ID Task Name Duration Start Finish 1

The document outlines a 190-day construction schedule for a transitional bus terminal project in Kandy, Sri Lanka starting on June 25th, 2018 and ending January 15th, 2019. It details 29 tasks necessary for the project including site clearing, material approvals, building construction, electrical and plumbing work, tiling, and project completion tasks. The schedule shows resource allocation and timing for each task to ensure the project is completed on schedule by its January 2019 deadline.

Uploaded by

Pja Shantha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
66 views3 pages

ID Task Name Duration Start Finish 1

The document outlines a 190-day construction schedule for a transitional bus terminal project in Kandy, Sri Lanka starting on June 25th, 2018 and ending January 15th, 2019. It details 29 tasks necessary for the project including site clearing, material approvals, building construction, electrical and plumbing work, tiling, and project completion tasks. The schedule shows resource allocation and timing for each task to ensure the project is completed on schedule by its January 2019 deadline.

Uploaded by

Pja Shantha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Catch up programme with effect from 02th Oct 2018 for transitional bus terminal for kandy multimodel

transpotation terminal project in Kandy


ID Task Name Duration Start Finish July August September October November December January
6/17 6/24 7/1 7/8 7/15 7/22 7/29 8/5 8/12 8/19 8/26 9/2 9/9 9/16 9/23 9/30 10/7 10/14 10/21 10/28 11/4 11/11 11/18 11/25 12/2 12/9 12/16 12/23 12/30 1/6 1/13
1 Construction of transitional bus terminal 190 days Mon 6/25/18 Tue 1/15/19
for Kandy Multimodal transpotation
terminal project at Bogambara in Kandy

2 Mobilization 4 days Mon 6/25/18 Thu 6/28/18 Excavater[4],Skilled Labour[8],Unskilled Labour[12]


3 Rerouting and relocating busses 5 days Thu 6/28/18 Mon 7/2/18 Skilled Labour[10],Unskilled Labour[40],Tipper truck[20],JCB Machine[5]
4 Clearing the site including removal of 9 days Tue 7/3/18 Wed 7/11/18 Skilled Labour[18],Unskilled Labour[18],JCB Machine[9]
roots and cut down top soil and
removing exsisting foundation
5 Sample & material approvals such as 20 days Fri 6/29/18 Wed 7/18/18 Site Engineer[20],Skilled Labour[20],Unskilled Labour[40]
sand,metal,cement,steel,structural
steel,Roofing sheet,etc
6 Central province passenger transport 98 days Tue 7/17/18 Tue 11/6/18
survices authority office building Upper
floor
7 Clearing and removing the existing slab 8 days Wed 7/25/18 Wed 8/1/18 Concrete bracker[8],Skilled Labour[24]
top wast materials and remove from
site
8 Demolishing and removing the existing 5 days Tue 7/17/18 Sat 7/21/18 JCB Machine[5],Operator[5],Unskilled Labour[10]
additional slab on top of staircase

9 Construction of column including form 11 days Sun 7/22/18 Wed 8/1/18 Ready mix concrete[1],Form work [1],Rainforcement[1],Skilled Labour[22],Unskilled Labour[11]
work,r/f and concreting work
10 Construction of roof tie beam and 9 days Thu 8/2/18 Fri 8/10/18 Mason[30],Unskilled Labour[40]
water tank slab
11 150 mm cement block work 9 days Thu 9/13/18 Fri 9/21/18 Mason[39],Unskilled Labour[39]
12 Fabricating steel roof 10 days Thu 8/2/18 Sat 8/11/18 Welder[48],Unskilled Labour[48]
13 Erecting steel roof 5 days Sun 9/2/18 Thu 9/6/18 Welder[30],Unskilled Labour[30]
14 Roof covering and roof plumbing 6 days Fri 9/7/18 Wed 9/12/18 Pumber[8]
15 Piping water supply ,sewerage and 8 days Sat 9/22/18 Sat 9/29/18 Pumber[10]
waste water
16 Conduting and wiring for electical 15 days Sat 9/22/18 Sat 10/6/18 Electrician[10]
fittings
17 Conduting and wiring for telephone 7 days Sat 9/22/18 Fri 9/28/18 Electrician[10]
system
18 Installating of sanitory fittings and 4 days Sat 11/3/18 Tue 11/6/18 Pumber[16],Unskilled Labour[16]
accesaries
19 Fixing electrical fittings including DBs 3 days Sat 11/3/18 Mon 11/5/18 Electrician[8],Unskilled Labour[12]

20 Installating of telephone system 9 days Fri 10/26/18 Sat 11/3/18 Electrician[26],Unskilled Labour[26]
21 instalating of Fire protection system 3 days Sat 11/3/18 Mon 11/5/18 Fire technician[8],Unskilled Labour[8]

22 Plastering work (Internaly) 9 days Sat 9/29/18 Sun 10/7/18 Mason[26],Unskilled Labour[26]
23 Plastering work (Externaly) 8 days Mon 10/8/18 Mon 10/15/18 Mason[44],Unskilled Labour[33]
24 Water proofing of bath rooms and 5 days Mon 10/8/18 Fri 10/12/18 Skilled Labour[6],Unskilled Labour[12]
water tank slab
25 Floor tiling 7 days Wed 10/17/18 Tue 10/23/18 Tiling Mason[18],Unskilled Labour[18]

