50% found this document useful (2 votes)
1K views1 page

OK Card

The document is an O.K. card for concrete pouring for the Polavaram Irrigation Project. It provides details of the planned concrete pour including the name of work, grade of concrete, contractor, location, estimated quantity, lift elevation, and methodology for concreting and compaction. It also lists pre-pour checks of the form work, reinforcement, and embedded parts to be completed and approved by representatives of the contractor and Government of Andhra Pradesh before concreting can proceed.

Uploaded by

Ramdeep Gowtham
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
50% found this document useful (2 votes)
1K views1 page

OK Card

The document is an O.K. card for concrete pouring for the Polavaram Irrigation Project. It provides details of the planned concrete pour including the name of work, grade of concrete, contractor, location, estimated quantity, lift elevation, and methodology for concreting and compaction. It also lists pre-pour checks of the form work, reinforcement, and embedded parts to be completed and approved by representatives of the contractor and Government of Andhra Pradesh before concreting can proceed.

Uploaded by

Ramdeep Gowtham
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

POLAVARAM IRRIGATION PROJECT

Card No. ……………………… Dt: ……………………

O.K. CARD FOR CONCRETE

Name of Work: Grade of Concrete:


Contractor: (All grades of concrete to be poured)
Location/ Structure: Estimated Quantity to be Poured:
R.D./ Chainage from: Lift Elevation: From…………….… To…………………
Ref Drawing No. Methodology of concreting:
i. Civil (i.e, Telebelt/ Boom Placer/ Agitor/ TM)
ii. HM Methodology of Compaction (i.e, by vibrator/ …………...)

Free Hand Sketch of form work for the above estimated quantity of concrete is shown on overleaf indicating
(L x B x H) and the levels etc

Comments
Sl. Rep. of
Description Rep. of GoAP Remarks
No. Contractor
YES NO YES NO
A) Pre Pour Checks
1) General
a) Survey line/ Centre line Position marked
b) Surface/ Joints/base preparation (placement of
rubber stopper etc kept in place)
c) Adequacy of construction aids/tools/ vibrators
available/ arrangements/ access etc
2) Form Work
a) Alignment Centering checked
b) Level marked/ checked
c) Vertically/ Slope Checked
d) Support/ Stability checked
e) Cleaning & applying oil etc
3) Reinforcement
a) Type/ diameter of bar
b) Spacing/ No. of bars
c) Cover
d) Extra reinforcement, if any
e) Deviation from drawing (if any)
f) Placement/ Alignment
g) Clean up
h) Welding/ Binding/ Lapping
4) Embedded Parts (EP)
a) Total No. of EP/ Structure/ Block outs
i. Civil
ii. HM
b) Position of EP
c) Arrangement for protection during Concrete

O.K./ Not O.K. for Concreting O.K./ Not O.K. for Concreting

(Sign of Rep. of Contractor) (Sign of Rep. of GoAP - Civil) (Sign of Rep. of GoAP - HM)