Good Conditions
2 Checking for Internal Gear Box Components in God Condition
3 Checking for Crank - Pin/Crown, roller & Lyre in Good condition
4 Checking for Absence of any Abnormal Oxidation
5 Checking for incoming Wires Property Secured
Monthly
6 Checking for Electrical Contacts in good Condition
7 Cleaning inside the MJ 81
Oiling of Gears, Teeth of Crank - Pin Crown & Control Shaft
8
Bearings
9 Greasing of Internal Part of the Lyre
P-3
Maintenance of Drives
1 Checking for Condition & Tightening of all Fittings & Bolts
2 Checking for Condition & Tightening of all nuts securing the Forks
3 Checking of all Rods in Good Condition Quarterly
4 Checking for Presence & Condition of All split Pins
5 Checking for wear on crank pins
6 Checking for Wear of Insulating Bushes & Washers on Axles
Maintenance of VCC Clamp Lock:-
1 Checking for Wear of the Locking Crank Pad
2 Checking for Wear of the Locking Piece
Checking for Wear of the Locking Crank supporting Shoe (Presence Quarterly
3
of the Chamfer).
Checking for Wear of the Locking Crank Joint (when gap on shim
4
plates).
Maintenance of VCC Detector-
1 Checking of Finger Working with switch rail Open Condition
Checking for the good compression stroke of contact blades of Quarterly
2
detector
3 Checking for good sliding stroke of the cam assembly
Maintenance of MJ 81:-
1 Checking for Condition & Tightening of all Fittings & Bolts
2 Measurement of the Manual/Motor establishment Contact Distance Quarterly
3 Measurement of the Clearance of the Dog Clutch on Motor Position
4 Checking for Gap Between Plastic Control Roller & dog Clutch
MAINTENANCE SCHEDULE FOR SDTC
S.No Details of Maintenance Activity Schedule
Page 10 of 22
T-1 SDTC Maintenance Track Side Activity
Visual Check:-
1 Verification of Tuning Unit Box Earthling
2 Cable Termination on Tuning Unit
3 CAD Weld Joints
4 Condition of Glued Joints
Quarterly
5 Condition of E-Joints
6 Condition of Rail Clips
Shunt Test
1 Vrx/Freq. (with 0.5 ohm, 0.2 ohm)
2 Vrx/Freq. (with pre-shunt)
Replacement of Filters
T-2
Measurements:-
Outdoors:
1 I-Rail:
Normal DOT every
2 V-Rail:- at TX end Va & Vb
Quarter and Reverse
3 Directionality (Va / Vb DOT every six months
4 Q-Factor
5 V-Rail:- at Rx and Vc & Vd.
6 Directionally (Vc/Vd)
Indoors:
1 Input Power Supply (V.AC)
Tx Card:- Normal DOT every
1 Tx-50V DC Voltage Quarter and Reverse
2 Vtx/Freq. DOT every six months
Rx Card
1 Vix/Freq.
RT Card:-
Normal DOT every
1 O/P Vdc
Quarter and Reverse
2 MSR Vdc DOT every six months
3 20 Khz Vac
MAINTENANCE SCHEDULE FOR Signal
S.
Details of Maintenance Activity Schedule
No.
S-1
1 Cleaning of Aspect Housing & LED Unit.
2 LED Functioning.
3 Earthing Verification
Quarterly
4 Cleaning of STB & SRB Box.
5 Tightening of all Nuts & Bolts.
6 Healthiness of all Supports, Brackets & Foundation etc.
7 Voltage Check in STB
ROUTE INDICATORS (RS-1) Quarterly
Page 11 of 22
1 Breakage of Lens.
2 Cleaning of Lens & Lamps.
3 Cleaning of Route indicator Housing
4 Lamp Functioning. (UECR Test with two Lamps)
MAINTENANCE SCHEDULE FOR UPS/SMPS
CCIP Schedule
S.No. Details of Maintenance Activity
C-1
1 Cleaning of Front Face of CCIP with Dry Cloth
2 Check Fans are working
Quarterly
3 Check Proper Working of Push Buttons
4 Check Proper Operation of Counters
C-2
1 Cleaning of front face of CCIP with Vacuum Cleaner
SIX
2 Cleaning of inside of panel with Vacuum Cleaner
MONTHLY
3 Functioning of Buzzer
ESP Schedule
S.No. Details of Maintenance activity
1 ESP Functional Test Quarterly
MAINTENANCE SCHEDULE FOR UPS/SMPS
S.No. Details of Maintenance activity Schedule
UPS/SMPS Maintenance activity:-
1 Battery Float Charge Voltage
Weekly
2 Battery Charge Current
3 O/P voltage & O/P current (R, B, Y & freq.) for UPS-1 & UPS-2
4 Battery Terminals
5 Checking of loose Connections Monthly
6 Checking of any Leakage from Cells
7 Average Ambient Temperature
Individual Cell Voltage on Float:-
1 Cleaning of Cells
2 Individual Cell voltage on Float
3 Spare Cells Voltage
Monthly
Battery tested on Load:-
1 Battery voltage before load test & after load test
2 Battery charge (%) after load test
3 Charging current after load test
4 Load during test (L1, L2, and L3 in KVA) for UPS-1 & UPS-2.
Cleaning of (PDC, UPS, IDB, SMPS, SCVS & BSC)
1 PCBs
Working Condition of:- As per PM
1 Cable & connectors Schedule
2 Cabinet Doors
3 Switching between UPS-1, UPS-2 & SCVS
Page 12 of 22
ANNEXURE-3E
SL
System Monthly Quarterly Half Yearly Yearly
No
BER Testing of
Power Checking loss of redundant cards STM
Cleaning supply (- spare fibers both input and output power
of Rack & 48V) sides of a station level with optical power
1 FOTS
checking checking at Checking of FMS, meter Testing of SDH
of alarms SDH jumpher cable and ring Cleaning of
equipment. connector equipments at card
level
Cleaning
and testing Cleaning
Checking and
of Zetron and Testing Cleaning and checking
cleaning of BDA in
sets and Train radio all connection of EBTS
U/G stations Internal
2 RADIO antennas Units. & Power measurement
cleaning of Train
at station Checking of 'Checking of Antenna
radio unit and power
and, DCC. GPs and RF cable.
