Project 2016 Part 1
Project 2016 Part 1
Project 2016 Part 1
Microsoft® Project
2016: Part 1
Microsoft® Project
2016: Part 1
Microsoft® Project 2016: Part 1
Part Number: 091062
Course Edition: 1.1
Acknowledgements
PROJECT TEAM
Logical Operations wishes to thank the Logical Operations Instructor Community, and in particular Tom Allen, Elizabeth Robinson,
and John Wilson for contributing their technical and instructional expertise during the creation of this course.
Notices
DISCLAIMER
While Logical Operations, Inc. takes care to ensure the accuracy and quality of these materials, we cannot guarantee their
accuracy, and all materials are provided without any warranty whatsoever, including, but not limited to, the implied warranties of
merchantability or fitness for a particular purpose. The name used in the data files for this course is that of a fictitious company. Any
resemblance to current or future companies is purely coincidental. We do not believe we have used anyone's name in creating this
course, but if we have, please notify us and we will change the name in the next revision of the course. Logical Operations is an
independent provider of integrated training solutions for individuals, businesses, educational institutions, and government agencies.
The use of screenshots, photographs of another entity's products, or another entity's product name or service in this book is for
editorial purposes only. No such use should be construed to imply sponsorship or endorsement of the book by nor any affiliation of
such entity with Logical Operations. This courseware may contain links to sites on the Internet that are owned and operated by third
parties (the "External Sites"). Logical Operations is not responsible for the availability of, or the content located on or through, any
External Site. Please contact Logical Operations if you have any concerns regarding such links or External Sites.
TRADEMARK NOTICES
Logical Operations and the Logical Operations logo are trademarks of Logical Operations, Inc. and its affiliates.
® ®
Microsoft and Windows are registered trademarks of Microsoft Corporation in the U.S. and other countries. The other Microsoft
products and services discussed or described may be trademarks or registered trademarks of Microsoft Corporation. All other
product and service names used may be common law or registered trademarks of their respective proprietors.
Copyright © 2016 Logical Operations, Inc. All rights reserved. Screenshots used for illustrative purposes are the property of the
software proprietor. This publication, or any part thereof, may not be reproduced or transmitted in any form or by any means,
electronic or mechanical, including photocopying, recording, storage in an information retrieval system, or otherwise, without
express written permission of Logical Operations, 3535 Winton Place, Rochester, NY 14623, 1-800-456-4677 in the United States
and Canada, 1-585-350-7000 in all other countries. Logical Operations’ World Wide Web site is located at
www.logicaloperations.com.
This book conveys no rights in the software or other products about which it was written; all use or licensing of such software or
other products is the responsibility of the user according to terms and conditions of the owner. Do not make illegal copies of books
or software. If you believe that this book, related materials, or any other Logical Operations materials are being reproduced or
transmitted without permission, please call 1-800-456-4677 in the United States and Canada, 1-585-350-7000 in all other countries.
Microsoft® Project 2016:
Part 1
Solutions............................................................................................ 111
Glossary............................................................................................. 113
Index.................................................................................................. 117
About This Course
Welcome to Microsoft® Project 2016: Part 1. This course is designed to familiarize you with the
basic features and functions of Microsoft Project Professional 2016 so you can use it
effectively and efficiently in a real-world environment.
This course covers the critical knowledge and skills a project manager needs to create a
project plan with Project 2016 during the planning phase of a project. In other words, if
your supervisor assigns you to lead a project, this course will enable you to draft a project
plan with Project 2016 and share it with your supervisor (and others) for review and
approval.
Course Description
Target Student
This course is designed for a person with an understanding of project management concepts
and who is responsible for creating and maintaining project plans. The course will give the
student a fundamental understanding of Microsoft Project 2016 necessary to create and save
project plans.
Course Prerequisites
To ensure your success in this course, you should have basic project management
knowledge and skills. The following Logical Operations course can help you in meeting this
requirement: Project Management Fundamentals (Second Edition).
You should also have basic knowledge and skills for using any current Windows® operating
system—preferably Windows 10. The following Logical Operations courses can help you
meet this requirement:
• Using Microsoft® Windows® 10
• Microsoft® Windows® 10 Transition from Windows® 7
Finally, you should have competency in using other Microsoft Office applications—
preferably Office 2016. You can take any of the Office 2016 course offerings from Logical
Operations to attain the requisite knowledge and skills.
Course Objectives
In this course, you will learn to create and engage in basic management of a project using
Microsoft Project Professional 2016.
You will:
• Identify project management concepts and navigate the Project 2016 environment.
• Create and define a new project plan.
• Create and organize tasks.
| Microsoft® Project 2016: Part 1 |
At the back of the book, you will find a glossary of the definitions of the terms and concepts used
throughout the course. You will also find an index to assist in locating information within the
instructional components of the book.
As You Review
Any method of instruction is only as effective as the time and effort you, the student, are willing to
invest in it. In addition, some of the information that you learn in class may not be important to you
immediately, but it may become important later. For this reason, we encourage you to spend some
time reviewing the content of the course after your time in the classroom.
As a Reference
The organization and layout of this book make it an easy-to-use resource for future reference.
Taking advantage of the glossary, index, and table of contents, you can use this book as a first
source of definitions, background information, and summaries.
Course Icons
Watch throughout the material for the following visual cues.
Icon Description
A Caution note makes you aware of places where you need to be particularly careful
with your actions, settings, or decisions so that you can be sure to get the desired
results of an activity or task.
LearnTO notes show you where an associated LearnTO is particularly relevant to
the content. Access LearnTOs from your CHOICE Course screen.
Checklists provide job aids you can use after class as a reference to perform skills
back on the job. Access checklists from your CHOICE Course screen.
Social notes remind you to check your CHOICE Course screen for opportunities to
interact with the CHOICE community using social media.
Lesson Objectives
In this lesson, you will navigate the Project environment. You will:
• Identify project management concepts and project phases.
• Navigate the Microsoft Project Professional 2016 interface.
Lesson Introduction
As a project manager, you need to create and manage many documents (artifacts) to
communicate the project's purpose and status. A key component of this responsibility is the
project plan, which incorporates the tasks, resources, and scheduling of a project. Not only
should the project plan be used in the initial phases of a project, but also keeping a plan up-
to-date as the project progresses enables you to effectively manage the project and
communicate status to all involved parties.
Microsoft® Project Professional 2016 is a powerful tool for planning and managing projects.
This lesson will provide you with the big picture—some basic knowledge and skills you
need to start using Project 2016.
The lesson starts with a brief review of basic project management concepts. The remainder
of the lesson is presented as if Microsoft Project Professional 2016 had just been installed
on your computer and you are running it for the first time. It will cover the essentials you
need to navigate the program. In later lessons, you will add to this framework.
2 | Microsoft® Project 2016: Part 1
TOPIC A
Identify Project Management Concepts
As a project manager, you have to manage and control your project to make it a success. Whether
you are a beginning project manager, or a seasoned professional, you need to understand project
management concepts and apply them as they relate to the application. Regardless of your project
management experience and training, this topic reviews some basic project management concepts in
the common terminology so that you can better understand Microsoft Project Professional 2016.
Projects
Project A project is a temporary initiative to create a unique result. Every project has a definite starting point
Ask learners: "Can you and ending point in time. When the desired result has been achieved, the project is over. Here are
briefly describe a project some project examples:
in which you
• A company engages in a 10-month project to develop a new tablet computer.
participated?"
• A county government implements a three-year project to construct four dog parks.
• A nonprofit organization engages in a six-week project to increase membership by 10 percent.
Initiating The project's goal is defined and the project is authorized. The output of this
process is often a project charter.
Planning The project's scope, time, cost, and other details are determined. The output
of this process is a project plan.
Executing Tasks are performed and resources are utilized to accomplish the project plan.
Monitoring and The project's progress is tracked and corrective action is taken when necessary
Controlling to keep the project on track.
Closing The project's products, services, or end results are accepted by those who
authorized the project, and the project is brought to an orderly conclusion.
The project management process groups relate to one another as shown in the following figure.
As you may have noticed, the Planning and Executing process groups are a continuous cycle. As the
project plan is executed, more planning is often required. Also, you may have noticed that the
Monitoring and Controlling process group interfaces with and affects the other four groups.
Note: Microsoft Project Professional 2016 is designed to help you with the Planning, Executing,
and Monitoring and Controlling process groups of project management.
Project Constraints
Project constraints are anything that constrains or dictates the actions of the project team. Scope, Time, Project Constraints
and Cost are the most important constraints. In fact, they are referred to as the triple constraints. Ask participants: "What
These knowledge areas are dynamically linked; any change in one will impact the others. Project happens to cost and
2016 is intended to help project managers deal with various project constraints. time when you increase
project scope? What
happens to project
scope when you
decrease the cost and
time available to perform
the project?"
Figure 1-2: The triple constraints of a project are dynamically linked; you cannot change one
without changing another.
Scope Creep
Project managers must be constantly on guard against scope creep, which is the uncontrolled
expansion of a project's scope. A multitude of seemingly minor scope changes can add up to major
time delays and cost overruns.
Project Management
Ask learners: "How Project management is the administration and supervision of projects using a well-defined set of
much project knowledge, skills, tools, and techniques. Project management is both a science and an art that—
management training when done properly—ensures projects are completed on time, within budget, and according to
and experience do you specifications.
have?"
Some project managers undergo a rigorous process to become certified by the Project Management
Institute (PMI®) as a Project Management Professional (PMP®). Other project managers find
themselves performing this job function with little or no formal training. Whether you are a project
management novice or master, Microsoft Project Professional 2016 is a powerful tool that will help
you plan and complete your projects successfully.
Note: The authoritative source for project management information and best practices is A
Guide to the Project Management Body of Knowledge (PMBOK® Guide), which is maintained by PMI. It
is an invaluable reference for anyone who manages projects. Visit www.pmi.org for more
information.
Project Roles
Project Roles Projects often require a group of people with different roles and responsibilities to communicate
Ask participants: "Who is with each other and work together. The cohesiveness of this group can affect the project’s
the sponsor for your successful completion.
projects? Who are the
stakeholders? Who are Role Description
your team members?"
