ID Task Name Duration Start Finish 1
ID Task Name Duration Start Finish 1
9 Construction of column including form 11 days Sun 7/22/18 Wed 8/1/18 Ready mix concrete[1],Form work [1],Rainforcement[1],Skilled Labour[22],Unskilled Labour[11]
work,r/f and concreting work
10 Construction of roof tie beam and 9 days Thu 8/2/18 Fri 8/10/18 Mason[30],Unskilled Labour[40]
water tank slab
11 150 mm cement block work 9 days Thu 9/13/18 Fri 9/21/18 Mason[39],Unskilled Labour[39]
12 Fabricating steel roof 10 days Thu 8/2/18 Sat 8/11/18 Welder[48],Unskilled Labour[48]
13 Erecting steel roof 5 days Sun 9/2/18 Thu 9/6/18 Welder[30],Unskilled Labour[30]
14 Roof covering and roof plumbing 6 days Fri 9/7/18 Wed 9/12/18 Pumber[8]
15 Piping water supply ,sewerage and 8 days Sat 9/22/18 Sat 9/29/18 Pumber[10]
waste water
16 Conduting and wiring for electical 15 days Sat 9/22/18 Sat 10/6/18 Electrician[10]
fittings
17 Conduting and wiring for telephone 7 days Sat 9/22/18 Fri 9/28/18 Electrician[10]
system
18 Installating of sanitory fittings and 4 days Sat 11/3/18 Tue 11/6/18 Pumber[16],Unskilled Labour[16]
accesaries
19 Fixing electrical fittings including DBs 3 days Sat 11/3/18 Mon 11/5/18 Electrician[8],Unskilled Labour[12]
20 Installating of telephone system 9 days Fri 10/26/18 Sat 11/3/18 Electrician[26],Unskilled Labour[26]
21 instalating of Fire protection system 3 days Sat 11/3/18 Mon 11/5/18 Fire technician[8],Unskilled Labour[8]
22 Plastering work (Internaly) 9 days Sat 9/29/18 Sun 10/7/18 Mason[26],Unskilled Labour[26]
23 Plastering work (Externaly) 8 days Mon 10/8/18 Mon 10/15/18 Mason[44],Unskilled Labour[33]
24 Water proofing of bath rooms and 5 days Mon 10/8/18 Fri 10/12/18 Skilled Labour[6],Unskilled Labour[12]
water tank slab
25 Floor tiling 7 days Wed 10/17/18 Tue 10/23/18 Tiling Mason[18],Unskilled Labour[18]
26 Wall tiling 9 days Wed 10/24/18 Thu 11/1/18 Tiling Mason[30],Unskilled Labour[30]
27 Ceiling warks 9 days Mon 10/8/18 Tue 10/16/18 Skilled Labour[30],Unskilled Labour[40]
28 Alumunium works 10 days Tue 10/16/18 Thu 10/25/18 Skilled Labour[48],Unskilled Labour[48]
29 Lightning protection system instalation 9 days Fri 10/26/18 Sat 11/3/18 Electrician[18],Skilled Labour[9]
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: Kandy project program
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Tue 10/2/18
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress
33 Removal of structure and obstruction 8 days Wed 10/10/18 Wed 10/17/18 Skilled Labour[16],Unskilled Labour[24],JCB Machine[8]
along the road side
34 Scarify and remove existing bitumen 8 days Thu 10/18/18 Thu 10/25/18 JCB Machine[8],Skilled Labour[16],Unskilled Labour[32]
layer as directed by the engineer
35 Dence graded aggregate base (Approx 12 days Fri 10/26/18 Tue 11/6/18
100mm )(Aggregate base course)
40 Construction of transitional bus terminal 176 days Mon 7/9/18 Tue 1/15/19
43 Removing top surface in building 12 days Fri 7/13/18 Tue 7/24/18 JCB Machine[12]
area and carted away
44 Excavation to reduce level 25 days Wed 7/25/18 Sun 9/2/18 JCB Machine[25],Tipper truck[100],Unskilled Labour[25]
45 Ground preparation 25 days Wed 7/25/18 Sun 9/2/18 Excavater[25]
46 setting out works 1 day Wed 8/1/18 Wed 8/1/18
47 Excavation of foundation 24 days Thu 8/2/18 Sun 9/9/18 JCB Machine[24],Operator[24],Unskilled Labour[24]
48 Laying screed concrete 25 days Tue 8/7/18 Sat 9/15/18 Skilled Labour[25],Unskilled Labour[25]
49 Formwork of base 44 days Fri 8/10/18 Sun 10/7/18 Skilled Labour[25],Unskilled Labour[25]
50 Rainforcement work of bace 45 days Sun 8/12/18 Wed 10/10/18
