Breakdown of Works Total (Area/Unit) Labor Cost (PHP) Unit Multiplier Man Hour (MH) Days

This document provides a breakdown of labor costs for various construction works. It lists 33 separate works items like site clearing, excavation, concrete pouring, wall construction, roofing works, and door installation. For each item it provides the labor requirements in man power, man hours and estimated costs in a range from low to high. The total estimated cost for all the works ranges from 14,000 to 41,000 Philippine pesos depending on the estimates used.

Uploaded by

Bella Artist
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
253 views2 pages

Breakdown of Works Total (Area/Unit) Labor Cost (PHP) Unit Multiplier Man Hour (MH) Days

This document provides a breakdown of labor costs for various construction works. It lists 33 separate works items like site clearing, excavation, concrete pouring, wall construction, roofing works, and door installation. For each item it provides the labor requirements in man power, man hours and estimated costs in a range from low to high. The total estimated cost for all the works ranges from 14,000 to 41,000 Philippine pesos depending on the estimates used.

Uploaded by

Bella Artist
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

LABOR COST

MULTIPLIER TOTAL MAN POWER (MP) MAN HOUR (MH) DAYS


BREAKDOWN OF WORKS UNIT (PHP)
(AREA/UNIT)
LOW AVERAGE HIGH unit SKILLED
SEMI-SKILLED
LABORER total LOW AVERAGE HIGH LOW AVE HIGH TOTAL
2
1 site clearing 0.96 0.48 0.38 mh/sm 637.85 m 0 0 4 4 153.08 76.54 60.60 19.1 9.6 7.6 1400
3
2 manual excavation (9 footings) 8.71 6 4.4 mh/cm 8.64 m 0 0 4 4 18.81 12.96 9.50 2.4 1.6 1.2 1400
3 fabrication of footing rebars 0.2 0.1 0.08 mh/kg 44.39 kg. 1 0 1 2 4.44 2.22 1.78 0.6 0.3 0.2 850
4 fabrication of column rebars 0.2 0.1 0.08 mh/kg 155.00 kg. 0 1 1 2 15.50 7.75 6.20 1.9 1.0 0.8 750
5 installation of footing rebars 1 0.53 0.42 mh/kg 44.39 kg. 1 1 2 4 11.10 5.88 4.66 1.4 0.7 0.6 1600
6 installation of column rebars 0.14 0.07 0.06 mh/kg 155.00 kg. 0 1 1 2 10.85 5.43 4.65 1.4 0.7 0.6 750
3
7 concrete pouring of footing foundations 14 11 5.6 mh/cm 1.73 m 1 1 2 4 6.05 4.75 2.42 0.8 0.6 0.3 1600
8 fabrication of column formworks 2.15 1.08 0.86 mh/sm 34.00 m2 1 1 2 4 18.28 9.18 7.31 2.3 1.1 0.9 1600
2
9 installation of column formworks 2.15 1.08 0.86 mh/sm 34.00 m 1 1 3 5 14.62 7.34 5.85 1.8 0.9 0.7 1950
