Sadas S
Sadas S
Sadas S
A. SHIELLA PRIETO
1 ASDEC
Prepared by:
RUSSEL MORALES
Construction Manager (CM)
MANHOURS FOR THE PERIOD
ACCOMPLISHMENT
Indirect Manpower Direct Manpower Total MH
Quantity of
Admin Skilled Item Done
Foreman Leadman Laborers Indirect Direct UOM
Support Workers for the
Period
Noted by:
JULIUS V. RAMOS
Project Manager (PM)
PROJECT The Arton Strip By Rockwell
WORK PACKAGE General Construction Works
PERIOD COVERED June 11, 2018 - June 16, 2018
Noted by:
JULIUS V. RAMOS
Project Manager (PM)
PROJECT The Arton Strip By Rockwell
WORK PACKAGE General Construction Works
PERIOD COVERED June 18, 2018 - June 23, 2018
Noted by:
JULIUS V. RAMOS
Project Manager (PM)
PROJECT The Arton Stop By Rockwell
WORK PACKAGE General Construction Works
PERIOD COVERED June 25, 2018 - June 30, 2018
.0.
OURS FOR THE PERIOD
ACCOMPLISHMENT
Direct Manpower Total MH
Labor
Quantity of Unit
Productivity Rate/man
Skilled Item Done rate/sqm
Laborers Indirect Direct UOM Index hour
Workers for the
(mh/uom)
Period
Noted by:
JULIUS V. RAMOS
Project Manager (PM)
PROJECT The Arton Stop By Rockwell
WORK PACKAGE General Construction Works
PERIOD COVERED July 2, 2018 - July 7, 2018
Noted by:
Noted by:
Noted by:
Noted by:
A. EUGENE MAYOR
1 ADMIN
SUPPLY OF LABOR, TOOLS, EQUIPMENT AND FULL TIME
SUPERVISION FOR INSTALLATION AND STRIPPING OF
FORMWORKS SYSTEM
C-1 (BLOCK 1) (C/3) 0.00 0.00 2.00
RW-2A (BLOCK 1) (B-C/2-3) 0.00 0.00 4.00
CTW-1 (BLOCK 1) (B-D/2-3) Provisional 0.00 0.00 40.00
FORMWORKS
C-5 (BLOCK 2) (F/1) Sum 0.00 0.00 2.00
C-5 (BLOCK 2) (G/1) 0.00 0.00 2.00
RW-1 (BLOCK 2) (E-H/1) 0.00 0.00 10.00
Noted by:
LABOR
DATE MANPOWER QTY HOURS MAN-HOURS LABOR RATE AMOUNT
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 1 8 8 ₱75.00 ₱600.00
May 31, 2018
CARPENTER 3 8 24 ₱64.00 ₱1,536.00
SUBTOTAL ₱2,736.00
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 0 8 0 ₱75.00 ₱0.00
June 1, 2018
CARPENTER 3 8 24 ₱64.00 ₱1,536.00
SUBTOTAL ₱2,136.00
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 0 8 0 ₱75.00 ₱0.00
June 2, 2018
CARPENTER 3 8 24 ₱64.00 ₱1,536.00
SUBTOTAL ₱2,136.00
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 0 8 0 ₱75.00 ₱0.00
June 5, 2018
CARPENTER 2 8 16 ₱64.00 ₱1,024.00
SUBTOTAL ₱1,624.00
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 0 8 0 ₱75.00 ₱0.00
June 6, 2018
CARPENTER 2 8 16 ₱64.00 ₱1,024.00
SUBTOTAL ₱1,624.00
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 0 8 0 ₱75.00 ₱0.00
June 7, 2018
CARPENTER 2 8 16 ₱64.00 ₱1,024.00
SUBTOTAL ₱1,624.00
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 0 8 0 ₱75.00 ₱0.00
June 8, 2018
CARPENTER 3 8 24 ₱64.00 ₱1,536.00
SUBTOTAL ₱2,136.00
TOTAL ₱14,016.00
ACCOMPLISHMENT
DATE STRUCTURE/BLOCK/GRIDLINE AREA (m2) COST PER SQM AMOUNT REMARKS
June 2, 2018 C-4 (BLOCK 2) (G.L. F/2) (1ST LIFT) 7.20 ₱205.47 ₱1,479.38 NOT YET STRIPPED
June 5, 2018 C-4 (BLOCK 2) (G.L. F/3) (1ST LIFT) 6.48 ₱205.47 ₱1,331.45 NOT YET STRIPPED
June 6, 2018 C-6 (BLOCK 2) (G.L. G/2) (1ST LIFT) 7.20 ₱205.47 ₱1,479.38 NOT YET STRIPPED
June 8, 2018 C-1 (BLOCK 1) (G.L. B/2) (1ST LIFT) 5.76 ₱205.47 ₱1,183.51 NOT YET STRIPPED
June 8, 2018 C-1 (BLOCK 1) (G.L. B/3) (1ST LIFT) 5.76 ₱205.47 ₱1,183.51 NOT YET STRIPPED
TOTAL 32.40 ₱6,657.23
* P 255.47 unit cost per sqm minus P 50.00 for stripping = P205.47
LABOR VS. ACCOMPLISHMENT
LABOR
DATE MANPOWER QTY HOURS MAN-HOURS LABOR RATE AMOUNT
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 8 0 ₱75.00 ₱0.00
June 11, 2018
CARPENTER 2 8 16 ₱64.00 ₱1,024.00
SUBTOTAL ₱1,624.00
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 8 0 ₱75.00 ₱0.00
June 14, 2018
CARPENTER 2 8 16 ₱64.00 ₱1,024.00
SUBTOTAL ₱1,624.00
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 8 0 ₱75.00 ₱0.00
June 16, 2018
CARPENTER 3 8 24 ₱64.00 ₱1,536.00
SUBTOTAL ₱2,136.00
TOTAL ₱5,384.00
ACCOMPLISHMENT
DATE STRUCTURE/BLOCK/GRIDLINE AREA (m2) COST PER SQM AMOUNT REMARKS
June 16, 2018 C-4 (BLOCK 2) (G.L. F/2) (1ST LIFT) 7.20 ₱50.00 ₱360.00 STRIPPING OK
June 16, 2018 C-4 (BLOCK 2) (G.L. F/3) (1ST LIFT) 6.48 ₱50.00 ₱324.00 STRIPPING OK
June 16, 2018 C-6 (BLOCK 2) (G.L. G/2) (1ST LIFT) 7.20 ₱50.00 ₱360.00 STRIPPING OK
June 16, 2018 C-16 (BLOCK 2) (G.L. G/3) (1ST LIFT) 6.48 ₱205.47 ₱1,331.45 NOT YET STRIPPED
June 16, 2018 C-1 (BLOCK 1) (G.L. A/3) (1ST LIFT) 5.76 ₱205.47 ₱1,183.51 NOT YET STRIPPED
TOTAL 33.12 ₱3,558.95
* P 255.47 unit cost per sqm minus P 50.00 for stripping = P205.47
LABOR VS. ACCOMPLISHMENT
LABOR
DATE MANPOWER QTY HOURS MAN-HOURS LABOR RATE AMOUNT
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 0 ₱75.00 ₱0.00
June 18, 2018
CARPENTER 3 8 24 ₱64.00 ₱1,536.00
SUBTOTAL ₱2,136.00
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 0 ₱75.00 ₱0.00
June 19, 2018
CARPENTER 3 8 24 ₱64.00 ₱1,536.00
SUBTOTAL ₱2,136.00
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 0 ₱75.00 ₱0.00
June 20, 2018
CARPENTER 4 8 32 ₱64.00 ₱2,048.00
SUBTOTAL ₱2,648.00
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 0 ₱75.00 ₱0.00
June 21, 2018
CARPENTER 2 8 16 ₱64.00 ₱1,024.00
SUBTOTAL ₱1,624.00
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 0 ₱75.00 ₱0.00
June 22, 2018
CARPENTER 2 8 16 ₱64.00 ₱1,024.00
SUBTOTAL ₱1,624.00