system
Checking antenna
of alarms
Checking
& cleaning
of Rack &
Checking of Cleaning of Server,
Physical
BRMA. VT- Checking of CPU Checking of PFCT,
verification
100 Switchover. Cleaning of rack at
TELE of IDF &
3 Functioning Checking of Call card level
PHONE MDF.
of NMS. diversity and other disconnecting all units
Undergrou
Network facilities and cables Cable
nd
accessibility testing
Emergenc
y Phone
Testing
Checking of
PAS line,
loudspeaker
, NLDC
Cleaning Switching of
Testing
of amplifier by spare Internal cleaning of
4 PAS centrally/loc
Loudspeak one and functioning amplifiers
ally
ers of gatekeeper
announcem
ent zone-
wise at
station
Page 13 of 22
Cleaning of
Cleaning internal
external portion of
surface of PIDS.
display Performing Cleaning and Internal cleaning of
5 PIDS
boards. centrally/loc Testing of MMI PAS/PIDS server
Checking ally sending
of LED of written
status massages
zone wise.
Cleaning of
Cleaning Internal cleaning of
Cameras.
of CCTV CCTV equipment
Focusing Testing of DVR Optical
6 CCTV rack and rack. Checking of
and fiber ring testing
Monitors at power supply and
alignment (if
Platforms SPD
required)
Cleaning Checking of CLK
of rack and parameters at
7 CLOCK
clocks at station equipment
stations rack and platform
Cleaning Measureme
of the rack nt of -48V Checking
ACCES Cleaning of racks at
8 & and different Redundancy of DTU
S cards level
Checking voltages at and control card
of alarms cards
Visual Earth resistance
EARTH inspection measurement and
9
PIT of Earth Maintenance of
Pits earthling Pits
Cleaning Checking the
of the rack redundancy of
Internal cleaning of
10 NW & checking switches and router
routers
all Rack's as well as power
Alarms supply
Load test -
Interior Cleaning of
Battery
UPS, SCVS, Isolation
Banks &
Txr cabinets, Battery
terminals
Banks & terminals.
Individual
Tightening and
Battery
Cleaning of checking of cable
Terminal
11 UPS Ups condition of different
voltage
cabinets terminals of UPS
reading
Individual Battery
Spare Cell
Terminal voltage
charger
reading Diagnostic
O/P
tests available on UPS
voltage
MMI
reading
Page 14 of 22
Battery
Banks &
terminals
Individual
Battery Cleaning of
12 SMPS
Terminal Rack
voltage
reading
and load
testing
Page 15 of 22
ANNEXURE-3F
Yearly (T4)
SL
Monthly (T1) Quarterl Half Yearly (T3)
No
y (T2)
Emergency Switch
Test and Testing
of Emergency from
SC, Extensive
Cleaning and
alignment of all
modules of Gates,
Check any
physical damage/
unscrewing of all
modules of gate,
Functionality test
and
1 Gate Alignment/Tighteni
ng (if required) of
CDS, ADS and
Container
Replacement, Run
All Maintenance
Tests, Checking
Power Supply or
Earthing,
Analyzing the
Failures of Gates
and taking
Corrective Action
accordingly.
Cleaning
Internal Cleaning of
exterior
Switch and Router,
of
Cleaning and checking
switches,
of Switch rack fan,
Router &
Check internal fan
Switch switch,
status of Switch and
2 and Router
Router, Check if
Router rack,
Switch and Router is
Check
working normal and all
data
equipments are on
connectio
LAN and sending data
ns, fan
properly
status
Check the
3 TR serviceability,
contrast and
Page 16 of 22
electrical
connection, Check
the maximum
distance from
which the Media is
detected.
Cleaning and checking of all
Hoppers, data and power cards,
SVT, Check Rear door lock and
sensor, Check if TVM has
Testing & Internal sufficient battery back-up, Check
Cleaning of BNA, fan status of TVM, CSC antenna
Check Date & functioning & buzzer testing,
Time of TVM, Check all the cables are properly
Check if TVM is on routed through cable ducts and
LAN and sending cable duct covers are in place,
4 TVM
data properly, Checking of Container Detection
calibration of Switch (CDS)(Thales) , Check
screen (if contrast of PID (LCD) & message
required), Run the is OK, Checking of Keyboard with
maintenance trackball(Thales).Testing & Internal
Tests. Cleaning of SVT and its internal
mechanical assembly, Cleaning &
Testing of CHS (Coin Handling
System Thales).
Page 17 of 22
Cleaning of CPU
interior & exterior,
Cleaning and
checking of sub
modules of SC
(Printer,
Keyboard and
6 SC
Mouse etc.),
Cleaning of HDD
and check their
proper fitment,
Check if
supervision
services running.
Page 18 of 22
ANNEXURE-3G
Sl Down Required
Activity Periodicity Remarks
No Time Man Power
1 Hrs/ 1+1
Allension of
Pre monsoon Pier Full As per
1 drainage pipes on
Post Monsoon 7 Days/ Team/ required
viaduct
Pier Agency
Pier Inspection
2 One Year 2 Hours 1+2
Routine
Detailed inspection
3 Ones in 5 years 4 Hours 2+4
of Piers by TMHP
Maintenance of
Depot Buildings
Once in 3 year Agency
(1) OBD etc.
4 Once Month As 2+Agen
(2) Leakage/
per required cy
Drainage
(3) Repairs
Maintenance of
station Buildings
(1) OBD etc.
5 Once in 2 years Agency
(2) Leakage/
Drainage
(3) Repairs
Truck Mount
Hydraulic platform
6
vehicle (TMHP)
Maintenance
Land Scaping
7 Daily Basis Regular Agency
Maintenance work
Rolling Shutter
Once in 3
Maintenance work
8 Months 4 Hours
(1) O&G
As Required
(2) Repair
Viaduct inspection
Once in year With
9 (1) Visual
Once in 5 Years TMHP
(2) Detail
Cleaning of Over
Once in Months
Head Tank (OHT)
10 Once in 3
(1) Drinking Water
Months
(2) Raw Water
Maintenance of
parking area at
Once in Week
11 station and Depot
As per required
(1) Cleaning
(2) Repair
Page 19 of 22
ANNEXURE-3H
Maintenance schedule, Down time and Man power for M&P adopted at DMRC
Page 20 of 22
Weekly 1 1
Monthly 4 1
11 Electric Fork Lift 6 Monthly 8
Yearly — —
Weekly 1 1
Monthly 4 1
12 Electric Stacker
6 Monthly 8 2
Yearly 8 2
Weekly 3 1
-
Monthly -
13 Compressor
3 Monthly 8 3
Yearly 16 3
- -
Weekly
14 Scrubber
Monthly 6 1
Weekly 8 1
15 Aerial Work lift Platform
3 Monthly 8 2
Page 21 of 22
ANNEXURE-3I
Maintenance schedule, Down time and Man power for Lifts Escalators and D.G.