3
10 concrete pouring of column 8 6 4.5 mh/cm 1.54 m 0 1 1 2 6.16 4.62 3.47 0.8 0.6 0.4 750
11 stripping of column formworks 0.5 0.25 0.2 mh/sm 34.00 m2 0 0 2 2 8.50 4.25 3.40 1.1 0.5 0.4 700
12 fabrication of beam rebars 0.2 0.1 0.08 mh/kg 416.14 m2 1 1 1 3 27.74 13.87 11.10 3.5 1.7 1.4 1250
2
13 fabrication of beam formworks 2.15 1.08 0.86 mh/sm 51.00 m 0 1 1 2 54.83 27.54 21.93 6.9 3.4 2.7 750
2
14 installation of beam formworks 2.01 1.25 0.5 mh/sm 51.00 m 1 1 4 6 17.09 10.63 4.25 2.1 1.3 0.5 2300
15 installation of beam rebars 0.9 0.6 0.3 mh/kg 416.14 m2 1 1 1 3 124.84 83.23 41.61 15.6 10.4 5.2 1250
3
16 installation of beam scaffolding 0.96 0.48 0.38 mh/sm 51.00 m 1 2 2 5 9.79 4.90 3.88 1.2 0.6 0.5 2000
17 Concrete pouring of beams 8 6 4.5 mh/cm 3.00 m3 1 0 1 2 12.00 9.00 6.75 1.5 1.1 0.8 850
3
18 stripping of beam formworks 2.06 1.03 0.82 mh/sm 51.00 m 0 0 3 3 35.02 17.51 13.94 4.4 2.2 1.7 1050
19 stripping of beam scaffolding 2.06 1.03 0.82 mh/sm 51.00 m3 1 1 4 6 17.51 8.76 6.97 2.2 1.1 0.9 2300
3
20 installation of slab rebar 0.14 0.07 0.06 mh/kg 176.00 m 1 1 4 6 4.11 2.05 1.76 0.5 0.3 0.2 2300
3
21 concrete pouring of slab 8 6 4.5 mh/cm 9.00 m 1 2 8 11 6.55 4.91 3.68 0.8 0.6 0.5 4100
22 CHB laying for exterior walls 3.2 1.6 1.28 mh/sm 101.00 1 1 4 6 53.87 26.93 21.55 6.7 3.4 2.7 2300
2
23 CHB laying for interiorr walls 2.66 1.33 1.06 mh/sm 37.35 m 1 1 2 4 24.84 12.42 9.90 3.1 1.6 1.2 1600
2
24 Plastering of exterior walls 6 3 2.4 mh/sm 202.00 m 1 1 4 6 202.00 101.00 80.80 25.3 12.6 10.1 2300
2
25 Plastering of interior walls 6 3 2.4 mh/sm 75.00 m 1 1 4 6 75.00 37.50 30.00 9.4 4.7 3.8 2300
26 Fabrication of Steel Truss 60 40.00 30 mh/piece 3.00 pcs 1 1 2 4 45.00 30.00 22.50 5.6 3.8 2.8 1600
27 Installation of Steel Truss 60 40 30 mh/m 3.00 pcs 1 1 2 4 45.00 30.00 22.50 5.6 3.8 2.8 1600
28 Installation of C-Purlins 0.53 0.27 0.21 mh/m 209.00 m 1 0 2 3 36.92 18.81 14.63 4.6 2.4 1.8 1200
29 Installation of Fascia Board 0.91 0.46 0.36 mh/bf 44.00 bf 1 0 1 2 20.02 10.12 7.92 2.5 1.3 1.0 850
3
30 installation of ceiling frame 0.73 0.36 0.29 mh/sqm 67.00 m 1 0 1 2 24.46 12.06 9.72 3.1 1.5 1.2 850
31 installation of plywood 2.00 1.00 0.8 mh/sqm 67.00 m2 1 0 1 2 67.00 33.50 26.80 8.4 4.2 3.4 850
32 Installation of insulator and roof sheets 6.12 3.06 0.86 mh/sqm 64.33 m2 1 1 2 4 98.42 49.21 13.83 12.3 6.2 1.7 1600