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 0 ₱75.00 ₱0.00
June 23, 2018
CARPENTER 2 8 16 ₱64.00 ₱1,024.00
SUBTOTAL ₱1,624.00
TOTAL ₱11,792.00
ACCOMPLISHMENT
DATE STRUCTURE/BLOCK/GRIDLINE AREA (m2) COST PER SQM AMOUNT REMARKS
June 19, 2018 C-1 (BLOCK 1) (G.L. B/2) (1ST LIFT) 5.76 ₱50.00 ₱288.00 STRIPPING OK
June 19, 2018 C-1 (BLOCK 1) (G.L. B/3) (1ST LIFT) 5.76 ₱50.00 ₱288.00 STRIPPING OK
June 19, 2018 C-1 (BLOCK 1) (G.L. A/3) (1ST LIFT) 5.76 ₱50.00 ₱288.00 STRIPPING OK
June 20, 2018 C-16 (BLOCK 2) (G.L. G/3) (1ST LIFT) 6.48 ₱50.00 ₱324.00 STRIPPING OK
June 21, 2018 C-4 (BLOCK 2) (G.L. F/4) (1ST LIFT) 7.20 ₱255.47 ₱1,839.38 STRIPPING OK
June 22, 2018 C-13 (BLOCK 2) (G.L. F/5) (1ST LIFT) 7.20 ₱255.47 ₱1,839.38 STRIPPING OK
TOTAL 38.16 ₱4,866.77
* P 255.47 unit cost per sqm minus P 50.00 for stripping = P205.47
LABOR VS. ACCOMPLISHMENT
LABOR
DATE MANPOWER QTY HOURS MAN-HOURS LABOR RATE AMOUNT
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 0 ₱75.00 ₱0.00
June 25, 2018
CARPENTER 3 8 24 ₱64.00 ₱1,536.00
SUBTOTAL ₱2,136.00
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 0 ₱75.00 ₱0.00
June 26, 2018
CARPENTER 3 8 24 ₱64.00 ₱1,536.00
SUBTOTAL ₱2,136.00
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 0 ₱75.00 ₱0.00
June 27, 2018
CARPENTER 2 8 16 ₱64.00 ₱1,024.00
SUBTOTAL ₱1,624.00
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 0 ₱75.00 ₱0.00
June 28, 2018
CARPENTER 6 8 48 ₱64.00 ₱3,072.00
SUBTOTAL ₱3,672.00
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 0 ₱75.00 ₱0.00
June 29, 2018
CARPENTER 6 8 48 ₱64.00 ₱3,072.00
SUBTOTAL ₱3,672.00
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 0 ₱75.00 ₱0.00
June 30, 2018
CARPENTER 6 8 48 ₱64.00 ₱3,072.00
SUBTOTAL ₱3,672.00
TOTAL ₱16,912.00
ACCOMPLISHMENT
DATE STRUCTURE/BLOCK/GRIDLINE AREA (m2) COST PER SQM AMOUNT REMARKS
June 27, 2018 CTW-1 (BLOCK 1) (G.L. E/1-2) (ZOCALLO) 2.88 ₱300.00 ₱864.00 STRIPPING OK
June 28, 2018 CTW-2 (BLOCK 1) (G.L. B-E/1-2) (ZOCALLO) 10.46 ₱300.00 ₱3,138.00 STRIPPING OK
June 28, 2018 RW-2 (BLOCK 1) (G.L. B-E/1) (ZOCALLO) 5.88 ₱300.00 ₱1,764.00 STRIPPING OK
June 28, 2018 SUMP PIT WALL (BLOCK 2) (G.L. H/1) (1ST LIFT) 17.64 ₱250.00 ₱4,410.00 NOT YET STRIPPED
* P 300.00 unit cost per sqm minus P 50.00 for stripping = P250.00
LABOR VS. ACCOMPLISHMENT
LABOR
DATE MANPOWER QTY HOURS MAN-HOURS LABOR RATE AMOUNT
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 1 8 8 ₱75.00 ₱600.00
July 2, 2018
CARPENTER 7 8 56 ₱64.00 ₱3,584.00
SUBTOTAL ₱4,784.00
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 1 8 8 ₱75.00 ₱600.00
July 3, 2018
CARPENTER 7 8 56 ₱64.00 ₱3,584.00
SUBTOTAL ₱4,784.00
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 1 8 8 ₱75.00 ₱600.00
July 4, 2018
CARPENTER 7 8 56 ₱64.00 ₱3,584.00
SUBTOTAL ₱4,784.00
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 1 8 8 ₱75.00 ₱600.00
July 5, 2018
CARPENTER 7 8 56 ₱64.00 ₱3,584.00
SUBTOTAL ₱4,784.00
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 1 8 8 ₱75.00 ₱600.00
July 6, 2018
CARPENTER 7 8 56 ₱64.00 ₱3,584.00
SUBTOTAL ₱4,784.00
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 1 8 8 ₱75.00 ₱600.00
July 7, 2018
CARPENTER 7 8 56 ₱64.00 ₱3,584.00
SUBTOTAL ₱4,784.00
TOTAL ₱28,704.00
ACCOMPLISHMENT
DATE STRUCTURE/BLOCK/GRIDLINE AREA (m2) COST PER SQM AMOUNT REMARKS
July 2, 2018 CTW-1 (BLOCK 1) (G.L. E/1-2) (ZOCALLO) 33.73 ₱300.00 ₱10,119.00 STRIPPING OK
July 2, 2018 CTW-2 (BLOCK 1) (G.L. B-E/1-2) (ZOCALLO) 19.57 ₱300.00 ₱5,871.00 STRIPPING OK
July 2, 2018 CTW-3 (BLOCK 1) (G.L. B-C/2) (ZOCALLO) 1.69 ₱300.00 ₱507.00 STRIPPING OK
July 2, 2018 RW-2 (BLOCK 1) (G.L. B-C/2-3) (ZOCALLO) 0.22 ₱300.00 ₱66.00 STRIPPING OK
July 3, 2018 RW-3 (BLOCK 1) (B-C/1-2) (ZOCALLO) 2.52 ₱300.00 ₱756.00 STRIPPING OK
July 3, 2018 CTW-4 (BLOCK 1) (G.L. B-C/2-3) 13.18 ₱300.00 ₱3,954.00 STRIPPING OK
July 3, 2018 KICKER (MF-1) (BLOCK 1) (B-E/1-2) 6.78 ₱250.00 ₱1,695.00 STRIPPING OK
July 3, 2018 TRENCH (MF-1) (BLOCK 1) (B-3/2-3) 33.33 ₱250.00 ₱8,332.50 STRIPPING OK
July 4-6, 2018 CTW-2 (GANG FORM FABRICATION) 125.10 FABRICATION ONLY
(BLOCK 1) (G.L. B-E/1-2) (1ST LIFT)
TOTAL 236.12 ₱31,300.50
* P 300.00 unit cost per sqm minus P 50.00 for stripping = P250.00
LABOR VS. ACCOMPLISHMENT
LABOR
DATE MANPOWER QTY HOURS MAN-HOURS LABOR RATE AMOUNT
SAFETY 1 10 10 ₱75.00 ₱750.00
FOREMAN 1 10 10 ₱75.00 ₱750.00
July 9, 2018
CARPENTER 7 10 70 ₱64.00 ₱4,480.00
SUBTOTAL ₱5,980.00
SAFETY 1 10 10 ₱75.00 ₱750.00
FOREMAN 1 10 10 ₱75.00 ₱750.00
July 10, 2018
CARPENTER 12 10 120 ₱64.00 ₱7,680.00
SUBTOTAL ₱9,180.00
SAFETY 1 10 10 ₱75.00 ₱750.00
FOREMAN 1 10 10 ₱75.00 ₱750.00
July 11, 2018
CARPENTER 10 10 100 ₱64.00 ₱6,400.00
SUBTOTAL ₱7,900.00
SAFETY 1 10 10 ₱75.00 ₱750.00
FOREMAN 1 10 10 ₱75.00 ₱750.00
July 12, 2018
CARPENTER 10 10 100 ₱64.00 ₱6,400.00
SUBTOTAL ₱7,900.00
SAFETY 1 10 10 ₱75.00 ₱750.00
FOREMAN 1 10 10 ₱75.00 ₱750.00
July 13, 2018
CARPENTER 13 10 130 ₱64.00 ₱8,320.00
SUBTOTAL ₱9,820.00
SAFETY 1 10 10 ₱75.00 ₱750.00
FOREMAN 1 10 10 ₱75.00 ₱750.00
July 14, 2018
CARPENTER 14 10 140 ₱64.00 ₱8,960.00
SUBTOTAL ₱10,460.00
TOTAL ₱51,240.00
ACCOMPLISHMENT
DATE STRUCTURE/BLOCK/GRIDLINE AREA (m2) COST PER SQM AMOUNT REMARKS
July 10, 2018 CTW-1 (BLOCK 1) (G.L. E/1-2) 59.55 ₱250.00 ₱14,887.50 NOT YET STRIPPED
