GHANA INSTITUTE OF MANAGEMENT AND

PUBLIC ADMINISTRATION (GIMPA).

CONSTRUCTION OF 2 NO. 3 STOREY LECTURE HALL


BLOCKS AT GIMPA CAMPUS LOT 1 & 2 – Accra

Monthly Progress Report

Employer: GIMPA, Accra-Ghana


Consultant: ALBERT ESSAMUAH ASSOCIATES LIMITED.
Contractor: China State Hualong Construction (GH) Ltd.

April 26th,2018
MONTHLY PROGRESS REPORT AS AT 26H APRIL,2018

PROJECT TITLE: CONSTRUCTION OF 3NO. 3-STOREY LECTURE HALL BLOCK AT GIMPA


CAMPUS, ACCRA-GHANA.

Client: Ghana Institute of Management and Public Administration, (GIMPA),


Accra – Ghana
Commencement date: 24/11/17
Expected completion date: 02/01/19
Overall actual planned progress: 30%
Forecast planned progress: 40%

1. WORK PROGRESS FOR LOT 1

ACTUAL FORCAST
PLANNED
ITEM ACTIVITY PLANNED PLANNED REMARKS
PROGRESS(%)
PROGRESS(%) PROGRESS(%)

(LOT 1)

SUBSTRUCTURE
1 WORKS
i.) Earthworks,Foundation
works,Sleeper wall,ground
beams and slabs,Isolated 100 100 COMPLETED
columns columns
construction.

SUPERSTRUCTURE
WORKS
2.0 Ground floor works

i)Column reinforcement 70 100

ii) Formworks, Casting of


Columns and curing 65 100

iii) Staircase works 70 90 100

2/8
3.0 First Floor works

i) Floor slab and beam reinforcement 60 70 100

ii)Formwork for slabs and beams 70 80 100

iii) Casting of floor slabs 70 70

iv)Column reinforcement works, Casting


and curing 60 60

v) Blockworks 70 70
Planned Progress for Lot
1:35 %
Actual Progress for Lot 1:
35 %
Forcast Progress for Lot 1
: 40 %

2. WORK PROGRESS FOR LOT 2

ACTUAL FORECAST
PLANNED
ITEM ACTIVITY PLANNED PLANNED REMARKS
PROGRESS(100%)
PROGRESS(%) PROGRESS(%)

(LOT 2)

SUBSTRUCTURE
WORKS
1 Preliminaries works:
i) Site setup
ii)Disposal of debris
and spoil material
iii)Leveling 100 100 COMPLETED

1.1 Setting out

1.2 Earthwork

3/8
1.3 Column base construction 95 95 100

1.4 Footing columns construction 95 95 100


100
1.5 Reinforcement for ground beams and slabs 65 85 100

1.6 Formwork for ground beams and slabs 65 80 100

1.7 Concrete works for ground beams and slabs 65 0 65

Planned
Progress for Lot
1:20 %
Actual Progress
for Lot 1: 20 %
Forecast
Progress for Lot
1 35 %

4/8
3. Site Labour Force

Chinese Staff Ghanaian Staff


Project Manager 1 Foreman 4
Site Manager 2 Carpenter 7
/ Mason / plasterer 3
/ Storekeeper 1
/ Labourer 16
/ Plumber 5
/ Steel bender 5
/ Security 2
Total: 3 Total : 43

4. Materials on Site

S/N Item Unit Q’ty


1 Fine Aggregate m³ 15
2 Coarse Aggregate m³ 15
3 Cement bags bags 200
4 Timber(5cmx10cm) pcs 673
5 6” blocks pcs 200
6 Plywood pcs 387

5. Health and Safety.

The site records no injury.

5/8
6. Progress Photos
LOT 1 Photos

Formwork to support floor concrete. Column base construction


Fig. 1

Reinforcement for floor beams


Fig.2

Columns on ground floor


Fig.3

6/8
LOT 2 Photos.

Compacted hardcore layer


Fig.4

Plumbing works on ground floor for Lot 2.


Fig. 5

7/8
Endorsed by: George Dabi

………………………………………
Clerk of works

Endorsed by: Mr. Mao

………………………………………......
Site Manager (China State)

Prepared by: Emmanuel Siaw

………………………………………......
Works Engineer (China State

8/8