33 Fabrication of Wooden Door Jambs 0.44 0.22 0.18 mh/bf 130.00 BF 1 0 1 2 28.60 14.30 11.70 3.6 1.8 1.5 850
34 Installation of Wooden Door Jambs 0.66 0.33 0.26 mh/bf 130.00 BF 1 0 1 2 42.90 21.45 16.90 5.4 2.7 2.1 850
35 Installation Wood Panel Door
36 D1 0.66 0.33 0.26 mh/pc 2.00 sets 1 0 1 2 0.66 0.33 0.26 0.1 0.0 0.0 850
37 D2 0.66 0.33 0.26 mh/pc 3.00 sets 1 0 1 2 0.99 0.50 0.39 0.1 0.1 0.0 850
38 D3 0.66 0.33 0.26 mh/pc 2.00 sets 1 0 1 2 0.66 0.33 0.26 0.1 0.0 0.0 850
39 Installation of Aluminum Framed Windows
40 W1 20 10 8 mh/each 4.00 sets 1 0 1 2 40.00 20.00 16.00 5.0 2.5 2.0 850
41 W2 20 10 8 mh/each 1.00 sets 1 0 1 2 10.00 5.00 4.00 1.3 0.6 0.5 850
42 W3 20 10 8 mh/each 1.00 sets 1 0 0 1 20.00 10.00 8.00 2.5 1.3 1.0 500
43 Installation of Door Locksets 3.2 1.6 1.28 mh/set 13.00 sets 1 0 0 1 41.60 20.80 16.64 5.2 2.6 2.1 500
44 Installation of Vitrified Floor tiles
2
45 living room 10.66 6.33 4.26 mh/sqm 12.89 m 1 0 1 2 68.70 40.80 27.46 8.6 5.1 3.4 850
2
46 kitchen 10.66 6.33 4.26 mh/sqm 10.00 m 1 0 1 2 53.30 31.65 21.30 6.7 4.0 2.7 850
47 dining 10.66 6.33 4.26 mh/sqm 11.79 m2 1 0 1 2 62.84 37.32 25.11 7.9 4.7 3.1 850
48 master bedroom 10.66 6.33 4.26 mh/sqm 10.00 m2 1 0 1 2 53.30 31.65 21.30 6.7 4.0 2.7 850
2
49 bedroom 1 10.66 6.33 4.26 mh/sqm 8.00 m 1 0 1 2 42.64 25.32 17.04 5.3 3.2 2.1 850
50 bedroom 2 10.66 6.33 4.26 mh/sqm 8.00 m2 1 0 1 2 42.64 25.32 17.04 5.3 3.2 2.1 850
2
51 Installation of Unglazed Floor tiles (t&b floor) 8.7 4.35 3.48 mh/sqm 2.50 m 1 0 1 2 10.88 5.44 4.35 1.4 0.7 0.5 850
52 Installation of glazed Floor tiles (t&b wall t 6 3 2.4 mh/sqm 6.32 m2 1 0 1 2 18.96 9.48 7.58 2.4 1.2 0.9 850
53 Grouting of Tiles 3.34 1.67 1.34 mh/sqm 67.32 m2 1 0 1 2 112.43 56.21 45.11 14.1 7.0 5.6 850
2
54 exterior surface preparation 0.86 0.43 0.34 mh/sqm 202.00 m 1 1 2 4 43.43 21.72 17.17 5.4 2.7 2.1 1600
55 interior surface preparation 0.86 0.43 0.34 mh/sqm 75.00 m2 1 0 1 2 32.25 16.13 12.75 4.0 2.0 1.6 850
2
56 ceiling surface preparation 0.86 0.43 0.34 mh/sqm 67.00 m 1 0 1 2 28.81 14.41 11.39 3.6 1.8 1.4 850
57 Painting of Exterior Walls 0.68 0.34 0.18 mh/sqm 202.00 m2 1 1 2 4 34.34 17.17 9.09 4.3 2.1 1.1 1600
2
58 Painting of Interior Walls 0.68 0.34 0.17 mh/sqm 75.00 m 1 1 2 4 12.75 6.38 3.19 1.6 0.8 0.4 1600