Sets Installed in DMRC Stations
LIFTS
ESCALATORS
Page 22 of 22
ANNEXURE-4A
Maintenance Schedule, Down time and Man hours for Rolling Stock adopted at
BMRCL
Page 1 of 11
ANNEXURE-4B
Maintenance schedule, Down time and Man power for Traction Power supply/
Distribution system adopted at BMRCL adopted by BMRCL
Maintenance Schedule(
Interval)
Down
SL DC SYSEM / Inspections Required
Quarterly
Time
Weekly
N 3RD RAIL to be done Man
Yearly
Yearly
in
Half
O EQUPIMENTS with interval Power
Hours
6
SWS Routine - - 10 8
Month
1 DISCONNECT
Complete 1
OR S/W - - - 20 4
Inspection Year
2
HSCB Visual Insp - - - 30 4
2 Year
FEEDERS
Detailed Insp - - - - 3 6
SEPCOS 1
3 Cleaning - - - 5 3
DISPLAY Month
SEPCOS NG 1
4 Cleaning - - - 5 3
(CPU) Month
1
Visual Insp - - - 20 5
HSCB Year
5
INCOMERS 2
Detailed Insp - - - 10
Year
6
Visual Insp - - - 8 6
Month
Cleaning & 6
DC SWITCH - - - 8 6
Lubrication Month
6 GEAR
Mechanical 1
COMPLETE - - - 20 8
Check Year
Electrical 1
- - - 20 8
Check Year
6
Visual Insp - - - 8 4
Month
Cleaning & 6
- - - 8 4
RECTIFIER Lubrication Month
7
CUBICLE Mechanical 1
- - - 20 4
Check Year
Electrical 1
- - - 20 4
Check Year
6
Visual Insp - - - 8 4
750 V DC Month
8 INCOMING Cleaning & 6
- - - 8 4
CUBICLE Lubrication Month
Mechanical - - 1 20 4
Page 2 of 11
Check Year
Electrical 1
- - 20 4
Check Year
6
Visual Insp - - - 8 4
Month
Cleaning & 6
750 V DC - - - 8 4
Lubrication Month
9 FEEDER
Mechanical 1
CUBICLE - - 20 4
Check Year
Electrical 1
- - - 20 4
Check Year
6
Visual Insp - - - 8 4
Month
Cleaning & 6
- - - 8 4
BY PASS Lubrication Month
10
CUBICLE Mechanical 1
- - - 20 4
Check Year
Electrical 1
- - - 20 4
Check Year
6
Visual Insp - - - 8 4
Month
DISCONNECT Cleaning & 6
11 - - 8 4
OR CABINET Lubrication Month
6
Visual Insp - - - 8 6
Month
OVPD
CABINET 20
12 1 Year 8
Electrical month
Check
CONDUCTOR 3
13 Visual Insp - - - 5 4
RAIL Month
3
Visual Insp - - - 5 4
EXPANSION Month
14
JOINT Cleaning & 6
- - - 5 4
Checking Month
ANCHOR Visual Insp
3
15 ASSEMBLY ,Cleaning & - - - 5 4
Month
(MPA) Checking
3
Visual Insp - - - 8 4
Month
16 RAMPS
Cleaning & 6
- - - 8 4
Checking Month
3
INSULATOR Visual Insp - - - 8 4
Month
17 SUPPORT
Cleaning & 6
ASSEMBLY - - - 8 4
Checking Month
Page 3 of 11
3
Visual Insp - - - 7 4
Month
18 POWER FEED
Cleaning & 6
- - - 5 4
Checking Month
3
Visual Insp - - - 5 4
COVER Month
19
SYSTEM Cleaning & 6
- - - 5 4
Checking Month
CONDUCTOR
Cleaning & 3
20 RAIL - - - 5 6
Checking Month
CLEANING
INSULATED Cleaning & 6
21 - - - 5 5
JOINTS (IJ) Checking Month
3 RD RAIL 7
22 GENERAL Visual Insp Da - - - 5 4
PATROLLING ys
ANNEXURE -4C
Maintenance schedule, Down time and Man power for Track adopted by
BMRCL
Sl Down Required
Activity Periodicity
no Time Manpower
Point & Crossing Inspection
1 Half yearly 1 y2 Hrs 4
(Ballastless track) Mainline
Point & Crossing Inspection
2 Quarterly 1 y2 Hrs 4
(Ballasted track) Mainline
Curve Inspection (up-to 30
3 Stations) for Ballastless track Half yearly 4 Hrs 4
Mainline
Curve Inspection (up-to 30
4 Stations) for Ballasted track Half yearly ( Quarterly) 4 Hrs 4
Mainline
5 Joint Inspection with S&T Half yearly 1 Hr 3
6 Hrs (for
6 Foot Inspection Monthly 2
whole beat
7 Cab Inspection Weekly 1 Hr 1
Track Patrolling (Ballastless - 6 Hrs (for
8 Whole beat (Weekly) 3
Main line) whole beat
Track Patrolling (Ballasted -
9 Daily (Weekly) 3 Hrs 2
Depot)
Yearly (Rails-after
200GMT, thereafter
every 8GMT: Skv
10 USFD Testing (Rails and welds) 36 Hrs 6
welds- after 1 year,
thereafter every 5
years
11 PC based OMS Recording Quarterly 3 Hrs 3
Page 4 of 11
Inspection and Maintenance of
12 Yearly 3 Hrs 5
Buffer Stops
th
Yearly(1/5 yearly-all
13 Measurement of Toe Load clips of 1 out of 30 1 Hr 4
sleepers)
Measurement of Rail Wear (upto
14 Monthly (Half Yearly) 3 Hrs 3
30 Stations) for Ballasted track
2 Hr (for
15 Measurement of Creep Monthly (Yearly) 2
R1)
Inspection and Maintenance of Weekly (insp-weekly:
16 12 Hrs 3
Fastenings and Fittings attention-need based)
Maintenance of Ballasted Track
17 Yearly(need Based) 4 Hrs 6
by TTM
Once in 2 Years (25%
18 Greasing of ERC clips 3 Hrs 4
yearly)
Weekly, (If rolling stock
19 Greasing of outer Rails on curves is not designed with 3 Hrs 3
