Critical Path
Critical Path
Project Scheduling
Project Scheduling 1
Prepared by: Derek Huether, PMP, CSM
What is Scheduling?
…Forming a network of activities and event relationships that portrays the sequential
relations between the tasks in a project…
…Planned completion of a project based on the logical arrangement of activities,
resources…
…Placing the project and its activities in a workable sequenced timetable…
…A detailed outline of activities/tasks with respect to time…
While scheduling is all of these things, the main thing to remember is that
scheduling is the development of planned dates
for performing project activities and meeting milestones.
“I keep six honest serving men (they taught me all I knew); their names
are What and Why and When and How and Where and Who.”
--- Rudyard Kipling
Planning involves making decisions with the objective of influencing the future.
Another way to consider planning is as the “thinking” phase. Defining
activities, their logical sequence, and their relationship to each other are all
planning functions. In planning you answer the following questions:
In what sequence?
• This question involves determining the order in which activities will be
performed to complete the project.
Project Scheduling 4
Prepared by: Derek Huether, PMP, CSM
Planning vs. Scheduling
With five main questions answered, only one last question remains: when. This
question involves scheduling.
Project Scheduling 5
Prepared by: Derek Huether, PMP, CSM
Project Scheduling
To satisfy the earned value management system (EVMS) criteria, the schedule
must:
On the following pages, we will discuss the process for developing a project
schedule, including how to ensure it is logical and how to ensure that it
includes all key milestones and deliverables.
Project Scheduling 6
Prepared by: Derek Huether, PMP, CSM
Project Scheduling
For the purpose of explaining the process in detail, we will use the BEST
Management Books project.
Project Scheduling 7
Prepared by: Derek Huether, PMP, CSM
Scheduling - Step 1. Develop a List of Project Activities
Project Scheduling 8
Prepared by: Derek Huether, PMP, CSM
Scheduling – Step 1. Develop a List of Project Activities
Here is the initial list of activities for the BEST Project Management book.
There are two things to remember at this stage of the process.
1. The activity list is not a complete list; additions and subtractions will be
made from it.
2. As you develop your list, you may see the need to update the WBS.
Remember the WBS is a dynamic tool, revisions may be needed and
should be expected as the scheduling of activities progresses.
WBS Activity List
1.1 Start Development of Project Management Book
For this example, we will assume
1.1.1.1.1 Writing Project Selection section for Chapter 1 that this is a complete list of
1.1.1.1.2 Writing Project Organization section for Chapter 1
1.1.1.1.3 Writing Project Planning section for Chapter 1
activities, and no revision to the
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 WBS is needed.
1.1.1.2.2 Writing Scheduling section for Chapter 2
1.1.1.2.3 Writing Project Controls section for Chapter 2
1.1.1.3.1 Writing Auditing section for Chapter 3
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3
1.1.2.1 Editing Chapter 1
1.1.2.2 Editing Chapter 2
1.1.2.3 Editing Chapter 3
1.1.3 Publishing Project Management Book
1.1 Finished Development of the Project Management Book
Project Scheduling 9
Prepared by: Derek Huether, PMP, CSM
Scheduling – Step 2. Sequence the List of Project Activities
This process requires the project manager, subject matter experts (SME), and
other project team members who are familiar with the nature of the specific
activities to meet, discuss and develop the sequencing of the project
activities. This process is known as “a pencil to paper” process.
Continuing to use our BEST Management book example, we will take a look at
this sequencing process on the next page.
Project Scheduling 10
Prepared by: Derek Huether, PMP, CSM
Scheduling – Step 2. Sequence the List of Project Activities
BEST Management
1. Start with the WBS… Books
1. …2. Develop the Activity List….