July 11, 2018 CTW-2 (BLOCK 1) (G.L. B-E/1-2) 83.04 ₱250.00 ₱20,760.00 NOT YET STRIPPED
July 12, 2018 RW-2 (BLOCK 1) (G.L. B-C/2-3) 84.72 ₱250.00 ₱21,180.00 NOT YET STRIPPED
July 13, 2018 C-5 (BLOCK 1) (D/1) 4.80 ₱250.00 ₱1,200.00 NOT YET STRIPPED
July 13, 2018 C-5 (BLOCK 1) (E/1) 4.80 ₱250.00 ₱1,200.00 NOT YET STRIPPED
July 13, 2018 C-1 (BLOCK 1) (C/1) 1.98 ₱250.00 ₱495.00 NOT YET STRIPPED
TOTAL 227.31 ₱56,827.50
* P 300.00 unit cost per sqm minus P 50.00 for stripping = P250.00
LABOR VS. ACCOMPLISHMENT
LABOR
DATE MANPOWER QTY HOURS MAN-HOURS LABOR RATE AMOUNT
FOREMAN 1 12 12 ₱75.00 ₱900.00
LEADMAN 1 12 12 ₱75.00 ₱900.00
July 9, 2018
CARPENTER 7 12 84 ₱64.00 ₱5,376.00
SUBTOTAL ₱7,176.00
FOREMAN 1 12 12 ₱75.00 ₱900.00
LEADMAN 1 12 12 ₱75.00 ₱900.00
July 10, 2018
CARPENTER 6 12 72 ₱64.00 ₱4,608.00
SUBTOTAL ₱6,408.00
FOREMAN 1 12 12 ₱75.00 ₱900.00
LEADMAN 1 12 12 ₱75.00 ₱900.00
July 11, 2018
CARPENTER 7 12 84 ₱64.00 ₱5,376.00
SUBTOTAL ₱7,176.00
FOREMAN 1 12 12 ₱75.00 ₱900.00
LEADMAN 1 12 12 ₱75.00 ₱900.00
July 12, 2018
CARPENTER 6 12 72 ₱64.00 ₱4,608.00
SUBTOTAL ₱6,408.00
FOREMAN 1 12 12 ₱75.00 ₱900.00
LEADMAN 1 12 12 ₱75.00 ₱900.00
July 13, 2018
CARPENTER 10 12 120 ₱64.00 ₱7,680.00
SUBTOTAL ₱9,480.00
FOREMAN 1 8 8 ₱75.00 ₱600.00
LEADMAN 1 8 8 ₱75.00 ₱600.00
July 14, 2018
CARPENTER 9 8 72 ₱64.00 ₱4,608.00
SUBTOTAL ₱5,808.00
TOTAL ₱42,456.00
ACCOMPLISHMENT
DATE STRUCTURE/BLOCK/GRIDLINE AREA (m2) COST PER SQM AMOUNT REMARKS
July 12, 2018 CTW-2 (BLOCK 1) (G.L. B-D/1-2) 112.95 ₱250.00 ₱28,237.50 NOT YET STRIPPED
July 12, 2018 CTW-3 (BLOCK 1) (G.L. B-C/2) 12.69 ₱250.00 ₱3,172.50 NOT YET STRIPPED
July 13, 2018 RW-2 (BLOCK 1) (G.L. B-D/1-2) 35.10 ₱250.00 ₱8,775.00 NOT YET STRIPPED
July 14, 2018 RW-3 (BLOCK 1) (G.L. B-C/1-2) 30.03 ₱250.00 ₱7,507.50 NOT YET STRIPPED
* P 300.00 unit cost per sqm minus P 50.00 for stripping = P250.00
LABOR VS. ACCOMPLISHMENT
LABOR
DATE MANPOWER QTY HOURS MAN-HOURS LABOR RATE AMOUNT
SAFETY 1 8 8 ₱75.00 ₱600.00
FOREMAN 1 8 8 ₱75.00 ₱600.00
July 16, 2018
CARPENTER 13 8 104 ₱64.00 ₱6,656.00
SUBTOTAL ₱7,856.00
SAFETY 1 4 4 ₱75.00 ₱300.00
FOREMAN 0 0 0 ₱75.00 ₱0.00
July 17, 2018
CARPENTER 0 0 0 ₱64.00 ₱0.00
SUBTOTAL ₱300.00
SAFETY 1 12 12 ₱75.00 ₱900.00
FOREMAN 1 12 12 ₱75.00 ₱900.00
July 18, 2018
CARPENTER 12 12 144 ₱64.00 ₱9,216.00
SUBTOTAL ₱11,016.00
SAFETY 1 12 12 ₱75.00 ₱900.00
FOREMAN 1 12 12 ₱75.00 ₱900.00
July 19, 2018
CARPENTER 13 12 156 ₱64.00 ₱9,984.00
SUBTOTAL ₱11,784.00
SAFETY 1 12 12 ₱75.00 ₱900.00
FOREMAN 1 12 12 ₱75.00 ₱900.00
July 20, 2018
CARPENTER 14 12 168 ₱64.00 ₱10,752.00
SUBTOTAL ₱12,552.00
SAFETY 1 12 12 ₱75.00 ₱900.00
FOREMAN 1 12 12 ₱75.00 ₱900.00
July 21, 2018
CARPENTER 15 12 180 ₱64.00 ₱11,520.00
SUBTOTAL ₱13,320.00
TOTAL ₱56,828.00
ACCOMPLISHMENT
DATE STRUCTURE/BLOCK/GRIDLINE AREA (m2) COST PER SQM AMOUNT REMARKS
July 20, 2018 C-4 (BLOCK 1) (G.L. E/3) 4.03 ₱250.00 ₱1,007.50 NOT YET STRIPPED
July 20, 2018 C-8A (BLOCK 1) (G.L. D/3) 3.67 ₱250.00 ₱917.50 NOT YET STRIPPED
July 21, 2018 CTW-1 (BLOCK 1) (G.L. D-E/2-4) 89.00 ₱250.00 ₱22,250.00 NOT YET STRIPPED
* P 300.00 unit cost per sqm minus P 50.00 for stripping = P250.00
LABOR VS. ACCOMPLISHMENT
LABOR
DATE MANPOWER QTY HOURS MAN-HOURS LABOR RATE AMOUNT
FOREMAN 1 8 8 ₱75.00 ₱600.00
LEADMAN 1 8 8 ₱75.00 ₱600.00
July 16, 2018
CARPENTER 10 8 80 ₱64.00 ₱5,120.00
SUBTOTAL ₱6,320.00
FOREMAN 0 0 0 ₱75.00 ₱0.00
LEADMAN 0 0 0 ₱75.00 ₱0.00
July 17, 2018
CARPENTER 0 0 0 ₱64.00 ₱0.00
SUBTOTAL ₱0.00
FOREMAN 1 12 12 ₱75.00 ₱900.00
LEADMAN 1 12 12 ₱75.00 ₱900.00
July 18, 2018
CARPENTER 10 12 120 ₱64.00 ₱7,680.00
SUBTOTAL ₱9,480.00
FOREMAN 1 12 12 ₱75.00 ₱900.00
LEADMAN 1 12 12 ₱75.00 ₱900.00
July 19, 2018
CARPENTER 10 12 120 ₱64.00 ₱7,680.00
SUBTOTAL ₱9,480.00
FOREMAN 1 12 12 ₱75.00 ₱900.00
LEADMAN 1 12 12 ₱75.00 ₱900.00
July 20, 2018
CARPENTER 10 12 120 ₱64.00 ₱7,680.00
SUBTOTAL ₱9,480.00
FOREMAN 1 12 12 ₱75.00 ₱900.00
LEADMAN 1 12 12 ₱75.00 ₱900.00
July 21, 2018
CARPENTER 10 12 120 ₱64.00 ₱7,680.00
SUBTOTAL ₱9,480.00
TOTAL ₱44,240.00
ACCOMPLISHMENT
DATE STRUCTURE/BLOCK/GRIDLINE AREA (m2) COST PER SQM AMOUNT REMARKS
July 20, 2018 C-1 (BLOCK 1) (G.L. C/3) 3.12 ₱250.00 ₱780.00 NOT YET STRIPPED
July 20, 2018 RW-2A (BLOCK 1) (G.L. B-C/2-3) 8.79 ₱250.00 ₱2,197.50 NOT YET STRIPPED
July 21, 2018 CTW-1 (BLOCK 1) (G.L. B-D/2-3) 70.98 ₱250.00 ₱17,745.00 NOT YET STRIPPED
July 19, 2018 C-5 (BLOCK 2) (G.L. F/1) 3.60 ₱250.00 ₱900.00 NOT YET STRIPPED
July 20, 2018 C-5 (BLOCK 2) (G.L.G/1) 3.60 ₱250.00 ₱900.00 NOT YET STRIPPED
July 21, 2018 RW-1 (BLOCK 2) (G.L. E-H/1) 30.60 ₱250.00 ₱7,650.00 NOT YET STRIPPED
TOTAL 120.69 ₱21,622.50
* P 300.00 unit cost per sqm minus P 50.00 for stripping = P250.00
PROJECT The Arton Strip
WORK PACKAGE General Construction Works
PERIOD COVERED July 23, 2018 - July 28, 2018
A. EUGENE MAYOR
1 ADMIN
SUPPLY OF LABOR, TOOLS, EQUIPMENT AND FULL TIME
SUPERVISION FOR INSTALLATION AND STRIPPING OF
FORMWORKS SYSTEM
RW-3 (BLOCK 1) (A-B/4) 0.00 0.00 18.00
RW-3 (BLOCK 1) (B-C/3-4) 0.00 0.00 24.00
C-22 (BLOCK 1) (A/4) 0.00 0.00 2.00
C-21 (BLOCK 1) (B/4) 0.00 0.00 2.00
RW-1 (BLOCK 1) (A/4-5) 0.00 0.00 2.00
SLABS
B2S-2 (BLOCK 1) (B-E/1-3) 0.00 0.00 4.00
B2S-3 (BLOCK 1) (B-D/1-3) 0.00 0.00 8.00
B2S-4 (BLOCK 1) (B-C/1-2) 0.00 0.00 2.00
Noted by:
LABOR
DATE MANPOWER QTY HOURS MAN-HOURS LABOR RATE
FOREMAN 1 12 12 ₱87.50
LEADMAN 1 12 12 ₱81.25
July 23, 2018
CARPENTER 10 12 120 ₱64.00
SUBTOTAL
FOREMAN 1 12 12 ₱87.50
LEADMAN 1 12 12 ₱81.25
July 24, 2018
CARPENTER 10 12 120 ₱64.00
SUBTOTAL
FOREMAN 1 12 12 ₱87.50
LEADMAN 1 12 12 ₱81.25
July 25, 2018
CARPENTER 10 12 120 ₱64.00
SUBTOTAL
FOREMAN 1 12 12 ₱87.50
LEADMAN 1 12 12 ₱81.25
July 26, 2018
CARPENTER 10 12 120 ₱64.00
SUBTOTAL
FOREMAN 1 12 12 ₱87.50
LEADMAN 1 12 12 ₱81.25
July 27, 2018
CARPENTER 10 12 120 ₱64.00
SUBTOTAL
FOREMAN 1 8 8 ₱87.50
LEADMAN 1 8 8 ₱81.25
July 28, 2018
CARPENTER 10 8 80 ₱64.00
SUBTOTAL
TOTAL
ACCOMPLISHMENT
DATE STRUCTURE/BLOCK/GRIDLINE AREA (m2) COST PER SQM AMOUNT
July 23, 2018 C-1 (BLOCK 1) (G.L. C/3) 3.12 ₱50.00 ₱156.00
July 23, 2018 RW-2A (BLOCK 1) (G.L. B-C/2-3) 8.79 ₱50.00 ₱439.50
July 23, 2018 CTW-1 (BLOCK 1) (G.L. B-D/2-3) 70.98 ₱50.00 ₱3,549.00
July 23, 2018 C-5 (BLOCK 2) (G.L. F/1) 3.60 ₱50.00 ₱180.00
July 23, 2018 C-5 (BLOCK 2) (G.L.G/1) 3.60 ₱50.00 ₱180.00
July 23, 2018 RW-1 (BLOCK 2) (G.L. E-H/1) 30.60 ₱50.00 ₱1,530.00
July 25, 2018 RW-3 (BLOCK 1) (A-B/4) 37.18 ₱300.00 ₱11,153.40
July 25, 2018 RW-3 (BLOCK 1) (B-C/3-4) 55.97 ₱300.00 ₱16,791.00
July 25, 2018 C-22 (BLOCK 1) (A/4) 2.47 ₱300.00 ₱739.50
July 26, 2018 C-21 (BLOCK 1) (B/4) 3.48 ₱300.00 ₱1,044.00
July 26, 2018 RW-1 (BLOCK 1) (A/4-5) 4.35 ₱300.00 ₱1,305.00
July 24, 2018 B2G-1 (BLOCK 1) (B-C/1-2) 2.16 ₱250.00 ₱540.75
July 25, 2018 B2G-9 (BLOCK 1) (B-C/2) 1.98 ₱250.00 ₱495.00
July 26, 2018 B2G-11 (BLOCK 1) (B-C/3) 1.86 ₱250.00 ₱465.00
July 26, 2018 B2S-2 (BLOCK 1) (B-E/1-3) 27.23 ₱250.00 ₱6,807.50
July 27, 2018 B2S-3 (BLOCK 1) (B-D/1-3) 44.12 ₱250.00 ₱11,030.00
July 28, 2018 B2S-4 (BLOCK 1) (B-C/1-2) 4.32 ₱250.00 ₱1,080.00
TOTAL 305.81 ₱57,485.65
* P 300.00 unit cost per sqm minus P 50.00 for stripping = P250.00
R VS. ACCOMPLISHMENT
LABOR
AMOUNT
₱1,050.00
₱975.00
₱7,680.00
₱9,705.00
₱1,050.00
₱975.00
₱7,680.00
₱9,705.00
₱1,050.00
₱975.00
₱7,680.00
₱9,705.00
₱1,050.00
₱975.00
₱7,680.00
₱9,705.00
₱1,050.00
₱975.00
₱7,680.00
₱9,705.00
₱700.00
₱650.00
₱5,120.00
₱6,470.00
₱54,995.00
ACCOMPLISHMENT
REMARKS
STRIPPING OK
STRIPPING OK
STRIPPING OK
STRIPPING OK
STRIPPING OK
STRIPPING OK
STRIPPING OK
STRIPPING OK
STRIPPING OK
STRIPPING OK
STRIPPING OK
NOT YET STRIPPED
NOT YET STRIPPED
NOT YET STRIPPED
NOT YET STRIPPED
NOT YET STRIPPED
NOT YET STRIPPED
PROJECT The Arton Strip
WORK PACKAGE General Construction Works
PERIOD COVERED July 23, 2018 - July 28, 2018
BEAMS
Provisional
B2B-1 (BLOCK 1) (D-E/1-2) FORMWORKS 0.00 2.00 2.00
Sum
B2B-1 (BLOCK 1) (D-E/1-2) 0.00 2.00 2.00
B2B-2 (BLOCK 1) (D-E/2-3) 0.00 2.00 2.00
Provisional
FORMWORKS
Sum
SLABS
B2S-1 (BLOCK 1) (B-E/1-3) 0.00 4.00 4.00
B2S-2 (BLOCK 1) (B-E/1-3) 0.00 8.00 12.00
B2S-3 (BLOCK 1) (B-D/1-3) 0.00 4.00 4.00
Noted by:
LABOR
DATE MANPOWER QTY HOURS MAN-HOURS LABOR RATE
SAFETY 1 8 8 ₱75.00
FOREMAN 1 8 8 ₱75.00
July 23, 2018
CARPENTER 15 8 120 ₱64.00
SUBTOTAL
SAFETY 1 10 10 ₱75.00
FOREMAN 1 12 12 ₱75.00
July 24, 2018
CARPENTER 15 10.5 157.5 ₱64.00
SUBTOTAL
SAFETY 1 10 10 ₱75.00
FOREMAN 1 12 12 ₱75.00
July 25, 2018
CARPENTER 18 9 162 ₱64.00
SUBTOTAL
SAFETY 1 10 10 ₱75.00
FOREMAN 1 12 12 ₱75.00
July 26, 2018
CARPENTER 18 10 180 ₱64.00
SUBTOTAL
SAFETY 1 10 10 ₱75.00
FOREMAN 1 12 12 ₱75.00
July 27, 2018
CARPENTER 16 9 144 ₱64.00
SUBTOTAL
SAFETY 1 8 8 ₱75.00
FOREMAN 1 8 8 ₱75.00
July 28, 2018
CARPENTER 18 8 144 ₱64.00
SUBTOTAL
TOTAL
ACCOMPLISHMENT
DATE STRUCTURE/BLOCK/GRIDLINE AREA (m2) COST PER SQM AMOUNT
July 23, 2018 C-4 (BLOCK 1) (G.L. E/3) 3.12 ₱50.00 ₱156.00
July 23, 2018 C-8A (BLOCK 1) (G.L. D/3) 8.79 ₱50.00 ₱439.50
July 23, 2018 CTW-1 (BLOCK 1) (G.L. D-E/2-4) 70.98 ₱50.00 ₱3,549.00
July 28, 2018 RW-1 (BLOCK 2) (G-H/1) 13.68 ₱250.00 ₱3,420.00
July 28, 2018 RW-1 (BLOCK 2) (H/1-5) 140.38 ₱250.00 ₱35,094.38
July 28, 2018 C-14A (BLOCK 2) (H/1) 1.56 ₱250.00 ₱390.94
July 28, 2018 C-14 (BLOCK 2) (H/2-5) 10.80 ₱250.00 ₱2,700.00
July 24, 2018 B2G-6 (BLOCK 1) (C/2-3) 9.43 ₱250.00 ₱2,356.88
July 24, 2018 B2G-7 (BLOCK 1) (D/1-2) 10.04 ₱250.00 ₱2,509.00
July 24, 2018 B2G-8 (BLOCK 1) (H/2-3) 10.70 ₱250.00 ₱2,675.63
July 24, 2018 B2G-10 (BLOCK 1) (D-E/3) 7.18 ₱250.00 ₱1,794.38
July 25, 2018 B2B-1 (BLOCK 1) (D-E/1-2) 7.22 ₱250.00 ₱1,806.00
July 25, 2018 B2B-1 (BLOCK 1) (D-E/1-2) 7.22 ₱250.00 ₱1,806.00
July 25, 2018 B2B-2 (BLOCK 1) (D-E/2-3) 7.00 ₱250.00 ₱1,749.75
July 25, 2018 B2B-3 (BLOCK 1) (D-E/2-3) 7.22 ₱250.00 ₱1,806.00
July 26, 2018 B2B-4 (BLOCK 1) (C-D/2-3) 7.28 ₱250.00 ₱1,819.13
July 26, 2018 B2B-4 (BLOCK 1) (C-D/2-3) 7.28 ₱250.00 ₱1,819.13
July 26, 2018 B2B-5 (BLOCK 1) (D-E/2-3) 1.73 ₱250.00 ₱431.25
July 26, 2018 B2B-7 (BLOCK 1) (D-E/2-3) 2.00 ₱250.00 ₱498.75
July 26, 2018 B2B-7 (BLOCK 1) (D-E/2-3) 2.00 ₱250.00 ₱498.75
July 27, 2018 B2S-1 (BLOCK 1) (B-E/1-3) 40.20 ₱250.00 ₱10,050.00
July 28, 2018 B2S-2 (BLOCK 1) (B-E/1-3) 102.44 ₱250.00 ₱25,610.00
July 28, 2018 B2S-3 (BLOCK 1) (B-D/1-3) 20.75 ₱250.00 ₱5,187.50
TOTAL 498.98 ₱67,320.44
* P 300.00 unit cost per sqm minus P 50.00 for stripping = P250.00
R VS. ACCOMPLISHMENT
LABOR
AMOUNT
₱600.00
₱600.00
₱7,680.00
₱8,880.00
₱750.00
₱900.00
₱10,080.00
₱11,730.00
₱750.00
₱900.00