Inform the students that project manager The primary person directing the project’s flow and the communication
more information about between project participants. The project manager leads the planning of
resources will be the project, watches for cost overruns, and manages disputes.
covered later in the
course.
project sponsor The person in your organization who authorizes, supports, and approves
the project. Usually, the project sponsor is a member of senior
management.
project stakeholder Anyone who is actively involved in the project or has an interest in its
outcome. Stakeholders can be inside your organization or outside of it.
For example, if the project is to drill a hydraulic fracturing well, internal
stakeholders might include geologists, construction workers, and drill
operators. External stakeholders might include landowners,
environmental groups, and government regulators.
team member A person who is responsible for performing or approving the work to
complete the project. This includes the people who work on the tasks,
referred to as human resources, such as engineers or operators, and may
also include resource managers, such as a foreman or director.
ACTIVITY 1-1
Identifying Project Management Concepts
Scenario
Use these questions to check your knowledge of project management concepts.
4. True or False? Project management is the application of knowledge, skills, tools, and techniques to
accomplish activities or tasks to meet the objectives set for a project.
☐ True
☐ False
5. Which project management process group involves the completion of tasks and the coordination of
people and other resources to carry out the plan?
○ Initiating
○ Executing
○ Planning
○ Closing
6. Who is the project sponsor?
A: The project sponsor is the person who has the authority to approve or terminate the project.
TOPIC B
Navigate the Microsoft Project 2016
Environment
Now that you have reviewed some basic information about project management, you can start to
work with Microsoft Project Professional 2016. If you are new to Microsoft Project, a good first
step is to launch the application and explore the interface and its functions before you begin using it
to develop live project plans. In this topic, you will navigate the Microsoft Project Professional 2016
interface to become familiar with the program's basic features.
It is essential to identify the various elements of any new application you are using for the first time.
By identifying the different components in the Microsoft Project 2016 interface, you can be at ease
with its features and functions and then work more efficiently on your project plan files.
Figure 1-3: The Start screen provides a launching point for opening or creating projects.
Command Description
Command Description
Open Other Projects Open other Project files that are not on the Recent list.
Search for online Search online for Project templates that you can use to start a new Project
templates file.
Suggested searches Use suggested keywords to browse Project templates.
Create from Choose to create a new blank project file, a new project from an existing
file, or a new project from a template.
Sign in Log in to your Microsoft account.
Note: You may already have a personal or organizational Microsoft account. Examples of
personal Microsoft accounts include Office 365, Skype®, OneDrive®, Xbox LIVE®, and
Outlook.com. If you don't have a Microsoft account, you can create one for free at http://
signup.live.com.
Views
Mention to the students Microsoft Project 2016 uses views to display information on the screen from the currently open
that they should take the project plan file. You can use a variety of views to focus on specific aspects of your project. These
Logical Operations might include Gantt Chart view, Network Diagram view, Calendar view, Resource Sheet view,
course Microsoft Project and Resource Usage view. Most views are separated into two panes—with the Sheet pane on the
2016: Part 2 to learn left and the Chart pane on the right.
more about customizing
views.
The Gantt Chart View
Gantt Chart View The Gantt Chart is the default view in Microsoft Project 2016. When you first open a blank project,
Project displays this view. Gantt charts are the most common method for displaying project
information.
In the right pane of the Gantt Chart view, you will see the duration of each task plotted as a bar
against the dates along the top of the pane.
Figure 1-4: The Gantt Chart view is where you will spend most of your time working with a
project plan.
Note: The Gantt chart is named after Henry Gantt, who designed this tool between 1910 and
1915. Although now regarded as a common charting technique, Gantt charts were considered
revolutionary when first introduced.
Figure 1-5: The View Bar enables you to quickly change between the most used views.
Figure 1-6: The Quick Access Toolbar is highly customizable and always available on the screen.
The Ribbon
The Ribbon The ribbon at the top of the window is where you will find most of the controls used in Microsoft
Project Professional 2016. The controls are grouped into six basic tabs:
• File
• Task
• Resource
• Report
• Project
• View
When you select a tab, the controls related to that tab are displayed on the ribbon. A different
default view button will be shown on the far left of the ribbon for each tab. For example, the Gantt
Chart view button is the default for the Task tab, and the Team Planner view button is the default
for the Resource tab.
Figure 1-7: The ribbon groups the most common commands into tabs by type.
The Backstage
The Backstage The File tab displays differently than the other tabs. When you select it, you will see the Backstage—
where you can access a number of file and program controls. The Backstage provides a central
location for commands used to take action on a project as a whole, such as creating a file, saving a
file, and preparing to print.
Figure 1-8: The Backstage enables you to work with project files and program settings.
Figure 1-9: The Contextual tab adapts to what you are doing in the view area.
Figure 1-10: The Status bar shows you current program status and enables you to quickly change
views and zoom levels.
Note: If you use Project with Microsoft Project Server or SharePoint, the status bar will also
show you status notifications from the server.
Figure 1-11: The Tell Me bar, new to Project 2016, is designed to help you find commands
quickly.
Access the Checklist tile on your CHOICE Course screen for reference information and
job aids on How to Navigate the Project 2016 Interface.
ACTIVITY 1-2
Navigating the Project 2016 Interface
Scenario
Building with Heart is a non-profit home construction organization whose purpose is to build family
homes for qualifying applicants using recycled materials and volunteer labor when possible.
You joined Building with Heart as a volunteer project manager. The organization received a
donation of new Microsoft software and you have just installed Microsoft Project Professional 2016
on your laptop. You begin to familiarize yourself with the program and identify the features you will
use most often.
Inform the students that
they need to close Note: Activities may vary slightly if the software vendor has issued digital updates. Your
Project if they have it instructor will notify you of any changes.
open to display the Start
screen.
Notify students of any
1. Open Microsoft Project Professional 2016.
changes to activities
based on digital software a) On the Windows 10 Start menu, select All apps, and find the Project 2016 tile.
updates issued by the
software vendor.
4. Zoom the time scale to the entire project using the Tell Me bar.
a) In the Tell Me bar, type zoom
b) In the results list, select Zoom Entire Project.
Verify that the time scale for the entire project fits the width of the Gantt chart's right pane.
6. Locate the commands on the View Bar that you will use the most.
a) On the right side of the Quick Access Toolbar, select Customize Quick Access Toolbar.
b) Select Print Preview.
Summary
In this lesson, you started using Microsoft Project Professional 2016. By reviewing the basics of
project management and navigating the Project interface, you laid the foundation for the knowledge
and skills that will enable you to use Project effectively.
Encourage students to
use the social What is your next big project—either at work or at home?
networking tools A: Answers will vary, but might include producing an ad campaign at work, painting a bedroom at home,
provided on the CHOICE or planning a theatre performance for a school.
Course screen to follow
up with their peers after How do you think Microsoft Project 2016 could help you with planning your project?
the course is completed
A: Answers will vary, but might include: searching for a template related to the project to save time,
for further discussion
and resources to support managing the project plan, helping the project stay on track.
continued learning.
Note: Check your CHOICE Course screen for opportunities to interact with your classmates,
peers, and the larger CHOICE online community about the topics covered in this course or
other topics you are interested in. From the Course screen you can also access available
resources for a more continuous learning experience.
Lesson Objectives
In this lesson, you will define a project. You will:
• Create a new project plan and identify options for creating a new plan.
• Define the project level options and project description.
• Modify and assign project calendars.
Lesson Introduction
Defining a new project encompasses all the steps that a project manager needs to take in
Microsoft® Project Professional 2016 to ensure that the new project plan has the necessary
information before the task planning process begins. Capturing the information about the
project that you discovered in the Initiating process is important so that anyone looking at
your plan understands what the project is about. This is helpful to even you, if you must put
it aside and come back later. Any project manager, whether new or very experienced, can
save time and effort down the road by taking advantage of pre-defined project plan
structures for common project types so that they don't have to start from scratch. Building a
well-defined project plan library over time is key to increasing your skills and efficiency on
future projects.
By creating a new project plan, and taking the time to enter the appropriate information
correctly and set up your calendars, you will lay the foundation for a sustainable project plan
that is easier to build, maintain, and share over the course of your project.
18 | Microsoft® Project 2016: Part 1
TOPIC A
Create a New Project Plan
Now that you're familiar with common project management concepts, and know your way around
the Microsoft Project 2016 interface, you're ready to start managing a project. In order to take full
advantage of the robust capabilities of Project, it stands to reason that you must first create a project
plan in the application. In this topic, you'll do just that.
Figure 2-1: You can choose from five methods for creating new projects.
The following table describes the different methods for creating new project plan files.
Method Description
Blank Project This method gives you a completely empty file into which you can add
all of your project information.
New from an existing This method enables you to reuse a Project file from a previous project.
project
New from Excel® This method imports project information created in Excel. When you
workbook choose this option, a wizard will open and guide you though the steps
of importing the project information from Excel to Project.
New from SharePoint® This method enables you to import project information from a
Tasks SharePoint task list. When you choose this option, you will be prompted
to enter a SharePoint URL and select a task list on the SharePoint site.
Method Description
From a Project template This method enables you to create a Project file that is customized for a
variety of different project types. When you choose this option, a
Project file containing sample information will be created. You can then
modify the information for your particular project.
Project Templates
A project template contains details for a sample project that you can edit to make your own or simply Project Templates
use to help frame your own project phases.
Microsoft Project Professional 2016 comes preloaded with twelve templates that are geared toward a
variety of different project types. Using a template can save you time because you do not have to
create the project structure from scratch. However, you will still need to modify the template with
the details of your particular project. If you do not see a template on the Start screen that is similar
to your project, you can search online for one that is.
Figure 2-2: Project templates help you create new project plans with much of the information and
formatting in place.
Access the Checklist tile on your CHOICE Course screen for reference information and
job aids on How to Create a New Project Plan.
ACTIVITY 2-1
Creating a New Project Plan
Scenario
Building with Heart, located in Greene City, is a non-profit home construction organization similar
to Habitat for Humanity. The Building with Heart program’s purpose is to build a two- or three-
bedroom home for each qualifying family. These homes have a mortgage with a very reasonable
interest rate, and because many materials and labor are donated, the mortgage is much less than if
everything had to be purchased outright.