WBS Activity List
1.1 Start Development of Project Management Book
Project Management 1.1.1.1.1 Writing Project Selection section for Chapter 1
- An Introduction
1.1 1.1.1.1.2 Writing Project Organization section for Chapter 1
1.1.1.1.3 Writing Project Planning section for Chapter 1
1.1.1.2.1 Writing Budget and Cost section for Chapter 2
Writing Editing Publishing 1.1.1.2.2 Writing Scheduling section for Chapter 2
Text Book Text Book Text Book
1.1.1 1.1.2 1.1.3
1.1.1.2.3 Writing Project Controls section for Chapter 2
1.1.1.3.1 Writing Auditing section for Chapter 3
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3
Chapter 1 Chapter 2 Chapter 3 Editing Editing Editing 1.1.2.1 Editing Chapter 1
1.1.1.1 1.1.1.2 1.1.1.3 Chapter 1 Chapter 2 Chapter 3
1.1.2.1 1.1.2.2 1.1.2.3 1.1.2.2 Editing Chapter 2
1.1.2.3 Editing Chapter 3
1.1.3 Publishing Project Management Book
Project Project Project Budget & Scheduling Project Auditing Administrative
Selection Organization Planning Cost 1.1.1.2.2 Controls 1.1.1.3.1 Closeout 1.1 Finished Development of the Project Management Book
1.1.1.1.1 1.1.1.1.2 1.1.1.1.3 1.1.1.2.1 1.1.1.2.3 1.1.1.3.2
Project Scheduling 11
Prepared by: Derek Huether, PMP, CSM
Scheduling - Step 3. Determine the Relationship Between
Project Activities
Once the sequence has been established, you need to determine the direct
relationship between each activity. But how does sequencing differ from
identifying the relationships of tasks and activities?
Sequencing is the order of how things will happen. First, second, third, etc. . .
• FS – Finish to Start
• SS – Start to Start
• FF – Finish to Finish
• SF – Start to Finish
Project Scheduling 12
Prepared by: Derek Huether, PMP, CSM
Scheduling - Step 3. Determine the Relationship Between
Project Activities
Let’s take a closer look at the first three scheduling dependencies. We will not
discuss the last dependence, as it is never used.
Project Scheduling 13
Prepared by: Derek Huether, PMP, CSM
Types of Scheduling Dependencies
The first type of relationship is called Finish to Start (FS). This means that activity
“A” must finish before activity “B” can start.
Let’s look at this relationship using the BEST Management Books example:
Finish-To-Start
You must “Finish” writing the Project Organization section of Chapter 1 before
you can “Start” writing the Project Planning section for Chapter 1.
Project Scheduling 14
Prepared by: Derek Huether, PMP, CSM
Types of Scheduling Dependencies
The second type of relationship is Start to Start (SS). This means that activity “B”
can start as soon as activity “A” starts.
Let’s look at this relationship using the BEST Management Books example:
Start-To-Start
Start BEST
Management
Books Project
SS Writing Project
Selection section
for Chapter 1
You can “Start” writing the Project Selection section for Chapter 1 as soon as
you “Start” the BEST Management Books Project.
Project Scheduling 15
. Prepared by: Derek Huether, PMP, CSM
Types of Scheduling Dependencies
The third type of relationship is Finish to Finish (FF). This means that activity
“B” cannot finish until activity “A” finishes.
Let’s look at this relationship using the BEST Management Books example:
Finish-To-Finish
FF
Editing Chapter 3
Finish BEST
Management
Books Project
You cannot “Finish” the project, Finish BEST Management Book Project,
until you “Finish” Editing Chapter 3.
Project Scheduling 16
Prepared by: Derek Huether, PMP, CSM
Step 3. Determine the Relationship Between Project
Activities
Using the relationships we have just described, the BEST Management Books
project activities and the logical relationships among them is diagrammed
below. This is formally known as a Network Diagram.
Start BEST
Finish BEST
Management Book
Management Book
Project
Project
Writing Project FS Writing Project FS
Organization Section Planning Section for Editing Chapter 1 FF
SS FS
for Chapter 1 Chapter 1
FS
Publishing Project
Writing Project Management Book
Selection Section for
FS
Chapter 1
FS
FS
With the relationships defined, we now need to establish the duration for each
activity. Let’s take a look on the next page.
