Testing and Commissioning of BMS Rev A
Testing and Commissioning of BMS Rev A
Testing and Commissioning of BMS Rev A
For
Rev.: A
*Additional Precautions: -
All operations are undertaking in accordance with OSHAD H&S requirements.
All work shall be in accordance with;
• SPS M JV Project HSE Plan P147-SPS-HSE-PRG-0001;
• SPS M JV Construction Environmental Management Pan P147-SPS-ENV-PRG-0001;
• SPS M JV Permit To Work Procedure P147-SPS-HSE-REP-0374;
• SPS M JV Construction and Demolition Waste Management Plan. P147-SPS-ENV-PRG-0002;
• SPS M JV Emergency Management Plan HSE/OP/EMP/01;
• SPS M JV Working at Height Plan SPS/WHP/P/01;
• SPS M JV Operational Control for Using Ladders P147-SPS-HSE-REP-0030;
• SPS M JV Traffic Management Plan SPS/HSE/REP/027;
• SPS M JV Summer Safety Plan HSE/S/P/01.
• SPS M JV Operational Control for the Testing Commissioning and Energization Activities. P147-SPS-HSE-RE-0248.
• Ensure the controls are typically established in those operations that are essential, and acceptance is too risky, and avoidance and sharing of residual risks are not possible.
• To ensure that controls are operating efficiently, testing is usually necessary.
• Corrective action is warranted when a control is weak, not in place or not functioning properly.
• Operatives undertaking other workers at the vicinity/ surrounding should be briefed on the hazards operations.
• Supervisor and other key personnel shall ensure that all mitigation measures are been implemented prior to commence the operations.
• No work is to be carried out without constant competent supervision.
RISK MATRIX