As a volunteer project manager at Building with Heart, you have just started a new construction
project to build a new three-bedroom home for a qualifying family whose previous residence was
destroyed by a storm. You need to create a new project plan for the project. Instead of starting from
a blank project plan, you want to find a template that will help you create your construction project
plan more quickly.
Let the students know
that they will be saving
the file later in the lesson 1. Open Microsoft Project Professional 2016.
and to leave the file
open at the end of the a) On the taskbar, select the Project 2016 shortcut.
activity. Verify that Project 2016 opens to the Start screen.
TOPIC B
Define a Project
After creating a new project plan, it is important to capture the information about your project and
save it so that you and others can easily understand what the project is about. In this topic, you will
define your project plan by entering the information and setting options specific to your project, and
then you will save your new file.
Figure 2-3: The place to view and modify high-level information about your project is the Project
Information dialog box.
Note: Filling in the project name and keywords in the Project Properties dialog box will help
search indexing on your local machine and in other shared file scenarios such as when using
SharePoint. It will help you and others in your organization find the project plan using the
Search command in Windows or SharePoint.
Figure 2-5: Scheduling a project from the start date or finish date.
Projects can be scheduled either from a start date or a finish date (but not both at the same time).
The Schedule from drop-down list in the Project Information dialog box shows whether your
project is scheduled from the start date or the finish date. If the Schedule from drop-down list is
set to Project Start Date, the Start date drop-down list will be active and the Finish date drop-
down list will be inactive. On the other hand, if the Schedule from drop-down list is set to Project
Finish Date, the Finish date drop-down list will be active and the Start date drop-down list will
be inactive.
By default, Microsoft Project 2016 schedules all new projects from a start date. In this mode, all
tasks are automatically scheduled to begin as soon as possible, giving the maximum amount of
schedule flexibility.
Figure 2-6: You can change the date that Project uses as the Current date.
Figure 2-7: You can choose where to save a project plan on the Save As screen.
Place Description
Sync with This option saves and syncs your Project file on a SharePoint site. This is a good
SharePoint option to use if you created the project file from a SharePoint task list and your
project team is utilizing SharePoint.
OneDrive This option saves your Project file in the cloud. This is a good option to use if you
need to access your Project file from more than one computer. It also means you
can retrieve your Project file if your computer is damaged, lost, or stolen.
This PC This options saves your Project file to your computer or network.
Note: If you save your Project files to OneDrive, be aware that you must have Microsoft Project
2016 installed on any computer you plan to use to access the file. For example, if you plan to
access a Project file using your work computer and your home computer, both computers must
have Microsoft Project 2016.
ACTIVITY 2-2
Defining and Saving a Project
Scenario
Now that you have created a new project plan for your residential construction project, you need to
make some updates to it. You have received word from the funding advisor that your project will
begin in May of 2016 and that the qualifying family, the Woods, have been approved for the new
home. The clearing of the debris from their lot is also included in the project. You also learn that the
Woods have two daughters, 12 and 9, who are excited to each be getting their own new bedroom
and a shared bathroom. Greene City Interiors has agreed to donate the time of an interior designer
to help the Woods choose their finishing touches. Teresa Sanchez, a respected business leader in
Greene City, has also announced that she will be joining Building with Heart as a director, and you
will be reporting progress to her going forward.
You capture this information in your project plan and save it.
d) In the text fields, enter the appropriate information as depicted in the following image:
e) Select OK.
TOPIC C
Assign a Project Calendar
When you create a new project plan, Microsoft Project 2016 assumes that your project tasks will be
performed during a standard work week. In reality, however, your project tasks may be performed
during a longer or shorter work week. You may also have to take into account holidays and vacation
schedules. In this topic, you will modify the project calendars in Microsoft Project 2016 so that they
reflect the realities of your particular project.
Project Calendars
Microsoft Project 2016 uses calendars to determine when to schedule tasks and when resources will Ask the students how
be available to perform work. The project calendar is the calendar that determines the overall schedule they use calendars in
of a project. For example, if you have defined your organization's holidays in the project calendar, everyday situations such
the end date that Project calculates for your project will automatically adjust so that your project will marking vacations or
end on a workday. Although the project calendar applies to the project as a whole, you can also holidays.
assign calendars to individual resources or tasks.
Base Calendars
A base calendar defines the working days and working hours in a calendar that can be assigned to the Base Calendars
project. The Project Information dialog box shows the base calendar assigned to your project in
the Calendar field. Microsoft Project 2016 gives you three built-in base calendars from which to
choose:
The Standard base calendar is the default for all new files in Microsoft Project 2016. You can change Explain each base
the base calendar to one of the other options in the Calendar drop-down list. calendar. The Night Shift
calendar can be
confusing to learners.
The Create New Base Calendar Dialog Box Ask learners: "When
might you use each of
You can use the Create New Base Calendar dialog box to create a new base calendar for your project by these base calendars?"
copying an existing base calendar and then changing it to fit your needs. You can access the Create The Create New Base
Calendar Dialog Box
New Base Calendar dialog box by selecting the Change Working Time button from the Project
tab, and then selecting Create New Calendar.
Figure 2-8: Copy a base calendar using the Create New Base Calendar dialog box.
Note: Make sure to name your calendars descriptively so they are easy to choose later.
Figure 2-9: Make changes to working time in the Change Working Time dialog box.
The Change Working Time dialog box displays a miniature calendar of the project's base calendar.
The Legend to the left of the miniature calendar briefly explains the coding used on the miniature
calendar. The following table expands on the Legend.
Item Meaning
Item Meaning
Edited working hours The period of time when labor is being performed on this date
is different than a normal working day.
Exception day Working hours on this date are different than usual. For
example, an organization might only be open during the
morning on the day before a major holiday.
Nondefault work week Working hours during this entire week are different than usual.
For example, an organization might be completely shut down
for a week.
Exceptions
Exceptions In Microsoft Project 2016, an exception is a day or week when working time is different than what is
normal for the base calendar. All exceptions to the base calendar are displayed in a table at the
bottom of the Change Working Time dialog box.
Figure 2-10: An exception to the base calendar might occur for a holiday.
You can add an exception to the base calendar by selecting a date or dates on the miniature calendar
in the Change Working Time dialog box and entering a name for the exception in the Exceptions
You may want to show table. For example, if your organization is closed for the Thanksgiving holiday, you would select the
LearnTO Change the fourth Thursday of November in the miniature calendar and enter Thanksgiving in the highlighted
Work Week from the
cell of the Exceptions table.
CHOICE Course screen
or have students Note: Microsoft Office 2016 also enables you to change the normal work week for a base
navigate out to the
calendar using the Work Weeks tab in the Change Working Time dialog box. For example,
Course screen and
watch it themselves as a
you can change the work week from the default of Monday–Friday to Tuesday–Saturday. This is
supplement to your an advanced skill that is not covered in this course. For more information, type Change
instruction. If not, please working days for the project calendar in the Tell Me bar field.
remind students to visit
the LearnTOs for this Note: To further explore work-week customization, you can access the LearnTO Change the
course on their CHOICE
Work Week presentation from the LearnTO tile on the CHOICE Course screen.
Course screen after
class for supplemental
information and
additional resources.
Figure 2-11: Working times for an exception appear in the Details dialog box.
Access the Checklist tile on your CHOICE Course screen for reference information and
job aids on How to Work with Project Calendars.
ACTIVITY 2-3
Creating and Assigning a New Calendar
Scenario
Building with Heart observes several federal holidays where no project work will be scheduled. Also,
work is only scheduled for half a day on Election Day. You decide to add these holidays to a new
base calendar, and then assign that as the project calendar to make the schedule more accurate.
Summary
In this lesson, you created a new project from a template and set the project's start date. You
captured relevant information in the project's properties, and you created a base calendar to reflect
your organization's working schedule. By practicing the good habit of properly defining your project
plan, you ensure that the plan will be easily understandable and maintainable throughout the life of
the project. Over time, you will build a library of solid project plans that you and your organization
can draw upon to improve future projects.
Encourage students to
use the social Why might you create a new project from a template instead of a blank project plan?
networking tools A: Answers will vary, but might include to get a head start on filling in the phases and tasks, to compare
provided on the CHOICE your approach to other common approaches, or to get a quick idea of how long this type of project
Course screen to follow might take.
up with their peers after
the course is completed What exceptions to the base calendar will you add to your next project? Will they be recurring?
for further discussion
and resources to support A: Answers will vary, but might include: Holidays are the most common exceptions. If a project's duration
continued learning. is longer than a year, a recurring exception is helpful.
Note: Check your CHOICE Course screen for opportunities to interact with your classmates,
peers, and the larger CHOICE online community about the topics covered in this course or
other topics you are interested in. From the Course screen you can also access available
resources for a more continuous learning experience.
Lesson Objectives
In this lesson, you will create and organize tasks. You will:
• Add tasks to the project plan.
• Import tasks from other programs such as Excel and SharePoint.
• Create and modify a work breakdown structure and milestones.
• Define relationships between tasks and describe task dependencies.
• Schedule tasks and manage constraints and deadlines.
Lesson Introduction
Now that you've created and defined your project plan, you need to modify the project plan
so that it reflects the work that needs to be done for a particular project. You understand
that Microsoft® Project Professional 2016 is a very powerful tool for defining and
scheduling the details of a project plan, but you may not know just how to do this.
You may already use a task list to keep track of things that need to be done in your personal
or professional life. You may use a notepad, or other software tools such as Microsoft
Outlook or Excel, to keep track of your tasks. However, when it comes to a robust project
plan that can be scheduled to the degree of precision that fits your needs, Project can help
you turn a basic task list into a real schedule. In this lesson, you will do just that.
38 | Microsoft® Project 2016: Part 1
TOPIC A
Add Tasks to a Project Plan
Once you have a Microsoft Project Professional 2016 file, you must update it with detailed
information about your project. In this topic, you will enter the tasks that must be performed to
complete the project, estimate how much time is needed to perform each task, and link the tasks
together into a chain.
