Grouting

1. The document is a field inspection and test plan for grouting work on a power plant project. 2. It outlines inspection activities to review grouting specifications and procedures, inspect materials, prepare equipment, inspect grouting application, and document inspection records. 3. Inspection items include verifying material specifications, storage conditions, equipment performance, concrete surface preparation, mixing, compression testing, and final visual inspection.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
241 views1 page

Grouting

1. The document is a field inspection and test plan for grouting work on a power plant project. 2. It outlines inspection activities to review grouting specifications and procedures, inspect materials, prepare equipment, inspect grouting application, and document inspection records. 3. Inspection items include verifying material specifications, storage conditions, equipment performance, concrete surface preparation, mixing, compression testing, and final visual inspection.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 1

Page 1 of 1

PT.TRUBA JAYA ENGINEERING ITP NO. : I-T-3122-QAQC-012


Rev. No. : 0
FIELD INSPECTION & TEST PLAN (F-ITP)
Date : 9-Mar-10
PROJECT NAME : CFSPP 2x660 MW-TJB U#3, #4 Central Java
OWNER : PT. Central Java Power
CLIENT : Sumitomo Corporation Erection Division (SCED)
TJE JOB NO. : T-3122
DESCRIPTION : GROUTING WORK

INSPECTION ACTIVITIES
REFERENCE
No. ITEM ACTIVITIES DOCUMENTS/ACCEPTANCE VERIFYING DOCUMENT
CRITERIA TJE SCED BVI Owner

1.0 REVIEW GROUTING SPECIFICATION & PROCEDURE


1.1 Tech. spec.procedures shall be clarified, understood, finalise deviation, Standard Operating Procedure, R R/A R/A R/A
Approved Technical
Document Contract Agreement,
generate a new procedure as required Specification & Procedures
Standard & Code

2.0 MATERIAL RECEIVING & STORAGING INSPECTION


2.1 Grouting Material Inspection
2.1.1 Mat'l Specification
2.1.2 Grouting type
2.1.3 Material safety Data sheet (MSDS) W SW SW SW
Tech. Spec., Drawing, Proc., -
2.1.4 Mat'l Quality report (Mill Test Report)
Manual Instruction.
2.2 Mat'l Storaging Inspection
2.2.1 The storage condition, cover protection, and dunage for leveling position
2.2.2 Storage Temperature as per MSDS
If any descripancy or non conformance report shall be reported for desposition
3.0 PREPARATION BEFORE STARTING WORK
3.1 Checking equipment and tool for grouting application, inspection, etc.
Tech. Spec., Drawing, Proc.,
(Performance Test, Capacity, type, etc.) - W SW SW SW
Manual Instruction.

4.0 GROUTING APPLICATION


4.1 Concrete Surface Preparation
4.2 Wetting area prior to grout (if any) Tech. Spec., Drawing,
4.3 Concrete Proportioning , Mixing Procedure, Manual Instruction Inspection Report (F2-3) W&R SW & R SW & R SW & R
4.4 Compression Strenght Test (Sample Testing)
4.5 Visual Final Inspection
5.0 DOCUMENTATION
All documentation/inspection record related with painting shall be Contract, Tech. Spec., Proc. All Inspection Reports, RFI, R R R R
documented and submitted to Client as per Contract Doc. NCR, Etc.