greasing equipment)
Preventive and Need based rail
20 Yearly 3 Hrs 7
grinding for operation of RGM
Attention of drainage pipes on
21 Monthly 3 Hrs 3
viaduct
Page 5 of 11
ANNEXURE-4D
Maintenance schedule, Down time and Man power for Signalling System
adopted by BMRCL
Sl Down Man
Gear Periodicity Remarks
No Time power
1 Signals Quarterly 30 min 3 Per unit
Biweekly 15 min 2 Per unit
2 Point machines Monthly 30 min 3 Per unit
Quarterly 30 min 4 Per unit
Track circuits
3 Quarterly 30 min 3 Per unit
(SDTC)
4 SDTC Cubicle Half yearly 4 hr 3 Per station
weekly 10 min 2 Per station
Monthly 30 min 3 Per station
5 UPS
4 hrs wait time
Quarterly 1 hr 3
for discharge
Complete shut-
6 TDC Quarterly 1 hr 3
down needed
7 ASCV cubicle Half yearly 3 hr 5 Per station
ATC track side
8 Half yearly 1hr 3 Per station
cubicle
9 ESP Quarterly 30 min 2 Per station
10 LATS Cleaning Half yearly 1 hr 3 Per station
11 CATS cleaning Half yearly 1 hr 3 Per station
Fitness 30 min 2 Per train
12 ATC onboard Biweekly 20 min 2 Per train
Quarterly 30 min 2 Per train
13 Video Wall Quarterly 3 hr 3 Per line
Joint Inspection
14 Half yearly
with Track
Page 6 of 11
ANNEXURE-4E
Maintenance schedule, Down time and Man power for Telecom Systems
adopted at BMRCL
Sl Man Power
System Periodicity Down Time
No Required
DAILY 15 Min/Station 1
WEEKLY 20 Min/Station 1
MONTHLY 1.25 hrs/Station 4
1 CCTV
QUARTERLY 30 Mins/Station 4
HALF YEARLY 45 mins/Station 3
YEARLY 2 hrs/Station 3
QUARTERLY 1.5 hrs 4
2 VIDEO WALL HALF YEARLY 1 hr 4
YEARLY 1.5 hr 4
MONTHLY 15 mins/Station 4
QUARTERLY 1 hr/Station 4
3 GE
HALF YEARLY 45 Mins/Station 4
YEARLY 2 hrs/Station 4
DAILY 10 Mins/Station 1
WEEKLY 10 mins/Station 1
MONTHLY 45 Mins/Station 4
4 PIDS/PAS
QUARTERLY 4 hrs/Station 5
HALF YEARLY 1 hr/Station 3
YEARLY 1.5 hrs/Station 3
MONTHLY 30 Mins/Station 3
QUARTERLY 30 Mins/Station 3
5 SDH
HALF YEARLY 30 Mins/Station 3
YEARLY 2 hrs 3
MONTHLY 30 Mins/Station 4
QUARTERLY 1 hr/Station 3
6 TELEPHONE
HALF YEARLY 1 hr/Station 3
YEARLY 2 hrs/Station 2
MONTHLY 15 Mins/Radio 3
QUARTERLY 45 Mins/BTS 3
7 RADIO
HALF YEARLY 1 hr/MSO 3
YEARLY 2 hrs/MTS 3
MONTHLY 30 Mins/Station 4
8 CLOCK HALF YEARLY 30 Mins/Station 2
YEARLY 30 Mins/Station 3
MONTHLY 15 Mins 2
9 T-SCADA
QUARTERLY 1 hr 2
10 Train radio system WEEKLY 15 mins/Train 2
HALF YEARLY 30 Mins 2
11 CDRS
YEARLY 1 hr 2
Page 7 of 11
ANNEXURE-4F
Maintenance schedule, Down time and Man power for Telecom Systems
Sl
System Periodicity Required Time ManPower
NO
MONTHLY 20 Mins/System 3
1 TOM/EFO
YEARLY 2 hrs/System 3
MONTHLY 45 Mins/System 3
2 AG & RVCT HALF YEARLY 1 hr/System 3
YEARLY 1.5 hrs/System 3
MONTHLY 3 hrs/System 3
3 SC
HALF YEARLY 3 hrs/System 3
DAILY 1 hr/System 3
WEEKLY 1.5 hrs/System 3
MONTHLY 2 hrs/System 3
4 CC
QUARTERLY 2 hrs/System 3
HALF YEARLY 4 hrs/System 3
YEARLY 4 hrs/System 3
MONTHLY 20 Mins/System 3
5 NETWORK QUARTERLY 1 hr/System 3
YEARLY 2 hrs/system 3
ANNEXURE-4G
Maintenance schedule, Down time and Man power for Civil Structures & Works
adopted at BMRCL
Sl. Required
Activity Periodicity Down Time
No. Manpower
1 ETP/STP Operation Weekly 1 Hr 5
2 WTP Operation Weekly 1 Hr 2
3 Pier inspection by TMHP, Yearly 2Hrs 2
4 Maintenance of Depot buildings Yearly 2Hrs 2
5 Maintenance of Station buildings Yearly 2Hrs 2
Truck Mounted Hydraulic Platform
6 Daily 1 Hr 1
Vehicle (TMHP) Maintenance
7 Land Scaping maintenance work Weekly 1 Hr 4
8 Rolling Shutter Maintenance work Monthly J4 Hr 2
9 Via-duct Inspection Weekly 4 Hrs 2
10 Cleaning of Over Head Tank (OHT) Quarterly 4 Hrs 4
Maintenance of Parking Area at
11 Weekly 2 Hrs 2
Stations and Depot
Maintenance of pump rooms and
12 checking of water availability at Weekly 2 Hrs 3
stations
Page 8 of 11
ANNEXURE-4H
Maintenance schedule, Down time and Man power for M&P adopted at BMRCL
Page 9 of 11
Monthly 4 2
6monthly 8 3
11 Electric Fork Lift
Yearly 16 3
Weekly 2 2
Monthly 4 3
6monthly 6 3
12 Electric Stacker
Yearly 8 3
Weekly 2 2
Monthly 4 3
13 Compressor 6 Monthly 6 3
Yearly 8 3
weekly 1.5 2
14 Scrubber
Monthly 4 2
Weekly 2 2
15 Aerial Work Lift Platform
Monthly 4 2
Page 10 of 11
ANNEXURE-4I
Maintenance schedule, Down time and Man power for Lifts Escalators and D.G.
