Fidic - Condictions of Contract For Epc-Turnkey Projects
Fidic - Condictions of Contract For Epc-Turnkey Projects
Fidic - Condictions of Contract For Epc-Turnkey Projects
2
Introduction (cont’d)
3
Project Delivery/Contract Model
4
Project Delivery/Contract Model (cont’d)
• Contract Model
• Follows the PDS adopted by the Owner
• A generally understood form of contract that specifies the
risk allocation that is generally assumed to apply and govern
the relationship between the parties, such as CCDC
standard contract forms.
• May include one or more pricing models, which in turn may
change the risk allocation generally assumed to apply by the
contract model
• e.g. Using CCDC 2 stipulated sum contract, but including
numerous cost reimbursable and unit prices for a majority of the
scope of work
5
Project Delivery/Contract Model (cont’d)
6
Contract Models
7
Contract Models (cont’d)
8
Contract Models (cont’d)
9
Contract Models (cont’d)
10
Acronym Alley (cont’d)
11
Risk Transfer
Shifting the risk
Increases Bankability
Contract/Pricing Model Risk
Owner Contractor
Management Contracts
Construction Management
Traditional Unit Price
Bill of Approximate Quantity
Traditional Lump Sum
Fixed Price / GMP
Design and Build
Complete “Package”
Design, Build, Operate &
Maintain
12
Typical Design–Bid–Build Relationship
LENDER
PREPARE
DESIGN OWNER
DESIGN
CONSULTANTS CONSTRUCTION TO
OWNER’S DESIGN
ADMINISTER
CONTRACT
CONTRACTOR
13
Design-Build/EPC Relationship (Theory)
LENDER
PERFORMANCE
SPECIFICATIONS OWNER
EMPLOYER’S
CONSULTANT DESIGN TO PERFORMANCE SPECIFICATIONS,
PROCURE AND CONSTRUCT
ADMINISTER
CONTRACT(?) EPC
CONTRACTOR
SPECIALTY
LABOUR VENDORS
SUBCONTRACTORS
PERFORMANCE
SPECIFICATIONS LENDER
OR
OWNER’S EMPLOYER
REQUIREMENTS
ADMINISTER EPC
CONTRACT(?)
CONTRACTOR
DESIGN
SUBCONTRACTORS VENDORS
CONSULTANTS
LENDER
EMPLOYER
EPCM
CONTRACTOR
16
Construction Management
(CM not “at risk”)
LENDER
OWNER
OWNER'S
CONSULTANT
CONSTRUCTION
MANAGER
17
Construction Management
(CM “at risk”)
LENDER
OWNER
OWNER'S
CONSULTANT CONSTRUCTION
MANAGER
CONSTRUCTION MANAGER
TRANSITIONS TO BECOME
CONTRACTOR
CONTRACTOR
18
Basic Bankability Issues
19
Lender’s “Wish List” for Financing
20
Lender’s “Wish List” for Financing (cont’d)
• Proven technology
• Adequate performance security
• Reasonable limitations on Contractor’s right to changes and
extensions of time; prior (discretionary) lender approval for
material changes
• Contractor obligation for all permits, licences and approvals (in
contractor’s name [and perhaps also in employer’s name])
• Reasonable defects liability period
• Restriction on subcontracting except to reputable
subcontractors
21
Pushback - Contractor’s “Wish List”
22
Bankability/Role of Lenders
23
Bankability/Role of Lenders (cont’d)
24
Bankability/Role of Lenders (cont’d)
• RISK REGISTERS
• What are they?
• Are they used/useful?
• Only for Lender? Employer? Contractor?
• When should they be prepared?
25
Project Roadmap for Lenders
26
Project Roadmap for Lenders (cont’d)
Project
A Project Overview
• Project Components
• Overall Project Structure/ Organization Chart
• Overall Project Schedule
• Overall Cost Estimate
B Market for Sales/Revenue
C Overall Project Economics
• Capital Cost
• O&M Costs
o Annual Cost
o Sustaining Capital
o Capital Replacements
• Project Cash Flow
o Revenue
o Account structure
o Debt service
o Equity return
o Tax burden
o Contingency
o Depreciation
• Financial Model
• Overall Project Economic Performance Projections
• Taxation Summary
27
Project Roadmap for Lenders (cont’d)
28
Project Roadmap for Lenders (cont’d)
29
Project Roadmap for Lenders (cont’d)
L Project Status
M Summary and Conclusions
30
Project Roadmap for Lenders (cont’d)
31
Mega Projects
• Many mega projects are too large for a single EPC contract or
a single contractor
• Split EPC contracts: Lender, Owner, Contractors,
Subcontractors and Vendors may have concerns
• Addressing concerns
• Clear contracts
• Clear scope definition/battery limits
• Clarification of inter-dependencies for performance guarantees
• JV/Consortium as Contractor:
• All for one and one for all? Or everyone for themselves?
• Should Owner/Lender be concerned?
• EPCM contract: is it a bankable alternative?
32
Bankability vs “Best Value”
33
Lenders’ Direct Agreement
34
Lenders’ Direct Agreement (cont’d)
35
Lenders’ Direct Agreement (cont’d)
36
Owner/Lender Step-in Rights
37
Security for Contractor’s Performance
• Performance Security:
• Letter of Credit/Bank Guarantee
• Surety Bond
• Parent Company Guarantee
• On demand or conditional security?
• To secure physical performance or LDs?
• Advantages and disadvantages of each to Lender, Employer
and Contractor
• Lender preference is often in favour of liquidity – on demand
payment instruments
• But is a 10% L/C really better than a 50% surety
performance bond?
38
Security for Contractor’s Performance
(cont’d)
39
Decennial Liability
• What is it?
• Concept of responsabilité décennale originated in French
Civil Code and desire to protect building owners who could
not ordinarily be expected to possess the technical expertise
required to identify defects in design or construction at
project turnover, particularly latent defects
• Concept now adopted in some common law countries and/or
states within countries
• Strict liability for period of 10 years from turnover, protecting
owner against collapse of building and latent defects
• Decennial liability insurance available (and mandatory in
France and some other jurisdictions)
40
Decennial Liability
41
Security for Payments to Contractor
42
“Back to Back” Obligations & Liabilities
43
“Back to Back” Obligations (cont’d)
44
Insurance as Risk Transfer Mechanism
45
Insurance as Risk Transfer Mechanism
(cont’d)
46
Insurance as Risk Transfer Mechanism
(cont’d)
47
Can Bankability be Enhanced?
48
©Helmut K. Johannsen, P.Eng., C.Arb.
[email protected]
49 +1-604-631-4819