26 Wall tiling 9 days Wed 10/24/18 Thu 11/1/18 Tiling Mason[30],Unskilled Labour[30]
27 Ceiling warks 9 days Mon 10/8/18 Tue 10/16/18 Skilled Labour[30],Unskilled Labour[40]
28 Alumunium works 10 days Tue 10/16/18 Thu 10/25/18 Skilled Labour[48],Unskilled Labour[48]
29 Lightning protection system instalation 9 days Fri 10/26/18 Sat 11/3/18 Electrician[18],Skilled Labour[9]

Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: Kandy project program
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Tue 10/2/18
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress

DGES RR JOINT VENTURE


Catch up programme with effect from 02th Oct 2018 for transitional bus terminal for kandy multimodel transpotation terminal project in Kandy
ID Task Name Duration Start Finish July August September October November December January
6/17 6/24 7/1 7/8 7/15 7/22 7/29 8/5 8/12 8/19 8/26 9/2 9/9 9/16 9/23 9/30 10/7 10/14 10/21 10/28 11/4 11/11 11/18 11/25 12/2 12/9 12/16 12/23 12/30 1/6 1/13
30 Painting works 8 days Fri 10/26/18 Fri 11/2/18 Skilled Labour[48]
31 Final touchup works 4 days Thu 11/1/18 Sun 11/4/18 Skilled Labour[24]
32 Improvement of road 58 days Wed 10/10/18 Thu 12/6/18

33 Removal of structure and obstruction 8 days Wed 10/10/18 Wed 10/17/18 Skilled Labour[16],Unskilled Labour[24],JCB Machine[8]
along the road side
34 Scarify and remove existing bitumen 8 days Thu 10/18/18 Thu 10/25/18 JCB Machine[8],Skilled Labour[16],Unskilled Labour[32]
layer as directed by the engineer

35 Dence graded aggregate base (Approx 12 days Fri 10/26/18 Tue 11/6/18
100mm )(Aggregate base course)

36 Supplying and application of prime 2 days Wed 11/7/18 Thu 11/8/18


coat on prepared base
37 Bituminous track coat 3 days Fri 11/9/18 Sun 11/11/18

38 Asphalt concrete surfacing 4 days Mon 11/12/18 Thu 11/15/18


39 Repairs to existing drains 21 days Fri 11/16/18 Thu 12/6/18 Mason[42],Unskilled Labour[84],Ready mix concre

40 Construction of transitional bus terminal 176 days Mon 7/9/18 Tue 1/15/19

41 Substructural works 166 days Mon 7/9/18 Sat 1/5/19


42 Demolishing existing building and 4 days Mon 7/9/18 Thu 7/12/18 Excavater[4]
debris carted away from site

43 Removing top surface in building 12 days Fri 7/13/18 Tue 7/24/18 JCB Machine[12]
area and carted away
44 Excavation to reduce level 25 days Wed 7/25/18 Sun 9/2/18 JCB Machine[25],Tipper truck[100],Unskilled Labour[25]
45 Ground preparation 25 days Wed 7/25/18 Sun 9/2/18 Excavater[25]
46 setting out works 1 day Wed 8/1/18 Wed 8/1/18
47 Excavation of foundation 24 days Thu 8/2/18 Sun 9/9/18 JCB Machine[24],Operator[24],Unskilled Labour[24]
48 Laying screed concrete 25 days Tue 8/7/18 Sat 9/15/18 Skilled Labour[25],Unskilled Labour[25]
49 Formwork of base 44 days Fri 8/10/18 Sun 10/7/18 Skilled Labour[25],Unskilled Labour[25]
50 Rainforcement work of bace 45 days Sun 8/12/18 Wed 10/10/18
51 Concreting of base 48 days Wed 8/29/18 Mon 10/15/18 Ready mix concrete[100],Skilled Labour[50],Unskilled Labour[75]
52 Column reinforcement work 46 days Sat 9/1/18 Tue 10/16/18 Rainforcement[6],Skilled Labour[25],Unskilled Labour[50]
53 Column formwork 44 days Tue 9/4/18 Wed 10/17/18 Skilled Labour[50],Unskilled Labour[50]
54 Column concreting work 45 days Fri 9/7/18 Sun 10/21/18 Ready mix concrete[10],Skilled Labour[50],Unskilled Labour[75]

55 Rubble work 9 days Tue 9/25/18 Wed 10/3/18 Rubble[1],Skilled Labour[18],Unskilled Labour[36]
56 Plinth beam and tie 25 days Fri 9/28/18 Mon 10/22/18 Ready mix concrete[75],Skilled Labour[28],Unskilled Labour[56]
beamr/f,formwork&concreting
57 Filling under floor and back filling 15 days Sun 11/18/18 Sun 12/2/18 Unskilled Labour[60]

