Absorption & Marginal Costing
Absorption & Marginal Costing
Example 1 :
Total budgeted fixed overheads for a firm are £712,000 these have traditionally been absorbed
on a machine hour basis. The firm makes two products, A and B.
A B
Required:
a) Calculate the total cost for each product on the assumption that the firm continues to
absorb overheads on a machine hours basis.
The firm is considering changing to an Activity Based Costing System and has identified
the following information:
Required:
Example 2 :
Hensau Ltd has a single production process for which the following costs have been
estimated for the period ending 31 December 20X1.
£
Material receipt and inspection cost 15,600
Power Cost 19,500
Material handling cost 13,650
Three products X,Y and Z are produced by workers who perform a number of
operations on material blanks using hand-held electrically powered drills. The
workers have a wage rate of £4 per hour.
The following budgeted information has been obtained for the period ending 31
December 20X1.
Overhead costs for material receipt and inspection, process power and material handling are
presently each absorbed by product units using rates per direct labour hour.
An activity-based costing investigation has revealed that the cost drivers for the overhead
costs area as follow:
Required:
Prepare a summary, which shows the budgeted product cost per unit for each of products X, Y
and Z for the period ending 31 December 20X1 detailing the unit costs for each cost element.
a) Using the existing method for the absorption of overhead costs; and
b) Using an approach, which recognizes the cost drivers revealed in the activity-based
costing investigation?
Question 2 :
A company has two production departments (A and B) in its factory. Overheads in
each department are currently absorbed into product cost based on machine hours
worked.
The production overhead absorption rate in Department A is £5.60 per machine hour.
In Department B the absorption rate is to be established from the following date
relating to the department for a period.
£
Allocated production overheads 24,260
Apportionment of factory level production overheads 37,539
Apportionment of service department production overheads 32,911
£94,710
Machine hours worked 11,550
The following information is available for the period to product X, one of the product
manufactured in the factory:
8 batches
2,540 machine hour (Department A 1,400; Department B 1,140)
58,068 units produced
2,303 labour hours
Required:
Question 3 :
Birtles pic is a manufacture of small domestic electrical appliances. It market is very
competitive in terms of both price and product innovation. As a result, product life cycles
are short.
Birtles pic’s managers are concerned about the reliability of its product costing system. It
currently uses an absorption costing system and absorbs overheads based on budgeted direct
labour hours. On this basis the estimated cost of its latest product, a talking electric kettle, is
as follows:
£ per unit
Direct material 4.50
Direct labour (£12 per hours) 0.50
Production overheads (£120 per hour) 5.00
Production 10.00
The firm’s management accountant has suggested that more accurate product costs would
be obtained if an activity based costing (ABC) approach were used. He has collected the
following information as a Budgeted factory overhead per annum.
Each talking kettle uses 10 different components and kettle manufacture will involve six-
production line set-up per annum. Five hundred dispatches will be required per annum.
Budgeted production is 10,000 Kettle per annum.
Required:
Estimate the cost of talking kettle using an ABC approach and the cost drivers
suggested by the management accountant.
Question 4 :
Naceur, a textile manufacturer, makes three products A, B, C. Budgeted cost, and production
information for the coming period is as follows:
Product A B C
Per thousand meters
Costs
Direct materials £120.00 £100.00 £60.00
Direct labour £42.00 £42.00 £28.00
The three products are manufactured using the same production technology. They are
usually produced in production runs of 10,000 meters and sold to wholesalers in batches of
5,000 meters.
The company uses a cost plus pricing system and a gross margin of 20% on sales to
calculate prices.
Budgeted production overhead is absorbed using a machine hour rate and the budgeted
overhead for the coming period has been analyzed as follows:
£
Rates, rent, supervision ,power and depreciation 26,000
Set up costs 15,000
Goods inwards 9,600
Finishing goods inspection 5,250
Dispatch 9,750
Total £65,600
Budgeted machine hours for the period are 1,640 hours.
Required:
a) Part one
(1) Calculate the budgeted total cost per thousand meters for each product, showing
clearly prime cost, overhead cost and total cost; (5 marks)
(2) Using your total cost estimates from (a) (1) and a GROSS MARGIN of 205 on
sales calculate the budgeted price per thousand meters of each of the three
products. ( 3 marks)
b) Part two
The sales manager of Naceur has complained that its main competitor is undercutting its
prices for products A by B by several pounds. Naceur’s price for product C on the other
hand is lower than that of the competitor. She believes three price differences are caused
by their competitors using an activity based costing (ABC) system to cost products, and a
cost plus pricing system with a mark-up 20% on total activity based cost to calculate prices.
In an attempt to make Naceur’s costing, more accurately reflect the usage of resources by
products you have ascertained that the cost drivers for the overhead activities are as
follows:
Required:
(1) Calculate the budgeted cost driver rate for each overhead activity ;(5 marks)
(2) Calculate the budgeted total cost per thousand meters for each product using an
activity-based costing approach ;(10 marks)
(3) Using your total cost estimates from b (2) and a MARK-Up of 20% on total cost,
calculate the price per thousand meters of each of the three products. Comment briefly
on the causes of any charges in prices. (7 marks)
Example 1. (Solution):
Calculation of Overheads Absorption Rate Based on Machine Hours:
= Total overhead Cost ÷ Total Direct Labour Hours
= 712,000 ÷ 178,000 (W-1)
= £ 4 per hour
(W-1):
= Production Quantity x Per Product Machine Hours
A: 6,000 x 6 = 18,000
B: 40,000 x 10 = 160,000
Total = £ 178,000
Example 2. (Solution):
(a) Using the existing absorption methods:
(W-2):
= Production Quantity x Per Product Labour Hours
X= 2,000 x 6 = 12,000
Y= 1,500 x 3 = 4,500
Z= 800 x 2 = 1,600
Total = £ 18,100
(W-3):
= Production Quantity x Per Product Labour Hours
X= 2,000 x 4 = 8,000
Y= 1,500 x 6 = 9,000
Z= 800 x 3 = 2,400
Total = £ 19,400
Question 2. (Solution):
(a) Using the existing absorption methods:
I. Calculation of Product Overheads Absorption Rate in
Department:
Department A: 5.60 per MH (Given)
(W-1):
= Total Overheads Cost ÷ Machine Hours Worked
= 94,710 ÷ 11,550
= 8.20 per MH
= £ 7,840
Department B:
= £ 9,348
iv. Servicing
=£ 39,375 ÷ 18,750
=£ 2.1 per labour hour
Question 3. (Solution):
Calculation of Product Overheads Absorption Rate for Each Activity:
i. Store Administration:
=£ 5,000,000 ÷ 2,000
=£ 2,500 per component
iii. Dispatch:
=£ 1,000,000 ÷ 20,000
=£ 50 per dispatch
Question 4. (Solution):
Using the existing absorption methods:
Calculation of Overheads Charged To Each Product & Sale Price on 20% Gross
Margin Under Existing Traditional Absorption Costing:
v. Dispatch Cost:
=£ 9,750 ÷ 60
=£ 162.5 per order