Sets Installed in BMRCL Stations
LIFTS
ESCALATORS
Page 11 of 11
ANNEXURE-5
Page 1 of 3
ANNEXURE-5
Page 2 of 3
ANNEXURE-5
5) Operating Procedures
i. On BMRCL, following documents have been issued for operations:
I. Special Instructions to Bangalore Metro Railway General Rules,
2011.
II. Station Working Order (SWO) for all the stations.
III. Standard Operating Procedure for the Depot.
IV. Standard Operating Procedure for OCC.
V. Standard Operating Procedure for Station Staff and Train
Operators.
VI. Competency Procedure for O&M staff.
VII. Hand book for dealing with serious incidents, accidents and
disaster.
VIII. Procedure for availing power blocks and traffic blocks.
IX. In addition draft Maintenance Manuals for various equipment’s for
Signaling, Track, Traction, Telecommunication and Rolling Stock
are issued in consultation with System Contractors.
Page 3 of 3
ANNEXURE-6
Page 1 of 5
ANNEXURE-6
3) O&M phase: During O&M phase, the OMC shall carry out following
functions:
Operate, maintain and repair the MRTS in a professional, timely, safe and
environmentally responsible manner as per laid down Key Performance
Indicators (KPI).
Act in accordance with the Good Industry Practice.
Implement time to time staffing plan.
Provide Daily/ Monthly reports.
Responsible for managing the warranty obligations of the Other
Contractors.
Page 3 of 5
ANNEXURE-6
c. To ensure that training is provided for all staff involved in operations and
maintenance of the MRTS.
d. The Operational Readiness Tests are part of the running tests which will
be conducted after system integration test mainly for checking the
readiness of staff and equipment before the Trial Run and shall be
completed.
b. The objective of the Trial Run is to demonstrate that the systems and/or
sub-system forming part of the MRTS (and their operations by the OMC
organization(including any subcontractors or affiliates) function sufficiently
to enable the Independent Engineer and Safety Commissioner to evaluate
and validate the readiness of the systems and/or sub-system.
Page 4 of 5
ANNEXURE-6
c. The process of Trial Runs will identify any requirements to optimize the
system functionality, to amend procedures and/or to implement additional
or revised training for the OMC staff.
a. In the final phase of Trial Run, the entire Rail System shall be operated as
if Revenue Operation has started, using the headways specified and
planned.
b. In general no specific test scenarios shall be planned for this phase but the
OMC shall perform their duties as they would if passengers were using the
system.
d. Specific issues and lower availability issues will be taken up with various
contractors for compliance through a punch-list format and section would
be opened for public if the availability of the system as a whole meets the
stipulated requirements.
c. OMC shall take care of progressive updation of SMS system during the
Project life cycle.
Page 5 of 5
ANNEXURE-7
(b) The Trains in each direction shall be operated such that the difference
between arrival time of two Trains at any Station shall not exceed 3
(three) minutes; provided that such difference may be increased, subject
to a maximum of 15 (fifteen) minutes, depending upon the number of
Users in the respective hour.
(c) The average speed of train movement from terminal to terminal during
any hour of the day, including stops at the Stations, shall not be less than
30 (thirty) kilometers per hour.
(d) For the avoidance of doubt, stops at the Stations shall not be less than 20
(twenty) seconds each.
(e) The punctuality for the day, calculated at the terminal Stations with
respect to the time table, shall be more than 95% (ninety five per cent).
For the avoidance of doubt, if the arrival of a train at the terminal Station is
delayed by more than 1 (one) minute, it will be deemed to have lost
punctuality.
(f) The number of coaches in each train and the frequency of Trains per hour
shall be such that the average number of Users does not exceed 6 (six)
persons per square meter of the floor space available for use by
passengers inside a coach during 4 (four) Peak Hours in a day and is less
than 4(four) such persons per square meter during other hours; provided
that the restriction herein contained shall not apply if the concessionaire is
operating 22 (twenty two) trains per hour in each direction with every Train
having a floor space of not less than 325 (three hundred and twenty five)
square meters.
Page 1 of 2
ANNEXURE-7
(h) The entry and exit gates, including the automatic ticket verification
machines, shall be so designed and operated that the waiting time for
Users shall not exceed 2 (two) minutes during Peak Hour.
(k) The Concessionaire shall, within 6 (six) months from COD, achieve and
thereafter maintain throughout the Concession Period, ISO 9001:2000
certification or a substitute thereof for all the facilities at the Rail System,
and shall provide a certified copy thereof to the Government forthwith.
(l) The Concessionaire shall publish and implement a charter articulating the
rights and expectations of Users (the Passenger Charter).
Page 2 of 2
ANNEXURE-7A
Page 1 of 3
ANNEXURE-7A
Page 2 of 3
ANNEXURE-7A
Page 3 of 3
ANNEXURE-8
Page 1 of 1
ANNEXURE-9
Phase-2 (Broad Gauge) - Out of 85 train sets it was mentioned that minimum 20
train sets will be manufactured in India. Further the items which were identified for
indigenization are given below:
Essential:
Sl No Description of Items
1. Pantograph
2. Vacuum Circuit Breaker (VCB)
3. Current Transformers, Potential Transformers and Insulators
4. Traction Motors
5. Converter / Inverter unit
6. Static inverter
7. Electrical Panels and cab Panels
8. Cables
9. Battery set box
10. Saloon air conditioner
11. Cab AC
12. Luminaries and lamps
13. All types of glasses
14. Public address (PA)/Public Information System (PAS)
15. DC-DC Converter
16. Consumables, Lubricants, Sealants, Oils, Greases etc.
Page 1 of 5
ANNEXURE-9
Desirable:
Sl No Description of Items
1. Axle box , covers with taper roller
bearings
2. Floor cover
3. Floor board
4. Dampers
5. Earthing brush assembly
6. Stainless steel sections
7. Steel sections
Page 2 of 5
ANNEXURE-9
Phase-2 (Standard Gauge) – Minimum 48 cars i.e. 16 three car train sets were to be
manufactured in India. Further the items which were identified for indigenization are
given below:
Essential:
Sl No Description of Items
1 Pantograph
2 Vacuum Circuit Breaker (VCB)
3 Current Transformers, Potential Transformers and Insulators
4 Traction Motors
5 Converter / Inverter unit
6 Static inverter
7 Electrical Panels and cab Panels
8 Cables
9 Battery set box
10 Saloon air conditioner
11 Cab AC
12 Luminaries and lamps
13 All types of glasses
14 Axle taper roller bearing complete with axle box, housing &
cover
15 DC-DC Converter
16 Consumables, Lubricants, Sealants, Oils, Greases etc.
17. Earth brush assembly
Desirable:
Sl No Description of Items
1 Cab mask
2 Floor cover
3 Floor board
4 Dampers
5 Internal panelling
6 Stainless steel sections
7 Steel sections
8 Insulation like glass wool etc.
9 Public address (PA)/Public Information
System (PAS)
10 Brake system
11 Couplers
12 Door panels
13 Auxiliary motors
14 Gangways
15 Bearings
16 Valves and cocks
17 Wipers
18 Pneumatic pipes
Page 3 of 5
ANNEXURE-9
19 Reservoirs
20 Primary conical + secondary springs
21 PCBs used in different equipment’s
Phase-3 (Standard Gauge)- It has been proposed in the new RS tender that only 20
train sets of six car each can be manufactured in offshore factory out-side India.
Further the items which were identified for indigenization are given below:
Essential:
Sl No Description of Items
1 Pantograph including strips
2 Vacuum Circuit Breaker (VCB)
3 Brake blocks
4 Traction Motors
5 Converter / Inverter unit
6 Static inverter (Auxiliary Converter)
7 Electrical Panels / cab Panels
8 Application & release valve, relay valve, isolating cocks, safety
valves & check valves
9 Battery set box
10 Saloon air conditioner
11 Saloon door accessories
12 Luminaries and lamps
13 All types of glasses
14 Axle taper roller bearing complete with axle box, housing &
cover
15 DC-DC Converter
16 Consumables, Lubricants, Sealants, Oils, Greases etc.
17 Earth brush assembly
18 Gear drive
Desirable:
Sl No Description of Items
1 Floor cover
2 Floor board
3 Dampers
4 Stainless steel sections
5 Steel sections
6 Insulation like glass wool etc.
7 Brake system
8 Couplers
9 Auxiliary motors
10 Gangways
11 Bearings
12 Wipers
Page 4 of 5
ANNEXURE-9
13 Pneumatic pipes
14 Reservoirs
15 Primary & secondary Springs
16 PCBs used in different equipment’s
17 Internal paneling
18 Public address (PA)/Public Information System (PAS)
19 Cab mask
AFC Equipments:
Following items have been indigenized:
1) AFM
2) Hybrid Flap
3) Normal Flap
4) PID with Voice
5) SMA top cover
6) SMV top cover
7) Talk back system
8) Ticket vending machine
9) Hand held device for common ticketing
Page 5 of 5
ANNEXURE-10
Indigenous
Description of Name of Supply
Sl.No Manufacturer
Equipment Manufacturer possible/
acceptable
Raw material from
Car body( except Hyundai Rotem,
1 Yes M/s SAIL, Salem or
side wall skin) Korea
Jindal Steel
Nippon Steel,
1.1 Side wall Skin No
Japan
2
Hyundai Rotem,
2.1 Bogie Frame Yes M/s Premier Pune
Korea
Gummi Metal M/s Siemens,
2.2 Primary Spring No
Technik,Germany Aurangabad
2.3 Secondary Spring SEI , Japan No
Bonatrans A.S. No
2.4 Wheels
Czech Republic
Bonatrans A.S., No
2.5 Axles
Cezh Republic
ZF Sachs AG,
2.6 Damper No
Germany
Flender
Gear Box and
2.7 Industriegetriebe, No
Couplings
Germany
Wheel flange
2.8 Lubrication Kelsan, Canada yes
equipment
2.9 Axle bearing Yes
3
Complete Brake Knorr Bremse,
3.1 yes M/s KBIL
System Munchen
Main air
Knorr Bremse,
3.2 compressor-motor No
Munchen
set
3.3 Air Dryer M/s KB, Munchen No
Page 1 of 13
ANNEXURE-10
Knorr Bremse,
3.4 Brake disc No
Munchen
Knorr Bremse,
3.5 Brake pads No
Munchen
4
Faiveley
Passenger Saloon
4.1 Transport, Iberica, Yes M/s KBIL, India
Doors
Spain
4.2 Cab Side Doors ADS Rail, Korea No
4.3 Saloon to Cab doors ADS Rail, Korea No
Ferraz Shawmut
5 Current Collector No
Co.Ltd, Mersen
High Speed Circuit Secheron SA,
6 No
Breaker Switzerland
Lighting Arrester
(Metal Oxide, OTOWA
7 No
Gapless) → Surge ELECTRIC, Japan
Arrester
8 Traction Motor MELCO, Japan No
9
Complete Traction
9.1 MELCO, Japan no
Inverter
10
Complete Auxiliary Mitsubishi Electric
10.1 No
Inverter Corp, Japan
HBL Power M/s AMCO, M/s
11 Battery Yes
System Ltd, India HBL, India
M/s Jindal,
11.1 Battery box Yes