Project Scheduling 17
Prepared by: Derek Huether, PMP, CSM
Project Scheduling - Step 4. Establish the Duration for Each
Activity
Now that you have the project network diagram, it is time to determine the
duration for each project activity. Once again, just like the sequencing
process: you need to enlist the help of the people or group of people familiar
with the nature of the project.
Establishing the duration of each project activity involves determining the work
periods needed to complete each identified activity. Work periods can be
– hours
– days
– weeks
– months, etc..
Regardless of the exact work period chosen, the period must be consistent for
all activities in the schedule. The project manager and team member(s)
must decide which work period is right for the project.
Project Scheduling 18
Prepared by: Derek Huether, PMP, CSM
Methods for Determining Activity Duration
Two major duration estimating tools can help project managers estimate the
activity duration: the PERT and CPM.
Project Scheduling 19
Prepared by: Derek Huether, PMP, CSM
Methods for Determining Activity Duration: an Example
For the activity “Editing Chapter 1,” the following estimates are determined:
– (O) Optimistic estimate = 6 days
– (P) Pessimistic estimate = 18 days
– (M) Most Likely = 9 days
Legend
Time Estimates
• Optimistic (O)
• Pessimistic (P)
• Most Likely (M)
Project Scheduling 20
Prepared by: Derek Huether, PMP, CSM
Project Scheduling - Step 4. Establish the Duration for Each
Activity
Now let’s look at the duration estimate for the activities in the BEST
Management Books project. For the purposes of this tutorial, it does not
matter which duration estimating method was used.
WBS Activity Description Duration
1.1 Start Development of Project Management Book 0 wks
Here is a list of the activities in 1.1.1.1.1
1.1.1.1.2
Writing Project Selection section for Chapter 1
Writing Project Organization section for Chapter 1
8 wks
10 wks
the BEST Management Books 1.1.1.1.3 Writing Project Planning section for Chapter 1 9 wks
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 9 wks
Project. The durations for each 1.1.1.2.2 Writing Scheduling section for Chapter 2 5 wks
activity have been determined. 1.1.1.2.3
1.1.1.3.1.
Writing Project Controls section for Chapter 2
Writing Auditing section for Chapter 3
7 wks
2 wks
From looking at the chart, what 1.1.1.3.2 Writing Administrative Closeout section for Chapter 3 1 wk
1.1.2.1 Editing Chapter 1 8 wks
is the work period chosen by the 1.1.2.2 Editing Chapter 2 8 wks
project manager? 1.1.2.3
1.1.3
Editing Chapter 3
Publishing Project Management Book
4 wks
4 wks
1.1 Finish Development of the Project Management Book 0 wks
The work period is weeks (wks). Remember the selected work period must
be consistent for all activities.
Project Scheduling 21
Prepared by: Derek Huether, PMP, CSM
Scheduling – Quick Review
At this point, you have covered a good bit of information. Take some
time now to review what you have learned.
The final step in this process is to determine the project duration (start
and completion dates) and the start and finish dates for each
individual activity. Take a closer look at this step on the following
page.
Project Scheduling 22
Prepared by: Derek Huether, PMP, CSM
Project Scheduling – Step 5. Determine Project Duration
Usually the project duration and activity start and completion dates are mapped
in a typical scheduling software application. The activities are placed in the
software tool, and the relationships are identified. The software calculates
the dates.
To better understand how the software calculates the dates, we will take a look
at the process known as Forward and Backward Pass.
The Forward Pass determines the The Backward Pass determines the
early start (ES) and the early finish late start (LS) and late finish (LF) of
(EF) of each activity. each activity.
Together, these processes give the total project duration, including the start
and finish dates for each activity. Additionally, the process will determine the
• critical path, which tells you the activities that cannot slip without increasing
the total duration of the project or moving the project completion date, and
• float, which tells you how much certain activities can slip without impacting
the total project duration.
We will look at critical path and float later in the module.
Project Scheduling 23
Prepared by: Derek Huether, PMP, CSM
Project Scheduling – Step 5. Determine Project Duration
Project Scheduling 24
Prepared by: Derek Huether, PMP, CSM
Project Scheduling – Step 5. Determine Project Duration
To begin the Forward Pass process, determine a project start date. Looking at
the BEST project, we will use January 1 as the project start date.
Start BEST
Management Book
The first activity that appears in the Network Diagram Project
Writing Project
is “Start BEST Management Books project.” SS Organization Section
for Chapter 1
FS
Accordingly, the information appears in the Writing Project
The early start (ES) is 1/1 since this is the First activity and the start date for
the project is 1/1. The early finish (EF) for this activity is also 1/1 since it is a
milestone and a milestone has no duration.
Project Scheduling 25
Prepared by: Derek Huether, PMP, CSM
Project Scheduling – Step 5. Determine Project Duration
Using the Network Diagram, the next activity is “Writing Project Selection
section of Chapter 1.” This activity is start to start (SS) with the previous
activity, thus its early start date is 1/1 (see chart). The early finish is
determine by the duration of the activity itself. This activity has a duration of
8 weeks, which translates to a early finish date of 2/25.
Start BEST
Management Book
Project
Writing Project
SS Organization Section
for Chapter 1
FS
Writing Project
Selection Section for
Chapter 1
Project Scheduling 26
Prepared by: Derek Huether, PMP, CSM
Project Scheduling – Step 5. Determine Project Duration
The next activity is “Writing the Project Organizational section of Chapter 1.” It
is finish to start (FS) with the previous activity. With the FS relationship in
mind, what is the early start date for this activity?
Start BEST
Management Book
Because you must finish writing the Project Project
Writing Project
Selection section before you start writing the SS Organization Section
for Chapter 1
FS
Project Organizational section, the early start Writing Project
Selection Section for
date for the current activity is 2/26. The early Chapter 1
Project Scheduling 27
Prepared by: Derek Huether, PMP, CSM
Project Scheduling – Step 5. Determine Project Duration
The next activity is “Writing the Project Budget and Cost section of Chapter 2.”
It is finish to start (FS). Can you determine the activity that must finish,
before this activity can start?
Start BEST
Management Book
It is finish to start (FS) with Writing the Project Selection Project
Writing Project
SS
section: because you must finish writing the project FS
Organization Section
for Chapter 1
selection section before you start writing the project Writing Project
Selection Section for
budget and cost section (same as Writing Project Chapter 1
This process is used to determine each activity’s ES and EF. On the page next
is the completed Forward Pass.
Project Scheduling 28
Prepared by: Derek Huether, PMP, CSM
Project Scheduling – Step 5. Determine Project Duration
By looking at the chart below, can you determine the project duration, start and
completion dates?
WBS Activity Duration ES EF LS LF
1.1 Start Development of Project Management Book 0 wks 1/1 1/1
1.1.1.1.1 Writing Project Selection section for Chapter 1 8 wks 1/1 2/25
1.1.1.1.2 Writing Project Organization section for Chapter 1 10 wks 2/26 5/6
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 9 wks 2/26 4/29
1.1.1.1.3 Writing Project Planning section for Chapter 1 9 wks 5/7 7/8
1.1.1.2.2 Writing Scheduling section for Chapter 2 5 wks 4/30 6/3
1.1.1.2.3 Writing Project Controls section for Chapter 2 7 wks 6/4 7/22
1.1.1.3.1. Writing Auditing section for Chapter 3 2 wks 7/23 8/5
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3 1 wk 8/6 8/12
1.1.2.1 Editing Chapter 1 8 wks 7/9 9/2
1.1.2.2 Editing Chapter 2 8 wks 7/23 9/16
1.1.2.3 Editing Chapter 3 4 wks 8/13 9/9
1.1.3 Publishing Project Management Book 4 wks 9/17 10/14
1.1 Finish Development of the Project Management Book 0 wks 10/14 10/14
Project Scheduling 29
Prepared by: Derek Huether, PMP, CSM
Project Scheduling – Step 5. Determine Project Duration
With the Forward Pass complete, let’s look at the Backward Pass. The
Backward Pass calculates the latest date that each activity can start and
finish in order to meet the project end date.
Again, using the BEST Management Books example, let’s now address the
Backward Pass. The chart below contains the Forward Pass information.
Unlike the Forward
Pass, which started 1.1WBS Start Development of Project Activity
Management Book
Duration
0 wks
ES
1/1
EF
1/1
LS LF
with the first activity, 1.1.1.1.1 Writing Project Selection section for Chapter 1
1.1.1.1.2 Writing Project Organization section for Chapter 1
8 wks
10 wks
1/1
2/26
2/25
5/6
the Backward Pass 1.1.1.1.3 Writing Project Planning section for Chapter 1
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 9 wks
9 wks
2/26
5/7
4/29
7/8
will start at the 1.1.1.2.2 Writing Scheduling section for Chapter 2
1.1.1.2.3 Writing Project Controls section for Chapter 2
5 wks
7 wks
4/30
6/4
6/3
7/22
bottom of the chart 1.1.1.3.1. Writing Auditing section for Chapter 3
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3
2 wks
1 wk
7/23
8/6
8/5
8/12
with the last activity 1.1.2.1
1.1.2.2
Editing Chapter 1
Editing Chapter 2
8 wks
8 wks
7/9
7/23
9/2
9/16
and work 1.1.2.3
1.1.3
Editing Chapter 3
Publishing Project Management Book
4 wks
4 wks
8/13
9/17
9/9
10/14
backwards. 1.1 Finish Development of the Project Management Book 0 wks 10/14 10/14
Project Scheduling 30
Prepared by: Derek Huether, PMP, CSM
Project Scheduling – Step 5. Determine Project Duration
The process works the same as the Forward Pass but in the opposite direction.
Once again using the Network Diagram, the last activity is “Finish the
Development of the Project Management Book” (see below). The late finish
(LF) and the late start (LS) will be the same as the early start (ES) and early
finish (EF) since it is the final activity. Finish BEST
Management Book
Project
Editing Chapter 1 FF
FS
Publishing Project
WBS Activity Duration ES EF LS LF Management Book
1.1 Start Development of Project Management Book 0 wks 1/1 1/1 FS
1.1.1.1.1 Writing Project Selection section for Chapter 1 8 wks 1/1 2/25
1.1.1.1.2 Writing Project Organization section for Chapter 1 10 wks 2/26 5/6
Edit ing Chapter 2 FS
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 9 wks 2/26 4/29
1.1.1.1.3 Writing Project Planning section for Chapter 1 9 wks 5/7 7/8
1.1.1.2.2 Writing Scheduling section for Chapter 2 5 wks 4/30 6/3 FS
1.1.1.2.3 Writing Project Controls section for Chapter 2 7 wks 6/4 7/22
1.1.1.3.1. Writing Auditing section for Chapter 3 2 wks 7/23 8/5
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3 1 wk 8/6 8/12 Edit ing Chapter 3
1.1.2.1 Editing Chapter 1 8 wks 7/9 9/2
1.1.2.2 Editing Chapter 2 8 wks 7/23 9/16
1.1.2.3 Editing Chapter 3 4 wks 8/13 9/9
1.1.3 Publishing Project Management Book 4 wks 9/17 10/14 9/17 10/14
1.1 Finish Development of the Project Management Book 0 wks 10/14 10/14 10/14 10/14
Looking at the Network Diagram on the previous page, you see that there are
three activities that have a relationship with Publishing Project Management
Book:
– Editing Chapter 1
– Editing Chapter 2
– Editing Chapter 3
Also note that the relationships are all finish to start (FS). With this in mind,
what is the LF and LS for each activity?