58 Anti-termite treatment 7 days Mon 12/24/18 Sun 12/30/18 Skilled Labour[14],Unskilled


59 Floor concreting 13 days Mon 12/24/18 Sat 1/5/19 Mason[30],Unskilled L
60 Superstructure 90 days Sun 9/9/18 Fri 12/7/18
61 Fabrication of potal frames 45 days Sun 9/9/18 Tue 10/23/18
62 Erection of potal frames 25 days Wed 10/24/18 Sat 11/17/18 Welder[100],Unskilled Labour[100]
63 Roof work and roof plumbing 20 days Sun 11/18/18 Fri 12/7/18 Welder[20],Unskilled Labour[30]

64 Structural work ground floor to first 22 days Tue 10/23/18 Tue 11/13/18 Mason[28],Unskilled Labour[28]
floor level
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: Kandy project program
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Tue 10/2/18
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress

DGES RR JOINT VENTURE


Catch up programme with effect from 02th Oct 2018 for transitional bus terminal for kandy multimodel transpotation terminal project in Kandy
ID Task Name Duration Start Finish July August September October November December January
6/17 6/24 7/1 7/8 7/15 7/22 7/29 8/5 8/12 8/19 8/26 9/2 9/9 9/16 9/23 9/30 10/7 10/14 10/21 10/28 11/4 11/11 11/18 11/25 12/2 12/9 12/16 12/23 12/30 1/6 1/13
65 Cement block work 13 days Wed 11/14/18 Mon 11/26/18 Mason[39],Unskilled Labour[39]
66 M&E works 50 days Tue 11/27/18 Tue 1/15/19

67 piping for water supply and 10 days Tue 11/27/18 Thu 12/6/18 Pumber[10],Unskilled Labour[10]
sewerage inside of the building
68 Conduiting and wiring electrical 10 days Tue 11/27/18 Thu 12/6/18 Electrician[10],Unskilled Labour[10]
work
69 Conduiting and wiring for fire alarm 10 days Tue 11/27/18 Thu 12/6/18 Electrician[10],Unskilled Labour[8]
and fire detection system
installation
70 Conduiting and wiring for CCTV 10 days Tue 11/27/18 Thu 12/6/18 CCTV Technician[10],Unskilled Labour[10]
system
71 Conduiting and wiring for public 10 days Tue 11/27/18 Thu 12/6/18 Electrician[10],Unskilled Labour[10]
address system
72 Water supply,sewerage and waste 8 days Mon 1/7/19 Mon 1/14/19 Pumber[45],Un
water external works
73 Construction of septic tank,sockage 6 days Mon 1/7/19 Sat 1/12/19 Mason[30],Unsk
pit and sump
74 Installation of sanitory fittings and 7 days Mon 1/7/19 Sun 1/13/19 Pumber[24],Un
accesaries
75 Installation of electrical fittings and 8 days Mon 1/7/19 Mon 1/14/19 Electrician[22]
D board
76 Installation of fire potection and 9 days Mon 1/7/19 Tue 1/15/19 Fire technician
detection system
77 Installation and fixing public address 6 days Mon 1/7/19 Sat 1/12/19 CCTV Technician
system and CCTV system

78 Finishes 31 days Fri 12/7/18 Sun 1/6/19


79 Plastering (internal walls 12 days Fri 12/7/18 Tue 12/18/18 Mason[60],Unskilled Labour[60]

80 Water proofing bath room and roof 7 days Wed 12/19/18 Tue 12/25/18 Skilled Labour[14],Unskilled Lab
slab
81 Plastering (external wall) 6 days Sat 12/8/18 Thu 12/13/18 Mason[28],Unskilled Labour[56]
82 Plinth plater 7 days Fri 12/14/18 Thu 12/20/18 Skilled Labour[7],Unskilled Labour[14
83 Aluminium works 20 days Fri 12/14/18 Wed 1/2/19 Skilled Labour[60],Unskill
84 Wall tiling bathroom area 12 days Thu 12/13/18 Mon 12/24/18 Tiling Mason[24],Unskilled Labou
85 Floor tiling 13 days Tue 12/25/18 Sun 1/6/19 Tiling Mason[39],Unsk

86 Ceiling finishes 5 days Wed 12/19/18 Sun 12/23/18 Skilled Labour[10],Unskilled Labou
87 Hand railing and steel staircase 8 days Wed 11/14/18 Wed 11/21/18 Skilled Labour[16],Unskilled Labour[32]
88 External works paving and aspalt 31 days Fri 12/7/18 Sun 1/6/19
surfacing including drain,turfing,paving

89 Painting 15 days Thu 12/13/18 Thu 12/27/18 Skilled Labour[60]


90 Fixing passenger seating 12 days Sat 12/22/18 Wed 1/2/19 Skilled Labour[24]

91 Final touchup works 8 days Fri 12/28/18 Fri 1/4/19 Skilled Labour[10],Unsk
92 Site clearing befor handing over 8 days Fri 12/28/18 Fri 1/4/19 Skilled Labour[10],Unsk
93 Handing over the project 1 day Sat 1/5/19 Sat 1/5/19 1/5

Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: Kandy project program
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Tue 10/2/18
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress