1 Feasibility Study
1 Feasibility Study
1 Feasibility Study
Dormann
The company is in need to perform electrical durability testing to determine the design
robustness and product life cycle. The published value of electrical durability life cycle is
100,000 operations. A test bench is in need to be designed to capture this data and perform
the testing that conforms to the norms of IEC (International Electrotechnical Commission) as
From the specifications list that was generated for the project, a set of critical
specifications were identified to be critical to the project. A ranking order matrix was used to
determine the potential challenge of the critical specifications that have been identified by the
company.
Min.
Design goals Cost Performance Maintenance Min. Parts Versatility Total
Type of Load 1 1 0.5 1 0.5 4
Data
acquisition 0.5 1 0.5 0.5 1 3.5
Efficiency 1 1 0 0.5 0 2.5
Cycling
options 0 1 0 0 1 2
The decision of the company for what would be the most critical specifications was
based on what would be the most critical components of the design. Based on these critical
specifications, the effort for choosing a solution has defined. While there are many
specifications that need to be addressed, the main points of the project can be boiled down to
Because of the various types of load options, the choice came down to cost for the
company. They have decided that the resistive load bank is the most cost effective option to
implement. While the costs of resistors are far less than that of electronic loads, they do
present their own set of challenges. The first challenge is to determine what type of resistor
There are three types of resistors that can be used for this project:
Rib wound
Grid Resistor
Each of these types of resistors has a given amperage range as well the span of
For the Smooth wound resistors the range of the product is as follows:
AC Load 750 W
83.3 < R < 250 Ohms
DC Load 72 W
8 < R < 24 Ohms
For the Rib wound resistors the range of the products is as follows:
AC Load 4000 W
15 < R < 50 Ohms
DC Load 384 W
1.5 < R < 4.8 Ohms
DC Load 384 W
0.48 < R < 1.2 Ohms
In order to minimize the number of resistors to be used and to maximize the test
capabilities,
slider taps to change the resistors value is unsafe, time consuming and a costly overrating of
the resistors (the more of the resistor that is partially used, the higher its linear heat dissipation
To address the challenge of versatility and flexibility for the potential to be able to
expand the capabilities in the future, the issue of maximization of productivity while reducing
To use the least amount of resistors as possible and to maximize the covered resistance
spectrum, (able to comply with all the different rated currents and making possible further
adds-on), it has been decided to use resistors that are adapted for these current levels both in
AC and DC:
The final challenge with the resistors will be that of heat dissipation. Thermal
Simulations will have to been performed to assess the direction of the heat flows and the
as the size of the enclosure, the resistors arrangement and the cooling power. Indeed
power supply and dissipation is an important issue considering that relays contacts are
For the data acquisition, there will be several topics that will need to be addressed:
PC and PLC must be able to communicate through the Ethernet network of the
company. Software will need to know the type of PLC used the type of network and the
device’s IP address to decide of the communication initiation sentence and of the data
accessible. There will be a need for software that will also be able to be used supervision.
This will be the software that will be able to allow for HMI. Another type of software that will
be required is one that will allow for the compilation of data and be used for reporting.
Finally there will be a need for software to program the tests that will be performed. It
will need to have a counter function, a watchdog timer, memory slots and buffers. Software
gives the possibility to refer to these memories with an alias, that will be used in the
supervision, with a more explicit and user-friendly way. Each device has it is own table.
EFFICIENCY
A complete supervision solution has to been setup, allowing for controlling and
monitoring of all the tests on the local network. Moreover, results must be available in an
Excel file with a friendly lay out. The Ethernet supervision will give capability to control the
count of the number of contacts operated so far. Furthermore, the supervision gives
A PLC will enable all the expected features; cycling, counting, 1 to 4 poles relay
testing as well as switching off the coils addresses when the relays are no longer operating
properly.
reach capability to test about 15 relays on the entire test-bench. Furthermore, most of the test
should be performed for relays with NO rating between 10 and 15 Amps in alternative
Trying to decrease global power supply and consequent dissipation, relays will be
fired on one by one. It also supplies the opportunity to use the same resistors for different
relays.
Because the cycling of the bench must meet the standards for both IEC and UL with
IEC 947 (European) and UL 508 (North American) standards instructions, the bench must be
able to have a speed selection. This is because each type of test requires different cycling rates
so depending on which type of test needs to be performed, the capability must be provided.
Testing is to be performed on every contacts according to IEC and only on one (NO or
NC) according to UL 508. Five (5) closing or opening misses can be tolerated if not
consecutives and solved without exterior assistance.1 Minimal real closing and opening time,
operations/hour according to datasheet. In different words, cycle length is set to 3s, with 0.5s
contact closed and current flowing (0.25s for UL) and 2.5s NC current closed 2.5s (2.75 for
UL) with current flowing 0.5s (0.25s). See chronology (figure 1) below.