Monthly Progress Report: Ghana Institute of Management and Public Administration (Gimpa)

Download as pdf or txt
Download as pdf or txt
Download as pdf or txt
You are on page 1/ 8

GHANA INSTITUTE OF MANAGEMENT AND

PUBLIC ADMINISTRATION (GIMPA).

CONSTRUCTION OF 2 NO. 3 STOREY LECTURE HALL


BLOCKS AT GIMPA CAMPUS LOT 1 & 2 – Accra

Monthly Progress Report

AS AT 24th May,2018

Employer: GIMPA, Accra-Ghana


Consultant: ALBERT ESSAMUAH ASSOCIATES LIMITED.
Contractor: China State Hualong Construction (GH) Ltd.
MONTHLY PROGRESS REPORT AS AT 24th May,2018

PROJECT TITLE: CONSTRUCTION OF 3NO. 3-STOREY LECTURE HALL BLOCK AT GIMPA


CAMPUS, ACCRA-GHANA.

Client: Ghana Institute of Management and Public Administration, (GIMPA),


Accra – Ghana
Commencement date: 24/11/17
Expected completion date: 02/01/19
Overall Planned Progress: 35
Overall actual planned progress: 35%
Forecast planned progress: 40%

1. WORK PROGRESS FOR LOT 1


ACTUAL FORECAST
PLANNED
ITEM ACTIVITY PLANNED PLANNED REMARKS
PROGRESS(100%)
PROGRESS(%) PROGRESS(%)

(LOT 1)

SUPERSTRUCTURE
WORKS

1.0 First floor works


i)Column
reinforcement 70 100

ii) Formworks for


columns 65 100

iii) Casting and curing


of columns 65 100

iv) Staircase works 70 100

6/8
2.0 Second floor works
i)Column
reinforcement 70 100

ii) Formworks for


columns 80 100

iii) Casting and


curing of columns 70 100

iv) Formworks for


floor slab and beams 90 100

v) Floor slab and


beam reinforcement
works 80 100

vi) Conduiting works


on floor slab 100

vii) Casting and


curing of floor slab
and beams 100

viii) Staircase works 100

Planned Progress
for Lot 1:40 %
Actual Progress
for Lot 1: 38%
Forcast Progress
for Lot 1 45 %

6/8
2. WORK PROGRESS FOR LOT 2

ACTUAL FORCAST
PLANNED
ITEM ACTIVITY PLANNED PLANNED REMARKS
PROGRESS(100%)
PROGRESS(%) PROGRESS(%)

(LOT 2)

SUPERSTRUCTURE
WORKS

1.0 Ground floor works

i)Column
85 100
reinforcement

ii) Formworks for


columns 95 100

iii) Casting and curing


100
of columns 95 100

viii) Staircase works 65 75 100

2.0 First floor works

i) Formworks for floor


slab and beams 90 100

ii) Floor slab and beam


reinforcement works 80 100

iii) Conduiting works


on floor slab 100

iv) Casting and curing


of floor slab and beams 100

v Formworks for
columns 100
vii)Column
reinforcement works

vi) Casting and curing


of columns 70 100

vii) Staircase works 100

6/8
Planned
Progress for
Lot 1:20 %
Actual
Progress for
Lot 1: 20%
Forcast
Progress for
Lot 1 25 %

3. Site Labour Force

Chinese Staff Ghanaian Staff


Project Manager 1 Foreman 4
Site Manager 5 Carpenter 7
/ Mason / plasterer 3
/ Storekeeper 1
/ Labourer 15
/ Plumber 4
/ Steel bender 8
/ Security 8
1
Total: 6 Total : 43

4. Materials on Site

S/N Item Unit Q’ty


1 Fine Aggregate m³ 10
2 Coarse Aggregate m³ 5

3 Cement bags bags 50


4 Timber(2x4) pcs -
5 6” blocks pcs -

5. Health and Safety.

The site records no injury related issues hence health and safety signage has
been installed on site to create health and safety awareness on site.

6/8
6. Progress Photos

LOT 1

Works on first floor column Works on first floor staircase


Fig 1. Fig 2.

Installing beam plates at first floor


Fig 3.

6/8
LOT 2

Formworks for columns Formworks for first floor slab and beams
Fig 4.. Fig 5.

Striking of formworks for columns Formworks for first floor slab and beams
Fig 6.. Fig 7

6/8
Endorsed by: George Dabi

………………………………………
Clerk of works

Endorsed by: Mr. Mao

………………………………………......
Site Manager (China State)

Prepared by: Emmanuel Siaw

………………………………………......
Works Engineer (China State)

6/8