Project Tasks
Project Tasks A task is a specific chunk of project work. In other words, tasks are the building blocks of effort that
Ask learners: "If your need to be done to execute the project. In Microsoft Project Professional 2016, you can use tasks to
project is to sell your break a project into manageable pieces of work. You can schedule the duration and sequence of
house, what are some of tasks in Project, and assign resources (people or materials) who will perform the tasks.
the tasks that need to be
done?"
Figure 3-1: Project tasks are the building blocks of a project plan.
Figure 3-2: You will build the basic structure of your project plan in the Task Entry table.
In the left pane of the Gantt Chart view, you will see the Task Entry table, which contains the
following project information in columns from left to right.
Column Description
Row Number The row in the Gantt chart. This number corresponds to the Task ID of
the task in that row.
Indicators Little icons that show the status of the tasks, help, and error information.
For example, if a task contains a note, this column will show a note
indicator.
Task Mode Shows whether the task is manually or auto scheduled.
Task Name A brief description of the work. Short, action-oriented task names are
best (for example, "Design logo").
Duration How long the task will take. By default, Microsoft Project 2016 uses days
as the unit of time for durations. However, if you wish, you can specify
minutes, hours, weeks, or months as the unit of time.
Start The date when the task is planned to begin.
Finish The date when the task is planned to be completed.
Predecessors The Task ID(s) of tasks on which this task is dependent to complete.
Figure 3-3: Update task data in the Task Information dialog box.
Task Durations
Task Durations The Duration field shows the amount of time it will take to complete the task. Usually, you will know
how long it will take to perform a task. However, if you're not sure how long a task will take, you
can mark the duration as Estimated. If you mark a duration as Estimated, it will be shown with a
question mark. Conversely, if you type a question mark after a duration, it will be marked as
Estimated.
Figure 3-4: You can enter an estimated Duration if you're not sure how long a task will take.
Note: If you are using New Tasks Auto Scheduled mode, all new tasks will automatically be
given an estimated duration of 1 day.
which drive its schedule, while its successors are the tasks which are dependent upon it. Every change
you make to a linked task will affect its successors, and its successors' successors, and so on.
By default, whenever you link two tasks in Microsoft Project Professional 2016, a simple Finish-to-
Start (FS) dependency is established between them. This means that the first task must be completed
before the second task can begin. The links between tasks are indicated with arrows. If your project
is simple, you might link all of the tasks together into a single chain (better known to project
managers as a path). However, in more complex projects, tasks are often linked together to form
multiple paths that may diverge, converge, or run in parallel with one another.
Note: Other types of dependencies between tasks—Start-to-Finish (SF), Start-to-Start (SS), and
Finish-to-Finish (FF)—will be discussed later in this course.
Task Selection
You can select multiple tasks and link them as dependencies using the Link Selected Tasks
command. You can select the first task in a sequence and then use the Shift key to select a sequence
of tasks, or you can use the Ctrl key to select non-contiguous tasks.
Access the Checklist tile on your CHOICE Course screen for reference information and
job aids on How to Add Tasks to a Project Plan.
ACTIVITY 3-1
Adding Tasks to a Project Plan
Data File
C:\091062Data\Creating and Organizing Tasks\Woods_3BR_Home_Project_Tasks.mpp
Scenario
Now that you have a project plan for the Woods family home, you need to add some tasks to it.
You know that the clearing of the debris from the lot needs to be completed. You add the tasks that
you think will be needed to tear down and clear the old house. You also want to make sure that any
reusable materials are either saved for the new home or sent to Building with Heart's recycling
center. You need to have some volunteers there to sort the debris and hire multiple trucks to haul
the appropriate containers to their different destinations. Since you aren't yet sure how to
incorporate these tasks into the overall project plan, you add them at the end of the sheet and will
move them later once you learn when those tasks need to be completed.
3. Add the following tasks below Demolition of Old House. If necessary, change the durations to one day.
• Place Containers
• Sort Debris
• Haul Recycling
• Haul Waste
TOPIC B
Import Tasks From Other Programs
You have already manually added tasks to a project plan. However, there may be times when a list of
tasks has already been created in another program. This is especially true when you are collaborating
with others who aren't using Microsoft Project. In this topic, you will import tasks from other
programs into your project plan.
Figure 3-6: Project won't open non-project files unless you enable it to in the Legacy Formats
dialog box.
Figure 3-7: The Import Wizard lets you map the columns of your data file to project plan
columns.
Access the Checklist tile on your CHOICE Course screen for reference information and
job aids on How to Import Tasks to a Project Plan.
ACTIVITY 3-2
Importing Tasks to a Project Plan
Data Files
C:\091062Data\Creating and Organizing Tasks\Landscape_Task_List.xlsx
C:\091062Data\Creating and Organizing Tasks\Home_move_plan.xlsx
Scenario
Gary Clark is a volunteer at Building with Heart who specializes in environmentally friendly
landscaping. He sent you an Excel file that contains some of the tasks that he wants to make sure
are included in the project plan for the Woods home. You decide to add his tasks to your plan.
Meanwhile, your new director, Teresa Sanchez, has a file that she thinks was exported from a project
management program, maybe even an older version of Project. She says that the file contains the
basic tasks that a family needs to follow when moving into a new home. She would like you to try to
open it in Microsoft Project and see if it might be something interesting to offer to the Woods and
other families as a handout to help them get ready while their home is being built.
a) On the Taskbar, select the Project shortcut to switch back to Microsoft Project.
b) In the Task Entry table, scroll down to the empty area.
c) Place the cursor in the Name column of the first empty row.
d) From the Task ribbon, select Paste.
Verify that the new tasks appear in the Task Entry table.
4. Save your changes to My_Woods_3BR_Home_Project_Tasks.mpp and then close the file and Excel.
a) Select File→Save.
b) Select File→Close to close My_Woods_3BR_Home_Project_Tasks.mpp.
c) On the Windows Taskbar, select Excel to switch back to Excel.
d) On the top-right corner of the Excel window, select Close to close the program. If prompted to save
changes, select No.
k) In the Import Wizard - Map Options dialog box, make sure that the selected check boxes are as
follows, and then select Next.
l) In the Import Wizard - Task Mapping dialog box, in the Source worksheet name list, select
Task_Table and then select Finish.
m) If necessary, select OK to dismiss the Microsoft Project warning dialog box about the start date.
n) Verify that the new project plan is created.
6. Save the new project plan as My_Family_Home_Move_Plan.mpp and then close the file.
a) Select File→Save As.
b) On the Save As backstage, select Browse and browse to the Creating and Organizing Tasks folder.
c) In the Save As dialog box, in the File Name field, enter My_Family_Home_Move_Plan
d) Select Save.
e) Select File→Close.
TOPIC C
Create a Work Breakdown Structure
Now that you've added tasks to a project plan, you need a way to group and organize those tasks. In
this topic, you will create and modify a work breakdown structure and milestones.
Figure 3-8: You should organize tasks in a hierarchical work breakdown structure.
Figure 3-9: You can collapse and expand summary tasks and subtasks in the Gantt Chart view.
You can create new summary tasks in Gantt Chart view using the Insert Summary Task button in
the Insert command group on the Task tab of the ribbon. You can convert a regular task into a
summary task using the Outdent Task button in the Schedule command group on the Task tab.
Conversely, you can convert a regular task into a subtask using the Indent Task button in the
Schedule command group on the Task tab.
Grouping tasks under a summary task does not automatically create dependencies among the
subtasks. You must link subtasks manually (if they aren't already linked).
You can change the duration of summary tasks, but doing so will not always change the duration of
the subtasks. It's better to change the duration of the subtasks, which will change the duration of the
summary task.
Figure 3-10: The project summary task is the highest level task in the work breakdown structure.
Outline Numbers
When you are working with complex projects that have a number of summary tasks and subtasks, Outline Numbers
you may find it helpful to see the outline numbers that Project 2016 automatically assigns to each
task. Project uses a decimal outline numbering scheme to show the sequencing and level of tasks.
Project hides the outline number by default. In Gantt Chart view, you can unhide the outline
numbers by selecting the Format contextual tab in the ribbon, finding the Show/Hide group, and
checking the Outline Number check box. The outline numbers will appear before each task in the
Gantt Chart.
Figure 3-11: Outline numbers help you refer to tasks and levels using a numbering system.
Milestone Tasks
A milestone is a significant point in the life of your project—such as a deliverable or the end of a Milestones
phase. In traditional project management practice, milestones are not tasks, do not take time, and do
not require resources. However, in Microsoft Project Professional 2016, milestones are tasks that
usually have zero duration but may have duration if needed.
In Gantt Chart view, milestones are indicated with a diamond. You can create a new milestone
using the Insert Milestone button in the Insert command group on the Task tab of the ribbon.
New milestones have zero duration. If you enter a new task in the Task Entry table and set the
Duration column to 0, Project will automatically convert it to a milestone. You can convert a
regular task into a milestone by checking the Mark task as milestone check box on the Advanced
tab of the Task Information dialog box. Regular tasks converted to milestones retain their
durations and their resources.
Task Notes
Task Notes You can use the Notes tab of the Task Information dialog box to add other facts about a task.
Figure 3-13: You can enter text into the Notes tab of the Task Information dialog box.
Method Description
Type You can type text directly into the Notes field. You can then format the text using
the buttons shown above the field or common keyboard shortcuts (such as Ctrl
+B for bold, Ctrl+I for italics, and Ctrl+U for underline).
Copy and You can copy text or graphics from a source document (such as Microsoft® Word,
paste Excel®, or PowerPoint®) and paste them into the Notes field. Formatting from
the source document is generally retained by the Notes field.
Method Description
Insert object You can import a file into the Notes field by selecting the Insert Object button.
Almost any Microsoft® Windows® file can be inserted. You have several options
for insertion: You can choose to insert a new file or an existing file. If you are
inserting an existing file, you can choose to insert a copy of the original file or link
to the original file. Finally, you can choose to display the file's contents or an icon
of the file.
Access the Checklist tile on your CHOICE Course screen for reference information and
job aids on How to Create a Work Breakdown Structure.