51 Concreting of base 48 days Wed 8/29/18 Mon 10/15/18 Ready mix concrete[100],Skilled Labour[50],Unskilled Labour[75]
52 Column reinforcement work 46 days Sat 9/1/18 Tue 10/16/18 Rainforcement[6],Skilled Labour[25],Unskilled Labour[50]
53 Column formwork 44 days Tue 9/4/18 Wed 10/17/18 Skilled Labour[50],Unskilled Labour[50]
54 Column concreting work 45 days Fri 9/7/18 Sun 10/21/18 Ready mix concrete[10],Skilled Labour[50],Unskilled Labour[75]
55 Rubble work 9 days Tue 9/25/18 Wed 10/3/18 Rubble[1],Skilled Labour[18],Unskilled Labour[36]
56 Plinth beam and tie 25 days Fri 9/28/18 Mon 10/22/18 Ready mix concrete[75],Skilled Labour[28],Unskilled Labour[56]
beamr/f,formwork&concreting
57 Filling under floor and back filling 15 days Sun 11/18/18 Sun 12/2/18 Unskilled Labour[60]
64 Structural work ground floor to first 22 days Tue 10/23/18 Tue 11/13/18 Mason[28],Unskilled Labour[28]
floor level
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: Kandy project program
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Tue 10/2/18
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress
67 piping for water supply and 10 days Tue 11/27/18 Thu 12/6/18 Pumber[10],Unskilled Labour[10]
sewerage inside of the building
68 Conduiting and wiring electrical 10 days Tue 11/27/18 Thu 12/6/18 Electrician[10],Unskilled Labour[10]
work
69 Conduiting and wiring for fire alarm 10 days Tue 11/27/18 Thu 12/6/18 Electrician[10],Unskilled Labour[8]
and fire detection system
installation
70 Conduiting and wiring for CCTV 10 days Tue 11/27/18 Thu 12/6/18 CCTV Technician[10],Unskilled Labour[10]
system
71 Conduiting and wiring for public 10 days Tue 11/27/18 Thu 12/6/18 Electrician[10],Unskilled Labour[10]
address system
72 Water supply,sewerage and waste 8 days Mon 1/7/19 Mon 1/14/19 Pumber[45],Un
water external works
73 Construction of septic tank,sockage 6 days Mon 1/7/19 Sat 1/12/19 Mason[30],Unsk
pit and sump
74 Installation of sanitory fittings and 7 days Mon 1/7/19 Sun 1/13/19 Pumber[24],Un
accesaries
75 Installation of electrical fittings and 8 days Mon 1/7/19 Mon 1/14/19 Electrician[22]
D board
76 Installation of fire potection and 9 days Mon 1/7/19 Tue 1/15/19 Fire technician
detection system
77 Installation and fixing public address 6 days Mon 1/7/19 Sat 1/12/19 CCTV Technician
system and CCTV system
80 Water proofing bath room and roof 7 days Wed 12/19/18 Tue 12/25/18 Skilled Labour[14],Unskilled Lab
slab
81 Plastering (external wall) 6 days Sat 12/8/18 Thu 12/13/18 Mason[28],Unskilled Labour[56]
82 Plinth plater 7 days Fri 12/14/18 Thu 12/20/18 Skilled Labour[7],Unskilled Labour[14
83 Aluminium works 20 days Fri 12/14/18 Wed 1/2/19 Skilled Labour[60],Unskill
84 Wall tiling bathroom area 12 days Thu 12/13/18 Mon 12/24/18 Tiling Mason[24],Unskilled Labou
85 Floor tiling 13 days Tue 12/25/18 Sun 1/6/19 Tiling Mason[39],Unsk
86 Ceiling finishes 5 days Wed 12/19/18 Sun 12/23/18 Skilled Labour[10],Unskilled Labou
87 Hand railing and steel staircase 8 days Wed 11/14/18 Wed 11/21/18 Skilled Labour[16],Unskilled Labour[32]
88 External works paving and aspalt 31 days Fri 12/7/18 Sun 1/6/19
surfacing including drain,turfing,paving
91 Final touchup works 8 days Fri 12/28/18 Fri 1/4/19 Skilled Labour[10],Unsk
92 Site clearing befor handing over 8 days Fri 12/28/18 Fri 1/4/19 Skilled Labour[10],Unsk
93 Handing over the project 1 day Sat 1/5/19 Sat 1/5/19 1/5
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: Kandy project program
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Tue 10/2/18
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress