This document provides a step-by-step guide to configure a Transport Management System (TMS) in SAP. It describes 37 steps to assign transport domains to systems, add systems to the transport domain, create transport routes between the systems, and activate the TMS configuration. The key steps are to assign a production system (SLP) as the transport domain controller, add quality (SLQ) and development (SLD) systems to the SLP domain, create a transport layer starting with Z, and establish consolidation and delivery transport routes between the systems.

Uploaded by

Gracia Stephen
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
242 views39 pages

Transport Management System

This document provides a step-by-step guide to configure a Transport Management System (TMS) in SAP. It describes 37 steps to assign transport domains to systems, add systems to the transport domain, create transport routes between the systems, and activate the TMS configuration. The key steps are to assign a production system (SLP) as the transport domain controller, add quality (SLQ) and development (SLD) systems to the SLP domain, create a transport layer starting with Z, and establish consolidation and delivery transport routes between the systems.

Uploaded by

Gracia Stephen
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 39

Transport Management System ( TMS ) Configuration In SAP Step By

Step With Snap Shots


I have 3 systems Production(SLP) Quality(SLQ) & Development
(SLD) step by step i will tell you how to configure TMS for them

Step 1- assign transport domain here I am assigning SLP as transport domain Goto T-Code STMS

Step 2- you will get popup, enter details as shown in below image in both boxes domain is SLP and then press Save
Step 3- you will get below screen after saving then press System Overview
Step 4- Click on update configuration
Step 5- Click on Distribute & activate configuration
Step 6- select first option &click on Green tick
Step 7- Now Go to anther system which is Quality (SLQ) and hit STMS in SLQ elow popup will come their
Step 8-Click on other configuration
Step 9- enter target host as oup domain controller which is SLP in my case
Step 10- Click on Save
Step 11- you will get below screen with below message
Step 12- Now again goto STMS of SLP which is our domain controller to approve newly added system (SLQ)
Step 13- Click on system overview
Step 14- you will find newly added system which is SLQ in my case
Step 14- Click on newly added system and press approve
Step 15- Click on YES
Step 17- Click on Green tick
Step 18- you will find same status for both
Step 19- you will find same status for both means system is added successfully to transport domain

Repeat Step 7 to Step 18 to add third system which is SLD in my


case
you will find below 3 system in System overview of SLP (Transport Domain ) after adding 3rd system (SLD)
Creating Transport Routes For TMS

Step 20- in transport domain controller (SLP) Click on Transport Routes


Step 21-Click on Display Change
Step 22-Click on Change
Step 23-Click on Transport route editor
Step 24-Click on Hierarchical list editor and press enter
Step 25-you will find below screen
Step 26-Click on Display Change
Step 27-Click on Change
Step 28-Droll down Transport Layer by clicking on + mark
Step 29-Click on right click on transport layers and select create option
Step 30-enter transport layer name and description, transport layer name should start with Z
Step 31- then right Click on transport route and select create option
Step 32-Select Consolidation and enter Development(SLD) & quality system (SLQ) and layer(ZABC) then click on
green tick
Step 33-you can see both systems are added
Step 34-again right click on transport route and select create
Step 35-this time click on select delivery and enter quality (SLQ) and production (SLP) system and click on green tick
Step 36-you can see all 3 systems in transport route; now click on SAVE
Step 37-Give short description and enter
Step 38-Distribute & activate configuration
Step 39-your TMS is created & activate ENjoy transpoting NOW !!!
THANKS....