ACTIVITY 3-3
Creating a Work Breakdown Structure
Scenario
You added some tasks for clearing the debris of the old home and you imported some tasks for
landscaping to the Woods project plan that were provided by the landscaper, Gary Clark. You need
to incorporate these tasks into the overall project plan and organize them into the work breakdown
structure.
3. Replace the Sod and complete plantings tasks with the new landscape tasks.
a) Scroll down and select the following tasks:
• Order Plants and Trees
• Build Compost Bin
• Build Flower Beds and Edges
TOPIC D
Define Task Relationships
Now that you've organized your tasks into a hierarchy, you can define more complex task
relationships. Tasks aren't always just a list of things that need to be done in order. Sometimes, they
must be done at the same time or need to have time left between them. In this topic, you will define
relationships between tasks and describe task dependencies.
Task Predecessors
Task Predecessors The Predecessors tab of the Task Information dialog box shows the task's predecessors. A
predecessor is a task that must be started or finished before another task can begin.
Figure 3-14: You can view a task's predecessors in the Predecessors tab of the Task Information
dialog box.
Dependencies
Dependency Types The Predecessors tab shows you all of a task's predecessors and their dependencies. A dependency is
the relationship between a task and its predecessor. The table describes the four types of
dependencies.
Finish-to-Start (FS) The predecessor must end You must finish applying
before the task can begin. primer (Task A) before you
This is the default in can start applying paint
Microsoft Project and the (Task B).
most commonly used
dependency.
Start-to-Start (SS) The predecessor must begin You must begin duplicating
before the task can begin. a report (Task A) before you
can begin binding the report
(Task B).
Finish-to-Finish (FF) The predecessor must end You cannot finish detouring
before the task can end. traffic (Task A) until you
finish road work (Task B).
Start-to-Finish (SF) The predecessor must begin The start of a concert (Task
before the task can end. A) ends ticket sales (Task
This is the most difficult B).
type of dependency to
understand. However, it will
make more sense if you
remember that the
predecessor task is later in
time than the successor task.
Lag Time
Normally in a Finish-to-Start (FS) relationship, there is no delay or overlap between the end of Task Normal Finish-to-Start
A and the beginning of Task B. Relationship
Figure 3-15: In a normal Finish-to-Start relationship, the second task starts as soon as the first
ends.
Lag Lag is a delay in time between two tasks that are linked together. For example, in the following
figure, even though Task A and Task B have an FS relationship, Task B is scheduled to begin some
time after Task A is completed rather than immediately. You can add lag to a link by opening the
Task Information dialog box of the successor task, selecting the Predecessors tab, and typing a
positive value into the Lag column.
Ask students for Here's a simple example to help you understand lag. Pretend you are making a birthday cake. You
additional examples of must bake the cake before you can put frosting on the cake. So, there is an FS relationship between
lag. baking the cake and frosting the cake. However, after you bake the cake, you must wait until the
cake has cooled down before you can apply the frosting. The delay period is the lag time.
Lead Time
Lead Lead is an overlap in time between two tasks that are linked together. For example, in the following
figure, even though Task A and Task B have an FS relationship, Task B is scheduled to begin when
Task A is only about 50 percent complete rather than 100 percent complete. You can add lead to a
link by opening the Task Information dialog box of the successor task, selecting the Predecessors
tab, and typing a negative value into the Lag column. (In other words, negative lag is lead.)
Ask students for
additional examples of
lead.
Figure 3-17: Lead time is the overlap in time between dependent tasks.
Here's a simple example to help you understand lead. Let's return to the birthday cake scenario. You
must mix the cake's ingredients before you bake the cake in the oven. So, there is an FS relationship
between mixing the cake and baking the cake. However, you want the oven to preheat while you are
mixing the cake so that the oven will be at the proper temperature for baking when you have
finished mixing the cake. The preheating period is the lead time.
Access the Checklist tile on your CHOICE Course screen for reference information and
job aids on How to Define Task Relationships.
ACTIVITY 3-4
Defining Task Relationships
Data File
My_Woods_3BR_Home_Project_Tasks.mpp
Scenario
You have organized your tasks in the project plan and now you want to better define the
dependencies between some of the tasks. For example, you know that the Sort Debris task cannot
finish until the demolition of the old house finishes and it will probably take at least another day for
the volunteers to sort through it. You also know that the Place Containers task can start as soon as
the Demolition of Old House task starts, and that the hauling tasks are not necessarily dependent
on each other. You have been notified that the demolition crew needs two weeks notice once the
contracts are signed before they begin. You make the appropriate changes to the tasks.
TOPIC E
Schedule Tasks
Now that you've defined the relationship between tasks, you can use Microsoft Project to schedule
the work. Understanding how Project schedules tasks will help you get the most from your project
plans. If you identify the real drivers of tasks in your project, for example that an event has to take
place on a certain day, you can use the powerful features of Project to make sure that all the
interdependent tasks are scheduled most efficiently. In this topic, you will schedule tasks and
manage constraints and deadlines.
Figure 3-18: You can easily switch between manually scheduled and auto scheduled tasks.
Task Constraints
A task constraint is a date-based limitation imposed on a task. You can set task constraints to control Task Constraints
the start and finish dates of a task. Tasks can have one of eight schedule constraint types:
• As Soon As Possible (the default when projects are scheduled from a start date)
• As Late As Possible (the default when projects are scheduled from a finish date)
• Finish No Earlier Than
• Finish No Later Than
• Must Finish On
• Must Start On
• Start No Earlier Than
• Start No Later Than
Figure 3-19: Constraint types are set in the Task Information dialog box.
Generally, you should keep the default constraint so that project scheduling remains as flexible as
possible. However, you may want to change the constraint if you have a task with a specific date
that is critical for project success.
Deadlines
Deadlines You may be familiar with the concept of deadlines in a variety of contexts, but in Microsoft Project
Ask the students if 2016, you can set a deadline on a task for the purpose of tracking how close the task finish is to the
they've missed a deadline date. Setting a deadline on a task does not affect the automatic scheduling of a task. It
deadline and what simply gives you a visual indicator that you can use to monitor progress.
happened.
Figure 3-20: A green arrow marks the deadline date in the Gantt chart.
Access the Checklist tile on your CHOICE Course screen for reference information and
job aids on How to Schedule Tasks.
ACTIVITY 3-5
Scheduling Tasks
Data File
My_Woods_3BR_Home_Project_Tasks.mpp
Scenario
You have continued to create the appropriate relationships in your work breakdown structure and
now you have some new information that you need to reflect in the project schedule. You have
been informed that the recycling center is scheduled to move to a larger facility and that they will
not be accepting any recycling during June 2016. The earliest they will be accepting recycling is July
5th, 2016. Also, your director is adamant that the project is completed before the end of the
calendar year so that the budget does not have to carry over. You make these schedule adjustments
to the project plan.
Summary
In this lesson, you added and organized tasks and created relationships in your project plan. Creating
a robust, well-thought-out work breakdown structure is an important part of project management.
By identifying the tasks that have special relationship and dependency requirements, you will be
ready to manage your resources and handle any scheduling issues that come up during project
execution. Taking advantage of these features while leaving your project plan flexible enough to
adapt to change will save you effort down the road.
Encourage students to
use the social Besides the Finish-to-Start dependency, which of the other dependency types (Start-to-Start, Finish-to-
networking tools Finish, Start-to-Finish) might you use and why?
provided on the CHOICE A: Answers will vary. Examples might include using Start-to-Start when you can start boxing finished
Course screen to follow manuals once the final binding starts, Finish-to-Finish when you can't finish putting away items until
up with their peers after
all the deliveries are finished, Start-to-Finish when the beginning of an event determines when you
the course is completed
finish promoting it.
for further discussion
and resources to support Which of the task scheduling features do you think will have the greatest impact on your future project
continued learning.
plans?
A: Answers will vary, but students are likely to find that setting constraints and using lag and lead time
are valuable for working with tasks that are unmoveable (such as a conference date) or dealing with
organizational policies (for example, a turn-around time for a permission request).
Note: Check your CHOICE Course screen for opportunities to interact with your classmates,
peers, and the larger CHOICE online community about the topics covered in this course or
other topics you are interested in. From the Course screen you can also access available
resources for a more continuous learning experience.
Lesson Objectives
In this lesson, you will manage project plan resources. You will:
• Add resources to a project and assign them to tasks.
• Create a calendar for a resource.
• Enter costs for different types of resources.
• Assign resources to tasks.
• Resolve resource conflicts in a project plan.
Lesson Introduction
Now that you have created a work breakdown structure, you must define who and what is
needed to complete the project tasks. As a project manager, one of the main areas you need
to focus on during the planning phase of a project is resources. You have to determine the
people, tools, equipment, and materials that will be required for the project. Defining
resource requirements early will solidify your project plan and help you adjust as resource
availability changes over the life of the project.
66 | Microsoft® Project 2016: Part 1
TOPIC A
Add Resources to a Project Plan
Once you have entered project tasks into a blank Microsoft® Project Professional 2016 file, project
resources are the next critical set of data. In this topic, you will add resources to a project and assign
those resources to your project tasks.
Resources
Resources Resources are people, equipment, materials, or other costs that are used to accomplish a project task.
Ask learners: "What In other words, resources are the staff, supplies, equipment, and other expenses that you need to
resources have you execute a project. In Microsoft Project Professional 2016, you can define your resources and assign
used on your projects?" them to tasks.
Work Resources
Work Resources A work resource is a resource that is employed on a time basis. The most common work resources are
Ask the students to the people who will perform the tasks, also known as human resources. You can refer to work
name some work resources by name (Gary Clark), or by generic labels (Landscaper) depending on your needs. In
resources. addition to human resources, work resources also include resources that you need to schedule or
track cost on a time basis. For example, a printing press can only run one job at a time, so you may
need to schedule based on its availability. Or, you may need to rent equipment, such as a moving
truck, to perform a task and you need to schedule most efficiently to minimize cost. Space can also
be treated as a work resource if you need to schedule around its availability or track its cost by time.
Examples include conference rooms, storage, convention centers, and so on.