₱10,368.00
₱12,018.00
₱750.00
₱900.00
₱11,520.00
₱13,170.00
₱750.00
₱900.00
₱9,216.00
₱10,866.00
₱600.00
₱600.00
₱9,216.00
₱10,416.00
₱67,080.00
ACCOMPLISHMENT
REMARKS
STRIPPING OK
STRIPPING OK
STRIPPING OK
NOT YET STRIPPED
NOT YET STRIPPED
NOT YET STRIPPED
NOT YET STRIPPED
NOT YET STRIPPED
NOT YET STRIPPED
NOT YET STRIPPED
NOT YET STRIPPED
NOT YET STRIPPED
NOT YET STRIPPED
NOT YET STRIPPED
NOT YET STRIPPED
NOT YET STRIPPED
NOT YET STRIPPED
NOT YET STRIPPED
NOT YET STRIPPED
NOT YET STRIPPED
NOT YET STRIPPED
NOT YET STRIPPED
NOT YET STRIPPED
PROJECT The Arton Strip
WORK PACKAGE General Construction Works
PERIOD COVERED July 30, 2018 - August 5, 2018
GIRDERS (BASEMENT 1)
B1G-7 (BLOCK 1) (C/1-2) 0.00 1.00 2.20
B1G-8 (BLOCK 1) (C/2-3) 0.00 1.00 2.20
B1G-14 (BLOCK 1) (D/1-2) 0.00 1.00 2.20
B1G-15 (BLOCK 1) (E/1-2) 0.00 1.00 2.20
B1G-22 (BLOCK 1) (E/1-2) 0.00 1.00 2.20
B1G-23 (BLOCK 1) (E/2-3) 0.00 1.00 2.20
B1G-44 (BLOCK 1) (D-E/2) 0.00 1.00 2.20
B1G-45 (BLOCK 1) (C-D/2) 0.00 1.00 2.20
B1G-47 (BLOCK 1) (D-E/3) 0.00 1.00 2.20
B1G-48 (BLOCK 1) (C-D/2) 0.00 1.00 2.20
BEAMS (BASEMENT 1)
B1B-5 (BLOCK 1) (D-E/1-2) 0.00 1.00 2.20
B1B-7 (BLOCK 1) (C-D/1-2) 0.00 1.00 2.20
B1B-5 (BLOCK 1) (D-E/2-3) 0.00 1.00 2.20
B1B-7 (BLOCK 1) (C-D/1-2) 0.00 1.00 2.20
Provisional
FORMWORKS
Sum
B1B-5 (BLOCK 1) (D-E/2-3) 0.00 1.00 2.20
B1B-9 (BLOCK 1) (C-D/2-3) Provisional 0.00 1.00 2.20
FORMWORKS
B1B-5 (BLOCK 1) (D-E/2-3) Sum 0.00 1.00 2.20
B1B-9 (BLOCK 1) (C-D/2-3) 0.00 1.00 2.20
SLABS (BASEMENT 1)
B1S-5 (BLOCK 1) (C-D/2-3) 0.00 3.00 6.60
B1S-5 (BLOCK 1) (C-D/2-3) 0.00 3.00 6.60
Noted by:
LABOR
DATE MANPOWER QTY HOURS MAN-HOURS
SAFETY 1 8 8
FOREMAN 1 8 8
July 30, 2018
CARPENTER 22 8 176
SUBTOTAL
SAFETY 1 10 10
FOREMAN 2 12 24
July 31, 2018
CARPENTER 23 12 276
SUBTOTAL
SAFETY 1 12 12
FOREMAN 2 12 24
August 1, 2018
CARPENTER 24 12 288
SUBTOTAL
SAFETY 1 10 10
FOREMAN 1 10 10
August 2, 2018
CARPENTER 11 10 110
SUBTOTAL
SAFETY 1 12 12
FOREMAN 2 12 24
August 3, 2018
CARPENTER 14 12 168
SUBTOTAL
SAFETY 1 8 8
FOREMAN 2 8 16
August 4, 2018
CARPENTER 27 8 216
SUBTOTAL
SAFETY 0 8 0
FOREMAN 2 8 16
August 5, 2018
CARPENTER 19 8 152
SUBTOTAL
ACCOMPLISHMENT
DATE STRUCTURE/BLOCK/GRIDLINE AREA (m2) COST PER SQM
July 30, 2018 RW-1 (BLOCK 2) (G-H/1) 13.68 ₱50.00
July 30, 2018 RW-1 (BLOCK 2) (H/1-5) 140.38 ₱50.00
July 30, 2018 C-14A (BLOCK 2) (H/1) 1.56 ₱50.00
July 30, 2018 C-14 (BLOCK 2) (H/2-5) 10.80 ₱50.00
August 1, 2018 CTW-1 (BLOCK 1) (D-E/1-4) 43.3 ₱300.00
August 1, 2018 CTW-2 (BLOCK 1) (B-E/1-2) 33.24 ₱300.00
August 1, 2018 RW-2 (BLOCK 1) (B-E/1) 20.55 ₱300.00
August 1, 2018 C-15 (BLOCK 1) (D/1) 1.08 ₱300.00
August 1, 2018 C-15 (BLOCK 1) (E/1) 1.07 ₱300.00
August 1, 2018 C-16 (BLOCK 1) (D/2) 0.87 ₱300.00
August 1, 2018 C-16A (BLOCK 1) (D/3) 0.96 ₱300.00
August 1, 2018 C-17 (BLOCK 1) (E/2) 0.81 ₱300.00
August 1, 2018 C-17 (BLOCK 1) (E/3) 1.05 ₱300.00
August 2, 2018 C-21 (BLOCK 5) (C/4) 7.20 ₱300.00
August 2, 2018 C-3A (BLOCK 5) (C/5) 6.03 ₱300.00
August 2, 2018 C-3 (BLOCK 4) (D/4) 4.52 ₱300.00
August 2, 2018 C-12 (BLOCK 4) (D/5) 4.52 ₱300.00
August 2, 2018 C-4 (BLOCK 4) (E/4) 7.20 ₱300.00
August 2, 2018 C-11 (BLOCK 4) (E/5) 7.20 ₱300.00
August 4, 2018 C-21 (BLOCK 1) (C/2) 5.40 ₱300.00
August 4, 2018 C-21 (BLOCK 1) (C/3) 5.40 ₱300.00
August 4, 2018 C-16 (BLOCK 1) (D/2) 4.52 ₱300.00
August 4, 2018 C-16A (BLOCK 1) (D/3) 4.52 ₱300.00
August 4, 2018 C-17 (BLOCK 1) (E/2) 5.40 ₱300.00
August 4, 2018 C-17 (BLOCK 1) (E/3) 5.40 ₱300.00
August 4, 2018 B1G-7 (BLOCK 1) (C/1-2) 2.65 ₱250.00
August 4, 2018 B1G-8 (BLOCK 1) (C/2-3) 2.86 ₱250.00
August 4, 2018 B1G-14 (BLOCK 1) (D/1-2) 2.67 ₱250.00
August 4, 2018 B1G-15 (BLOCK 1) (E/1-2) 2.88 ₱250.00
August 4, 2018 B1G-22 (BLOCK 1) (E/1-2) 2.71 ₱250.00
August 4, 2018 B1G-23 (BLOCK 1) (E/2-3) 2.86 ₱250.00
August 4, 2018 B1G-44 (BLOCK 1) (D-E/2) 2.21 ₱250.00
August 4, 2018 B1G-45 (BLOCK 1) (C-D/2) 2.72 ₱250.00
August 4, 2018 B1G-47 (BLOCK 1) (D-E/3) 2.20 ₱250.00
August 4, 2018 B1G-48 (BLOCK 1) (C-D/2) 2.70 ₱250.00
August 4, 2018 B1B-5 (BLOCK 1) (D-E/1-2) 2.26 ₱250.00
August 4, 2018 B1B-7 (BLOCK 1) (C-D/1-2) 2.81 ₱250.00
August 4, 2018 B1B-5 (BLOCK 1) (D-E/2-3) 2.26 ₱250.00
August 4, 2018 B1B-7 (BLOCK 1) (C-D/1-2) 2.81 ₱250.00
August 4, 2018 B1B-5 (BLOCK 1) (D-E/2-3) 2.26 ₱250.00
August 4, 2018 B1B-9 (BLOCK 1) (C-D/2-3) 2.77 ₱250.00
August 4, 2018 B1B-5 (BLOCK 1) (D-E/2-3) 2.26 ₱250.00
August 4, 2018 B1B-9 (BLOCK 1) (C-D/2-3) 2.77 ₱250.00
August 5, 2018 B1S-5 (BLOCK 1) (C-D/2-3) 15.00 ₱250.00
August 5, 2018 B1S-5 (BLOCK 1) (C-D/2-3) 15.00 ₱250.00
TOTAL 413.32
* P 300.00 unit cost per sqm minus P 50.00 for stripping = P250.00
ABOR VS. ACCOMPLISHMENT
LABOR
LABOR RATE AMOUNT
₱75.00 ₱600.00
₱75.00 ₱600.00
₱64.00 ₱11,264.00
₱12,464.00
₱75.00 ₱750.00
₱75.00 ₱1,800.00
₱64.00 ₱17,664.00
₱20,214.00
₱75.00 ₱900.00
₱75.00 ₱1,800.00
₱64.00 ₱18,432.00
₱21,132.00
₱75.00 ₱750.00
₱75.00 ₱750.00
₱64.00 ₱7,040.00
₱8,540.00
₱75.00 ₱900.00
₱75.00 ₱1,800.00
₱64.00 ₱10,752.00
₱13,452.00
₱75.00 ₱600.00
₱75.00 ₱1,200.00
₱64.00 ₱13,824.00
₱15,624.00
₱75.00 ₱0.00
₱75.00 ₱1,200.00
₱64.00 ₱9,728.00
₱10,928.00
TOTAL ₱102,354.00
ACCOMPLISHMENT
AMOUNT REMARKS
₱684.00 STRIPPING OK
₱7,018.88 STRIPPING OK
₱78.19 STRIPPING OK
₱540.00 STRIPPING OK