WBS Activity Duration ES EF LS LF
1.1 Start Development of Project Management Book 0 wks 1/1 1/1
1.1.1.1.1 Writing Project Selection section for Chapter 1 8 wks 1/1 2/25
1.1.1.1.2 Writing Project Organization section for Chapter 1 10 wks 2/26 5/6
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 9 wks 2/26 4/29
1.1.1.1.3 Writing Project Planning section for Chapter 1 9 wks 5/7 7/8
1.1.1.2.2 Writing Scheduling section for Chapter 2 5 wks 4/30 6/3
1.1.1.2.3 Writing Project Controls section for Chapter 2 7 wks 6/4 7/22
1.1.1.3.1. Writing Auditing section for Chapter 3 2 wks 7/23 8/5
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3 1 wk 8/6 8/12
1.1.2.1 Editing Chapter 1 8 wks 7/9 9/2 7/23 9/16
1.1.2.2 Editing Chapter 2 8 wks 7/23 9/16 7/23 9/16
1.1.2.3 Editing Chapter 3 4 wks 8/13 9/9 8/20 9/16
1.1.3 Publishing Project Management Book 4 wks 9/17 10/14 9/17 10/14
1.1 Finish Development of the Project Management Book 0 wks 10/14 10/14 10/14 10/14
Project Scheduling 32
Prepared by: Derek Huether, PMP, CSM
Project Scheduling – Step 5. Determine Project Duration
Because “Publishing
WBS Activity Duration ES EF LS LF
Project Management 1.1 Start Development of Project Management Book 0 wks 1/1 1/1
1.1.1.1.1 Writing Project Selection section for Chapter 1 8 wks 1/1 2/25
Book” has an LS of 1.1.1.1.2
1.1.1.2.1
Writing Project Organization section for Chapter 1
Writing Budget and Cost section for Chapter 2
10 wks
9 wks
2/26
2/26
5/6
4/29
1.1.1.1.3 Writing Project Planning section for Chapter 1 9 wks 5/7 7/8
9/17 and all three 1.1.1.2.2 Writing Scheduling section for Chapter 2 5 wks 4/30 6/3
1.1.1.2.3 Writing Project Controls section for Chapter 2 7 wks 6/4 7/22
activities are finish to 1.1.1.3.1.
1.1.1.3.2
Writing Auditing section for Chapter 3
Writing Administrative Closeout section for Chapter 3
2 wks
1 wk
7/23
8/6
8/5
8/12
start (FS), the late 1.1.2.1
1.1.2.2
Editing Chapter 1
Editing Chapter 2
8 wks
8 wks
7/9
7/23
9/2
9/16
7/23
7/23
9/16
9/16
1.1.2.3 Editing Chapter 3 4 wks 8/13 9/9 8/20 9/16
finish (LF) for each 1.1.3 Publishing Project Management Book 4 wks 9/17 10/14 9/17 10/14
1.1 Finish Development of the Project Management Book 0 wks 10/14 10/14 10/14 10/14
must be 9/16.
How do you determine the late start (LS) for each activity? Subtract the
duration for each activity from LF, as shown in the chart.
Project Scheduling 33
Prepared by: Derek Huether, PMP, CSM
Project Scheduling – Step 5. Determine Project Duration
Here is the completed list of all the activities, including the early starts (ES),
early finishes (FS), late starts (LS) and late finishes (LF). What can you
determine about the project from this data?
Project Scheduling 34
Prepared by: Derek Huether, PMP, CSM
Project Scheduling – Step 5. Determine Project Duration
From the Forward Pass information, we know the Project duration, Project
Start, and Completion date.
Now it is time to use the information from the Backward Pass to determine the
project’s critical path.