Gurgaon, India
Sigma Coachair
12 HVAC Unit Yes M/s KBIL, India
Group, Australia
Mitsubishi Electric
13 Main relays No
Corp. Japan
Schneider Electric
14 MCB No
SA
Mitsubishi Electric
15 Isolating Switches No
Corp. Japan
Huber + Suhner
16 Cables No
AG, Switzerland
16.1 Cable duct Yes
Page 2 of 13
ANNEXURE-10
17
Automatic Digital
voice
TOA Engineering ,
17.1 announcement and No
Japan
Public Address
System
Electronic
TOA Engineering
17.2 information Display No
,Japan
System
Electronic TOA Engineering,
17.3 No
Destination Display Japan
18
Voith turbo
18.1 Automatic coupler Schharfenberg, No
Germany
Voith turbo
Semi perm anent M/s Voith
18.2 Schharfenberg, Yes
coupler Hyderabad
Germany
19
M/s Milwaukee
19.1 Flooring Board Composites Inc., No
USA
19.2 Cushion Getnerg, Austria No
19.3 Floor Cover Mando, Italy NO
19.4 Glass wool U D TWIGA, India Yes
Han Kuk Fibre
M/s Kemrock,
20 Interior / Panelling Glass Co. Ltd, Yes
Vadodara
Korea
21
Dae won Kang,
21.1 For Train operator No
Korea
KBI tech company M/s Presston Engg
22.2 For passenger Yes
limited, Korea Bangalore
23
Vestibules ( inter
23.1 Hubner, GMBH No
Gangways)
M/s Presston Engg,
Cabling harnessing Kyung Sung,
23.2 Yes Bangalore and M/s
system Korea
Bhoruka, Bangalore
Head light, taillight,
23.3 Samkong, korea Yes M/s K Lite, India
flasher lights etc.,
23.4 Saloon Light Samkong, korea Yes M/s K Lite, India
Page 3 of 13
ANNEXURE-10
24
24.1 Master Controller MELCO, Japan No
24.2 Mode Selector MELCO, Japan No
24.3 PWM Generator MELCO, Japan No
24.4 Windscreen wiper Sparague, USA Yes M/s KBIL
Knorr Bremse,
24.5 Horn Yes M/s KBIL
Munchen
Earthing brush Stemman,
24.6 Yes M/s Schunk India
assembly Germany
25 TMS MELCO, Japan No
Shin-Myung Steel
Axle Box and covers M/s Rine Engg,
25.1 Cast Co., Ltd., Hyundai Rotem
(Casting) Himachal Pradesh
Korea
Hyundai Rotem,
26 Stickers and Labels Yes 3M, Permacel India
Korea
Hyundai Rotem,
27 Sun visor Yes
Korea
Hyundai Rotem
28 Foot Pedal Yes
Korea
Cab mask, Cab
Hyundai Rotem, M/s Kemrock,
29 skirt, driver desk Yes
Korea Vadodara
and end fairing
Page 4 of 13
ANNEXURE-10
Indigenous likely
Sl.
Description of Spares Supplier supply /recommended
No.
possible source
M/s. SAIL, BHILAI,
1 Rail 60 kg 90 UTS
India
M/s. SAIL, BHILAI,
1 Rail 60 kg HH Austria YES M/s. Jindal ,
Laxmi Mittal, etc.
M/s. Vossoloh,
2 Washer Uls 60 YES -
Germany
Thermit Welding portion M/s. ITC, Kanpur,
4 - -
for SAIL rail India
Thermit Welding Portion M/s. ITC,
5 - -
for HH rail Kanpur,india
6 Grooved Rubber Pad Local,India - -
7 GFN Liner Local,India - -
8 Elastic Rail Clips (ERC) Local,India - -
M/s.
9 Elastomeric pad - 4 holes YES -
Vossoloh,Germany
M/s.
10 Elastomeric pad - 2 holes YES -
Vossoloh,Germany
M/s.
11 Insulating Bush YES -
Vossoloh,Germany
M/s. Carbanaire
Industries
12 Rail Pad - -
(Madras) Pvt. Ltd. /
India
M/s. Carbanaire
Industries
13 Collared Washer - -
(Madras) Pvt. Ltd. /
India
M/s.
14 Helical Spring YES -
Vossoloh,Germany
Ribbed plate Rph M/s. Nelcast Ltd.,
15
49/20/12 - 4 Hole Gudur, India
Ribbed plate Rph M/s. Nelcast Ltd.,
16
49/20/12 - 2 Hole Gudur, India
M/s.
17 Tension Clamp Skl-12 YES -
Vossoloh,Germany
Page 5 of 13
ANNEXURE-10
M/s. Carbanaire
Industries
18 Intermediate Pad - 4 hole - -
(Madras) Pvt. Ltd. /
India
M/s. Hiten
Fasteners Pvt Ltd,
19 T Bolt (HS-32) with nut - -
Gadag/ Maddur,
India
M/s. Hiten
Anchor Bolt M-
Fasteners Pvt Ltd,
20 27X38285mm long with - -
Gadag/ Maddur,
nut
India
21 Jogled fish plate C-clamp Local,India - -
M/s. Paramount
Glued Insulated Rail Joint
22 Industries, - -
60kg
Hyderabad, India
23 CMS Crossing 1 in 9 M/s. VAE, Austria YES -
24 CMS Crossing 1 in 7 M/s. VAE, Austria YES -
M/s. Mazda,
25 PSC Sleeper for 3rd rail Tumkur, - -
Bangalore, India
M/s. Mazda,
PSC Sleeper for Standard
26 Tumkur, - -
Gauge
Bangalore,India
M/s. Carbanaire
Intermediated Pad - 2 Industries
27 - -
hole (Madras) Pvt. Ltd. /
India
M/s. Balfour
28 Wheel Stop/ Stopper YES -
Beatty, UK
M/s. Balfour
29 Buffer stop for slow line YES -
Beatty, UK
M/s. Balfour
30 Buffer stop for main line YES -
Beatty, UK
Derailing Switch - 60 kg
31 M/s. VAE, Austria YES -
RH
Derailing Switch - 60 kg
32 M/s. VAE, Austria YES -
LH
Switches of 1 in 9 RH
33 M/s. VAE, Austria YES -
Turn out
Switches of 1 in 9 LH
34 M/s. VAE, Austria YES -
Turn out
Page 6 of 13
ANNEXURE-10
Switches of 1 in 7 RH
35 M/s. VAE, Austria YES -
Turn out
Switches of 1 in 7 LH
36 M/s. VAE, Austria YES -
Turn out
PSC Sleeper for Scissor M/s. Mazda,
37 Cross over including Tumkur, - -
Daimond Crossing Bangalore, India
M/s. ITC, Kanpur,
38 Dry Mould (60kg) - -
India
1 m fish plate with
39 Local, India - -
modified clamp
1 m long fish plates for 60
40 Local ,India - -
kg rail with C-Clamp
41 Fish plate with Bolt & nut Local, India - -
Page 7 of 13
ANNEXURE-10
Indigenous
likely
Sl. Description of supply
Supplier /recommended
No Spares possible /
source
acceptable
Split Head Indigenous M/s. Plasser
1 Tamping M/s. Plasser, Austria supply India,
Machine possible Faridabad
Rail Grinding
2 M/s. LORAM, USA - -
Machine (RGM)
M/s. EEC, M/s. PARAS, M/s.