₱12,990.00 STRIPPING OK
₱9,972.00 STRIPPING OK
₱6,165.00 STRIPPING OK
₱324.00 STRIPPING OK
₱322.38 STRIPPING OK
₱261.23 STRIPPING OK
₱287.75 STRIPPING OK
₱243.00 STRIPPING OK
₱313.88 STRIPPING OK
₱2,160.00 STRIPPING OK
₱1,809.00 STRIPPING OK
₱1,356.00 STRIPPING OK
₱1,356.00 STRIPPING OK
₱2,160.00 STRIPPING OK
₱2,160.00 STRIPPING OK
₱1,620.00 STRIPPING OK
₱1,620.00 STRIPPING OK
₱1,356.00 STRIPPING OK
₱1,356.00 STRIPPING OK
₱1,620.00 STRIPPING OK
₱1,620.00 STRIPPING OK
₱662.50 NOT YET STRIPPED
₱715.00 NOT YET STRIPPED
₱667.50 NOT YET STRIPPED
₱720.00 NOT YET STRIPPED
₱677.50 NOT YET STRIPPED
₱715.00 NOT YET STRIPPED
₱552.50 NOT YET STRIPPED
₱680.00 NOT YET STRIPPED
₱550.00 NOT YET STRIPPED
₱675.00 NOT YET STRIPPED
₱565.00 NOT YET STRIPPED
₱702.50 NOT YET STRIPPED
₱565.00 NOT YET STRIPPED
₱702.50 NOT YET STRIPPED
₱565.00 NOT YET STRIPPED
₱692.50 NOT YET STRIPPED
₱565.00 NOT YET STRIPPED
₱692.50 NOT YET STRIPPED
₱3,750.00 NOT YET STRIPPED
₱3,750.00 NOT YET STRIPPED
₱78,558.30
PROJECT The Arton Strip
WORK PACKAGE General Construction Works
PERIOD COVERED July 30, 2018 - August 5, 2018
GIRDERS (BASEMENT 2)
B2G-1 (BLOCK 1) (A-C/1-2) 0.00 0.00 6.00
B2G-2 (BLOCK 1) (A-B/2-3) 0.00 0.00 1.00
B2G-9 (BLOCK 1) (B-C/2) 0.00 0.00 1.00
Provisional
FORMWORKS
Sum
B2CG-1 (BLOCK 1) (A-B/2) 0.00 0.00 1.00
B2G-4 (BLOCK 1) (B/2-3) Provisional 0.00 0.00 1.00
FORMWORKS
B2G-11 (BLOCK 1) (B-C/3) Sum 0.00 0.00 1.00
B2G-12 (BLOCK 1) (A-B/3) 0.00 0.00 1.00
B2G-5 (BLOCK 1) (B/3-4) 0.00 0.00 1.00
B2G-3 (BLOCK 1) (A/3-4) 0.00 0.00 1.00
BEAMS (BASEMENT 2)
B2B-5 (BLOCK 1) (D-E/1-2) 0.00 0.00 1.00
B2B-5 (BLOCK 1) (C-D/1-2) 0.00 0.00 1.00
B2B-6 (BLOCK 1) (D-E/2-3) 0.00 0.00 1.00
B2B-2 (BLOCK 1) (C-D/1-2) 0.00 0.00 1.00
SLABS (BASEMENT 2)
B2S-1 (BLOCK 1) (A-B/3-4) 0.00 0.00 3.00
B2S-2 (BLOCK 1) (A-C/2-4) 0.00 0.00 11.00
B2S-3 (BLOCK 1) (A-B/2-3) 0.00 0.00 3.00
B2S-4 (BLOCK 1) (A-C/1-2) 0.00 0.00 1.00
Noted by:
LABOR
DATE MANPOWER QTY HOURS MAN-HOURS
FOREMAN 1 12 12
LEADMAN 1 12 12
July 30, 2018
CARPENTER 12 11 132
SUBTOTAL
FOREMAN 1 12 12
LEADMAN 2 12 24
July 31, 2018
CARPENTER 13 11 143
SUBTOTAL
FOREMAN 1 12 12
LEADMAN 2 12 24
August 1, 2018
CARPENTER 13 11 143
SUBTOTAL
FOREMAN 1 12 12
LEADMAN 1 12 12
August 2, 2018
CARPENTER 12 11 132
SUBTOTAL
FOREMAN 1 12 12
LEADMAN 2 12 24
August 3, 2018
CARPENTER 13 11 143
SUBTOTAL
FOREMAN 1 8 8
LEADMAN 1 8 8
August 4, 2018
CARPENTER 13 8 104
SUBTOTAL
ACCOMPLISHMENT
DATE STRUCTURE/BLOCK/GRIDLINE AREA (m2) COST PER SQM
July 30, 2018 CTW-1 (BLOCK 1) (D-E/1-4) 20.25 ₱250.00
July 30, 2018 CTW-2 (BLOCK 1) (B-E/1-2) 27.54 ₱250.00
July 30, 2018 CTW-3 (BLOCK 1) (B-E/1-2) 4.50 ₱250.00
July 31, 2018 RW-2 (BLOCK 1) (B-E/1-2) 5.07 ₱250.00
July 31, 2018 RW-2A (BLOCK 1) (B-E/1-2) 9 ₱250.00
July 31, 2018 RW-3 (BLOCK 1) (B-E/1-2) 16.81 ₱250.00
July 31, 2018 C-21 (BLOCK 1) (C-E/1) 3.06 ₱250.00
August 2, 2018 B2G-1 (BLOCK 1) (A-C/1-2) 18.92 ₱250.00
August 2, 2018 B2G-2 (BLOCK 1) (A-B/2-3) 2.77 ₱250.00
August 2, 2018 B2G-9 (BLOCK 1) (B-C/2) 0.83 ₱250.00
August 2, 2018 B2CG-1 (BLOCK 1) (A-B/2) 0.49 ₱250.00
August 2, 2018 B2G-4 (BLOCK 1) (B/2-3) 2.86 ₱250.00
August 3, 2018 B2G-11 (BLOCK 1) (B-C/3) 0.66 ₱250.00
August 3, 2018 B2G-12 (BLOCK 1) (A-B/3) 2.36 ₱250.00
August 3, 2018 B2G-5 (BLOCK 1) (B/3-4) 3.00 ₱250.00
August 3, 2018 B2G-3 (BLOCK 1) (A/3-4) 2.96 ₱250.00
August 3, 2018 B2B-5 (BLOCK 1) (D-E/1-2) 0.88 ₱250.00
August 3, 2018 B2B-5 (BLOCK 1) (C-D/1-2) 1.43 ₱250.00
August 3, 2018 B2B-6 (BLOCK 1) (D-E/2-3) 1.90 ₱250.00
August 4, 2018 B2B-2 (BLOCK 1) (C-D/1-2) 1.90 ₱250.00
August 4, 2018 B2S-1 (BLOCK 1) (A-B/3-4) 15.46 ₱250.00
August 4, 2018 B2S-2 (BLOCK 1) (A-C/2-4) 69.63 ₱250.00
August 4, 2018 B2S-3 (BLOCK 1) (A-B/2-3) 13.06 ₱250.00
August 4, 2018 B2S-4 (BLOCK 1) (A-C/1-2) 6.96 ₱250.00
TOTAL 232.30
* P 300.00 unit cost per sqm minus P 50.00 for stripping = P250.00
ABOR VS. ACCOMPLISHMENT
LABOR
LABOR RATE AMOUNT
₱75.00 ₱900.00
₱75.00 ₱900.00
₱64.00 ₱8,448.00
₱10,248.00
₱75.00 ₱900.00
₱75.00 ₱1,800.00
₱64.00 ₱9,152.00
₱11,852.00
₱75.00 ₱900.00
₱75.00 ₱1,800.00
₱64.00 ₱9,152.00
₱11,852.00
₱75.00 ₱900.00
₱75.00 ₱900.00
₱64.00 ₱8,448.00
₱10,248.00
₱75.00 ₱900.00
₱75.00 ₱1,800.00
₱64.00 ₱9,152.00
₱11,852.00
₱75.00 ₱600.00
₱75.00 ₱600.00
₱64.00 ₱6,656.00
₱7,856.00
TOTAL ₱63,908.00
ACCOMPLISHMENT
AMOUNT REMARKS
₱5,062.50 NOT YET STRIPPED
₱6,885.00 NOT YET STRIPPED
₱1,125.00 NOT YET STRIPPED
₱1,267.50 NOT YET STRIPPED
₱2,250.00 NOT YET STRIPPED
₱4,202.50 NOT YET STRIPPED
₱765.00 NOT YET STRIPPED
₱4,730.00 NOT YET STRIPPED
₱692.50 NOT YET STRIPPED
₱206.25 NOT YET STRIPPED
₱122.50 NOT YET STRIPPED
₱715.00 NOT YET STRIPPED
₱165.00 NOT YET STRIPPED
₱590.00 NOT YET STRIPPED
₱750.00 NOT YET STRIPPED
₱740.00 NOT YET STRIPPED
₱220.00 NOT YET STRIPPED
₱357.50 NOT YET STRIPPED
₱475.00 NOT YET STRIPPED
₱475.00 NOT YET STRIPPED
₱3,865.00 NOT YET STRIPPED
₱17,407.50 NOT YET STRIPPED
₱3,265.00 NOT YET STRIPPED
₱1,740.00 NOT YET STRIPPED
₱58,073.75
PROJECT The Arton Strip
WORK PACKAGE General Construction Works
PERIOD COVERED August 5, 2018 - August 12, 2018
GIRDERS (BASEMENT 1)
B1G-59 (BLOCK 2) (F/1-2) 0.00 1.00 2.00
B1G-21 (BLOCK 2) (G/1-2) 0.00 1.00 2.00
B1G-29 (BLOCK 2) (F/2-3) 0.00 1.00 2.00
B1G-35 (BLOCK 2) (G/2-3) 0.00 1.00 2.00