Project Scheduling 35
Prepared by: Derek Huether, PMP, CSM
Project Scheduling – Step 5. Determine Project Duration
The Critical Path tells you the activities that cannot slip a day without increasing
the total duration of the project or moving the project completion date. The
critical path is the longest path of logically related activities through the
network which cannot slip without impacting the total project duration.
WBS Activity Duration ES EF LS LF
1.1 Start Development of Project Management Book 0 wks 1/1 1/1 1/1 1/1
1.1.1.1.1 Writing Project Selection section for Chapter 1 8 wks 1/1 2/25 1/1 2/25
1.1.1.1.2 Writing Project Organization section for Chapter 1 10 wks 2/26 5/6 3/12 5/20
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 9 wks 2/26 4/29 2/26 4/29
1.1.1.1.3 Writing Project Planning section for Chapter 1 9 wks 5/7 7/8 5/21 7/22
1.1.1.2.2 Writing Scheduling section for Chapter 2 5 wks 4/30 6/3 4/30 6/3
1.1.1.2.3 Writing Project Controls section for Chapter 2 7 wks 6/4 7/22 6/4 7/22
1.1.1.3.1. Writing Auditing section for Chapter 3 2 wks 7/23 8/5 7/30 8/12
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3 1 wk 8/6 8/12 8/13 8/19
1.1.2.1 Editing Chapter 1 8 wks 7/9 9/2 7/23 9/16
1.1.2.2 Editing Chapter 2 8 wks 7/23 9/16 7/23 9/16
1.1.2.3 Editing Chapter 3 4 wks 8/13 9/9 8/20 9/16
1.1.3 Publishing Project Management Book 4 wks 9/17 10/14 9/17 10/14
1.1 Finish Development of the Project Management Book 0 wks 10/14 10/14 10/14 10/14
Project Scheduling 36
Prepared by: Derek Huether, PMP, CSM
Project Scheduling – Step 5. Determine Project Duration
• If the result is a number greater the zero, then the activity is not on the
critical path and has float.
Project Scheduling 37
Prepared by: Derek Huether, PMP, CSM
Project Scheduling – Step 5. Determine Project Duration
To better understand critical path, take a look at this chart. Note a column
was added to calculate float and determine the critical path. From
reviewing the chart, what activities are on the critical path?
WBS Activity Duration ES EF LS LF Float
1.1 Start Development of Project Management Book 0 wks 1/1 1/1 1/1 1/1 0
1.1.1.1.1 Writing Project Selection section for Chapter 1 8 wks 1/1 2/25 1/1 2/25 0
1.1.1.1.2 Writing Project Organization section for Chapter 1 10 wks 2/26 5/6 3/12 5/20 14
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 9 wks 2/26 4/29 2/26 4/29 0
1.1.1.1.3 Writing Project Planning section for Chapter 1 9 wks 5/7 7/8 5/21 7/22 14
1.1.1.2.2 Writing Scheduling section for Chapter 2 5 wks 4/30 6/3 4/30 6/3 0
1.1.1.2.3 Writing Project Controls section for Chapter 2 7 wks 6/4 7/22 6/4 7/22 0
1.1.1.3.1. Writing Auditing section for Chapter 3 2 wks 7/23 8/5 7/30 8/12 7
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3 1 wk 8/6 8/12 8/13 8/19 7
1.1.2.1 Editing Chapter 1 8 wks 7/9 9/2 7/23 9/16 14
1.1.2.2 Editing Chapter 2 8 wks 7/23 9/16 7/23 9/16 0
1.1.2.3 Editing Chapter 3 4 wks 8/13 9/9 8/20 9/16 7
1.1.3 Publishing Project Management Book 4 wks 9/17 10/14 9/17 10/14 0
1.1 Finish Development of the Project Management Book 0 wks 10/14 10/14 10/14 10/14 0
All the activities with zero float are on the Critical Path!!!!
But what exactly does this mean? Take a look on the next page.
Project Scheduling 38
Prepared by: Derek Huether, PMP, CSM
Project Scheduling – Step 5. Determine Project Duration
The Critical Path tells management the activities that are critical or essential in
completing the project on time. It is also important for management to look
at activities with minor float because any delays in those activities could
cause them to be on the critical path.