You can also specify the maximum number of units that the resource can work on the project. For
example, a person may only be able to devote 50% of his or her time to the project, or, if you have
three identical pieces of equipment, you can create one resource for all three and set the Max Units
field to 300%.
Cost Resources
A cost resource is a resource used to capture expenses or track a budget. A budget resource is a special Cost Resources
type of cost resource used to keep track of costs versus budget through the project lifecycle.
Standard cost resources are assigned to tasks to keep track of expenses associated with the task such
as a travel expense, purchase of a license, and so on. Budget resources can only be assigned to the
project summary task and are used to track the budget at the project level.
Material Resources
A material resource is a resource that is measured by how many units are used. For example, you may Material Resources
need to use carpet to complete a flooring task. If you purchase carpet by the square foot, you can Check students
create a material resource for the carpet and set its unit of measure to square foot. You can also understanding by giving
enter the cost per unit and have Project calculate estimated costs per task. some example of
resources and asking
them to identify the type.
The Resource Sheet
When you select the Resource Sheet button on the View bar, the Resource Sheet will be The Resource Sheet
displayed. (You may need to scroll down the View bar to see the Resource Sheet button.) The
Resource Sheet view shows you all the resources that you have defined for the project. You will see
information about the resource in columns.
Figure 4-2: You can view and enter resources on the Resource Sheet.
The table describes the first seven columns, from left to right. The other columns will be discussed
later in this course.
Column Description
Row Number This is simply the row in the resource sheet. This number is not actually
part of a resource's information.
Indicators These are pictures that show the status of the resources. For example, if a
resource contains a note, a note indicator will be shown in this column.
Resource Name This is a brief description of the resource. If the resource is a person, you
can use the person's name.
Type This indicates the kind of resource. In Microsoft Project Professional
2016, the types of resources are Work, Material, and Cost.
Material Label This is the unit of measure (pounds, gallons, boxes, and so forth) for
material resources.
Initials This is an abbreviation for the Resource Name. For example, Gloria
Rodriquez could be abbreviated as GR.
Group This is usually the department or team to which the resource belongs. For
example, Gloria Rodriquez might be part of the Advertising group.
Note: You can paste resource information into the Resource Sheet just as you can tasks into
the Task Entry table. You can also import resources from other programs.
ACTIVITY 4-1
Adding Resources
Data File
C:\91062Data\Managing Project Plan Resources
\Woods_3BR_Home_Project_Resources.mpp
Scenario
You've created a solid work breakdown structure and now it is time to enter the resources that you
want to track for your project. The construction company will be handing all of the standard
materials once construction starts, but you will be responsible for tracking the volunteer resources,
equipment, and materials provided through Building with Heart. You will have four volunteers that
can do any kind of work, but you won't know their names until closer to the project start date. You
have one volunteer, Gary Clark, who is the landscape expert. You will need to rent at least two
containers for the waste and recycling. You will be allowed to use the organization's dump truck for
free, but there is a waste dumping fee charged per ton. You also need to create an overall budget for
your project and a cost resource for construction estimates. You enter these resources into your
project plan.
1. Open the Woods_3BR_Home_Project_Resources.mpp project plan file. Inform the students that
a) Select File→Open. they are only creating
b) In the Open backstage, select Browse. resources and will add
more information to
c) In the Open dialog box, navigate to the C:\91062Data\Managing Project Plan Resources folder
them later in the lesson.
containing your class files.
d) Select Woods_3BR_Home_Project_Resources.mpp and select Open.
3. Change the Resource Name of the Landscape contractor resource to Gary Clark
a) Locate the resource in row 22, Landscape contractor.
b) In the Resource Name field, enter Gary Clark
a) In the first empty row of the Resource Sheet, in the Resource Name column, enter Construction
Fixed Cost
b) In the Type column, select Cost.
TOPIC B
Create a Resource Calendar
Now that you've entered resources into your project plan, you may also need to create custom
calendars for the resources to account for availability of individual people or other work resources.
In this topic, you'll do just that.
Resource Calendars
If you have created and applied a base calendar for your project before you start building your Resource Calendars
resource list, that calendar will automatically appear in the Base Calendar column for each work Ask the students if they
resource. However, if the working and nonworking times of your project calendar do not coincide are planning on going on
with the availability of a resource, you can create a resource calendar. A resource calendar is specific to vacation and point out
a particular resource. For example, a resource calendar might reflect a resource’s personal vacation that resources can have
schedule. specific calendar needs.
If you are using Microsoft Project Professional in an environment with Microsoft SharePoint or
Project Server and integrated with your email server, the human resources in your project can
update their own calendars. If configured by your administrator, this will enable Project to alert you
to any potential conflicts.
Resource Availability
There are times when a resource may not be available until a certain date or not available after a Resource Availability
certain date. For example, you may need to hire a contractor who doesn't start until a certain date. Discuss with the
Or, you may depend on a person who is moving to another department at the end of the month or students when they
a piece of equipment that must be returned by a certain date. In these cases, you can use the Resource might use a resource
Availability table in the Resource Information dialog box to set a start and/or end date for the calendar versus
resource. You can also use the availability table to set a time period when a resource has more or availability settings.
less availability to work on the project. For example, if a person can only spend half of his or her
time working on the project before a certain date, you can set his or her Units to 50% during that
time period.
Figure 4-4: The Resource Availability table specifies a start or end date for a resource.
Access the Checklist tile on your CHOICE Course screen for reference information and
job aids on How to Create a Resource Calendar.
ACTIVITY 4-2
Creating a Resource Calendar
Scenario
You have just received an email from Gary Clark notifying you of his availability for the project. He
is going to be assisting with the move of the Recycling Center and taking a vacation the week of July
4th, 2016, so he will not be able to start on the project until July 11, 2016. Also, he volunteers to
teach urban gardening on Fridays, so he will only be available Mondays through Thursdays. You
create a resource calendar for Gary.
TOPIC C
Enter Costs for Resources
Now that you've set up your resources and adjusted their availability, you can define how the
resources accumulate cost. This will give you further flexibility in tracking your costs as the project
progresses.
Resource Costs
The Cost rate table on the Cost tab enables you to see, add, and change the costs associated with a Resource Costs
resource. You can set a resource's normal Standard Rate, Overtime Rate, and Per Use Cost.
Figure 4-5: Enter resource costs on the Costs tab of the Resource Information dialog box.
You can specify different rates beginning on specified dates. There are two methods for doing this.
The first method is to enter the changed rate as a number (such as 110). The second method is to
enter the changed rate as a percentage of the old rate (such as 10%). When using the second
method, you must add the percent sign or Project 2016 will interpret it as a number. Entering a
positive percentage increases the rate, and a negative percentage decreases the rate.
lettered. Each table can contain rates that change at specified time periods. For example, you can use
Cost Table A to specify the default rates of a resource and any change in that resource's default
rate, such as a raise, or a discount during the off-season. You can use multiple cost tables if a
resource has different rate schedules that may come into play during a project. For example, a
contractor may charge more for tasks that are dangerous. You can create a cost table that can be
specified at the time you assign the resource to the task to reflect the different rate.
You can also use cost tables with material resources. For example, you may have discounted rates
for buying larger quantities or different rates depending on the choice of material quality. You can
use the cost rate tables to see how the variable rates affect the project cost when you change them.
Figure 4-6: Use Cost Rate Tables to record changing rates over the life of a project.
Access the Checklist tile on your CHOICE Course screen for reference information and
job aids on How to Enter Resource Costs.
ACTIVITY 4-3
Entering Resource Costs
Scenario
You have some information back on your estimate requests for the Woods family home. The
container rental fee is about $20 per day and two are available. The waste dumping fee is about $150
per ton. Also, the maid service is informing you that they are raising their rates from $40 per hour to
$50 per hour on 12/15/2016. You capture these resource costs in your project plan.
TOPIC D
Assign Resources to Tasks
After you plan tasks and add resources, you need to make a connection between the tasks and the
resources that will be used to complete the tasks. In this topic, you will assign resources to tasks.
In the Team Planner view, all the work resources are shown in the left pane. The tasks to which
they are assigned are displayed in the right pane, plotted along the project timeline. Unassigned tasks
appear in the bottom pane of the Team Planner. You can assign a task to a single resource by
dragging it from the bottom pane to a date in the desired resource's row. Similarly, you can reassign
a task by dragging it from one resource's row to another. You can also reschedule a task by dragging
it from one date to another.
resource to more than one task. For example, consider the tasks “Draw plans” and “Review
blueprints.” It makes sense that the architect would be assigned to both of these tasks. You can also
assign multiple resources to a single task.
Figure 4-8: The Assign Resources dialog box is where you manage the assignment between
resources and tasks.
Figure 4-9: View the details for all of a task's assigned resources in the Task Usage table.
Figure 4-10: View and update details about an assignment in the Assignment Information dialog
box.
Note: More about the features of the Assignment Information dialog box will be covered in
Microsoft Project 2016: Part 2.
Access the Checklist tile on your CHOICE Course screen for reference information and
job aids on How to Assign Resources.
ACTIVITY 4-4
Assigning Resources to Tasks
Scenario
Now that you've added some resources and tasks, you need to make assignments. You believe that
with four volunteers, you can sort the debris in five working days. Gary Clark will be performing
many of the tasks. There should be about 20 tons (2 truckloads) of debris to take to the dump.
You've also received the estimate from the construction company of $180,000. Also, your director
has set the maximum project budget to $250,000. You make the changes to your project plan. You
decide to try Team Planner view to quickly make a simple assignment.
TOPIC E
Resolve Resource Conflicts
After you enter resources for your project and assign them to your project, it's a good idea to make
sure you aren't planning to give your resources more project work to do than they have time
available. When you find that some resources have too much project work assigned to them, you
will want to reassign the extra work to other resources that aren't being used to capacity.
Overallocation
Allocation is the scheduling of tasks and resources, taking into account both resource availability and Over-allocated
project duration. A resource is over-allocated when it is assigned to do more work on a project than it Resources
can do within its normal working capacity. For example, if you schedule Samantha Barlow to spend
100% of her time on Task A and 50% of her time on Task B during the same period of time, she is
an over-allocated resource.