B1G-41 (BLOCK 2) (G-H/2) 0.00 1.00 2.00
Provisional
B1G-42 (BLOCK 2) (F-G/2) FORMWORKS 0.00 1.00 2.00
Sum
B1G-41 (BLOCK 2) (G-H/3) 0.00 1.00 2.00
B1G-42 (BLOCK 2) (F-G/3) 0.00 1.00 2.00
BEAMS (BASEMENT 1)
B1B-45 (BLOCK 2) (G-H/1-2) 0.00 1.00 2.00
B1B-4 (BLOCK 2) (G-H/1-2) 0.00 1.00 2.00
B1B-3 (BLOCK 2) (G-H/1-2) 0.00 1.00 2.00
B1B-4 (BLOCK 2) (F-G/1-2) 0.00 1.00 2.00
B1B-5 (BLOCK 2) (F-G/1-2) 0.00 1.00 2.00
B1B-4 (BLOCK 2) (G-H/2-3) 0.00 1.00 2.00
B1B-5 (BLOCK 2) (F-G/2-3) 0.00 1.00 2.00
B1B-4 (BLOCK 2) (G-H/2-3) 0.00 1.00 2.00
B1B-5 (BLOCK 2) (F-G/2-3) 0.00 1.00 2.00
SLABS (BASEMENT 1)
B1S-3 (BLOCK 2) (F-H/1-2) 0.00 7.00 14.00
B1S-5 (BLOCK 2) (F-H/1-3) 0.00 12.00 24.00
B1S-6 (BLOCK 2) (F-G/1-2) 0.00 4.00 7.00
Noted by:
LABOR
DATE MANPOWER QTY HOURS MAN-HOURS
SAFETY 1 10 10
FOREMAN 1 11 11
August 6, 2018
CARPENTER 26 11 286
SUBTOTAL
SAFETY 1 10 10
FOREMAN 2 11 22
August 7, 2018
CARPENTER 33 11 363
SUBTOTAL
SAFETY 1 10 10
FOREMAN 2 11 22
August 8, 2018
CARPENTER 24 11 264
SUBTOTAL
SAFETY 1 10 10
FOREMAN 2 11 22
August 9, 2018
CARPENTER 26 11 286
SUBTOTAL
SAFETY 1 10 10
FOREMAN 2 11 22
August 10, 2018
CARPENTER 27 11 297
SUBTOTAL
SAFETY 1 8 8
FOREMAN 2 8 16
August 11, 2018
CARPENTER 26 8 208
SUBTOTAL
SAFETY 0 0 0
FOREMAN 0 0 0
August 12, 2018
CARPENTER 0 0 0
SUBTOTAL
1877
ACCOMPLISHMENT
DATE STRUCTURE/BLOCK/GRIDLINE AREA (m2) COST PER SQM
RETAINING WALLS (BASEMENT 2 - BASEMENT 1)
August 11, 2018 RW-2 (BLOCK 1) (B-F/1) 92.32 ₱300.00
GIRDERS (BASEMENT 1)
August 6, 2018 B1G-59 (BLOCK 2) (F/1-2) 2.65 ₱250.00
August 6, 2018 B1G-21 (BLOCK 2) (G/1-2) 2.86 ₱250.00
August 6, 2018 B1G-29 (BLOCK 2) (F/2-3) 2.67 ₱250.00
August 6, 2018 B1G-35 (BLOCK 2) (G/2-3) 2.88 ₱250.00
August 6, 2018 B1G-41 (BLOCK 2) (G-H/2) 2.71 ₱250.00
August 6, 2018 B1G-42 (BLOCK 2) (F-G/2) 2.86 ₱250.00
August 6, 2018 B1G-41 (BLOCK 2) (G-H/3) 2.21 ₱250.00
August 6, 2018 B1G-42 (BLOCK 2) (F-G/3) 2.72 ₱250.00
BEAMS (BASEMENT 1)
August 7, 2018 B1B-45 (BLOCK 2) (G-H/1-2) 0.81 ₱250.00
August 7, 2018 B1B-4 (BLOCK 2) (G-H/1-2) 2.30 ₱250.00
August 7, 2018 B1B-3 (BLOCK 2) (G-H/1-2) 2.42 ₱250.00
August 7, 2018 B1B-4 (BLOCK 2) (F-G/1-2) 2.42 ₱250.00
August 7, 2018 B1B-5 (BLOCK 2) (F-G/1-2) 2.30 ₱250.00
August 7, 2018 B1B-4 (BLOCK 2) (G-H/2-3) 2.40 ₱250.00
August 7, 2018 B1B-5 (BLOCK 2) (F-G/2-3) 2.34 ₱250.00
August 7, 2018 B1B-4 (BLOCK 2) (G-H/2-3) 2.40 ₱250.00
August 7, 2018 B1B-5 (BLOCK 2) (F-G/2-3) 2.34 ₱250.00
SLABS (BASEMENT 1)
August 10, 2018 B1S-3 (BLOCK 2) (F-H/1-2) 69.48 ₱250.00
August 11, 2018 B1S-5 (BLOCK 2) (F-H/1-3) 217.15 ₱250.00
August 12, 2018 B1S-6 (BLOCK 2) (F-G/1-2) 11.38 ₱250.00
TOTAL 468.29
* P 300.00 unit cost per sqm minus P 50.00 for stripping = P250.00
BOR VS. ACCOMPLISHMENT
LABOR
LABOR RATE AMOUNT
₱75.00 ₱750.00
₱75.00 ₱825.00
₱64.00 ₱18,304.00
₱19,879.00
₱75.00 ₱750.00
₱75.00 ₱1,650.00
₱64.00 ₱23,232.00
₱25,632.00
₱75.00 ₱750.00
₱75.00 ₱1,650.00
₱64.00 ₱16,896.00
₱19,296.00
₱75.00 ₱750.00
₱75.00 ₱1,650.00
₱64.00 ₱18,304.00
₱20,704.00
₱75.00 ₱750.00
₱75.00 ₱1,650.00
₱64.00 ₱19,008.00
₱21,408.00
₱75.00 ₱600.00
₱75.00 ₱1,200.00
₱64.00 ₱13,312.00
₱15,112.00
₱75.00 ₱0.00
₱75.00 ₱0.00
₱64.00 ₱0.00
₱0.00
TOTAL ₱122,031.00
ACCOMPLISHMENT
AMOUNT REMARKS
₱27,695.25 STRIPPING OK
₱1,620.00 STRIPPING OK
₱1,620.00 STRIPPING OK
₱1,620.00 STRIPPING OK
₱1,620.00 STRIPPING OK
₱1,620.00 STRIPPING OK
₱742.50 STRIPPING OK
₱1,080.00 STRIPPING OK
₱1,080.00 STRIPPING OK
A. EUGENE MAYOR
1 ADMIN
SUPPLY OF LABOR, TOOLS, EQUIPMENT AND FULL TIME
SUPERVISION FOR INSTALLATION AND STRIPPING OF
FORMWORKS SYSTEM
SLABS (BASEMENT 1)
B1S-2 (BLOCK 1) (A-B/2-3) 0.00 0.00 3.00
B1S-5 (BLOCK 1) (A-B/2-4) 0.00 0.00 8.00
B1S-3 (BLOCK 1) (A-B/3-4) 0.00 0.00 3.00
LABOR
DATE MANPOWER QTY HOURS MAN-HOURS
FOREMAN 1 11 11
LEADMAN 1 11 11
August 6, 2018
CARPENTER 12 11 132
SUBTOTAL
FOREMAN 1 11 11
LEADMAN 1 11 11
August 7, 2018
CARPENTER 13 11 143
SUBTOTAL
FOREMAN 1 12 12
LEADMAN 1 12 12
August 8, 2018
CARPENTER 12 11 132
SUBTOTAL
FOREMAN 1 10 10
LEADMAN 1 10 10
August 9, 2018
CARPENTER 13 10 130
SUBTOTAL
FOREMAN 1 10 10
LEADMAN 1 10 10
August 10, 2018
CARPENTER 12 10 120
SUBTOTAL
FOREMAN 1 8 8
LEADMAN 1 8 8
August 11, 2018
CARPENTER 13 8 104
SUBTOTAL
FOREMAN 1 8 8
LEADMAN 0 8 0
August 12, 2018
CARPENTER 10 8 80
SUBTOTAL
ACCOMPLISHMENT
DATE STRUCTURE/BLOCK/GRIDLINE AREA (m2) COST PER SQM
RETAINING WALLS (FOUNDATION - BASEMENT 2)
August 11, 2018 RW-1 (BLOCK 5) (A/4-5) 38.10 ₱250.00
August 11, 2018 SPW-1 (BLOCK 5) (A/4-5) 45.00 ₱250.00
August 12, 2018 RW-3 (BLOCK 1) (A-C/3-4) 26.90 ₱250.00
* P 300.00 unit cost per sqm minus P 50.00 for stripping = P250.00
BOR VS. ACCOMPLISHMENT
LABOR
LABOR RATE AMOUNT
₱75.00 ₱825.00
₱75.00 ₱825.00
₱64.00 ₱8,448.00
₱10,098.00
₱75.00 ₱825.00
₱75.00 ₱825.00
₱64.00 ₱9,152.00
₱10,802.00
₱75.00 ₱900.00
₱75.00 ₱900.00
₱64.00 ₱8,448.00
₱10,248.00
₱75.00 ₱750.00
₱75.00 ₱750.00
₱64.00 ₱8,320.00
₱9,820.00
₱75.00 ₱750.00
₱75.00 ₱750.00
₱64.00 ₱7,680.00
₱9,180.00
₱75.00 ₱600.00
₱75.00 ₱600.00
₱64.00 ₱6,656.00
₱7,856.00
₱75.00 ₱600.00
₱75.00 ₱0.00
₱64.00 ₱5,120.00
₱5,720.00
TOTAL ₱58,004.00
ACCOMPLISHMENT
AMOUNT REMARKS
A. EUGENE MAYOR
1 ADMIN
SUPPLY OF LABOR, TOOLS, EQUIPMENT AND FULL TIME
SUPERVISION FOR INSTALLATION AND STRIPPING OF