Ultra Sonic Flaw
3 Modsonic, etc. (RDSO - -
detector machine
Approved), India
PC Based OMS M/s. Systems Aids,
4 - -
2000 Machine Bangalore, India
Page 8 of 13
ANNEXURE-10
Page 9 of 13
ANNEXURE-10
Page 10 of 13
ANNEXURE-10
Page 11 of 13
ANNEXURE-10
Location of Works,
Sl. No. Equipment
Country of origin
(i) Items manufactured in India
Page 12 of 13
ANNEXURE-10
Location of Works,
Sl. No. Equipment
Country of origin
(i) Items manufactured in India
1. Contactless Cards & tokens M/s Siepmanns India
2. Network switch M/s HP, India
3. Cat-6 cable M/s RM, India
4. Optical Fibre Cable M/s RM, India
5. Electrical cables M/s CMI India
6. Network rack M/s HCL, India
Likely indigenous
(ii) Imported items and likely indigenous source
source
7. Ticket Office Machine HP Singapore HCL, Wipro India
8. Servers HP Singapore HCL India
9. Printer Lukan Korea Wipro, TVS India
Huangmin, Shanghai,
10. Automatic Gates Not available
China
Page 13 of 13
ANNEXURE-11
Page 1 of 1
ANNUXURE-12
Page 1 of 1
ANNEXURE-13
Managing
Director
Total Staff: 25
Financial HR
Division Division
QHSE
Division
Marketing &
Operations Technical
sales
Division Division Division
Page 1 of 5
ANNEXURE-13
ii. HR Division:
Assistant
Chief financial
officer Total Staff: 30
Assistant
Page 2 of 5
ANNEXURE-13
QHSE
Director
Total Staff: 20
Assistant
Quality &
Health Safety Security
environment
manager manager manager
manager
Marketing &
sales
director
Total Staff: 50
Assistant
Communication,
Marketing CRM
PR & advertising
product manager manager manager
Page 3 of 5
ANNEXURE-13
Chief operations
officer
Total Staff: 1500
Engineering
Assistant
department
Communication
Depot Ticket Gateline
& security
Controllers officers controlllers
controllers
Host Security
officers officers
Engineering
Manager
Methods
Planner Technicians Reporting officers
Page 4 of 5
ANNEXURE-13
Maintenance
director
Methods &
Supply Chain Assistant
departement
Infrastructure &
SIG, Comms & Track, OHE & PSS Rolling-stock
auxilaries
manager AFC Manager Manager Manager
Auxilaries
Infrastructure Jr AFC Comms SIG PSS Track OHE RS
technical
auditors Engineer Jr Engineers Jr Engineers Jr Engineers Jr Engineers Jr Engineers Jr Engineers Jr Engineers
Page 5 of 5
ANNEXURE-14
Page 1 of 3
ANNEXURE-14
8) Recruitment and training of the Operator Personnel and ensuring that the
Operator Personnel are well qualified and competent prior to the
commencement of Blank Operations.
Page 2 of 3
ANNEXURE-14
Page 3 of 3
ANNEXURE-15
Page 1 of 1
ANNEXURE-16
Page 1 of 3
ANNEXURE-16
V. Inflation Risk
o Under the O&M contract, the operator is only protected from 80% of
the India inflation risk, therefore it will be exposed to approximately
1.4% inflation risk per annum, over the next seven years; based on
an assumed rate of Inflation at seven percent (1.4%=20% x 7%).
Page 3 of 3
ANNEXURE-17
Sl
Mock drill Item Location Frequency Remarks
No
1 Emergency Stop Plunger At PSB and SCR Quarterly
Key switch in PSBs and Switching OFF of
2 Under Platform Sprinkler operation also by motor Monthly OCS supply is
operated valves desirable
Emergency
At platform ends, inside
3 Emergency tripping switches Yearly telephone checked
tunnel and in SCRs
every two months
4 Fire Alarm and Control panel SCRs Fortnightly
5 Seismic sensor Fortnightly
6 Mimic Fire Repeater panel Fireman Staircase Fortnightly
7 Public Announcement System Mic in PSBs and SCRs Fortnightly
8 Hooter with strobe (flasher) At PFs & Concourse Fortnightly
In ASS rooms at platform
Switching ON of tunnel lights
9 ends Fortnightly
through MCBs
Load test for 30
10 DG Set Ancillary building Monthly
minutes
11 Fire pumps Ancillary building Monthly
12 Tunnel Ventilation System Monthly SC also associates
13 Gas Flooding System ASS Room Fortnightly SC also associates
Monthly in
Carried out by all
14 Extension of Power supply OCC non-revenue
TPCs
hours
15 Fire Drill Depot & Stations Quarterly
Rescue of Disabled Train. Main Line (Non-Revenue
16 Quarterly
Hours)
Detrainment of Passengers
Main Line (Non-Revenue
17 between Stations Quarterly
Hours)
Passenger Evacuation from Main Line (Non-Revenue
18 Quarterly
Station and via duct Hours)
Drill for use of Rescue & Relief Main Line (Non-Revenue
19 Quarterly
Train Hours)
Communication Failure Main Line & Depot
20 Half Yearly
(TETRA) (Revenue Hours)
Failure of Third Rail Supply Main Line & Depot (Non-
21 Half Yearly
Revenue Hours)
Rail Fracture (leading to TC Depot (Non-Revenue
22 Half Yearly
Failure) Hours)
23 Point failure in Mainline & Depot Quarterly
24 Lifts & Escalators Failure Stations & Depot Monthly
Preparedness & Preventive
25 Stations & Depot Quarterly
actions against Terrorist attack
26 Single line working Main Line Half Yearly
Page 1 of 1