In the Gantt view, tasks with overallocated resources will display an overallocation indicator in the
Indicators column. The red icon is sometimes referred to as the burning man indicator. In Team
Planner view, when a work resource is over-allocated, it will be shown in red text in the left pane.
The tasks to which the resource is assigned will be shown with red brackets around them in the right
pane.
and, if available, methods for quickly resolving them. For example, you can have Project move the
start date of the task to the next time the resource is available.
Figure 4-12: The Task Inspector pane gives you information on overallocations and quick
resolutions if available.
Note: It's a best practice to only allow Project to automatically level over-allocations for specific
resources at a time before resorting to Level All.
Task Priorities
Prior to leveling, you may want to set the task priorities in the Task Information dialog box. The
priority sets the task's importance and its availability for leveling. The priority value that you enter is
a subjective value between 1 and 1000, which enables you to specify the amount of control you have
over the leveling process. For example, if you don't want Project to level a particular task, set its
priority level to 1000. By default, priority values are set at 500, or a medium level of control. Tasks
that have lower priority are delayed or split before those that have higher priority.
Figure 4-13: The Resource Leveling dialog box gives you control over Project's automatic leveling
features.
The following table describes the features of the Resource Leveling dialog box.
Button Function
Level Selection This button is only active when you select two or more tasks. When you
select this button, the selected tasks will be leveled according to the
settings in the Leveling Options dialog box.
Level Resource When you select this button, the selected resource will be leveled
according to the settings in the Leveling Options dialog box.
Button Function
Level All When you select this button, all over-allocated resources will be leveled
according to the settings in the Leveling Options dialog box.
Leveling Options When you select this button, the Leveling Options dialog box will open.
There are many options from which you can choose:
• You can change Leveling calculations from Manual to Automatic
and vice versa.
• You can change the time units used to identify over-allocations. The
default is Day by Day, but you can select Minute by Minute, Hour
by Hour, Week by Week, or Month by Month.
• You can choose whether to clear old leveling values before new ones
are applied.
• You can choose whether to level for the entire duration of the project
or only for a specific period of time.
• You can choose which rules are followed when resolving over-
allocations.
After you change the desired options, remember to select OK.
Clear Leveling When you select this button, any leveling you previously applied to the
project will be undone. If you select two or more tasks before selecting
this button, only the leveling for those tasks will be undone.
Next Overallocation When you select this button, Microsoft Project Professional 2016 finds
the next over-allocated resource.
Figure 4-14: Review the changes made by automatic leveling in the Leveling Gantt Chart.
Access the Checklist tile on your CHOICE Course screen for reference information and
job aids on How to Resolve Resource Conflicts.
ACTIVITY 4-5
Resolving Resource Conflicts
Data File
C:\91062Data\Managing Project Plan Resources\Woods_3BR_Home_Project_Level.mpp
Scenario
You have assigned resources to your tasks. Now you need to make sure that your resources are not
overallocated so that they have the time to get the work done. You use various methods to resolve
any conflicts.
Remind the students
that it is best practice to
1. Open the Woods_3BR_Home_Project_Level.mpp project plan file. use the least invasive
a) Select File→Open. techniques first, then
progress until the project
b) In the Open backstage, select Browse. is leveled.
c) In the Open dialog box, navigate to the C:\91062Data\Managing Project Plan Resources folder Encourage the students
containing your class files. to use this file to avoid
d) Select Woods_3BR_Home_Project_Level.mpp and select Open. differences in this
activity.
2. Manually resolve conflicts with Team Planner view.
a) Select Resource→Team Planner to open Team Planner view.
b) In the Resource Name column, locate the Inspector resource.
c) Scroll to the right in the schedule pane to Tue Oct 25 and locate the overallocated tasks (you may
need to zoom in):
• Conduct rough-in plumbing inspection
• Conduct rough-in electrical inspection
d) Drag the Conduct rough-in electrical inspection task to the right in the schedule and drop it in the
column for Wed Oct 26.
c) Select OK.
d) In the Task Entry table, select 6 - Place Containers.
e) Select Resource→Level Resource.
f) In the Level Resources dialog box, in the Selected Resources list, select Gary Clark and verify that
Container is not selected.
g) Select Level Now.
Ask the students why h) In the Microsoft Project dialog box, review the message about Gary Clark. Select Skip. Repeat until
project can't level Gary the dialog box closes.
Clark. Reinforce the i) On the ribbon, select Resource→Leveling Options.
concept that they should
try to level within slack
first so the end date
doesn't change.
j) In the Resource Leveling dialog box, uncheck the Level only within available slack check box.
Ensure that the other options are set as follows:
k) Select OK.
l) In the Task Entry table, select 6 - Place Containers.
m) Select Resource→Level Resource.
n) In the Level Resources dialog box, in the Selected Resources list, select Gary Clark and verify that
Container is not selected.
o) Select Level Now.
p) Verify the changes in the Gantt chart.
Summary
In this lesson, you managed project resources in a number of ways using the Resources
Information dialog box. You also leveled over-allocated resources in your project.
Encourage students to
Which features of the Resource Information dialog box are you most likely to use during your next project? use the social
A: Answers will vary, but might include adding a resource's email address, changing a resource's type networking tools
from Work to Material or Cost, changing a resource's availability, adding cost rates to a resource, and provided on the CHOICE
adding notes about a resource. Course screen to follow
up with their peers after
Which leveling methods will you use during your next project, and why? the course is completed
for further discussion
A: You might want to use the automatic method if you don't need to maintain tight control over your and resources to support
project's schedule. You might choose the manual method if you need to control the duration of tasks continued learning.
and when they occur.
Note: Check your CHOICE Course screen for opportunities to interact with your classmates,
peers, and the larger CHOICE online community about the topics covered in this course or
other topics you are interested in. From the Course screen you can also access available
resources for a more continuous learning experience.
Lesson Objectives
In this lesson, you will finalize a project plan. You will:
• Optimize the project plan using the critical path.
• Set the project baseline and describe how the baseline fields are used.
• Share the project plan with team members and stakeholders.
Lesson Introduction
You have created a project plan by creating a work breakdown structure and adding the
resources needed to complete the project. Now that you have a plan, you need to review it
to see if it meets your needs. Often, a first attempt at the project plan stretches beyond a key
deadline or has areas that can be optimized to decrease work and cost. Finally, you will need
to prepare for executing the project and share your final plan with stakeholders and team
members.
92 | Microsoft® Project 2016: Part 1
TOPIC A
Optimize a Project Plan
Every task is important, but those tasks that directly determine the total duration of the project are
especially critical. In this topic, we will discuss how to identify those tasks and then modify them to
optimize the overall project plan..
Figure 5-1: The critical path defines the overall project duration.
Project 2016 automatically calculates the critical path for you. In both the Gantt Chart and
Network Diagram views, tasks on the critical path are depicted in red.
Demonstrate how to
make the critical path
appear in red.
Note: If the critical path is not showing up in red in your version of Project 2016, you probably
need to change a setting. On the ribbon, select the Format tab, find the Bar Styles command
group, and check the Critical Tasks check box.
Note: After you build your plan and Project calculates the schedule and cost for the project, in
rare instances you might have more time or an increased budget. You can choose to end the
project ahead of schedule or under budget. Or, with stakeholder approval, you can increase the
scope and add quality to the project deliverables.
Effort-Driven Tasks
In an effort-driven task, the work required to complete the task is constant even if the number of
resources is changed. For example, packing boxes is a task that could be shortened by adding
additional resources, but the amount of work (effort) will not change. Not all tasks are effort driven.
For example, when you bake a cake, the amount of time that the cake needs to bake in the oven
cannot be changed by adding resources. You can decide for each task whether it should be effort-
driven or not.
Access the Checklist tile on your CHOICE Course screen for reference information and
job aids on How to Optimize Duration.
ACTIVITY 5-1
Optimizing a Project Plan
Data File
C:\91062Data\Finalizing a Project Plan\Woods_3BR_Home_Project_Optimize.mpp
Scenario
You've modified your project plan and resolved the resource conflicts, but now your project finish
date is coming in after the end of the year. You need to understand the critical path and make
changes so that you can meet your December 31, 2016 deadline. Also, the concrete contractor has
agreed to add another resource to double their effort. They still want you to hold off on building the
backyard fence so they can get the trucks into the backyard to finish pouring the patio. After seeing
how that impacts the plan, you think you can tighten up some of the durations and dependencies.
Thankfully, you've been informed that another volunteer will be able to drive the truck so you can
relieve Gary Clark if needed. Also, you find out that you don't have to wait on building the fence
until the appliances are delivered since that truck is much smaller. You make the necessary
adjustments to optimize the plan.
TOPIC B
Set a Baseline
When you are moving from project planning to project execution, it's a good idea to set a baseline
so that you can measure how well your project is performing. In this topic, you'll discuss baselines
and how to set them.
Baselines
A baseline is a measurement, calculation, or location used as a basis for comparison. A project baseline is Ask students if they
an approved plan for a project. Normally the project plan is approved by the project sponsor (the have baselined previous
person in an organization who authorizes, supports, and approves a project). The baseline is a projects.
snapshot of the planned scope, time, and cost of a project. As the project is executed, you can
compare actual scope, time, and cost against the baseline to measure how the project is performing.
Here are some of the questions that can be answered.
If your project is not performing as expected, you can take corrective action to finish the project
according to scope, on time, and within budget. This is the monitoring and controlling function of
project management.
Figure 5-4: You can view the current Baseline values in the Baseline table.
Because the baseline provides the reference points against which you compare actual project
progress, the baseline should include your best estimates for task duration, start and finish dates,
costs, and other project variables that you want to monitor. The baseline may also represent a
contractual obligation for the project. Baseline information that consistently differs from current
data may indicate that your original plan is no longer accurate, possibly because the scope needs
review or because the nature of the project has changed. If project stakeholders agree that the
difference warrants it, you can modify or rework the baseline at any time during the project. You
may find that setting multiple baselines is especially useful for long projects or for projects in which
the baseline is rendered irrelevant by significant changes to scheduled tasks or costs.