59 ceiling surface preparation 0.86 0.43 0.34 mh/sqm 67.00 m2 1 0 1 2 28.81 14.41 11.39 3.6 1.8 1.4 850
2
60 ceiling finishing 0.68 0.34 0.18 mh/sqm 67.00 m 1 0 1 2 22.78 11.39 6.03 2.8 1.4 0.8 850
61 Laying of PVC pipes 1/2'" dia 1.32 0.66 0.53 mh/lm 25.00 m 1 0 1 2 16.50 8.25 6.63 2.1 1.0 0.8 850
62 Laying of PVC pipes 4" dia 6.58 3.29 2.63 mh/lm 12.00 m 1 0 1 2 39.48 19.74 15.78 4.9 2.5 2.0 850
63 Laying of PVC pipes 2" dia 4.38 2.19 1.75 mh/lm 4.00 m 1 1 1 3 5.84 2.92 2.33 0.7 0.4 0.3 1250
64 Installation of Lavatory 16 8 6.4 mh/ each 1.00 each 1 0 0 1 16.00 8.00 6.40 2.0 1.0 0.8 500
65 Installation of Water closet 24 12 9.6 mh/ each 1.00 each 1 0 0 1 24.00 12.00 9.60 3.0 1.5 1.2 500
66 Installation of shower 20 10 8 mh/ each 1.00 each 1 0 0 1 20.00 10.00 8.00 2.5 1.3 1.0 500
67 Installation of kitchen sink 16 8 6.4 mh/ each 1.00 each 1 0 0 1 16.00 8.00 6.40 2.0 1.0 0.8 500
68 Installation of floor drains 2 1 0.5 mh/ each 1.00 each 1 0 0 1 4.00 2.00 1.60 0.3 0.1 0.1 500
69 Installation of faucet 4 2 1.6 mh/ each 4.00 sets 1 0 0 1 16.00 4.00 6.40 2.0 1.0 0.8 500
3
70 excavation of septic tank 16 8 6.4 mh/cm 7.00 m 0 0 2 2 56.00 28.00 22.40 7.0 3.5 2.8 700
71 CHB laying 3.2 1.6 1.28 mh/sm 20.00 m2 1 0 1 2 32.00 16.00 12.80 4.0 2.0 1.6 850
72 Concreting of septic tank cover 10 5 4 mh/cm 0.60 m3 1 0 1 2 3.00 1.50 1.20 0.4 0.2 0.2 850
73 installation of septic tank piping system 4.92 2.46 1.97 mh/lm 3.00 m 1 0 0 1 14.76 7.38 5.91 1.8 0.9 0.7 500
74 downspout intallation 2.16 1.08 0.86 mh/lm 32.00 m 1 0 1 2 34.56 17.28 13.76 4.3 2.2 1.7 850
75 laying of electrical conduits 1.35 0.6 0.5 mh per 30m. 70.00 m 1 0 0 1 3.15 1.40 1.17 0.4 0.2 0.1 500
76 installation of panel board 24 16 8 mh/pc 1.00 pc 1 0 0 1 24.00 16.00 8.00 3.0 2.0 1.0 500
77 installation of utility and junction boxes 0.38 0.19 0.15 mh/pc 28.00 pcs 1 0 0 1 10.64 5.32 4.20 1.3 0.7 0.5 500
78 installation of electrical wirings 0.39 0.2 0.14 mh per 30m. 210.00 m 1 0 0 1 2.73 1.40 0.98 0.3 0.2 0.1 500
79 installation of outlets and switches 1.13 0.52 0.45 mh/pc 56.00 pcs 1 0 0 1 63.28 29.12 25.20 7.9 3.6 3.2 500
80 installation of lighting fixtures 1.86 1.36 0.8 mh/pc 14.00 pcs 1 0 0 1 26.04 19.04 11.20 3.3 2.4 1.4 500
81 cabinet boarding 0.36 0.18 0.14 mh/bf 1,392.00 bf 1 0 0 1 501.12 250.56 194.88 62.6 31.3 24.4 500
82 Painting of cabinets 0.68 0.34 0.17 mh/sm 10.78 sm 1 0 1 2 3.67 1.83 0.92 0.5 0.2 0.1 850