WBS Activity Duration ES EF LS LF Float
1.1 Start Development of Project Management Book 0 wks 1/1 1/1 1/1 1/1 0
1.1.1.1.1 Writing Project Selection section for Chapter 1 8 wks 1/1 2/25 1/1 2/25 0
1.1.1.1.2 Writing Project Organization section for Chapter 1 10 wks 2/26 5/6 3/12 5/20 14
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 9 wks 2/26 4/29 2/26 4/29 0
1.1.1.1.3 Writing Project Planning section for Chapter 1 9 wks 5/7 7/8 5/21 7/22 14
1.1.1.2.2 Writing Scheduling section for Chapter 2 5 wks 4/30 6/3 4/30 6/3 0
1.1.1.2.3 Writing Project Controls section for Chapter 2 7 wks 6/4 7/22 6/4 7/22 0
1.1.1.3.1. Writing Auditing section for Chapter 3 2 wks 7/23 8/5 7/30 8/12 7
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3 1 wk 8/6 8/12 8/13 8/19 7
1.1.2.1 Editing Chapter 1 8 wks 7/9 9/2 7/23 9/16 14
1.1.2.2 Editing Chapter 2 8 wks 7/23 9/16 7/23 9/16 0
1.1.2.3 Editing Chapter 3 4 wks 8/13 9/9 8/20 9/16 7
1.1.3 Publishing Project Management Book 4 wks 9/17 10/14 9/17 10/14 0
1.1 Finish Development of the Project Management Book 0 wks 10/14 10/14 10/14 10/14 0
Project Scheduling 39
Prepared by: Derek Huether, PMP, CSM
Project Scheduling – Step 5. Determine Project Duration
Below is the PERT chart layout of the project. The boxes in red indicate those
activities on the critical path. The blue boxes are for all other activities.
Notice the information in the boxes, it shows the activity name, duration,
early start and finish, and late start and finish. See the legend below for
details.
Writing
WritingProject
Project
Organization
Organizationsection
section Duration
for Chapter 1
Start Development Early Start 10 wks
10 wks Early Finish
of Proj ect
Management Book 2/26/2002 5/6/2002
2/26/2002 5/6/2002
0 days 3/12/2002 5/20/2002
3/12/2002 5/20/2002
1/1/ 2002 1/1/ 2002 Late Start Late Finish
1/1/ 2002 1/1/ 2002
W riting
W riting Budget and W riting Proj ect Finish Development
W riting Scheduling W riting Auditing Administr ative
Cost section for Controls section for Editing Chapter 3 of the Proj ect
section for Chapter 2 section for Chapter 3 Closeout section
Chapter 2 Chapter 2 4 wks Management Book
5 wks 2 wks for Chapter 3
9 wks 7 wks 8/13/2002 9/9/ 2002 0 days
4/30/2002 6/3/2002 7/23/2002 8/5/ 2002 1 wk
2/26/2002 4/29/2002 6/4/2002 7/22/2002 8/20/2002 9/16/2002 10/ 14/ 2002 10/ 14/ 2002
4/30/2002 6/3/2002 7/30/2002 8/12/2002 8/6/ 2002 8/12/2002
2/26/2002 4/29/2002 6/4/2002 7/22/2002 10/ 14/ 2002 10/ 14/ 2002
8/13/2002 8/19/2002
Editing Chapter 2
8 wks
7/23/2002 9/16/2002
7/23/2002 9/16/2002
Project Scheduling 40
Prepared by: Derek Huether, PMP, CSM
Review
The Critical Path tells you the activities that can not slip
a day without increasing the total duration of the project
or moving the project completion date. It is the longest
path of logically related activities through the network
which cannot slip without impacting the total project
duration, termed zero float.
Project Scheduling 41
Prepared by: Derek Huether, PMP, CSM