Figure 5-5: The Set Baseline dialog box is where you can record your current project plan as a
baseline.
Note: As a project manager, you should have a clearly defined process for evaluating and
approving changes to the project baseline. The positive and negative effects of potential changes
to project scope, time, or cost must be carefully considered before implementing them.
Access the Checklist tile on your CHOICE Course screen for reference information and
job aids on How to Set a Baseline.
ACTIVITY 5-2
Setting a Baseline
Data File
C:\91062Data\Finalizing a Project Plan\Woods_3BR_Home_Project_Finalize.mpp
Scenario
Now that you have optimized your project plan and you have a plan that completes before the end-
of-year deadline, it's time to save the baseline so that you can compare progress against the plan as
you execute the project. You create a new baseline.
TOPIC C
Share a Project Plan
Once you draft a project plan, you will need to deliver it to your project stakeholders for review and
to your project sponsor for approval. In this topic, you will use several methods for delivering
project plans.
Once the view is adjusted to your desired detail amount and zoom level, you can start printing by
selecting the File tab on the ribbon and then selecting the Print tab on the Backstage. The first
thing you will probably notice on the Print screen is the large Print Preview area in the right pane,
which shows you exactly how the printed page will look. In the bottom-right corner of the Print
Preview pane you will find several controls for navigating and zooming the preview.
Figure 5-6: The Print screen on the Backstage enables you to preview your current settings
before you print.
If you are not satisfied with the preview, you can change the Settings options in the left pane of the
Print tab. You can choose to print:
• The entire project.
• Specific dates.
• Specific pages.
• In landscape or portrait page orientation.
• A variety of page sizes.
If you select the Page Setup link, a Page Setup dialog box will open that gives you many more
options grouped into six tabs. These include the margins, header, footer, and legend.
When the Print Preview looks like you want, you can select a printer and select the Print button.
Access the Checklist tile on your CHOICE Course screen for reference information and
job aids on How to Print a Project View.
When you select the Sync with SharePoint button on the Share screen, you will be prompted to
go to the Save As screen. When you select the Sync with SharePoint button on the Save As
screen, you will have the option of syncing with a new SharePoint site or an existing one. In ether
case you will need a valid SharePoint Site address, User Name, and Password.
Figure 5-7: Syncing with SharePoint is integrated into the Save As screen.
Note: You can access the Sync with SharePoint button directly from the Save As screen if you
wish.
Figure 5-8: You can email a project from the Share screen.
Figure 5-9: Use the Save As dialog box to select an alternate file format.
Access the Checklist tile on your CHOICE Course screen for reference information and
job aids on How to Share a Project Plan.
ACTIVITY 5-3
Sharing a Project Plan
Data File
C:\91062Data\Finalizing a Project Plan\Home_move_plan_handout.mpp
Scenario
You have a project plan file for a home move. You want to share it as a handout with the Woods
family and other families to use as a guideline for preparing to move into their new home. You will
prepare the file for printing by scheduling the project from the end date to correspond with the
targeted move-in date, prepare the view of the plan, and print it.
Inform the students that
they will be simulating
printing by printing to a 1. Open the Home_move_plan_handout.mpp project plan file.
file. Alternatively, you a) Select File→Open.
can print to a printer in
the classroom if it is b) In the Open backstage, select Browse.
available to the student c) In the Open dialog box, navigate to the C:\91062Data\Finalizing a Project Plan folder containing
computers. your class files.
d) Select Home_move_plan_handout.mpp and select Open.
d) In the Save Print Output As dialog box, in the File Name field, enter my_printout and select Save.
e) Monitor the progress in the Printing dialog box.
Summary
In this lesson, you optimized and delivered a Microsoft Project Professional 2016 plan on paper and
in several electronic formats.
Encourage students to
use the social Which view(s) of your next project plan are you most likely to print, and why?
networking tools A: Answers will vary, but Gantt Chart and Calendar are the most frequently printed views.
provided on the CHOICE
Course screen to follow Why should you optimize the project plan?
up with their peers after
A: Answers will vary, but decreasing the duration of the project and minimizing resource costs are the
the course is completed
most common reasons.
for further discussion
and resources to support
Note: Check your CHOICE Course screen for opportunities to interact with your classmates,
continued learning.
peers, and the larger CHOICE online community about the topics covered in this course or
other topics you are interested in. From the Course screen you can also access available
resources for a more continuous learning experience.
Course Follow-Up
Congratulations! You have completed the Microsoft® Project 2016: Part 1 course. You successfully
drafted and shared a project plan.
Businesses, academic institutions, and other organizations conduct various projects to develop
products, improve processes, and meet organizational goals. There is a growing demand for
professionals like you to manage these project successfully. The ability to complete projects on time,
within budget, and according to specifications is crucial for all professionals—regardless of whether
project management is an official part of your duties. Creating and sharing well-developed project
plans will help you meet these goals while keeping your project running smoothly. Microsoft Project
Professional 2016 is a powerful tool that can enable you to plan projects effectively and efficiently.
What's Next?
Microsoft® Project 2016: Part 2 is the next course in this series. In that course, you will learn the
advanced features of Microsoft Project Professional 2016—such as capturing progress of executing
projects, customizing Project using templates and views, and creating reports. You will also perform
higher-level analysis of a project's progress and apply strategies to keep the project on track.
You are encouraged to explore Project further by actively participating in any of the social media
forums set up by your instructor or training administrator through the Social Media tile on the
CHOICE Course screen.
Course Follow up
Solutions
4. True or False? Project management is the application of knowledge, skills, tools, and
techniques to accomplish activities or tasks to meet the objectives set for a project.
☑ True
☐ False
5. Which project management process group involves the completion of tasks and the
coordination of people and other resources to carry out the plan?
○ Initiating
◉ Executing
○ Planning
○ Closing
6. Who is the project sponsor?
A: The project sponsor is the person who has the authority to approve or terminate the project.
112 | Microsoft® Project 2016: Part 1
Solutions
Glossary
duration leveling
The number of working time periods The rescheduling and reassignment of
(seconds, minutes, hours, days, weeks, tasks to resolve resource over-allocations.
months, years) from the beginning of a
task until its end. Leveling Gantt chart
A special Gantt chart view comparing the
effort-driven project plan before and after leveling.
When a task is effort driven, Project keeps
the total task work at its current value, link
regardless of how many resources are In Project 2016, the act or result of joining
assigned to the task. When new resources two tasks together to create a dependency.
are assigned, remaining work is distributed
to them.. manually scheduled
A mode of task scheduling in which you
exception manually control the task's start date, end
In Project 2016, a day or week when date, and duration.
working time is different than what is
normal for the base calendar. material resource
A resource tracked by the amount of units
FF consumed.
(Finish-to-Finish) A dependency between
two tasks in which the first task must be milestone
completed before the second task can be An important point in a project.
completed.
over-allocated
FS When a resource is assigned to do more
(Finish-to-Start) A dependency between work on a project than it can do within its
two tasks in which the first task must be normal working capacity.
completed before the second task can
predecessor
begin.
A task that must be started or finished
Gantt chart before another task can be performed.
A method for displaying project tasks over
project
time. Named after Henry Gantt, who
A temporary initiative to create a unique
designed the tool between 1910 and 1915.
result.
import map
project baseline
The map which defines how data from a
The collection of baseline measurements
source file corresponds to the columns in a
that constitute the approved plan for the
Project plan.
project.
Import Wizard
project calendar
The wizard which walks you through
The calendar that determines the overall
importing data from another program into
schedule of a project.
Project 2016.
project constraint
lag
Anything that constrains or dictates the
A delay between two tasks that are linked
actions of the project team.
together.
lead
An overlap in time between two tasks that
are linked together.
Glossary
Microsoft® Project 2016: Part 1 | 115
Glossary
116 | Microsoft® Project 2016: Part 1
team member
A person who is responsible for performing or
approving the work to complete the project.
Tell Me bar
The area above the ribbon where you can
search for commands and help content.
triple constraint
The three most important factors in a project
—scope, time, and cost—which are
dynamically linked so that any change in one
will impact the others.
Trust Center
The area in the Project settings which controls
security and privacy settings such as enabling
legacy file formats.
view
A combination of specific tables and/or charts
in the main window used by Project to display
information relevant to the task at hand.
WBS
(Work Breakdown Structure) The hierarchical
arrangement of a task list.
Glossary
Index
A FS
dependency 40, 57
allocation 81
G
B
Gantt Chart
base calendars 29
leveling 84
baseline
setting 98
baseline table 97 I
import map 44
C Import Wizard 44
calendars
resource 71 L
cost lag
project area 97 defined 58
resources 67 time 57
critical path lead
viewing 92 defined 58
time 58
D leveling 81
Leveling Gantt Chart 84
deadline 62
link 40
dependencies 40, 56
duration 94
M
E material resources 67
Microsoft Project
email 104
2016 7
exceptions 32
Assignment Information dialog box 78
Assign Resources dialog box 76
F Change Working Time dialog box 30
FF 40 contextual tab 11
finish dates 22, 23 Details dialog box 33
Finish-to-Finish, See FF Duration spin box 40
Finish-to-Start, See FS Gantt Chart 8
118 | Microsoft® Project 2016: Part 1
Index
Microsoft® Project 2016: Part 1 | 119
SS 40 working time
start dates 22 changing 30
Start-to-Finish, See SF defined 33
Start-to-Start, See SS work resources 66
status bar 11
subtasks 49
successor 40
summary tasks 49
syncing
with SharePoint 103
T
Task Entry Table 38
Task Information dialog box
General tab 40
Notes tab 52
Predecessors tab 56
Task Inspector pane 81
tasks
auto scheduled 61
constraints 61
deadline 62
dependencies 56
duration 40
effort-driven 93
importing methods 43
lag 57
lead 58
links 40
manually scheduled 61
milestones 51
notes 52
predecessors 56
summary 49
Task Usage table 77
team member 4
Team Planner 76
Tell Me bar 12
time 97
triple constraints 3
Trust Center 43
V
View Bar 9
W
WBS 49
work 94
Work Breakdown Structure, See WBS
Index
091062S rev 1.1