FORMWORKS SYSTEM
Provisional
FORMWORKS
Sum
SLAB (BASEMENT 1)
S9 ( BLOCK 3 ) ( E-F/3-4) Provisional 0.00 0.00 2.00 1.00
FORMWORKS
S9 ( BLOCK 3 ) ( E-F/3-5) Sum 0.00 0.00 2.00 1.00
S9 ( BLOCK 3 ) ( E-F/4-5) 0.00 0.00 2.00 1.00
Noted by:
LABOR
DATE MANPOWER QTY HOURS MAN-HOURS
FOREMAN 0 8 0
LEADMAN 1 8 8
August 27, 2018
CARPENTER 6 8 48
SUBTOTAL
FOREMAN 1 10 10
LEADMAN 1 10 10
August 28, 2018
CARPENTER 20 10 200
SUBTOTAL
FOREMAN 1 10 10
LEADMAN 1 10 10
August 29, 2018
CARPENTER 22 10 220
SUBTOTAL
FOREMAN 1 10 10
LEADMAN 1 10 10
August 30, 2018
CARPENTER 22 10 220
SUBTOTAL
FOREMAN 1 10 10
LEADMAN 1 10 10
August 31, 2018
CARPENTER 24 10 240
SUBTOTAL
FOREMAN 1 8 8
LEADMAN 1 8 8
September 1, 2018
CARPENTER 24 8 192
SUBTOTAL
FOREMAN 0 4 0
LEADMAN 0 4 0
September 2, 2018
CARPENTER 6 4 24
SUBTOTAL
1248
ACCOMPLISHMENT
DATE STRUCTURE/BLOCK/GRIDLINE AREA (m2) COST PER SQM
BEAM AND GIRDER BASE (BASEMENT - 1)
August 27, 2018 B1G-43 (BLOCK 3) (E-F/4) 3.72 ₱250.00
August 27, 2018 B1G-56 (BLOCK 3) (E-F/5) 3.72 ₱250.00
August 28, 2018 B1B-6 (BLOCK 3) (E-F/4-5) 3.72 ₱250.00
August 29, 2018 B1B-6 (BLOCK 3) (E-F/4-5) 3.72 ₱250.00
September 1, 2018 B1G-24 (BLOCK 4) (E/3-4) 3.00 ₱250.00
September 2, 2018 B1G-25 (BLOCK 4) (E/4-5) 2.98 ₱251.00
BEAMS AND GIRDERS SIDINGS (BASEMENT - 1)
August 28, 2018 B1G-43 (BLOCK 3) (E-F/4) 10.70 ₱250.00
August 29, 2018 B1G-56 (BLOCK 3) (E-F/5) 10.70 ₱250.00
August 30, 2018 B1B-6 (BLOCK 3) (E-F/4-5) 8.84 ₱250.00
August 30, 2018 B1B-6 (BLOCK 3) (E-F/4-5) 8.84 ₱250.00
SLAB (BASEMENT 1)
August 30, 2018 S9 ( BLOCK 3 ) ( E-F/3-4) 43.48 ₱250.00
August 30, 2018 S9 ( BLOCK 3 ) ( E-F/3-5) 43.48 ₱250.00
August 31, 2018 S9 ( BLOCK 3 ) ( E-F/4-5) 60.13 ₱250.00
* P 300.00 unit cost per sqm minus P 50.00 for stripping = P250.00
R VS. ACCOMPLISHMENT
LABOR
LABOR RATE AMOUNT
₱81.25 ₱0.00
₱81.25 ₱650.00
₱64.00 ₱3,072.00
₱3,722.00
₱81.25 ₱812.50
₱81.25 ₱812.50
₱64.00 ₱12,800.00
₱14,425.00
₱81.25 ₱812.50
₱81.25 ₱812.50
₱64.00 ₱14,080.00
₱15,705.00
₱81.25 ₱812.50
₱81.25 ₱812.50
₱64.00 ₱14,080.00
₱15,705.00
₱81.25 ₱812.50
₱81.25 ₱812.50
₱64.00 ₱15,360.00
₱16,985.00
₱81.25 ₱650.00
₱81.25 ₱650.00
₱64.00 ₱12,288.00
₱13,588.00
₱81.25 ₱0.00
₱75.00 ₱0.00
₱64.00 ₱1,536.00
₱1,536.00
TOTAL ₱81,666.00
ACCOMPLISHMENT
AMOUNT REMARKS
₱930.00 INSTALLATION
₱930.00 INSTALLATION
₱930.00 INSTALLATION
₱930.00 INSTALLATION
₱750.00 INSTALLATION
₱747.98 INSTALLATION
₱2,673.75 INSTALLATION
₱2,673.75 INSTALLATION
₱2,208.75 INSTALLATION
₱2,208.75 INSTALLATION
₱10,870.00 INSTALLATION
₱10,870.00 INSTALLATION
₱15,032.50 INSTALLATION
₱11,658.00 INSTALLATION
₱9,990.00 INSTALLATION
₱8,406.00 INSTALLATION
₱6,010.80 STRIPPING
₱2,043.00 INSTALLATION
₱89,863.28
PROJECT The Arton Strip
WORK PACKAGE General Construction Works
PERIOD COVERED August 27, 2018 - September 2, 2018
A. EUGENE P. MAYOR
1 XANDER
SLAB (BASEMENT 1)
B1S-5 (BLOCK 3) (F-G/4-5) 0.00 2.00 3.00
B1S-5 (BLOCK 3) (F-G/4-5) 0.00 2.00 3.00
B1S-5 (BLOCK 3) (F-G/4-5) 0.00 2.00 3.00
B1S-5 (BLOCK 3) (F-G/5-6) 0.00 2.00 3.00
B1S-5 (BLOCK 3) (G-H/5-6) 0.00 2.00 3.00
B1S-5 (BLOCK 3) (G-H/5-6) 0.00 2.00 3.00
B1S-5 (BLOCK 3) (G-H/5-6) 0.00 2.00 3.00
B1S-5 (BLOCK 3) (G-H/5-6) 0.00 2.00 3.00
FIXING & ALIGNMENT OF FORMS
Noted by:
LABOR
DATE MANPOWER QTY HOURS
SAFETY 1 4
FOREMAN 1 4
August 27, 2018
CARPENTER 17 4
SUBTOTAL
SAFETY 1 10
FOREMAN 2 10
August 28, 2018
CARPENTER 18 10
SUBTOTAL
SAFETY 1 0
FOREMAN 2 10
August 29, 2018
CARPENTER 18 10
SUBTOTAL
SAFETY 1 12
FOREMAN 2 12
August 30, 2018
CARPENTER 18 12
SUBTOTAL
SAFETY 1 10
FOREMAN 2 10
August 31, 2018
CARPENTER 18 10
SUBTOTAL
SAFETY 1 11
FOREMAN 1 11
September 1, 2018
CARPENTER 22 11
SUBTOTAL
SAFETY 0 0
FOREMAN 2 4
September 2, 2018
CARPENTER 12 4
SUBTOTAL
ACCOMPLISHMENT
DATE STRUCTURE/BLOCK/GRIDLINE AREA (m2)
RETAINING WALLS (BASEMENT 1 - LOWER GROUND FLR.)
FIRST LIFT
August 27, 2018 RW-1 (BLOCK 2) (E-H/1) (ONE-SIDE) 53.64
August 28, 2018 RW-1 (BLOCK 2) (H/1-3) (ONE-SIDE) 41.71
August 29, 2018 RW-1 (BLOCK 2) (E-H/1) (ONE-SIDE) 51.96
August 30, 2018 RW-1 (BLOCK 2) (H/1-3) (ONE-SIDE) 41.71
August 31, 2018 RW-1 FIXING & ALIGNMENT OF FORMS
SLAB (BASEMENT 1)
August 28, 2018 B1S-5 (BLOCK 3) (F-G/4-5) 13.25
August 28, 2018 B1S-5 (BLOCK 3) (F-G/4-5) 13.25
August 28, 2018 B1S-5 (BLOCK 3) (F-G/4-5) 10.30
August 29, 2018 B1S-5 (BLOCK 3) (F-G/5-6) 7.60
August 29, 2018 B1S-5 (BLOCK 3) (G-H/5-6) 13.58
August 29, 2018 B1S-5 (BLOCK 3) (G-H/5-6) 9.60
August 30, 2018 B1S-5 (BLOCK 3) (G-H/5-6) 13.28
August 30, 2018 B1S-5 (BLOCK 3) (G-H/5-6) 4.55
August 31, 2018 FIXING & ALIGNMENT OF FORMS
TOTAL 379.79
* P 300.00 unit cost per sqm minus P 50.00 for stripping = P250.00
VS. ACCOMPLISHMENT
LABOR
MAN-HOURS LABOR RATE AMOUNT
4 ₱75.00 ₱300.00
4 ₱75.00 ₱300.00
68 ₱64.00 ₱4,352.00
₱4,952.00
10 ₱75.00 ₱750.00
20 ₱75.00 ₱1,500.00
180 ₱64.00 ₱11,520.00
₱13,770.00
0 ₱75.00 ₱0.00
20 ₱75.00 ₱1,500.00
180 ₱64.00 ₱11,520.00
₱13,020.00
12 ₱75.00 ₱900.00
24 ₱75.00 ₱1,800.00
216 ₱64.00 ₱13,824.00
₱16,524.00
10 ₱75.00 ₱750.00
20 ₱75.00 ₱1,500.00
180 ₱64.00 ₱11,520.00
₱13,770.00
11 ₱75.00 ₱825.00
11 ₱75.00 ₱825.00
242 ₱64.00 ₱15,488.00
₱17,138.00
0 ₱75.00 ₱0.00
8 ₱75.00 ₱600.00
48 ₱64.00 ₱3,072.00
₱3,672.00
1268 TOTAL ₱82,846.00
ACCOMPLISHMENT
COST PER SQM AMOUNT REMARKS
₱94,947.63